Extension Request for Response to Generic Letter 2008-01
ML082970163
Person / Time
Site: Nine Mile Point Constellation icon.png
Issue date: 10/28/2008
From: Richard Guzman
Plant Licensing Branch 1
To: Polson K
Nine Mile Point
Guzman R, NRR/DORL, 415-1030
References
GL-08-001, TAC MD7848
Download: ML082970163 (2)


Text

October 28, 2008 Mr. Keith J. Polson Vice President Nine Mile Point Nine Mile Point Nuclear Station, LLC P.O. Box 63 Lycoming, NY 13093

SUBJECT:

NINE MILE POINT NUCLEAR STATION, UNIT NO. 1 - RE: EXTENSION REQUEST FOR RESPONSE TO GENERIC LETTER 2008-01 (TAC NO. MD7848)

Dear Mr. Polson:

By letter dated April 10, 2008, as revised by letter dated October 6, 2008, Nile Point Nuclear Station, LLC, the licensee, submitted a 3-month response to Generic Letter 2008-01 for the Nine Mile Point Nuclear Station, Unit No. 1 (NMP1).

The U.S. Nuclear Regulatory Commission staff reviewed the licensees proposed alternative course of action, including the regulatory commitments made, and the associated basis for acceptance and has concluded that for NMP1, they are acceptable. This letter allows the licensee to implement its proposed alternative course of action.

Please contact me, if you have any questions at, (301) 415-1030.

Sincerely,

/RA/

Richard V. Guzman, Senior Project Manager Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-220 cc: Distribution via Listserv

October 28, 2008 Mr. Keith J. Polson Vice President Nine Mile Point Nine Mile Point Nuclear Station, LLC P.O. Box 63 Lycoming, NY 13093

SUBJECT:

NINE MILE POINT NUCLEAR STATION, UNIT NO. 1 - RE: EXTENSION REQUEST FOR RESPONSE TO GENERIC LETTER 2008-01 (TAC NO. MD7848)

Dear Mr. Polson:

By letter dated April 10, 2008, as revised by letter dated October 6, 2008, Nile Point Nuclear Station, LLC, the licensee, submitted a 3-month response to Generic Letter 2008-01 for the Nine Mile Point Nuclear Station, Unit No. 1 (NMP1).

The U.S. Nuclear Regulatory Commission staff reviewed the licensees proposed alternative course of action, including the regulatory commitments made, and the associated basis for acceptance and has concluded that for NMP1, they are acceptable. This letter allows the licensee to implement its proposed alternative course of action.

Please contact me, if you have any questions at, (301) 415-1030.

Sincerely,

/RA/

Richard V. Guzman, Senior Project Manager Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-220 cc: Distribution via Listserv DISTRIBUTION:

PUBLIC RidsNrrDorlLPL1-1 RidsNrrPMRGuzman (hard copy)

PDI-1 RF RidsNrrSLittle (hard copy)

RidsNrrDorlDPR RidsNrrDorlDPR RidsRgn1MailCenter RidsAcrsAcnw&mMailCenter RidsOGCRp DBeaulieu, DPR /PGCB Rids NrrDprPgcb(MMurphy)

WLyons, DSS/SRXB SSun, DSS/SRXB RidsNrrDssD(JWermeil)

Accession Number: ML082970163 NRR-106 OFFICE LPLI-1/PM LPLI-1/LA DCI/DD LPLI-1/BC NAME RGuzman SLittle JWermeil MKowal DATE 10/24/08 10/27/08 10/27/08 10/28/08 OFFICIAL RECORD COPY