MONTHYEARML0912701622009-05-0101 May 2009 Relief Request (PRR)-19, Jet Pump Instrumentation Nozzle Weld, RPV-N9A-1 Repair Plan Project stage: Request ML0913206562009-05-0707 May 2009 Response to NRC Request for Additional Information (RAI) Dated May 7, 2009, Regarding Pilgrim Relief Request (PRR)-19, Jet Pump Instrumentation Nozzle Weld, RPV-N9A-1 Repair Plan Project stage: Response to RAI ML0912704392009-05-0707 May 2009 E-mail from R. Guzman to W. Lobo RAI for Jet Pump Instrumentation Nozzle Weld Repair Plan Project stage: RAI ML0913100732009-05-11011 May 2009 E-mail Pilgrim Verbal Authorization for Relief Request PRR-19 Project stage: Other ML0914701522009-05-15015 May 2009 Results of UT Examination of Jet Pump Instrumentation Nozzle RPV-N9A-1 Weld Overlay Project stage: Other ML0923201242009-08-13013 August 2009 Stress Analysis Reports for Reactor Pressure Vessel (RPV) Jet Pump Instrumentation Nozzle Weld, RPV-N9A-1 Overlay Repair (Pilgrim Relief Request (PRR) -19) Project stage: Request ML0923705492009-09-11011 September 2009 Relief Request (PRR)19, Install a Weld Overlay on Jet Pump Instrumentation Nozzle Weld RPV-N9A-1- Pilgrim Nuclear Power Station Project stage: Acceptance Review ML1107400392011-03-0404 March 2011 Relief Request PRR-21, Application of NRC Approved In-Service Inspection of Pilgrim Relief Request PRR-19, (Jet Pump Instrumentation Nozzle Weld RPV-N9A-1 Repair Plan) for Reactor Pressure Vessel N14-1, N14-NV.. Project stage: Request ML11230A9192011-08-0505 August 2011 Revised Relief Request (PRR)-21, Contingency Repair Plan for Reactor Pressure Vessel (RPV) Standby Liquid Control Nozzle Weld, RPV-N14-1 Project stage: Request 2009-05-07
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML22335A2802022-11-0404 November 2022 11-4-2022 Email Transmitting Draft Questions Pertaining to Pilgrim ISFSI Exemption Request ML22270A0422022-09-26026 September 2022 Acknowledgement Email for Holtec'S Request for Reporting Exemption with Regards to the Pilgrim ISFSI Annual Radioactive Effluent Release Report (Docket No. 05000293) ML22154A1622022-05-26026 May 2022 Letter and Email from Save Our Bay/Diane Turco Regarding Irradiated Water Release from Pilgrim ML22007A2602021-12-0606 December 2021 E-mail from P. O'Brien, Holtec, to A. Snyder, NRC, on Pilgrim Effluent Discharge ML21287A6192021-10-14014 October 2021 E-mail from S. Phillips, MEMA, to A. Snyder, NRC, Pilgrim Nuclear Power Station, Commonwealth of Massachusetts Consultation Response to Amendment Review for Emergency Preparedness ML21266A2512021-09-23023 September 2021 Consultation with Commonwealth of Massachusetts Regarding Proposed Amendment Application for Emergency Plan and Emergency Action Levels ML21266A2772021-09-23023 September 2021 HDI Clarification of Exemption Requested from 10 CFR 20, Appendix G, Section Iii.E ML21267A0012021-09-23023 September 2021 E-mail from A. Snyder, NRC, to A. Sterdis, Holtec, - Pilgrim Nuclear Power Station - Request for Exemption from 10 CFR 20, Appendix G, Section Iii.E Acceptance Review ML21257A3832021-09-15015 September 2021 E-mail from A. Snyder, NRC, to A. Sterdis, Holtec, - Pilgrim Nuclear Power Station - Follow-on Request Re Request for Additional Information 2 Pilgrim - License Amendment Request Independent Spent Fuel Storage Installation Only Emergency Pl ML21211A5912021-07-22022 July 2021 Consultation Response from Commonwealth of Massachusetts Regarding Proposed Pilgrim ISFSI Only Technical Specifications ML21211A5162021-07-22022 July 2021 Consultation Response from Commonwealth of Massachusetts Regarding Proposed Pilgrim ISFSI Only Physical Security Plan ML21200A2352021-07-13013 July 2021 Consultation Request to Commonwealth of Massachusetts Regarding Proposed Pilgrim ISFSI Only Technical Specifications ML21200A1522021-07-13013 July 2021 Consultation Request to Commonwealth of Massachusetts Regarding Proposed Pilgrim Isfi Only Physical Security Plan ML21176A1842021-06-25025 June 2021 Email from HDI Regarding Pilgrim Nuclear Power Station Training ML21180A0582021-06-17017 June 2021 Email from Region I Regarding Pilgrim Nuclear Power Station Inspection - EA-13-132 ML21097A0402021-04-0606 April 2021 E-Mail Consult with Commonwealth of Mass Re - Amendment Application - Physical Security Plan for the Pilgrim Nuclear Power Station L-20-092, Email Pilgrim Nuclear Power Station-Exemption from Annual Force-On-Force Exercise Requirements of 10 CFR Part 73, Appendix B,2020-12-10010 December 2020 Email Pilgrim Nuclear Power Station-Exemption from Annual Force-On-Force Exercise Requirements of 10 CFR Part 73, Appendix B, L-20-096, Supplemental Information to Support Physical Security Plan Revision and License Amendment Request to Incorporate Alternate Measures - Holtec Email Dated December 10, 20102020-12-10010 December 2020 Supplemental Information to Support Physical Security Plan Revision and License Amendment Request to Incorporate Alternate Measures - Holtec Email Dated December 10, 2010 ML20328A2982020-11-16016 November 2020 Response from Commonwealth of Massachusetts on No Significant Hazard for Pilgrim ISFSI Amendment to Address ISFSI II Dated November 16, 2020 ML20297A2372020-10-22022 October 2020 Request for Additional Information - HDI Fleet Decommissioning Quality Assurance Program ML20266G4032020-09-22022 September 2020 Acceptance Review Email - Request for Approval of HDI Fleet Decommissioning Quality Assurance Program, Revision 0 ML20163A6802020-06-11011 June 2020 Confirmation of the Scope of the Requested Regulatory Relief for Pilgrim Security Qualifications ML20280A1912020-04-17017 April 2020 Request for Additional Information- Clarifying Information for Pilgrim ISFSI Physical Security Amendment Application ML20269A3542020-03-0505 March 2020 CFR 26.717 Reports 2019 Transmittal Email ML19336A0302019-11-27027 November 2019 OEDO-15-00479 - Re 2.206 Petition Regarding Pilgrim Nuclear Power Station'S Current Licensing Basis for Flooding ML19336A0332019-11-26026 November 2019 OEDO-15-00479 - E-mail to Petitioner - 2.206 Petition Regarding Pilgrim Nuclear Power Station'S Current Licensing Basis for Flooding (CAC No. MF6460; EPID L-2015-CRS-0002)- Issuance of Final Director'S Decision ML19331A1952019-11-21021 November 2019 NRR E-mail Capture - (External_Sender) Pilgrim Nuclear Power Station - Commonwealth Consultation Response - Amendment Regarding Site Emergency Plan and Emergency Action Level Scheme ML19331A1732019-11-12012 November 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station -Consult with Commonwealth - Amendment Regarding Cyber Security Plan ML19331A1642019-11-0505 November 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station -Consult with Commonwealth - Amendment Regarding Site Emergency Plan and Emergency Action Level Scheme ML19331A1792019-11-0505 November 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - EA and Fonsi for Pilgrim Emergency Planning Exemption CY-19-007, LTR-19-0441 Henrietta Cosentino, E-mail SECY-19-0078 Request by Entergy Nuclear Operations Inc. for Exemptions from Certain Emergency Planning Requirements for the Pilgrim Nuclear Power Station2019-11-0404 November 2019 LTR-19-0441 Henrietta Cosentino, E-mail SECY-19-0078 Request by Entergy Nuclear Operations Inc. for Exemptions from Certain Emergency Planning Requirements for the Pilgrim Nuclear Power Station ML19275H1962019-09-24024 September 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - Consult with Commonwealth - Amendment Regarding Permanently Defueled Technical Specifications (PDTS) ML19239A0372019-08-26026 August 2019 E-mail from Entergy Dated August 26, 2019, Notification of Pilgrim License Transfer ML19239A0262019-08-23023 August 2019 LTR-19-0330 Janet Azarovitz, E-mail a Plea for More Time and Reasonable Discussion Including the Citizens of the Commonwealth in the Sale of the Pilgrim Nuclear Power Station ML19234A2072019-08-20020 August 2019 LTR-19-0328 Lawrence Delafield, President, Six Ponds Improv Assoc., Plymouth, Ma, Ltr Requests NRC to Postpone Consideration of Transferring the Licenses for the Pilgrim Nuclear Power Until the NRC Has Answered Concerns by Pilgrim Watch, Se ML19232A4032019-08-20020 August 2019 LTR-19-0322 Diane Turco, Director, Cape Downwinders, Massachusetts, Letter/E-mail Requests Suspension of the Pilgrim License Transfer from Entergy to Holtec Until the Adjudicatory Hearing Is Held and Raised Contentions Are Resolved ML19308A9942019-08-19019 August 2019 Entergy Nuclear Operations, Inc. Confirmatory Order Rescission Supplemental Information ML19226A3912019-08-14014 August 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - EA and Fonsi for Pilgrim Decommissioning Trust Fund Exemption (Holtec) ML19226A3962019-08-14014 August 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station -Consult with Commonwealth - Conforming Amendment in Support of Pilgrim License Transfer Application ML19226A1212019-08-13013 August 2019 OEDO-15-00479-2.206 Petition Regarding Pilgrim Nuclear Power Station'S Current Licensing Basis for Flooding - Status (CAC No. MF6460; EPID L-2015-CRS-0002) ML19227A1032019-08-0707 August 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - Draft Wording for Potential Condition of License Transfer Order ML19207B3662019-07-26026 July 2019 NRR E-mail Capture - Pilgrim - RAI Direct and Indirect Transfer of Lic.; Conforming Lic. Amend.; Req. for Exemption 10 CFR 50.82(A)(8)(I)(A) for Holtec Decom. International, Llc ML19176A3452019-06-25025 June 2019 2.206 Petition Regarding Pilgrim Nuclear Power Station'S Current Licensing Basis for Flooding - Information (OEDO-15-00479) (CAC No. MF6460; EPID L-2015-CRS-0002) ML19154A0652019-06-0303 June 2019 NRR E-mail Capture - Pilgrim - Permanent Cessation of Power Operations ML19154A5242019-06-0303 June 2019 NRR E-mail Capture - RAI - Pilgrim Post-Decommissioning Technical Specifications (PDTS) License Amendment Request (LAR) ML19161A2122019-05-20020 May 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - Acceptance of License Amendment Request to Remove Cyber Security Plan Requirements ML19123A0332019-05-0101 May 2019 NRR E-mail Capture - Logbook Entry: 05/01/2019 Endangered Species Report Regarding a Confirmed Sighting of North Atlantic Right Whale(S) (Balaena Glacialis) ML19122A4912019-04-29029 April 2019 NRR E-mail Capture - Logbook Entry: 04/29/2019 Regarding the Confirmed Sighting of Ten North Atlantic Right Whales (Balaena Glacialis) ML19108A2372019-04-18018 April 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - Acceptance of Requested Licensing Action, Proposed Exemptions from 10 CFR 50.54(w)(1) - On-Site Property Damage Insurance ML19108A2362019-04-18018 April 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - Acceptance of Requested Licensing Action, Proposed Exemptions from 10 CFR 140.11(a)(4) - Primary and Secondary Liability Insurance 2022-09-26
[Table view] |
Text
From: Richard Guzman Sent: Thursday, May 07, 2009 10:46 AM To: 'wlobo@entergy.com' Cc: James Kim
Subject:
5/7/09 Telecom - RAI for Pilgrim PRR-19, Jet Pump Instrumentation Nozzle Weld Repair Plan
- Walt, As we discussed during today's conference call, please provide a supplemental response for the subject submittal dated May 1, 2009, to address the NRC staff's questions shown below.
- 1. Clarify the paragraph at the top of page 1 of Attachment 2 to Enclosure 1. The second sentence states, The area limitation in Attachment 3 is 500 square inches. Is Attachment 3 referring to ASME Code Case N-638, Revision 3?
If not, please explain what is being referred as Attachment 3.
- 2. What evidence (e.g., operating experience) is there that the existing Alloy 82 weld overlay will maintain its integrity for the life of the plant, i.e., has there ever been a field or laboratory failure of this material in a boiling-water reactor environment? In support of this response, please provide the reference to Section V.A.2.(b) on page 8 of PRR-19, i.e.,
the documentation that supports the sentence, Buisine, et al. evaluated the IGSCC resistance Also, revise the reference list shown on page 1 of PRR-19 to include the EPRI Topical Report MRP-115 and all other applicable references used to address this question.
- 3. Provide dates for each of the references shown on page 1 of PRR-19.
- Thanks, Rich Guzman Sr. Project Manager US NRC NRR/DORL 301-415-1030 Richard.Guzman@nrc.gov E-mail Properties Mail Envelope Properties ()
Subject:
5/7/09 Telecom - RAI for Pilgrim PRR-19, Jet Pump Instrumentation Nozzle Weld Repair Plan
Sent Date: 05/07/2009 10:28:08 AM Received Date: 05/07/2009 10:46:00 AM From: Richard Guzman Created By: Richard.Guzman@nrc.gov Recipients:
wlobo@entergy.com ('wlobo@entergy.com')
Tracking Status: None James.Kim@nrc.gov (James Kim)
Tracking Status: None Post Office:
Files Size Date & Time MESSAGE 12209 05/07/2009 Options Expiration Date:
Priority: olImportanceNormal ReplyRequested: False Return Notification: False Sensitivity: olNormal Recipients received: