From:
Nadiyah Morgan Sent:
Wednesday, October 29, 2008 12:33 PM To:
sarvers@firstenergycorp.com
Subject:
BEAVER VALLEY 1 -No. 1-TYP-3-IWB-2412 Acceptance Review (MD9733)
- Steve, By letter dated September 24,2008, FirstEnergy Nuclear Operating Company submitted a relief request for Beaver Valley Power Station, Unit No. 1 (BVPS-1). The proposed relief request would extend the inspection period so that inservice inspection of the area containing the flaw indication can be performed during the BVPS-1 spring 2009 refueling outage (1R19). The purpose of this email is to provide the results of the Nuclear Regulatory Commission (NRC) staff's acceptance review of this relief request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
Pursuant to Sections 50.55a(a)(3)(i) and 50.55a(a)(3)(ii) of Title 10 of the Code of Federal Regulations (10 CFR), the applicant shall demonstrate that the proposed alternatives would provide an acceptable level of quality and safety, or that compliance with the specified requirements of Section 50.55a would result in hardship or unusual difficulty without a compensating increase in the level of quality or safety.
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the proposed relief request in terms of regulatory requirements and the protection of public health and safety and the environment. If additional information is needed for the NRC staff to complete its technical review, you will be advised by separate correspondence.
- Thanks,
Dee E-mail Properties Mail Envelope Properties (3E54A9B051CAB64F8DA8BE1178BC8D377E77B3D3D5)
Subject:
BEAVER VALLEY 1 -No. 1-TYP-3-IWB-2412 Acceptance Review (MD9733)
Sent Date: 10/29/2008 11:46:54 AM Received Date: 10/29/2008 11:46:55 AM From: Nadiyah Morgan Created By: Nadiyah.Morgan@nrc.gov Recipients:
sarvers@firstenergycorp.com (sarvers@firstenergycorp.com)
Tracking Status: None Post Office:
HQCLSTR01.nrc.gov Files Size Date & Time MESSAGE 5355 10/29/2008 Options Expiration Date: