E-mail, Acceptance Review for Relief Requests MD9781 and MD9783
ML082940070
Person / Time
Site: Seabrook NextEra Energy icon.png
Issue date: 10/20/2008
From: Geoffrey Miller
Plant Licensing Branch 1
To: O'Keefe M
Florida Power & Light Co, Florida Power & Light Energy Seabrook
References
TAC MD9781, TAC MD9783
Download: ML082940070 (2)


Text

From:

Ed Miller Sent:

Monday, October 20, 2008 9:14 AM To:

'michael_okeefe@fpl.com' Cc:

'gary_kilby@fpl.com'

Subject:

Acceptance Review for Relief Requests

Mike, By letters dated September 30, 2008, FPL Energy Seabrook submitted relief requests for the Seabrook Station, Unit No. 1. The first request would allow the use of a subsequent edition and addenda of the ASME Code and the second would allow for reduced ISI requirements of the pressurizer vessel welded attachments due to impracticality (TAC Nos. MD9781 and MD9783).

The purpose of this e-mail is to provide you with the results of the Nuclear Regulatory Commission (NRC) staff's acceptance review of these submittals. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The NRC staff has reviewed your submittals and concluded that it does provide technical information in sufficient detail to enable the NRC staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and protection of public health and safety and the environment.

If additional information is needed for the staff to complete its technical review, you will be advised by separate correspondence. If you have any questions, please contact me at (301) 415-2481.

G. Edward Miller Project Manager Plant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation P.S.

The other two relief requests submitted on September 30, 2008 are still undergoing their acceptance review. There will be a separate correspondence to communicate the results of those acceptance reviews.

E-mail Properties Mail Envelope Properties ()

Subject:

Acceptance Review for Relief Requests Sent Date: 10/20/2008 8:49:19 AM Received Date: 10/20/2008 9:14:00 AM From: Ed Miller

Created By: Ed.Miller@nrc.gov Recipients:

michael_okeefe@fpl.com ('michael_okeefe@fpl.com')

Tracking Status: None gary_kilby@fpl.com ('gary_kilby@fpl.com')

Tracking Status: None Post Office:

Files Size Date & Time MESSAGE 9293 10/20/2008 Options Expiration Date:

Priority: olImportanceNormal ReplyRequested: False Return Notification: False Sensitivity: olNormal Recipients received: