Letter Sequence Acceptance Review |
|---|
|
|
MONTHYEARML0903607382009-01-30030 January 2009 Request for Temporary Exemption from the Provisions of 10 CFR 50.46 and 10 CFR 50, Appendix K for Lead Fuel Assemblies, and Proposed Change Number (PCN)-589, Amendment Application Numbers 254 and 240, Respectively Project stage: Request 05000362/LER-2008-003, For San Onofre, Regarding Missed TS Completion Time Results in TS Violation2009-01-30030 January 2009 For San Onofre, Regarding Missed TS Completion Time Results in TS Violation Project stage: Request ML0907001972009-02-11011 February 2009 Acceptance Review Email, Insufficient Info, Temporary Exemption from 10 CFR 50.46 and 10 CFR 50, Appendix K for Lead Fuel Assemblies & License Amendment to Revise TS 5.7.1.5, Core Operating Limits Report (TAC ME0602-ME0605) Project stage: Acceptance Review ML0907003302009-03-11011 March 2009 Acceptance Review Complete Email, Temporary Exemption from 10 CFR 50.46 and 10 CFR 50, Appendix K for Lead Fuel Assemblies & License Amendment to Revise TS 5.7.1.5, Core Operating Limits Report (TAC Nos. ME0602-ME0605) Project stage: Acceptance Review ML0907802512009-03-16016 March 2009 Response to NRC Questions Regarding Request for Temporary Exemption from the Provisions of 10 CFR 50.46 and 10 CFR 50, Appendix K for Lead Fuel Assemblies, and Proposed Change Number -589, Amendment Application Numbers 254 Project stage: Request ML0923805722009-08-26026 August 2009 E-mail Request for Additional Information Temporary Exemption Request and License Amendment Request for Use of Areva Lead Fuel Assemblies Project stage: RAI ML0923805832009-08-26026 August 2009 Request for Additional Information E-mail Temporary Exemption Request and License Amendment Request for Use of Areva Lead Fuel Assemblies Project stage: RAI ML0908307052009-09-28028 September 2009 Environmental Assessment and Finding of No Significant Impact Related to Request for Temporary Exemption from 10 CFR 50, Appendix K, for Lead Fuel Assemblies Project stage: Approval ML0908307002009-09-28028 September 2009 Transmittal Letter, Environmental Assessment and Finding of No Significant Impact Related to Request for Temporary Exemption from 10 CFR 50, Appendix K, for Lead Fuel Assemblies Project stage: Approval NRC-2009-0439, Environmental Assessment and Finding of No Significant Impact Related to Request for Temporary Exemption from 10 CFR 50, Appendix K, for Lead Fuel Assemblies (TAC Nos. ME0602 and ME0603)2009-09-28028 September 2009 Environmental Assessment and Finding of No Significant Impact Related to Request for Temporary Exemption from 10 CFR 50, Appendix K, for Lead Fuel Assemblies (TAC Nos. ME0602 and ME0603) Project stage: Approval ML0927403102009-09-29029 September 2009 Response to Request for Additional Information on Request for Temporary Exemption from the Provisions of 10 CFR 50.46 and 10 CFR 50, Appendix K for Lead Fuel Assemblies, and Proposed Change Number Project stage: Response to RAI ML0932201052009-12-15015 December 2009 Issuance of Amendment Nos. 222 and 215, Revise Technical Specification 5.7.1.5, Core Operating Limits Report Project stage: Approval ML0908604152009-12-17017 December 2009 Letter, Temporary Exemption from the Requirement of 10 CFR Part 50, Section 50.46 and Appendix K for Lead Fuel Assemblies Project stage: Approval ML0908604292009-12-17017 December 2009 Temporary Exemption from the Requirement of 10 CFR Part 50, Section 50.46 and Appendix K for Lead Fuel Assemblies Project stage: Approval NRC-2009-0570, Temporary Exemption from the Requirement of 10 CFR Part 50, Section 50.46 and Appendix K for Lead Fuel Assemblies2009-12-17017 December 2009 Temporary Exemption from the Requirement of 10 CFR Part 50, Section 50.46 and Appendix K for Lead Fuel Assemblies Project stage: Approval ML13073A1402013-02-15015 February 2013 Core Operating Limits Report for Unit 2 Cycle 17 and Unit 3 Cycle 16 Project stage: Other 2009-03-11
[Table View] |
Text
From:
Kaly Kalyanam Sent:
Wednesday, March 11, 2009 10:47 AM To:
Linda.Conklin@sce.com Cc:
Marshall David; Karl Feintuch; Janet Burkhardt; Susan Lent
Subject:
Acceptance Review completed for 1) Exemption Request and 2) License Amendment Request The NRC staff has reviewed your application dated January 30, 2009, with an Exemption Request and a License Amendment Request, as detailed below:
- 1. Request for Temporary Exemption from the Provisions of 10 CFR 50.46 and 10 CFR 50, Appendix K for Lead Fuel Assemblies (TAC Nos. ME0602 and ME0603).
- 2. Proposed Change Number (PCN)-589, Amendment Application Numbers 254 and 240, respectively for Units 2 and 3, Request to Revise Technical Specification 5.7.1.5, "Core Operating Limits Report (COLR)." (TAC Nos. ME0604 and ME0605).
The NRC staff has concluded the application provides sufficient technical information in sufficient detail to enable the NRC staff to proceed with its technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of the regulatory requirements, and the protection of the public health and safety and of the environment. If additional information is needed for the staff to complete its review, you will be advised by separate correspondence.
Thanks Kaly E-mail Properties Mail Envelope Properties (CEEA97CC21430049B821E684512F6E5EB70ADDB9FF)
Subject:
Acceptance Review completed for 1) Exemption Request and 2) License Amendment Request Sent Date: 3/11/2009 10:47:27 AM Received Date: 3/11/2009 10:47:27 AM From: Kaly Kalyanam Created By: Kaly.Kalyanam@nrc.gov Recipients:
Linda.Conklin@sce.com (Linda.Conklin@sce.com)
Tracking Status: None Marshall.David@nrc.gov (Marshall David)
Tracking Status: None Karl.Feintuch@nrc.gov (Karl Feintuch)
Tracking Status: None
Janet.Burkhardt@nrc.gov (Janet Burkhardt)
Tracking Status: None Susan.Lent@nrc.gov (Susan Lent)
Tracking Status: None Post Office:
HQCLSTR01.nrc.gov Files Size Date & Time MESSAGE 8086 3/11/2009 Options Expiration Date:
Priority: olImportanceNormal ReplyRequested: False Return Notification: False Sensitivity: olNormal Recipients received: