MONTHYEARML0810102072008-04-0303 April 2008 Diablo Canon, Units 1 & 2 - License Amendment Request 08-02, Revision to Technical Specification 3.7.5, Auxiliary Feedwater System and 3.7.6 Condensate Storage Tank and Fire Water Storage Tank Project stage: Other ML0815405402008-06-0404 June 2008 Amendments Auxiliary Feedwater and Condensate Storage Tanks (TACs MD8471 and MD8472) Project stage: Other DCL-08-023, Supplement to License Amendment Request 08-02, Revision to Technical Specifications 3.7.5, 'Auxiliary Feedwater System,' and 3.7.6, 'Condensate Storage Tank and Fire Water Storage Tank.2008-06-20020 June 2008 Supplement to License Amendment Request 08-02, Revision to Technical Specifications 3.7.5, 'Auxiliary Feedwater System,' and 3.7.6, 'Condensate Storage Tank and Fire Water Storage Tank. Project stage: Supplement ML0825404362008-07-24024 July 2008 Email Sending Request for Additional Information, Revise TS 3.7.5, Auxiliary Feedwater System and 3.7.6, Condensate Storage Tank and Fire Water Storage Tank Project stage: RAI ML0825404962008-07-24024 July 2008 Draft Diablo Canyon, Units 1 and 2, Request for Additional Information, Revise TS 3.7.5, Auxiliary Feedwater System and 3.7.6, Condensate Storage Tank and Fire Water Storage Tank Project stage: Draft RAI ML0820407482008-08-0101 August 2008 Acceptance Review of Proposed Amendments Revision to Technical Specifications 3.7.5, 'Auxiliary Feedwater System,' & 3.7.6, 'Condensate Storage Tank & Fire Water Storage Tank (Tac Nos. MD8471 and MD8472) Project stage: Acceptance Review ML0828314432008-09-21021 September 2008 CST Rai'S (Email) Project stage: Other ML0826702672008-09-21021 September 2008 Request for Additional Information on Condensate Storage Tank Level Amendment Project stage: RAI DCL-08-081, Response to Request for Additional Information, License Amendment Request 08-02, Revision to Technical Specifications 3.7.5, 'Auxiliary Feedwater System,' and 3.7.6, 'Condensate Storage Tank and Fire Water Storage Tank.'2008-10-0101 October 2008 Response to Request for Additional Information, License Amendment Request 08-02, Revision to Technical Specifications 3.7.5, 'Auxiliary Feedwater System,' and 3.7.6, 'Condensate Storage Tank and Fire Water Storage Tank.' Project stage: Response to RAI ML0906904322008-11-0404 November 2008 Unit Nos.1 and 2 - Email Request for Additional Information Re License Amendment Request Project stage: RAI DCL-08-093, Response to NRC Request for Additional Information Regarding License Amendment Request 08-02, Revision to Technical Specifications 3.7.5, 'Auxiliary Feedwater System,' and 3.7.6, 'Condensate Storage Tank and Fire Water..2008-11-0606 November 2008 Response to NRC Request for Additional Information Regarding License Amendment Request 08-02, Revision to Technical Specifications 3.7.5, 'Auxiliary Feedwater System,' and 3.7.6, 'Condensate Storage Tank and Fire Water.. Project stage: Response to RAI ML0906902942008-11-21021 November 2008 Meeting Slide, Spectra 6.5 Slide from Pacific Gas and Electric Regarding License Amendment Request Re AFW System and CST, Diablo Canyon Power Plant, Unit Nos. 1 and 2 Project stage: Meeting ML0906902422008-11-21021 November 2008 Email from Pacific Gas and Electric Regarding Spectra 6.5 Slide, License Amendment Request Re AFW System and CST Project stage: Request DCL-08-106, Response to NRC RAI Regarding License Amendment Request 08-02, Revision to Technical Specifications 3.7.5, 'Auxiliary Feedwater System,' and 3.7.6, 'Condensate Storage Tank and Fire Water Storage Tank2008-12-16016 December 2008 Response to NRC RAI Regarding License Amendment Request 08-02, Revision to Technical Specifications 3.7.5, 'Auxiliary Feedwater System,' and 3.7.6, 'Condensate Storage Tank and Fire Water Storage Tank Project stage: Response to RAI ML0906308082009-03-30030 March 2009 Issuance of Amendment Nos. 204 and 205, Revise TS 3.7.5, Auxiliary Feedwater (AFW) System, and TS 3.7.6, Condensate Storage Tank (CST) and Fire Water Storage Tank (Fwst) Project stage: Approval 2008-04-03
[Table View] |
|
---|
Category:Letter
MONTHYEARML24302A2622024-11-0101 November 2024 Letter to CA SHPO Regarding DCPP Dseis ML24302A2612024-11-0101 November 2024 Letter to Achp Re DCPP Dseis ML24275A0622024-10-30030 October 2024 NRC to NMFS Request Initiate Formal Endangered Species Act Consultation and Abbreviated Essential Fish Habitat for Proposed License Renewal of DCP Plant Units 1, 2 ML24269A0122024-10-29029 October 2024 OEDO-24-00083 2.206 Petition Diablo Canyon Seismic CDF - Response to Petitioner Letter ML24261B9492024-10-24024 October 2024 Issuance of Amendment Nos. 246 and 248 Revision to Technical Specification 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR) DCL-24-103, Pg&Es Voluntary Submittal of Information Related to 10 CFR 2.206 Petition Regarding Seismic Core Damage Frequency for DCPP, Units 1 and 22024-10-24024 October 2024 Pg&Es Voluntary Submittal of Information Related to 10 CFR 2.206 Petition Regarding Seismic Core Damage Frequency for DCPP, Units 1 and 2 IR 05000275/20244042024-10-23023 October 2024 Security Baseline Inspection Report 05000275/2024404 and 05000323/2024404 ML24277A0292024-10-18018 October 2024 NRC to Fws Req. for Concurrence W. Endangered Species Act Determinations for Diablo Canyon Power Plant Units 1,2, ISFSI Proposed License Renewals in San Luis Obispo Co., CA DCL-24-092, Supplement and Annual Update License Renewal Application, Amendment 12024-10-14014 October 2024 Supplement and Annual Update License Renewal Application, Amendment 1 DCL-24-098, Material Status Report for the Period Ending August 31, 20242024-10-0909 October 2024 Material Status Report for the Period Ending August 31, 2024 DCL-24-091, Response to Request for Additional Information by the Office of Nuclear Reactor Regulation2024-10-0303 October 2024 Response to Request for Additional Information by the Office of Nuclear Reactor Regulation IR 05000275/20253012024-10-0303 October 2024 Notification of NRC Initial Operator Licensing Examination 05000275/2025301; 05000323/2025301 ML24240A0222024-09-20020 September 2024 Letter to A. Peck Environmental Impact Statement Scoping Summary Report for Diablo Canyon Nuclear Power Plant Units 1 and 2 ML24260A1222024-09-14014 September 2024 14 Sept 2024 Ltr - California Coastal Commission to Pg&E, Incomplete Consistency Certification for Requested Nuclear Regulatory Commission License Renewal for Diablo Canyon Power Plant DCL-24-087, License Renewal - Historic and Cultural Resources Reference Documents (Redacted)2024-09-12012 September 2024 License Renewal - Historic and Cultural Resources Reference Documents (Redacted) ML24262A2462024-09-11011 September 2024 10 CFR 2.206 - Diablo Canyon Units 1 and 2 Seismic - Petitioner Response to Acknowledgement Letter - DCL-24-083, CFR Part 21 Notification: Commercially Dedicated Snubber Valve Not Properly Heat Treated2024-09-0909 September 2024 CFR Part 21 Notification: Commercially Dedicated Snubber Valve Not Properly Heat Treated DCL-24-078, Pre-Notice of Disbursement from Decommissioning Trust2024-09-0303 September 2024 Pre-Notice of Disbursement from Decommissioning Trust DCL-24-082, Decommissioning Draft Biological Assessment and Draft Essential Fish Habitat Assessment2024-08-28028 August 2024 Decommissioning Draft Biological Assessment and Draft Essential Fish Habitat Assessment ML24205A0662024-08-27027 August 2024 OEDO-24-00083 - 10 CFR 2.206 - Ack Letter - Diablo Canyon Units 1 and 2 Seismic Core Damage Frequency - IR 05000275/20243012024-08-26026 August 2024 NRC Examination Report 05000275/2024301; 05000323/2024301 IR 05000275/20240052024-08-22022 August 2024 Updated Inspection Plan for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2024005 and 05000323/2024005) DCL-24-077, Responses to NRC Requests for Additional Information on Diablo Canyon Power License Renewal Application Severe Accident2024-08-15015 August 2024 Responses to NRC Requests for Additional Information on Diablo Canyon Power License Renewal Application Severe Accident DCL-24-075, Response to Request for Additional Information for License Amendment Request 23-02, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power React2024-08-0808 August 2024 Response to Request for Additional Information for License Amendment Request 23-02, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power React IR 05000275/20240022024-08-0606 August 2024 Integrated Inspection Report 05000275/2024002 and 05000323/2024002 DCL-24-079, DC-2024-07 Post Exam Comments Analysis2024-08-0202 August 2024 DC-2024-07 Post Exam Comments Analysis DCL-24-070, License Amendment Request 24-03 Revision to Technical Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies2024-07-31031 July 2024 License Amendment Request 24-03 Revision to Technical Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies DCL-24-071, Core Operating Limits Report for Unit 2 Cycle 252024-07-22022 July 2024 Core Operating Limits Report for Unit 2 Cycle 25 DCL-2024-523, Submittal of Report on Discharge Self-Monitoring2024-07-18018 July 2024 Submittal of Report on Discharge Self-Monitoring ML24187A1352024-07-16016 July 2024 Letter to Paula Gerfen - Diablo Canyon Units 1 and 2 - Summary of June 2024 Audit Related to the License Renewal Application Severe Accident Mitigation Alternatives Review IR 05000275/20240142024-07-11011 July 2024 Age-Related Degradation Inspection Report 05000275/2024014 and 05000323/2024014 ML24190A0812024-07-10010 July 2024 NRC Initial Operator Licensing Examination Approval 05000275/2024301; 05000323/2024301 IR 05000275/20244012024-07-0808 July 2024 Security Baseline Inspection Report 05000275/2024401 and 05000323/2024401 (Full Report) IR 05000323/20240112024-07-0303 July 2024 License Renewal Phase Report 05000323/2024011 DCL-2024-527, Sea Turtle Stranding Report (Loggerhead Sea Turtle) Diablo Canyon Power Plant2024-07-0101 July 2024 Sea Turtle Stranding Report (Loggerhead Sea Turtle) Diablo Canyon Power Plant DCL-24-066, Request to Extend the Nrg Approval of Alternative for Use of Full Structural Weld Overlay, REP-RHR-SWOL2024-06-27027 June 2024 Request to Extend the Nrg Approval of Alternative for Use of Full Structural Weld Overlay, REP-RHR-SWOL ML24155A2182024-06-18018 June 2024 OEDO-23-00350-NRR - (LTR-23-0228-1) - Closure Letter - 10 CFR 2.206 Petition from Mothers for Peace and Friends of the Earth Regarding Diablo Canyon ML24129A1762024-06-14014 June 2024 National Historic Preservation Act Section 106 Consultation – Results of Identification and Evaluation (Docket Number: 72-026) ML24200A2052024-06-0707 June 2024 Fws to NRC, List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Your Proposed Project for Diablo Canyon License Renewal ML24099A2192024-05-29029 May 2024 Issuance of Amendment Nos. 245 and 247 Revision to TSs to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24117A0132024-05-20020 May 2024 Letter to Paula Gerfen-Diablo Canyon Units 1 and 2-Regulatory Audit Regarding Severe Accident Mitigation Alternatives for the License Renewal Application 05000323/LER-2024-001, LCO 3.0.3 Completion Time Limits2024-05-17017 May 2024 LCO 3.0.3 Completion Time Limits DCL-24-052, Responses to NRC Requests for Additional Information on the Diablo Canyon Power Plant License Renewal Application Environmental Report2024-05-16016 May 2024 Responses to NRC Requests for Additional Information on the Diablo Canyon Power Plant License Renewal Application Environmental Report DCL-24-051, One Hundred Eighty Day Steam Generator Report for Twenty-Fourth Refueling Outage2024-05-0808 May 2024 One Hundred Eighty Day Steam Generator Report for Twenty-Fourth Refueling Outage ML24127A2042024-05-0202 May 2024 02May2024 Ltr - California Coastal Commission to Pg&E, Coastal Development Permit Needed for Pg&E’S Proposed Relicensing of Diablo Canyon Nuclear Power Plant DCL-24-047, 2023 Annual Non-radiological Environmental Operating Report2024-05-0101 May 2024 2023 Annual Non-radiological Environmental Operating Report DCL-24-049, 2023 Annual Radiological Environmental Operating Report2024-05-0101 May 2024 2023 Annual Radiological Environmental Operating Report L-24-004, Independent Spent Fuel Storage Installation - Responses to NRC Requests for Additional Information on the Diablo Canyon Independent Spent Fuel Storage Installation License Renewal Application (Cac/Epid 001028/L-2022-RNW-0007)2024-04-30030 April 2024 Independent Spent Fuel Storage Installation - Responses to NRC Requests for Additional Information on the Diablo Canyon Independent Spent Fuel Storage Installation License Renewal Application (Cac/Epid 001028/L-2022-RNW-0007) DCL-24-048, O CFR 50.59 and 1 O CFR 72.48 Summary Report for the Period of January 1, 2022, Through December 31, 20232024-04-30030 April 2024 O CFR 50.59 and 1 O CFR 72.48 Summary Report for the Period of January 1, 2022, Through December 31, 2023 DCL-24-027, 2023 Annual Radioactive Effluent Release Report2024-04-28028 April 2024 2023 Annual Radioactive Effluent Release Report 2024-09-09
[Table view] |
Text
June 4, 2008 Mr. John Conway Senior Vice President - Station Generation and Chief Nuclear Officer Pacific Gas and Electric Company Diablo Canyon Power Plant P.O. Box 770000 San Francisco, CA 94177-0001
SUBJECT:
DIABLO CANYON POWER PLANT, UNIT NOS. 1 AND 2 - AMENDMENTS RE:
AUXILARY FEEDWATER AND CONDENSATE STORAGE TANKS (TAC NOS.
MD8471 AND MD8472)
Dear Mr. Conway:
By letter dated April 3, 2008, Pacific Gas and Electric Company, the licensee, submitted a license amendment request for Diablo Canyon Power Plant, Unit Nos. 1 and 2 (DCPP). The proposed amendment would revise Technical Specification (TS) 3.7.5, Auxiliary Feedwater System, to remove Surveillance Requirement 3.7.5.6, and revise TS 3.7.6, Condensate Storage Tank (CST) and Fire Water Storage Tank (FWST), to remove the FWST level requirements, revise the CST level requirements, and revise TS 3.7.6 to be consistent with the NUREG-1431 Standard Technical Specifications. The purpose of this letter is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this amendment. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review.
The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an amendment to the license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required.
This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.
The NRC staff has reviewed your application and concluded that the information delineated in the enclosure to this letter is necessary to enable the staff to make an independent assessment regarding the acceptability of the proposed amendment request in terms of regulatory requirements and the protection of public health and safety and the environment.
In order to make the application complete, the NRC staff requests that PG&E supplement the application to address the information requested in the enclosure by June 20, 2008. This will enable the NRC staff to begin its detailed technical review. If the information responsive to the
J. Conway NRC staffs request is not received by the above date, the application will not be accepted for review pursuant to 10 CFR 2.101, and the NRC will cease its review activities associated with the application. If the application is subsequently accepted for review, you will be advised of any further information needed to support the staffs detailed technical review by separate correspondence.
The information requested and associated time frame in this letter were discussed with Mr. Ken Shrader of your staff on June 2, 2008.
If you have any questions, please contact me at (301) 415-1445.
Sincerely,
/RA/
Alan Wang, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-275 and 50-323
Enclosure:
As stated cc w/encl: See next page
ML081540540 OFFICE NRR/DORL/PM NRR/DORL/LA NRR/DSS/SBPB/BC NRR/DORL/BC NAME AWang GLappert DHarrison THiltz DATE 6/2/08 6/2/08 6/4/08, w/edits 6/4/08 Diablo Canyon Power Plant, Units 1 and 2 (3/10/2008 2007) cc:
NRC Resident Inspector City Editor Diablo Canyon Power Plant The Tribune c/o U.S. Nuclear Regulatory Commission 3825 South Higuera Street P.O. Box 369 P.O. Box 112 Avila Beach, CA 93424 San Luis, Obispo, CA 94306-0112 Sierra Club San Lucia Chapter Director, Radiologic Health Branch ATTN: Andrew Christie State Department of Health Services P.O. Box 15755 P.O. Box 997414, MS 7610 San Luis Obispo, CA 93406 Sacramento, CA 95899-7414 Ms. Nancy Culver Mr. James Boyd, Commissioner San Luis Obispo California Energy Commission Mothers for Peace 1516 Ninth Street MS (31)
P.O. Box 164 Sacramento, CA 95831 Pismo Beach, CA 93448 Mr. James R. Becker Chairman Site Vice President San Luis Obispo County Diablo Canyon Power Plant Board of Supervisors P.O. Box 56 1055 Monterey Street, Suite D430 Avila Beach, CA 93424 San Luis Obispo, CA 93408 Jennifer Tang Mr. Truman Burns Field Representative Mr. Robert Kinosian United States Senator Barbara Boxer California Public Utilities Commission 1700 Montgomery Street, Suite 240 505 Van Ness, Room 4102 San Francisco, CA 94111 San Francisco, CA 94102 Diablo Canyon Independent Safety Committee Attn: Robert R. Wellington, Esq.
Legal Counsel 857 Cass Street, Suite D Monterey, CA 93940 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064 Jennifer Post, Esq.
Pacific Gas & Electric Company P.O. Box 7442 San Francisco, CA 94120
IDENTIFICATION OF INFORMATION INSUFFICIENCY BY THE OFFICE OF NUCLEAR REACTOR REGULATION REGARDING CONDENSATE STORAGE TANK AMENDMENT REQUEST FOR DIABLO CANYON POWER PLANT, UNIT NOS. 1 AND 2 DOCKET NOS. 50-275 AND 50-323 By letter dated April 3, 2008, Pacific Gas and Electric Company, the licensee submitted a license amendment request (LAR) for Diablo Canyon Power Plant, Unit Nos. 1 and 2 (DCPP).
The proposed amendment would revise Technical Specification (TS) 3.7.5, Auxiliary Feedwater System, to remove Surveillance Requirement 3.7.5.6, and revise TS 3.7.6, Condensate Storage Tank (CST) and Fire Water Storage Tank (FWST), to remove the FWST level requirements, revise the CST level requirements, and revise TS 3.7.6 to be consistent with the NUREG-1431 Standard Technical Specifications. As part of the acceptance review process the NRC staff has concluded that the information delineated below is necessary to enable the NRC staff to make an independent assessment regarding the acceptability of the proposed amendment request in terms of regulatory requirements and the protection of public health and safety and the environment:
- 1) On page 2 of the LAR, the licensee states, The revised CST minimum storage usable volume calculations are being performed by PG&E under 10 CFR 50.59, and NRC review of the calculations is not being requested. The NRC staff request that this calculation and supporting documentationbe provided for our review as it is the basis for the revised CST minimum volume.
- 2) The licensee bases the TS change on the ability of the CST to hold an increased volume of water. The calculations or documentation supporting this premise is needed by the NRC staff for performance of this review. In particular, the NRC staff requests the licensee supplement the application with sufficient documentation and detailed analysis to justify how the CST usable volume has increased from 164,678 gallons to 220,600 gallons.
- 3) The LAR mentions modifications adding plenum inside the tank to raise the intake level for this piping in the event of a downstream pipe break, but does not explicitly address the concern of rupturing the non-seismic connections to the tank wall due to a seismic event. The licensee performed the modifications under 10 CFR 50.59. The NRC staff request that sufficient documentation and design calculations for this modification be provided for review. In addition to the design calculations, please include information regarding how the tank and piping connections were modified and explain by the seismic event, with the modification, will no longer render the necessary volume of water above the break unusable.