MONTHYEARML24025A0922024-01-25025 January 2024 Requalification Program Inspection L-23-267, Submittal of Discharge Monitoring Report (Npdes), Permit No. PA00256152023-12-18018 December 2023 Submittal of Discharge Monitoring Report (Npdes), Permit No. PA0025615 IR 05000334/20230112023-12-0404 December 2023 Age-Related Degradation Inspection Report 05000334/2023011 and 05000412/2023011 L-23-229, Request for Additional Information Regarding the Spring 2023 Generic Letter 95-05 Voltage-Based Alternate Repair Criteria and Steam Generator F-Star Reports2023-11-29029 November 2023 Request for Additional Information Regarding the Spring 2023 Generic Letter 95-05 Voltage-Based Alternate Repair Criteria and Steam Generator F-Star Reports IR 05000334/20233012023-11-27027 November 2023 Initial Operator Licensing Examination Report 05000334/2023301 L-23-247, Discharge Monitoring Report (NPDES) Permit No. PA00256152023-11-17017 November 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 IR 05000334/20230032023-11-0606 November 2023 Integrated Inspection Report 05000334/2023003 and 05000412/2023003 L-23-227, Discharge Monitoring Report (NPDES) Permit No. PA0025615 for Third Quarter 20232023-10-20020 October 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 for Third Quarter 2023 ML23279A0612023-10-0505 October 2023 Paragon Energy Solutions LLC, Part 21 Final Report Re Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23198A3592023-10-0202 October 2023 Issuance of Amendment Nos. 322 and 212 Analytical Methodology to the Core Operating Limits Report for a Full Spectrum Loss of Coolant Accident (EPID L-2022-LLA-0129) - Nonproprietary IR 05000334/20234022023-09-29029 September 2023 Security Baseline Inspection Report 05000334/2023402 and 05000412/2023402 (Cover Letter Only) ML23237B4222023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Letter Regarding Order Approving Transfer of Licenses and Draft Conforming License Amendments ML23269A1242023-09-27027 September 2023 Request for Withholding Information from Public Disclosure IR 05000334/20234012023-09-21021 September 2023 Cybersecurity Inspection Report 05000334/2023401 and 05000412/2023401 (Cover Letter Only) ML23263A0192023-09-20020 September 2023 Operator Licensing Examination Approval ML23243A9272023-09-19019 September 2023 Review of the Fall 2022 Steam Generator Tube Inspection Report ML23249A1842023-09-18018 September 2023 Authorization and Safety Evaluation for Alternative Request No. 2-TYP-4-RV-06 L-23-208, Submittal of Discharge Monitoring Report Cnpdes), Permit No. PA00256152023-09-14014 September 2023 Submittal of Discharge Monitoring Report Cnpdes), Permit No. PA0025615 L-23-167, Twenty-Third Refueling Outage Inservice Inspection Summary Report2023-09-13013 September 2023 Twenty-Third Refueling Outage Inservice Inspection Summary Report L-23-205, Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-09-12012 September 2023 Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments IR 05000334/20230052023-08-31031 August 2023 Updated Inspection Plan for Beaver Valley Power Station Units 1 and 2 (Report 05000334/2023005 and 05000412/2023005) L-23-172, Quality Assurance Program Manual2023-08-31031 August 2023 Quality Assurance Program Manual ML23129A1722023-08-25025 August 2023 Request for Withholding Information from Public Disclosure for Beaver Valley Power Station, Units 1 and 2; Davis Besse Nuclear Power Station, Unit 1; and Perry Nuclear Power Plant, Unit 1 IR 05000334/20230022023-08-0909 August 2023 Integrated Inspection Report 05000334/2023002 and 05000412/2023002 ML23219A0592023-08-0707 August 2023 Steam Generator Inspection Reports - Spring 2023 Spring Refueling Outrage L-23-188, Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-08-0707 August 2023 Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-179, Submittal of Discharge Monitoring Report, (NPDES) Permit No. PA00256152023-07-18018 July 2023 Submittal of Discharge Monitoring Report, (NPDES) Permit No. PA0025615 ML23188A0982023-07-17017 July 2023 Correction to the Safety Evaluation Issued Related to Amendment Nos. 321 and 211 Consolidate Fuel Decay Time Technical Specifications in a New Limiting Condition for Operation Titled Decay Time ML23188A0672023-07-10010 July 2023 Project Manager Assignment L-23-165, Discharge Monitoring Report (NPDES) Permit No. PA00256152023-06-26026 June 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-23-139, Response to Request for Additional Information Regarding Fall 2022 180-Day Steam Generator Tube Inspection Report2023-06-13013 June 2023 Response to Request for Additional Information Regarding Fall 2022 180-Day Steam Generator Tube Inspection Report ML23157A1072023-06-0707 June 2023 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000334/2023011 and 05000412/2023011 ML23143A0272023-05-23023 May 2023 Licensed Operator Positive Fitness-For-Duty Test L-23-055, Submittal of the Updated Final Safety Analysis Report, Revision 342023-05-23023 May 2023 Submittal of the Updated Final Safety Analysis Report, Revision 34 ML23102A1472023-05-22022 May 2023 Issuance of Amendment Nos. 321 and 211 Consolidate Fuel Decay Time Technical Specifications in a New Limiting Condition for Operation Titled Decay Time L-23-065, Annual Financial Report2023-05-22022 May 2023 Annual Financial Report ML23135A7872023-05-19019 May 2023 Summary of Conference Calls Regarding the Spring 2023 Steam Generator Tube Inspections L-23-137, Discharge Monitoring Report (NPDES) Permit No. PA00256152023-05-18018 May 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 ML23124A1742023-05-17017 May 2023 Energy Harbor Fleet Vistra License Transfer - Request for Withholding Information from Public Disclosure for Commance Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 L-23-125, Cycle 24 Core Operating Limits Report2023-05-17017 May 2023 Cycle 24 Core Operating Limits Report ML23124A3882023-05-16016 May 2023 Summary of Regulatory Audit in Support of License Amendment Request to Revise Technical Specification 5.6.3, Core Operating Limits Reports (COLR) and TS 4.2.1 Fuel Assemblies ML23129A0112023-05-16016 May 2023 Notice of Consideration of Approval of Indirect and Direct License Transfer for Comanche Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 (EPID L-2023-LLM-0000) (Letter) L-23-132, Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations2023-05-10010 May 2023 Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations IR 05000334/20230012023-05-0808 May 2023 Integrated Inspection Report 05000334/2023001 and 05000412/2023001 L-23-129, Response to Request for Additional Information for 10 CFR 50.55a Request 2-TYP-4-RV-06 for Alternative Repair Methods for Reactor Pressure Vessel Head Penetrations2023-05-0505 May 2023 Response to Request for Additional Information for 10 CFR 50.55a Request 2-TYP-4-RV-06 for Alternative Repair Methods for Reactor Pressure Vessel Head Penetrations ML23118A3812023-04-28028 April 2023 10 CFR 50.55a Request 2-TYP-4-RV-06 for Alternative Repair Methods for Reactor Pressure Vessel Head Penetrations L-23-115, Submittal of 2022 Annual Radioactive Effluent Release Report, 2022 Annual Radiological Environmental Operating Report, and 2022 Annual Environmental Operating Report (Non-Radiological2023-04-27027 April 2023 Submittal of 2022 Annual Radioactive Effluent Release Report, 2022 Annual Radiological Environmental Operating Report, and 2022 Annual Environmental Operating Report (Non-Radiological L-23-126, Discharge Monitoring Report (Npdes), Permit No. PA00256152023-04-22022 April 2023 Discharge Monitoring Report (Npdes), Permit No. PA0025615 CP-202300181, ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, ISFSI, Corrected Affidavit for Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-04-20020 April 2023 ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, ISFSI, Corrected Affidavit for Application for Order Consenting to Transfer of Licenses and Conforming License Amendments ML23107A2502023-04-18018 April 2023 Requalification Program Inspection 2024-01-25
[Table view] |
Text
October 1, 2008 Ms. Susan M. Pierce Deputy State Historic Preservation Officer West Virginia Division of Culture & History The Culture Center 1900 Kanawha Blvd., E.
Charleston, WV 25305-0300
SUBJECT:
BEAVER VALLEY POWER STATION LICENSE RENEWAL APPLICATION REVIEW (FR#: 07-206-HK)
Dear Ms. Pierce:
The U.S. Nuclear Regulatory Commission (NRC) staff is reviewing an application to renew the operating license for the Beaver Valley Power Station (BVPS), Units 1 and 2, which is located in Shippingport, PA about 25 miles northwest of Pittsburgh, PA. BVPS is owned and operated by FirstEnergy Nuclear Operating Company. As part of its review of the proposed action, the NRC staff has prepared a site-specific Supplemental Environmental Impact Statement (SEIS) to its AGeneric Environmental Impact Statement for License Renewal of Nuclear Plants,@ NUREG-1437. The SEIS includes analyses of relevant environmental issues, including potential impacts to historic, archeological and cultural properties from extended operation and refurbishment activities associated with license renewal. In accordance with our letter to you dated November 2, 2007, a copy of the draft supplement is enclosed. Pursuant to 36 CFR 800.8(c),
we are requesting your comments on the draft supplement and on our preliminary conclusions regarding historic properties.
As stated in our November 2, 2007, letter the NRC staff has determined that the area of potential effect (APE) for a license renewal action is the area at the power plant site and its immediate environs that may be impacted by post-license renewal land disturbing operation or projected refurbishment activities associated with the proposed action. The staff views the APE for the BVPS license renewal as including the BVPS site and the immediate environs.
The NRC staff has conducted an environmental audit at the site and has reviewed historic and archaeological records. The NRC staff also contacted fifteen Native American Tribes identified as having potential interest in the proposed undertaking. To date, no comments have been received.
In the context of the National Environmental Policy Act of 1969, under which the draft environmental impact statement was prepared, the NRC staff=s preliminary determination is that the impact of license renewal on historical and archaeological resources is small, and additional mitigation is not warranted. Under the provisions of the National Historic Preservation Act of 1966, the NRC staff=s preliminary determination is that no historic properties will be affected by the proposed action.
S. Pierce Please note that the period for public comment expires on December 3, 2008. If your office requires additional time, or if there are any other questions regarding this correspondence, please have your representative contact the NRC Project Manager, Mr. Emmanuel Sayoc, at 301-415-1924 or Emmanuel.Sayoc@nrc.gov.
Sincerely,
\RA\
Rani Franovich, Branch Chief Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-334 and 50-412
Enclosure:
As stated cc w/encl: See next page
- 1. Letter w/Svc List, FRN: ML2620404
- 2. ?Generic Environmental Impact Statement for License Renewal of Nuclear Plants, Supplement 36@: ML082600147
- 3. Pkg: ML082630506 OFFICE LA:DLR: PM:DLR:RPB2 PM:DLR:RPB2 BCDLR:RPB2 NAME SFigueroa ESayoc KHoward RFranovich DATE 09/23/08 09/26/08 09/26/08 10/01/08
Letter to B. Franco from R. Franovich dated October 01, 2008 DISTRIBUTION:
SUBJECT:
BEAVER VALLEY POWER STATION LICENSE RENEWAL APPLICATION REVIEW (SHPO NO. ER 85-0426-007-C)
E-MAIL B. Holian (RidsNrrDlr)
S. Lee (RidsNrrDlr)
R. Franovich (RidsNrrDlrRpb2)
