E-mail from R. Guzman to W. Lobo RAI for Jet Pump Instrumentation Nozzle Weld Repair Plan
ML091270439
Person / Time
Site: Pilgrim
Issue date: 05/07/2009
From: Richard Guzman
Plant Licensing Branch 1
To: Lobo W
Entergy Nuclear Generation Co
Guzman R, NRR/DORL, 415-1030
References
TAC ME1151
Download: ML091270439 (2)


Text

From: Richard Guzman Sent: Thursday, May 07, 2009 10:46 AM To: 'wlobo@entergy.com' Cc: James Kim

Subject:

5/7/09 Telecom - RAI for Pilgrim PRR-19, Jet Pump Instrumentation Nozzle Weld Repair Plan

Walt, As we discussed during today's conference call, please provide a supplemental response for the subject submittal dated May 1, 2009, to address the NRC staff's questions shown below.
1. Clarify the paragraph at the top of page 1 of Attachment 2 to Enclosure 1. The second sentence states, The area limitation in Attachment 3 is 500 square inches. Is Attachment 3 referring to ASME Code Case N-638, Revision 3?

If not, please explain what is being referred as Attachment 3.

2. What evidence (e.g., operating experience) is there that the existing Alloy 82 weld overlay will maintain its integrity for the life of the plant, i.e., has there ever been a field or laboratory failure of this material in a boiling-water reactor environment? In support of this response, please provide the reference to Section V.A.2.(b) on page 8 of PRR-19, i.e.,

the documentation that supports the sentence, Buisine, et al. evaluated the IGSCC resistance Also, revise the reference list shown on page 1 of PRR-19 to include the EPRI Topical Report MRP-115 and all other applicable references used to address this question.

3. Provide dates for each of the references shown on page 1 of PRR-19.
Thanks, Rich Guzman Sr. Project Manager US NRC NRR/DORL 301-415-1030 Richard.Guzman@nrc.gov E-mail Properties Mail Envelope Properties ()

Subject:

5/7/09 Telecom - RAI for Pilgrim PRR-19, Jet Pump Instrumentation Nozzle Weld Repair Plan

Sent Date: 05/07/2009 10:28:08 AM Received Date: 05/07/2009 10:46:00 AM From: Richard Guzman Created By: Richard.Guzman@nrc.gov Recipients:

wlobo@entergy.com ('wlobo@entergy.com')

Tracking Status: None James.Kim@nrc.gov (James Kim)

Tracking Status: None Post Office:

Files Size Date & Time MESSAGE 12209 05/07/2009 Options Expiration Date:

Priority: olImportanceNormal ReplyRequested: False Return Notification: False Sensitivity: olNormal Recipients received: