National Institute of Standards and Technology, License Amendment, Issuance of Renewed Facility License No. TR-5 for the National Bureau of Standards Reactor
ML090990120
Person / Time
Site: National Bureau of Standards Reactor
Issue date: 07/02/2009
From: William Kennedy
Research and Test Reactors Licensing Branch
To: Richards W
US Dept of Commerce, National Institute of Standards & Technology (NIST)
Kennedy, WB NRR, 301-415-2784
Shared Package
ML090990113 List:
References
TAC MD3410
Download: ML090990120 (7)


Text

July 2, 2009 Dr. Wade Richards, Manager of Operations and Engineering NIST Center for Neutron Research National Institute of Standards and Technology U. S. Department of Commerce 100 Bureau Drive, Mail Stop 8561 Gaithersburg, MD 20899-8561

SUBJECT:

NATIONAL INSTITUTE OF STANDARDS AND TECHNOLOGY, ISSUANCE OF RENEWED FACILITY LICENSE NO. TR-5 FOR THE NATIONAL BUREAU OF STANDARDS REACTOR (TAC NO. MD3410)

Dear Dr. Richards:

The U.S. Nuclear Regulatory Commission (NRC) has issued renewed Facility Operating License No. TR-5 for the National Institute of Standards and Technology National Bureau of Standards Reactor in response to the application for license renewal dated April 9, 2004, as supplemented on October 2, 2006, May 30 and August 14, 2007, September 16, October 21, and December 8, 2008, and March 3, March 19, and April 22, 2009. The renewed license is effective as of the date of this letter and shall expire at midnight, 20 years from the date of issuance, unless sooner terminated. Enclosed with the renewed license is a copy of the Notice of Issuance of Renewed Facility Operating License No. TR-5 that is being sent to the Office of the Federal Register for publication and a copy of the safety evaluation report associated with the license renewal. The NRC sent the Notice of Availability of the Final Environmental Impact Statement and the Final Environmental Impact Statement associated with the license renewal to you under separate cover dated January 14, 2008. If you have any questions regarding this action, please contact me at 301-415-2784 or by electronic mail at William.Kennedy@nrc.gov.

Sincerely,

/RA/

William B. Kennedy, Project Manager Research and Test Reactors Branch A Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Docket No. 50-184

Enclosures:

1. Renewed Facility License No. TR-5
2. Safety Evaluation Report
3. Notice of Issuance of Renewed Facility License No. TR-5 cc: See next page

National Institute of Standards and Technology Docket No. 50-184 cc:

Director, Department of State Planning 301 West Preston Street Baltimore, MD 21201 Director, Air & Radiation Management Adm.

Maryland Dept of the Environment 1800 Washington Blvd., Suite 710 Baltimore, MD 21230 Director, Department of Natural Resources Power Plant Siting Program Energy and Coastal Zone Administration Tawes State Office Building Annapolis, MD 21401 President Montgomery County Council 100 Maryland Avenue Rockville, MD 20850 Test, Research, and Training Reactor Newsletter University of Florida 202 Nuclear Sciences Center Gainesville, FL 32611

July 2, 2009 Dr. Wade Richards, Manager of Operations and Engineering NIST Center for Neutron Research National Institute of Standards and Technology U. S. Department of Commerce 100 Bureau Drive, Mail Stop 8561 Gaithersburg, MD 20899-8561

SUBJECT:

NATIONAL INSTITUTE OF STANDARDS AND TECHNOLOGY, ISSUANCE OF RENEWED FACILITY LICENSE NO. TR-5 FOR THE NATIONAL BUREAU OF STANDARDS REACTOR (TAC NO. MD3410)

Dear Dr. Richards:

The U.S. Nuclear Regulatory Commission (NRC) has issued renewed Facility Operating License No. TR-5 for the National Institute of Standards and Technology National Bureau of Standards Reactor in response to the application for license renewal dated April 9, 2004, as supplemented on October 2, 2006, May 30 and August 14, 2007, September 16, October 21, and December 8, 2008, and March 3, March 19, and April 22, 2009. The renewed license is effective as of the date of this letter and shall expire at midnight, 20 years from the date of issuance, unless sooner terminated. Enclosed with the renewed license is a copy of the Notice of Issuance of Renewed Facility Operating License No. TR-5 that is being sent to the Office of the Federal Register for publication and a copy of the safety evaluation report associated with the license renewal. The NRC sent the Notice of Availability of the Final Environmental Impact Statement and the Final Environmental Impact Statement associated with the license renewal to you under separate cover dated January 14, 2008. If you have any questions regarding this action, please contact me at 301-415-2784 or by electronic mail at William.Kennedy@nrc.gov.

Sincerely,

/RA/

William B. Kennedy, Project Manager Research and Test Reactors Branch A Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Docket No. 50-184

Enclosures:

1. Renewed Facility License No. TR-5
2. Safety Evaluation Report
3. Notice of Issuance of Renewed Facility License No. TR-5 cc: See next page DISTRIBUTION:

PUBLIC RidsNrrDpr RidsNrrDprPrta RidsNrrDprPrtb PRTA Reading File SCollins RI GHill(2)

RidsOgcRp Resource RidsNrrAdro RidsAcrsAcnw_MailCtr WKennedy, NRR GLappert, NRR RidsNrrDprPfpb ACCESSION NO. PKG: ML090990113, LTR: ML090990120, TS: ML090990141, SE: ML090990135, FRN:

ML090990107

Office PRTA:PM PRTA:LA PFPB:BC OGC PRTA:BC DPR:DD DPR:D NRR:D PRTA:PM Name WKennedy wbk GLappert gkl RCarlson*

BMizuno bm KBrock kmb TBlount (TMcGinty for)

TMcGinty tm ELeeds el WKennedy wbk Date 05/04/09 05/03/09 02/03/09 06/05/09 05/18/09 06/09/09 06/09/09 7/2/09 7/2/09

UNITED STATES NUCLEAR REGULATORY COMMISSION THE NATIONAL INSTITUTE OF STANDARDS AND TECHNOLOGY DOCKET NO. 50-184 NATIONAL BUREAU OF STANDARDS TEST REACTOR RENEWED FACILITY OPERATING LICENSE License No. TR-5

1.

The U.S. Nuclear Regulatory Commission (the Commission) has found that:

A.

The application for renewal of Facility Operating License No. TR-5 filed by the National Institute of Standards and Technology (the licensee) dated April 9, 2004, as supplemented on October 2, 2006, May 30 and August 14, 2007, September 16, October 21, and December 8, 2008, and March 3, March 19, and April 22, 2009 (the application), complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commissions rules and regulations set forth in Title 10, Chapter 1, of the Code of Federal Regulations (10 CFR);

B.

Construction of the National Bureau of Standards test reactor (the facility) was completed in substantial conformity with Construction Permit No. CPTR-5 dated April 22, 1963, the provisions of the Act, and the rules and regulations of the Commission; C.

The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; D.

There is reasonable assurance that (i) the activities authorized by this renewed license can be conducted at the designated location without endangering the health and safety of the public, and (ii) such activities will be conducted in compliance with the rules and regulations of the Commission; E.

The licensee is technically and financially qualified to engage in the activities authorized by this license in accordance with the rules and regulations of the Commission; F.

The licensee is a Federal agency which, in accordance with 10 CFR Part 140, is not required to furnish proof of financial protection. The licensee has executed an indemnity agreement which satisfies the requirements of 10 CFR Part 140; G.

The issuance of this license will not be inimical to the common defense and security or to the health and safety of the public; H.

The issuance of this license is in accordance with 10 CFR Part 51, Environmental Protection Regulations for Domestic Licensing and Related Regulatory Functions, of the Commissions regulations and all applicable requirements; and I.

The receipt, possession and use of byproduct and special nuclear materials as authorized by this license will be in accordance with the Commission's regulations in 10 CFR Part 30 and 10 CFR Part 70.

2.

Facility Operating License No. TR-5 is hereby renewed in its entirety to read as follows:

A.

This license applies to the National Bureau of Standards test reactor (the reactor) that is owned by the National Institute of Standards and Technology (NIST or the licensee), located on NISTs campus one mile southwest of Gaithersburg, Maryland, and described in the licensees application, as supplemented.

B.

Subject to the conditions and requirements incorporated herein, the Commission hereby licenses the National Institute of Standards and Technology:

1.

Pursuant to subsection 104c of the Act, and Title 10, Part 50, Domestic Licensing of Production and Utilization Facilities, of the Code of Federal Regulations (10 CFR Part 50), to possess, use, and operate the reactor as a utilization facility at the designated location in accordance with the procedures and limitations described in the application and this license.

2.

Pursuant to the Act and 10 CFR Part 70, Domestic Licensing of Special Nuclear Material, to receive, possess, and use in connection with operation of the reactor:

a.

up to 45.0 kilograms of contained uranium-235 of any enrichment, provided that less than 5.0 kilograms of this amount be unirradiated;

b.

to possess and use, but not to separate such special nuclear material as may be produced by operation of the reactor.

3.

Pursuant to the Act and 10 CFR Part 30, Rules of General Applicability to Domestic Licensing of Byproduct Material, to possess and use a two-curie americium-beryllium neutron source for reactor startup.

4.

Pursuant to the Act and 10 CFR Part 30 to possess, use, and transfer but not to separate, except for byproduct material produced in non-fueled experiments, such byproduct material as may be produced by operation of the reactor.

C.

This license shall be deemed to contain and is subject to the conditions specified in Parts 20, 30, 50, 51, 55, 70, 73, and 100 of the Commissions regulations; is subject to all applicable provisions of the Act and rules, regulations, and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified below:

1.

The licensee is authorized to operate the reactor at steady-state power levels up to a maximum of 20 megawatts (thermal).

2.

The technical specifications contained in Appendix A are hereby incorporated in the license. The licensee shall operate the reactor in accordance with the technical specifications.

3.

The licensee shall maintain and fully implement all of the provisions of the Commission-approved physical security plan, including changes made pursuant to the authority of 10 CFR 50.54(p). The approved physical security plan consists of a National Institute of Standards and Technology document, withheld from public disclosure pursuant to 10 CFR 73.21, entitled, NBSR Safeguards Plan, dated May 1983, transmitted by letter dated May 5, 1983.

D.

This license is effective as of the date of issuance and shall expire at midnight twenty years from the date of issuance.

FOR THE NUCLEAR REGULATORY COMMISSION

/RA/

Eric J. Leeds, Director Office of Nuclear Reactor Regulation

Attachment:

Appendix A, Technical Specifications Date of Issuance: July 2, 2009