IR 05000346/2008403

From kanterella
(Redirected from ML082030631)
Jump to navigation Jump to search
IR 05000346-08-403, (Drs), on 06/09/2008 - 06/13/2008, Davis-Besse, Routine Security Baseline Inspection - Cover Letter
ML082030631
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 07/15/2008
From: Eric Duncan
Plant Support Branch II
To: Allen B
FirstEnergy Nuclear Operating Co
References
IR-08-403
Download: ML082030631 (4)


Text

July 15, 2008

SUBJECT:

DAVIS-BESSE NUCLEAR POWER STATION

NRC SECURITY BASELINE INSPECTION REPORT 05000346/2008403(DRS)

Dear Mr. Allen:

On June 13, 2008, the U.S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at your Davis-Besse Nuclear Power Station. The inspection covered one or more of the key attributes of the security cornerstone of the NRCs Reactor Oversight Process.

The enclosed inspection report documents the inspection results, which were discussed on June 13, 2008, with you and other members of your staff.

The inspection examined activities conducted under your license as they relate to security and compliance with the Commissions rules and regulations and with the conditions of your license.

The inspector reviewed selected procedures and records, observed activities, and interviewed personnel.

No findings of significance were identified.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

However, because of the security-related concerns contained in the enclosures, and in accordance with 10 CFR 2.390, a copy of this letters enclosure will not be available for public inspection.

Enclosure Contains Sensitive Unclassified Non-Safeguards Information. Upon separation, this page is decontrolled. Should you have any questions concerning this inspection, we will be pleased to discuss them with you.

Sincerely,

/RA by D. Funk for/

Eric Duncan, Chief Plant Support Branch Division of Reactor Safety

Docket No. 50-346 License No. NPF-3

Nonpublic Enclosure: Inspection Report 05000346/2008403(DRS);

w/Attachment: Supplemental Information

cc w/encl:

D. Riffle, NSIR/DSO/DDSO

C. OClaire, State Liaison Officer

Ohio Emergency Management Agency

cc w/o encl:

The Honorable Dennis Kucinich

J. Hagan, President and Chief

Nuclear Officer - FENOC

J. Lash, Senior Vice President of

Operations and Chief Operating Officer - FENOC

Manager - Site Regulatory Compliance - FENOC

D. Pace, Senior Vice President of

Fleet Engineering - FENOC

J. Rinckel, Vice President, Fleet Oversight - FENOC

P. Harden, Vice President, Nuclear Support

D. Jenkins, Attorney, FirstEnergy Corp.

Director, Fleet Regulatory Affairs - FENOC

Manager - Fleet Licensing - FENOC

R. Owen, Administrator, Ohio Department of Health

Public Utilities Commission of Ohio

President, Lucas County Board of Commissioners

President, Ottawa County Board of Commissioners