ML083230085

From kanterella
Jump to navigation Jump to search

Email, Boska (NRC) to Prussman (Entergy), ME0011 Acceptance Review for Indian Point 3 Relief Request
ML083230085
Person / Time
Site: Indian Point Entergy icon.png
Issue date: 11/18/2008
From: Boska J
Plant Licensing Branch 1
To: Prussman S
Entergy Nuclear Operations
Boska J, NRR, 301-415-2901
References
TAC ME0011
Download: ML083230085 (2)


Text

From: John Boska Sent: Tuesday, November 18, 2008 9:21 AM To:

'Prussman, Stephen G'

Subject:

TAC ME0011 Indian Point 3 Relief Request RR-3-44 Acceptance Review By letter dated October 20, 2008, ADAMS ML083030053, Entergy submitted a relief request for Indian Point Unit 3. The proposed relief request would use a reactor coolant system leakage test to the normal operating pressure boundary rather than the hydrostatic test to the full ASME Class 1 pressure boundary. The purpose of this letter is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staff's acceptance review of this relief request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

Pursuant to Sections 50.55a(a)(3)(i) and 50.55a(a)(3)(ii) of Title 10 of the Code of Federal Regulations (10 CFR), the applicant shall demonstrate that the proposed alternatives would provide an acceptable level of quality and safety, or that compliance with the specified requirements of Section 50.55a would result in hardship or unusual difficulty without a compensating increase in the level of quality or safety.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the proposed relief in terms of regulatory requirements and the protection of public health and safety and the environment. If additional information is needed for the staff to complete its technical review, you will be advised by separate correspondence.

If you have any questions, please contact me at 301-415-2901.

John Boska Indian Point Project Manager, DORL U.S. Nuclear Regulatory Commission 301-415-2901 email: john.boska@nrc.gov

E-mail Properties Mail Envelope Properties ()

Subject:

TAC ME0011 Indian Point 3 Relief Request RR-3-44 Acceptance Review Sent Date:

11/18/2008 8:54:40 AM Received Date:

11/18/2008 9:21:00 AM From:

John Boska Created By:

John.Boska@nrc.gov Recipients:

SPrussm@entergy.com ('Prussman, Stephen G')

Tracking Status: None Post Office:

Files Size Date & Time MESSAGE 6626 11/18/2008 Options Expiration Date:

Priority:

olImportanceNormal ReplyRequested:

False Return Notification:

False Sensitivity:

olNormal Recipients received: