MONTHYEARML0816402442008-08-15015 August 2008 (Redacted) Information Request Pursuant to 10 CFR 50.54(F) Related to External Flooding, Including Failure of the Jocassee Dam at Oconee Nuclear Station, Units 1, 2, and 3 Project stage: Other ML12363A1322008-08-15015 August 2008 Information Request Pursuant to 10 CFR 50.54(f) Related to External Flooding, Including Failure of the Jocassee Dam at Oconee Nuclear Station, Units 1, 2, and 3 Project stage: Other ML0823906692008-08-26026 August 2008 E-mail Oconee Nuclear Station - Kick Off for Risk Analysis of the Failure of the Jocassee and Keowee Dams to Assess the Potential Effects on the Safe Shutdown Facility of ONS Project stage: Other ML0823906902008-08-26026 August 2008 Letter Kick Off for Risk Analysis of the Failure of the Jocassee and Keowee Dams to Assess the Potential Effects on the Safe Shutdown Facility at the Oconee Nuclear Station Project stage: Other ML12326A3892008-09-0909 September 2008 Memorandum from E. Leeds, NRR to V. Ordaz, EDO on Communication Plan for Information Request Pursuant to 10 CFR 50.54(f) Related to External Flooding, Including Failure of the Jocassee Dam Project stage: Other ML0822501662008-09-0909 September 2008 (Redacted) Oconee Nuclear Station - Communication Plan for Information Request Related to Failure Frequencies for the Jocassee Pumped Storage Dam (Jocassee Dam) at the Oconee Nuclear Station and Potential Generic Implications Project stage: Other ML13121A3262008-09-0909 September 2008 Communication Plan for Information Request Pursuant to 10 CFR 50.54(f) Related to External Flooding, Including Failure of the Jocassee Dam, at Oconee Nuclear Station, Units 1, 2, and 3 Project stage: Other ML0827501062008-09-26026 September 2008 (Redacted) Oconee, Units 1, 2 and 3 - Response to 10 CFR 50.54(f) Request Project stage: Other ML12363A1292008-09-26026 September 2008 Response to 10 CFR 50.54(f) Request Project stage: Other ML0833004272008-12-16016 December 2008 Summary of Closed Meeting to with Duke Energy Carolinas, LLC to Discuss the August 15, 2008, 50.54(f) Letter on External Flooding Project stage: Meeting ML0906807372009-03-13013 March 2009 (Redacted) 12/04/09 Summary of Closed Meeting to Discuss the Duke Energy Carolinas, Llc., 09/26/08 Response to Nrcs, August 15, 2008 50.54(f) Letter on External Flooding at Oconee Project stage: Meeting ML0911701042009-04-0606 April 2009 (Redacted) Oconee Nuclear Station, Units 1, 2 and 3 - Non-concurrence on Evaluation of Duke Energy Carolinas, LLC September 26, 2008, Response to Nuclear Regulatory Commission Letter Dated August 15, 2008 Related to External Flooding Project stage: Other ML0908204702009-04-22022 April 2009 Notice of Forthcoming Closed Meeting with Duke Energy Carolinas, LLC, to Discuss Sensitivity Studies Concerning Failure of the Jocassee Dam & Resultant Flooding at the Oconee Nuclear Station, Unit 1, 2, & 3 Project stage: Meeting ML0905707792009-04-30030 April 2009 Evaluation of Duke Energy Carolinas September 26, 2008, Response to 10 CFR 50.54(f), Letter Dated August 15, 2008, Related to External Flooding, Including Failure of the Jocassee Dam Project stage: Other ML12363A1332009-04-30030 April 2009 Evaluation of Duke Energy Carolina September 26, 2008, Response to 10 CFR 50.554(f), Letter Dated August 15, 2008, Related to External Flooding, Including Failure of the Jocassee Dam Project stage: Other ML0913804242009-05-11011 May 2009 Slides for Closing Meeting May 11, 2009 with Duke on the Oconee Flooding Issue Project stage: Request ML0914203192009-06-0101 June 2009 (Redacted) 12/04/2008 Meeting Summary, Meeting to Discuss External Flooding at Oconee Nuclear Station (Reissuance, with Error on Page 3 Corrected) Project stage: Meeting ML0910607612009-06-18018 June 2009 (Redacted) 11/05/08 Summary of Closed Meeting with Duke on External Flooding Issues, Including Failure of the Jocassee Dam, at Oconee Nuclear Station, Units 1, 2, and 3 Project stage: Meeting ML0916206692009-07-0909 July 2009 Summary of Closed Meeting with Duke Carolina to Discuss External Flooding at Oconee Project stage: Meeting ML0929407692009-11-10010 November 2009 Summary of Closed Meeting with Duke Energy Carolinas, LLC, to Discuss Preliminary Results of the Recent Inundation and Sensitivity Studies Concerning Failure of the Jocassee Dam and Resultant Flooding at Oconee Nuclear Station, 1, 2, and 3 Project stage: Meeting ONS-2016-001, Transmittal of Supplemental Information Regarding NRC 2008 and 2012 Requests for Information, Pursuant to 10 Cer 50.54(f) Pertaining to External Flooding - Revision 12016-01-0808 January 2016 Transmittal of Supplemental Information Regarding NRC 2008 and 2012 Requests for Information, Pursuant to 10 Cer 50.54(f) Pertaining to External Flooding - Revision 1 Project stage: Supplement 2009-04-22
[Table View] |
Text
OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION August 26, 2008 Mr. R. J. Freudenberger Manager, Safety Assurance Duke Energy Carolinas, LLC 7800 Rochester Highway Seneca, SC 29672
SUBJECT:
KICKOFF FOR RISK ANALYSIS OF THE FAILURE OF THE JOCASSEE AND KEOWEE DAMS TO ASSESS THE POTENTIAL EFFECTS ON THE SAFE SHUTDOWN FACILITY AT THE OCONEE NUCLEAR STATION
Dear Mr. Freudenberger:
Thank you for informing the U.S. Nuclear Regulatory Commission (NRC) staff of the planned work to reassess the risk to the Oconee Nuclear Station from external flooding events. This reassessment could be useful and informative in a number of risk-informed regulatory contexts.
For example, a risk-informed licensing action that conformed to the American Society of Mechanical Engineers (ASME) probabilistic risk assessment (PRA) standard would benefit from having a realistic flooding risk analysis.
While the subject of the risk reassessment is of interest to the NRC, we do not plan to attend the kickoff meeting between you and your contractor scheduled for September 15 through 19, 2008.
If you believe it valuable, we would be willing to meet with you to discuss the results of that meeting and any plant reanalysis.
Our August 15, 2008, letter to you focused on the protection of the Oconee facilities in the event of a flooding situation taking into consideration the level of protection from flooding events and the available defense-in-depth.
If you have any questions on this matter, please contact Leonard N. Olshan at 301-415-1419.
Sincerely,
/RA/
Joseph G. Giitter, Director Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-269, 50-270, and 50-287 LIMITED INTERNAL DISTRIBUTION PERMITTED
OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION August 26, 2008 Mr. R. J. Freudenberger Manager, Safety Assurance Duke Energy Carolinas, LLC 7800 Rochester Highway Seneca, SC 29672
SUBJECT:
KICKOFF FOR RISK ANALYSIS OF THE FAILURE OF THE JOCASSEE AND KEOWEE DAMS TO ASSESS THE POTENTIAL EFFECTS ON THE SAFE SHUTDOWN FACILITY AT THE OCONEE NUCLEAR STATION
Dear Mr. Freudenberger:
Thank you for informing the U.S. Nuclear Regulatory Commission (NRC) staff of the planned work to reassess the risk to the Oconee Nuclear Station from external flooding events. This reassessment could be useful and informative in a number of risk-informed regulatory contexts.
For example, a risk-informed licensing action that conformed to the American Society of Mechanical Engineers (ASME) probabilistic risk assessment (PRA) standard would benefit from having a realistic flooding risk analysis.
While the subject of the risk reassessment is of interest to the NRC, we do not plan to attend the kickoff meeting between you and your contractor scheduled for September 15 through 19, 2008.
If you believe it valuable, we would be willing to meet with you to discuss the results of that meeting and any plant reanalysis.
Our August 15, 2008, letter to you focused on the protection of the Oconee facilities in the event of a flooding situation taking into consideration the level of protection from flooding events and the available defense-in-depth.
If you have any questions on this matter, please contact Leonard N. Olshan at 301-415-1419.
Sincerely,
/RA/
Joseph G. Giitter, Director Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-269, 50-270, and 50-287 DISTRIBUTION: Non-public LPL2-1 R/F RGalloway, NRR RidsNrrDorlLpl2-1 (MWong)
RidsAcrsAcnwMailCenter RidsRgn2MailCenter (SShaeffer)
Accession Number: Pkg: ML082390650 Incoming: ML082390669 Response Ltr: ML OFFICE NRR/LPL2-1 NRR/LPL2-1/PM NRR/LPL2-1/LA DRA/DDD NRR/LPL2-1/BC NRR/DORL/DD NAME JThompson LOlshan MOBrien MGalloway*
MWong*
JGiitter DATE 8/26/08 8/26/08 8/26/08 8/26/08 8/26/08 8/26/08 OFFICIAL RECORD COPY