B. Pham (RidsNrrDlrRerb)
R. Schaaf K. Howard E. Sayoc N. Morgan R. Barkley M. McLaughlin E. Brenner D. Screnci D. Werkheiser L.Subin N. Sheehan RidsOGCMailRoom DLR/RPB2 DLR/RERB
Beaver Valley Power Station, Units 1 and 2 cc:
Joseph J. Hagan Ohio EPA-DERR President and Chief Nuclear Officer ATTN: Zack A. Clayton FirstEnergy Nuclear Operating Company P.O. Box 1049 Mail Stop A-GO-19 Columbus, OH 43266-0149 76 South Main Street Akron, OH 44308 Peter P. Sena III Site Vice President James H. Lash FirstEnergy Nuclear Operating Company Senior Vice President of Operations Beaver Valley Power Station and Chief Operating Officer Mail Stop A-BV-SEB-1 FirstEnergy Nuclear Operating Company P.O. Box 4, Route 168 Mail Stop A-GO-14 Shippingport, PA 15077 76 South Main Street Akron, OH 44308 Director, Fleet Regulatory Affairs FirstEnergy Nuclear Operating Company Danny L. Pace Mail Stop A-GO-2 Senior Vice President, Fleet Engineering 76 South Main Street FirstEnergy Nuclear Operating Company Akron, Ohio 44308 Mail Stop A-GO-14 76 South Main Street Manager, Site Regulatory Compliance Akron, OH 44308 FirstEnergy Nuclear Operating Company Beaver Valley Power Station Jeannie M. Rinckel Mail Stop A-BV-A Vice President, Fleet Oversight P.O. Box 4, Route 168 FirstEnergy Nuclear Operating Company Shippingport, PA 15077 Mail Stop A-GO-14 76 South Main Street Richard Anderson Akron, OH 44308 Vice President, Nuclear Support FirstEnergy Nuclear Operating Company David W. Jenkins, Attorney Mail Stop A-GO-14 FirstEnergy Corporation 76 South Main Street Mail Stop A-GO-15 Akron, OH 44308 76 South Main Street Akron, OH 44308 Commissioner James R. Lewis Manager, Fleet Licensing West Virginia Division of Labor FirstEnergy Nuclear Operating Company 749-B, Building No. 6 Mail Stop A-GO-2 Capitol Complex 76 South Main Street Charleston, WV 25305 Akron, OH 44308 Director, Utilities Department Public Utilities Commission 180 East Broad Street Columbus, OH 43266-0573
Beaver Valley Power Station, Units 1 and 2 cc:
Jennifer Kagel Cliff Custer Pennsylvania Field Office FirstEnergy Nuclear Operating Company 315 South Allen St. Suite 322 Beaver Valley Power Station State College, PA 16801-4850 P.O. Box 4, Route 168 Shippingport, PA 15077 Director, Pennsylvania Emergency Management Agency Mike Banko 2605 Interstate Dr. FirstEnergy Nuclear Operating Company Harrisburg, PA 17110-9364 Beaver Valley Power Station P.O. Box 4, Route 168 Dr. Judith Johnsrud Shippingport, PA 15077 Environmental Coalition on Nuclear Power Sierra Club Julie Firestone 433 Orlando Avenue FirstEnergy Nuclear Operating Company State College, PA 16803 Beaver Valley Power Station P.O. Box 4, Route 168 Director Shippingport, PA 15077 Bureau of Radiation Protection Pennsylvania Department of Sherry White Environmental Protection Cultural Preservation Officer Rachel Carson State Office Building Stockbridge-Munsee Band of the Mohican P.O. Box 8469 Nation, Wisconsin Harrisburg, PA 17105-8469 Route 1, P.O. Box 70 Bowler, WI 54416 Mayor of the Borough of Shippingport P.O. Box 3 Greg Bunker Shippingport, PA 15077 Director Environmental/NEPA Stockbridge-Munsee Band of the Mohican Regional Administrator, Region I Nation, Wisconsin U.S. Nuclear Regulatory Commission Route 1, P.O. Box 70 475 Allendale Road Bowler, WI 54416 King of Prussia, PA 19406 Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 298 Shippingport, PA 15077 Tony Gonyea Onondaga Nation RR#1, Route 11A Box 319B Via Nedrow, NY 13120