MONTHYEARML21294A3762021-11-16016 November 2021 Federal Register Notice for Order Approving Indirect Transfer of Licenses ML21145A0142021-05-26026 May 2021 Fleet and the Associated Independent Spent Fuel Storage Installations - Extension of Comment Period for Notice of Consideration of Approval of Transfer of Licenses and Conforming Amendments and Opportunity to Request a Hearing EPID L-2021-L ML21145A0152021-05-26026 May 2021 FRN Exelon License Transfer - Extend Comment Period ML21102A0752021-04-28028 April 2021 Fleet - Notice of Consideration of Approval of Transfer of Licenses and Conforming Amendments and Opportunity for a Hearing (FRN) ML20269A2002020-09-30030 September 2020 Request to Use a Provision of Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI (EPID L2020-LLR-0117 ML20243A0002020-09-23023 September 2020 FRN - Notice of Issuance of Multiple Exemptions Regarding Various Parts of 10 CFR Due to COVID-19 Impacts for August 2020 ML20216A3742020-08-0505 August 2020 Letter with Withdrawal of an Amendment Request ML20146A0042020-07-21021 July 2020 Federal Register Notice - Exemption from the Requirements of Appendix J to 10 CFR Part 50 ML20177A6452020-07-15015 July 2020 FRN - Notice of Issuance of Multiple Exemptions Regarding Various Parts of 10 CFR Due to COVID-19 Impacts for June 2020 ML20035C4082020-02-18018 February 2020 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 02/25/2020 ML20021A2232020-01-24024 January 2020 FRN - James A. Fitzpatrick Nuclear Power Plant - Individual Notice of Consideration of Issuance of Amendment to Renewed Facility Operating License and Opportunity for a Hearing ML19295F0902019-11-0505 November 2019 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 11/05/2019 ML19238A3692019-09-0303 September 2019 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 09/10/2019 ML19085A2172019-03-29029 March 2019 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 04/09/2019 ML18304A3042018-11-23023 November 2018 Federal Register Notice: Environmental Assessment and Finding of No Significant Impact Regarding Exelon Generation Company, LLC License Amendment Request to Change Emergency Plan Staffing NRC-2018-0262, Federal Register Notice: Environmental Assessment and Finding of No Significant Impact Regarding Exelon Generation Company, LLC License Amendment Request to Change Emergency Plan Staffing2018-11-23023 November 2018 Federal Register Notice: Environmental Assessment and Finding of No Significant Impact Regarding Exelon Generation Company, LLC License Amendment Request to Change Emergency Plan Staffing ML18184A2422018-07-0606 July 2018 Letter, Individual SUNSI Notice of Consideration of Issuance of Amendment, Revise Technical Specification 2.1.1, 'Reactor Core Sls, to Change Cycle 24 Safety Limit Minimum Critical Power Ratio Numeric Values NRC-2018-0140, Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 7/17/20182018-07-0505 July 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 7/17/2018 ML18180A2182018-07-0505 July 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 7/17/2018 ML17240A0482017-11-0808 November 2017 FRN Order Approving Direct Transfer of Renewed Facility Operating License and Independent Spent Fuel Storage Installation General License and Conforming Amendment NRC-2017-0177, FRN Order Approving Direct Transfer of Renewed Facility Operating License and Independent Spent Fuel Storage Installation General License and Conforming Amendment2017-11-0808 November 2017 FRN Order Approving Direct Transfer of Renewed Facility Operating License and Independent Spent Fuel Storage Installation General License and Conforming Amendment ML17221A0372017-08-14014 August 2017 Notice of Consideration of Approval of Transfer of Facility Operating License and Conforming Amendment and Opportunity for a Hearing ML17221A0392017-08-14014 August 2017 Federal Register Notice of Consideration of Approval of Transfer or License and Conforming Amendment NRC-2017-0128, FRN Individual Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Sig. Hazards Consideration Determination, and Opportunity for Hearing2017-05-24024 May 2017 FRN Individual Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Sig. Hazards Consideration Determination, and Opportunity for Hearing ML17143A1172017-05-24024 May 2017 FRN Individual Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Sig. Hazards Consideration Determination, and Opportunity for Hearing ML17041A2742017-03-0101 March 2017 Federal Register Notice - Order Approving Direct License Transfer of FitzPatrick Power Plant from Entergy Nuclear FitzPatrick, LLC and Entergy Nuclear Operations, Inc. to Exelon Generation Company, LLC ML16336A5002017-01-27027 January 2017 Federal Register Notice of Issuance of Order for Mta Transfer of Indian Pt 3 and FitzPatrick to Entergy Nuclear Operations, Inc. NRC-2017-0015, Federal Register Notice of Issuance of Order for Mta Transfer of Indian Pt 3 and FitzPatrick to Entergy Nuclear Operations, Inc. (CAC Nos. MF8286 and MF8287)2017-01-27027 January 2017 Federal Register Notice of Issuance of Order for Mta Transfer of Indian Pt 3 and FitzPatrick to Entergy Nuclear Operations, Inc. (CAC Nos. MF8286 and MF8287) ML16244A7382016-10-20020 October 2016 FRN Regarding Exemption from the Requirements of 10 CFR Part 73, Sections 55(p)(1)(i) and (p)(1)(ii) Related to the Suspension of Security Measures in an Emergency or During Severe Weather NRC-2016-0221, FRN Regarding Exemption from the Requirements of 10 CFR Part 73, Sections 55(p)(1)(i) and (p)(1)(ii) Related to the Suspension of Security Measures in an Emergency or During Severe Weather2016-10-20020 October 2016 FRN Regarding Exemption from the Requirements of 10 CFR Part 73, Sections 55(p)(1)(i) and (p)(1)(ii) Related to the Suspension of Security Measures in an Emergency or During Severe Weather ML16271A0922016-09-28028 September 2016 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: October 11, 2016 NRC-2016-0202, Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: September 27, 20162016-09-19019 September 2016 Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: September 27, 2016 ML16257A5172016-09-19019 September 2016 Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: September 27, 2016 ML16243A0562016-09-0909 September 2016 FRN for License Transfer for FitzPatrick NPP: from ENO to Exelon ML16243A0552016-09-0909 September 2016 Notice of Consideration of Approval of Transfer of Renewed Facility Operating License and Conforming Amendment, and Opportunity for a Hearing - James A. Fitzpatrick Nuclear Power Plant NRC-2016-0071, FRN - Withdrawal of Amendment Request to Revise Technical Specification 5.5.6 for Extension of Type a and Type C Leak Rate Test Frequencies2016-03-29029 March 2016 FRN - Withdrawal of Amendment Request to Revise Technical Specification 5.5.6 for Extension of Type a and Type C Leak Rate Test Frequencies ML16082A4962016-03-29029 March 2016 Letter - Withdrawal of Amendment Request to Revise Technical Specification 5.5.6 for Extension of Type a and Type C Leak Rate Test Frequencies ML16082A4682016-03-29029 March 2016 FRN - Withdrawal of Amendment Request to Revise Technical Specification 5.5.6 for Extension of Type a and Type C Leak Rate Test Frequencies ML16004A1182016-01-0707 January 2016 FRN, Issuance of Confirmatory Orders, Authorize Use of Preemption Authority Granted Under Provisions of Section 161A of the Atomic Energy Act of 1954, as Amended ML15320A0212015-12-0808 December 2015 Cover Letter for Transmitting Final Fonsi EA Related to Preemption Authority Requests (Firearms) ML15177A2162015-10-22022 October 2015 James. a FitzPatrick Nuclear Power Plant - Draft Environmental Assessment ML15177A2082015-10-22022 October 2015 Draft Environmental Assessment and Finding of No Significant Impact Related to Preemption Authority Requests ML15162A6902015-08-27027 August 2015 G20130211 - Transmittal Letter to Petitioner Judson Regarding Final Director'S Decision for James A. FitzPatrick Power Plant, Pilgrim Nuclear Power Station and Vermont Yankee Nuclear Power Station ML15204A2792015-07-27027 July 2015 Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: August 4, 2015 ML14335A6302015-01-15015 January 2015 G20110262 - Final Response to Paul Gunter and Kevin Kamps Letter 2.206 - Immediately Suspend the Operating License of General Electric Boiling Water Reactors Mark I Units ML14335A6482015-01-15015 January 2015 G20110262 - FRN - Paul Gunter and Kevin Kamps Letter 2.206 - Immediately Suspend the Operating License of General Electric Boiling Water Reactors Mark I Units NRC-2015-0009, G20110262 - FRN - Paul Gunter and Kevin Kamps Letter 2.206 - Immediately Suspend the Operating License of General Electric Boiling Water Reactors Mark I Units2015-01-15015 January 2015 G20110262 - FRN - Paul Gunter and Kevin Kamps Letter 2.206 - Immediately Suspend the Operating License of General Electric Boiling Water Reactors Mark I Units ML14205A3142014-07-28028 July 2014 Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations- Published July 22, 2014 ML14189A6652014-07-24024 July 2014 Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving Proposed No Significant Hazards Considerations and Containing Sensitive Unclassified Non-Safeguards Information - August 5, 2014 ML14177A6452014-06-27027 June 2014 Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations 2021-05-26
[Table view] |
Text
[7590-01-P]
NUCLEAR REGULATORY COMMISSION JAMES A. FITZPATRICK NUCLEAR POWER PLANT DOCKET NO. 50-333 ENVIRONMENTAL ASSESSMENT AND FINDING OF NO SIGNIFICANT IMPACT
[NRC-2010-0095]
The U.S. Nuclear Regulatory Commission (NRC) is considering issuance of an exemption from the requirements of Part 50 of Title 10 of the Code of Federal Regulations (10 CFR), Appendix R, Fire Protection Program for Nuclear Power Facilities Operating Prior to January 1, 1979, issued to Entergy Nuclear Operations, Inc. (the licensee), for the operation of the James A. FitzPatrick Nuclear Power Plant (JAFNPP) located in Oswego County, NY.
Therefore, as required by 10 CFR 51.21, the NRC is issuing this environmental assessment and finding of no significant impact.
ENVIRONMENTAL ASSESSMENT Identification of Proposed Action:
Regulatory Issue Summary (RIS) 2006-10 documents the NRC position on the use of operator manual actions as part of a compliance strategy to meet the requirements of 10 CFR Part 50, Appendix R, Section III.G.2. The NRC requires plants which credit manual actions for 10 CFR Part 50, Appendix R, Section III.G.2 compliance to obtain NRC approval for the manual action using the exemption process in accordance with the requirements of 10 CFR 50.12. In response to RIS 2006-10, the licensee requested this licensing action which would exempt the JAFNPP from the requirements of 10 CFR Part 50, Appendix R, Section III.G.2. The proposed exemption would allow operator manual action, in a safe area of the reactor building, that will
prevent the failure of the systems in Fire Area 10 from affecting the ability to achieve and maintain hot shutdown conditions of the reactor as required by Title 10 of the Code of Federal Regulations Part 50, Appendix R,Section III.G.2.
The proposed action is in accordance with the licensee=s application dated February 18, 2009, as supplemented by letters dated March 30, November 17, December 11, 2009, and January 19, 2010. Portions of letters dated February 18 and March 30, 2009, contain security related sensitive information, and are withheld from public disclosure in accordance with 10 CFR 2.390. Publicly available versions of the letters dated February 18, and March 30, 2009, are accessible electronically from the Agencywide Documents Access and Management System (ADAMS) with Accession Nos. ML090860980 and ML091320387, respectively. Also, the letters dated November 17, December 11, 2009, and January 19, 2010, are accessible electronically from ADAMS with Accession Nos. ML093270075, ML093520408, and ML100210195, respectively.
The Need for the Proposed Action:
The proposed action is needed to allow the licensee an alternate method, not authorized in 10 CFR Part 50, to achieve and maintain hot shutdown conditions in the event of a fire that could disable electrical cables and equipment in Fire Area 10.
The criteria for granting specific exemptions from 10 CFR Part 50 Regulations are specified in 10 CFR 50.12. In accordance with 10 CFR 50.12(a)(1), the NRC is authorized to grant an exemption upon determining that the exemption is authorized by law, will not present an undue risk to the public health and safety, and is consistent with the common defense and security.
Environmental Impacts of the Proposed Action:
The NRC has completed its evaluation of the environmental impact of the proposed action. The staff has concluded that such actions would not adversely affect the environment.
The proposed action would not result in an increased radiological hazard. There will be no change to the radioactive effluent releases that effect radiation exposures to plant workers and members of the public. The proposed action will be performed inside the reactor building. No changes will be made to plant structures or the site property. Therefore, no changes or different types of radiological impacts are expected as a result of the proposed exemption.
The proposed action does not result in changes to land use or water use, or result in changes to the quality or quantity of non-radiological effluents. No changes to the National Pollution Discharge Elimination System permit are needed. No effects on the aquatic or terrestrial habitat in the vicinity or the plant, or to threatened, endangered, or protected species under the Endangered Species Act, or impacts to essential fish habitat covered by the Magnuson-Stevens Act are expected. There are no impacts to historical and cultural resources. There would be no impact to socioeconomic resources. Therefore, no changes or different types of non-radiological environmental impacts are expected as a result of the proposed exemption.
Accordingly, the NRC concludes that there are no significant environmental impacts associated with the proposed action.
The details of the staff=s safety evaluation will be provided in the license exemption that will be issued as part of the letter to the licensee approving the exemption to the regulation.
Environmental Impacts of the Alternatives to the Proposed Action:
As an alternative to the proposed action, the NRC staff considered denial of the proposed action (i.e., the no-action alternative). Denial of the application would result in no
change in current environmental impacts. The environmental impacts of the proposed action and the alternative action are similar.
Alternative Use of Resources:
The action does not involve the use of any different resources than those previously considered in the Final Environmental Statement for the James A. FitzPatrick Nuclear Power Plant, Docket No. 50-333, dated March 1973 and Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding James A. FitzPatrick Nuclear Power Plant (NUREG-1437, Supplement 31) Final Report.
Agencies and Persons Consulted:
In accordance with its stated policy and the requirements of 10 CFR 51.30(a)(2), on May 4, 2009, the NRC staff consulted with the New York State official, at the New York State Energy Research and Development Authority, regarding the environmental impact of the proposed action. The New York State official provided comments by e-mail dated June 12, 2009 (ADAMS Accession No. ML091690397).
One comment is related to Federal Regulations governing the exemption process.
Regulations under 10 CFR 50.12, Specific exemptions, do not include comment period and opportunity for a hearing. The public can pursue other avenues, such as petition for changes to the regulatory framework to allow hearings via the rulemaking process (10 CFR 2.802), or a petition for enforcement action (10 CFR 2.206) where stakeholders assert that license holders are not meeting regulatory requirements.
The other comments from the New York State addressed the security issues, the feasibility of the proposed manual action during a fire, and the cumulative effects of this change in conjunction with previous fire protection changes. Based on its review the NRC staff has determined that the comments do not pertain to the environmental impacts associated with the
proposed exemption request and therefore, do not alter the staffs finding that there are no significant environmental impacts associated with the proposed exemption request. However, the comments related to the safety aspect of the exemption request will be appropriately considered in the NRC staffs safety evaluation.
FINDING OF NO SIGNIFICANT IMPACT On the basis of the environmental assessment, the NRC concludes that the proposed action will not have a significant effect on the quality of the human environment. Accordingly, the NRC has determined not to prepare an environmental impact statement for the proposed action.
For further details with respect to the proposed action, see the licensee=s letter dated February 18, 2009, as supplemented by letters dated March 30, November 17, December 11, 2009, and January 19, 2010. Portions of letters dated February 18 and March 30, 2009, contain security related sensitive information, and are withheld from public disclosure in accordance with 10 CFR 2.390. Publicly available versions of the letters dated February 18, and March 30, 2009, are accessible electronically from the Agencywide Documents Access and Management System (ADAMS) with Accession Nos. ML090860980 and ML091320387, respectively. Also, the letters dated November 17, December 11, 2009, and January 19, 2010, are accessible electronically from ADAMS with Accession Nos. ML093270075, ML093520408, and ML100210195, respectively. Publicly available versions of the documents may be examined, and/or copied for a fee, at the NRC=s Public Document Room (PDR), located at One White Flint North, Public File Area O1 F21, 11555 Rockville Pike (first floor), Rockville, Maryland. Publicly available records will be accessible electronically from the ADAMS Public Electronic Reading Room on the Internet at the NRC Web site, http://www.nrc.gov/reading-rm/adams.html.
Persons who do not have access to ADAMS or who encounter problems in accessing the documents located in ADAMS should contact the NRC PDR Reference staff by telephone at 1-800-397-4209 or 301-415-4737, or send an e-mail to pdr.resource@nrc.gov.
Dated at Rockville, Maryland, this 4th day of March 2010.
FOR THE NUCLEAR REGULATORY COMMISSION
/RA/
Bhalchandra K. Vaidya, Project Manager Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation