MONTHYEARML0816402442008-08-15015 August 2008 (Redacted) Information Request Pursuant to 10 CFR 50.54(F) Related to External Flooding, Including Failure of the Jocassee Dam at Oconee Nuclear Station, Units 1, 2, and 3 Project stage: Other ML12363A1322008-08-15015 August 2008 Information Request Pursuant to 10 CFR 50.54(f) Related to External Flooding, Including Failure of the Jocassee Dam at Oconee Nuclear Station, Units 1, 2, and 3 Project stage: Other ML0823906692008-08-26026 August 2008 E-mail Oconee Nuclear Station - Kick Off for Risk Analysis of the Failure of the Jocassee and Keowee Dams to Assess the Potential Effects on the Safe Shutdown Facility of ONS Project stage: Other ML0823906902008-08-26026 August 2008 Letter Kick Off for Risk Analysis of the Failure of the Jocassee and Keowee Dams to Assess the Potential Effects on the Safe Shutdown Facility at the Oconee Nuclear Station Project stage: Other ML12326A3892008-09-0909 September 2008 Memorandum from E. Leeds, NRR to V. Ordaz, EDO on Communication Plan for Information Request Pursuant to 10 CFR 50.54(f) Related to External Flooding, Including Failure of the Jocassee Dam Project stage: Other ML0822501662008-09-0909 September 2008 (Redacted) Oconee Nuclear Station - Communication Plan for Information Request Related to Failure Frequencies for the Jocassee Pumped Storage Dam (Jocassee Dam) at the Oconee Nuclear Station and Potential Generic Implications Project stage: Other ML13121A3262008-09-0909 September 2008 Communication Plan for Information Request Pursuant to 10 CFR 50.54(f) Related to External Flooding, Including Failure of the Jocassee Dam, at Oconee Nuclear Station, Units 1, 2, and 3 Project stage: Other ML0827501062008-09-26026 September 2008 (Redacted) Oconee, Units 1, 2 and 3 - Response to 10 CFR 50.54(f) Request Project stage: Other ML12363A1292008-09-26026 September 2008 Response to 10 CFR 50.54(f) Request Project stage: Other ML0833004272008-12-16016 December 2008 Summary of Closed Meeting to with Duke Energy Carolinas, LLC to Discuss the August 15, 2008, 50.54(f) Letter on External Flooding Project stage: Meeting ML0906807372009-03-13013 March 2009 (Redacted) 12/04/09 Summary of Closed Meeting to Discuss the Duke Energy Carolinas, Llc., 09/26/08 Response to Nrcs, August 15, 2008 50.54(f) Letter on External Flooding at Oconee Project stage: Meeting ML0911701042009-04-0606 April 2009 (Redacted) Oconee Nuclear Station, Units 1, 2 and 3 - Non-concurrence on Evaluation of Duke Energy Carolinas, LLC September 26, 2008, Response to Nuclear Regulatory Commission Letter Dated August 15, 2008 Related to External Flooding Project stage: Other ML0908204702009-04-22022 April 2009 Notice of Forthcoming Closed Meeting with Duke Energy Carolinas, LLC, to Discuss Sensitivity Studies Concerning Failure of the Jocassee Dam & Resultant Flooding at the Oconee Nuclear Station, Unit 1, 2, & 3 Project stage: Meeting ML0905707792009-04-30030 April 2009 Evaluation of Duke Energy Carolinas September 26, 2008, Response to 10 CFR 50.54(f), Letter Dated August 15, 2008, Related to External Flooding, Including Failure of the Jocassee Dam Project stage: Other ML12363A1332009-04-30030 April 2009 Evaluation of Duke Energy Carolina September 26, 2008, Response to 10 CFR 50.554(f), Letter Dated August 15, 2008, Related to External Flooding, Including Failure of the Jocassee Dam Project stage: Other ML0913804242009-05-11011 May 2009 Slides for Closing Meeting May 11, 2009 with Duke on the Oconee Flooding Issue Project stage: Request ML0914203192009-06-0101 June 2009 (Redacted) 12/04/2008 Meeting Summary, Meeting to Discuss External Flooding at Oconee Nuclear Station (Reissuance, with Error on Page 3 Corrected) Project stage: Meeting ML0910607612009-06-18018 June 2009 (Redacted) 11/05/08 Summary of Closed Meeting with Duke on External Flooding Issues, Including Failure of the Jocassee Dam, at Oconee Nuclear Station, Units 1, 2, and 3 Project stage: Meeting ML0916206692009-07-0909 July 2009 Summary of Closed Meeting with Duke Carolina to Discuss External Flooding at Oconee Project stage: Meeting ML0929407692009-11-10010 November 2009 Summary of Closed Meeting with Duke Energy Carolinas, LLC, to Discuss Preliminary Results of the Recent Inundation and Sensitivity Studies Concerning Failure of the Jocassee Dam and Resultant Flooding at Oconee Nuclear Station, 1, 2, and 3 Project stage: Meeting ONS-2016-001, Transmittal of Supplemental Information Regarding NRC 2008 and 2012 Requests for Information, Pursuant to 10 Cer 50.54(f) Pertaining to External Flooding - Revision 12016-01-0808 January 2016 Transmittal of Supplemental Information Regarding NRC 2008 and 2012 Requests for Information, Pursuant to 10 Cer 50.54(f) Pertaining to External Flooding - Revision 1 Project stage: Supplement 2009-04-22
[Table View] |
Text
December 16, 2008 LICENSEE:
DUKE ENERGY CAROLINAS, LLC (DUKE)
FACILITY:
OCONEE NUCLEAR STATION, UNITS 1, 2, AND 3 (OCONEE)
SUBJECT:
SUMMARY
OF CLOSED AUGUST 28, 2008, MEETING TO DISCUSS THE AUGUST 15, 2008, 50.54(f) LETTER ON EXTERNAL FLOODING (TAC NOS.
MD8224, MD8225, AND MD8226)
On August 28, 2008, the U.S. Nuclear Regulatory Commission (NRC) had a closed meeting with Duke (the licensee) to discuss the August 15, 2008, 50.54(f) letter (ML081640244) on external flooding at Oconee. A copy of the slides presented by the NRC staff is available under ADAMS accession number ML082550290. Enclosed is a list of the meeting attendees.
The August 15, 2008, 50.54(f) letter had recommended that the licensee meet with the NRC staff within 3 weeks to discuss the issues and questions in the letter in order to ensure that the licensees responses will have sufficient level of detail for the NRC staff to make an appropriate determination.
The NRC staff presented the basis for its concern with the protection against external flooding at Oconee. The NRC staff then discussed each of the three questions contained in the August 15, 2008, letter and NRC expectation for the response.
Following are some of the comments made by the licensee during the meeting:
- 1. The NRC internal guidance that prohibits contact with the licensee during the backfit process should be re-evaluated.
- 2. A 2004 Federal Energy Regulatory Commission study provided additional information on the Jocassee Dam.
- 3. The licensee considers the 1992 Inundation Study to be conservative.
- 4. The licensee intends to evaluate the frequency of specific mechanisms of dam failure and create a class of flood heights associated with these specific failure mechanisms.
- 5. The licensee is considering interim measures, such as providing protection against flood heights of about 10 feet and utilizing the B.5.b equipment to mitigate the postulated flood.
Following are some of the comments made by the NRC staff during the meeting:
- 1. Adequate protection issues are distinct from risk issues.
- 2. It would be a challenge for the NRC to accept the licensee eliminating complete failure of the Jocassee Dam because it is not credible.
Duke
- 3. The issuance of a 50.54(f) letter is very unusual and reflects the NRCs level of concern on the failure of the Jocassee Dam.
/RA/
Leonard N. Olshan, Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-269, 50-270, and 50-287
Enclosure:
Meeting Attendees
Duke
- 4. The issuance of a 50.54(f) letter is very unusual and reflects the NRCs level of concern on the failure of the Jocassee Dam.
/RA/
Leonard N. Olshan, Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-269, 50-270, and 50-287
Enclosure:
Meeting Attendees Docket Nos. 50-269, 50-270, and 50-287
Enclosure:
Meeting Attendees Distribution:
NON-PUBLIC NRR LPL2-1 R/F E. Riggs RidsNrrPMJStang Resource RidsNrrDss Resource G. DeMoss, RES RidsRgn2MaiICenter Resource RidsNrrDe Resource R. Pichumani, NRR RidsOgcMailCenter Resource RidsNrrDra Resource R. Carroll, DRP RidsNrrDorlLpl2-1 (MWong)
K. Manoly, NRR J. Zimmerman, NRR RidsNrrLAMO'Brien M. Simon, OGC J. Vail, NRR RidsNrrPMLOlshan Resource L. Wert, DRP K. Lois, NRR RidsNrrAdes Resource A. Hutto, DRP E. Williamson, OGC RidsNrrDorl Resource G. Mizuno, OGC J. Thompson, NRR RidsNrrDpr Resource W. Rodgers, DRS Accession Number: ML083300427 OFFICE LPL2-1/PM LPL2-1/LA LPL2-1/BC NAME LOlshan MOBrien MWong (RMartin for)
DATE 12/8/08 12/8/08 12/16/08 OFFICIAL AGENCY RECORD
MEETING ATTENDEES AT THE CLOSED AUGUST 28, 2008, MEETING WITH DUKE ENERGY CAROLINAS, LLC (DUKE)
TO DISCUSS THE AUGUST 15, 2008, 50.54(f) LETTER ON EXTERNAL FLOODING NRC DUKE J. Grobe J. Giitter D. Baxter T. McGinty R. Freudenberger P. Hiland T. Brown M. Galloway D. Cummings L. Wert R. McCoy S. Bahadur S. Nader K. Lois G. Davenport*
M. Simon S. Severance*
K. Manoly R. Meixell*
J. Zimmerman M. Wong E. Williamson G. DeMoss G. Mizuno R. Pichumani J. Vail J. Thompson L. Olshan R. Carroll*
W. Rogers*
A. Hutto*
E. Riggs*