MONTHYEARBSEP 19-0012, Submittal of 2018 Sea Turtle Annual Report2019-01-17017 January 2019 Submittal of 2018 Sea Turtle Annual Report BSEP 18-0052, Annual Radiological Environmental Operating Report - 20172018-05-10010 May 2018 Annual Radiological Environmental Operating Report - 2017 BSEP 18-0051, Annual Radioactive Effluent Release Report - 20172018-04-26026 April 2018 Annual Radioactive Effluent Release Report - 2017 BSEP 18-0045, Request for License Amendment: Technical Specification 3.8.3, Diesel Fuel Oil, One-Time Extension of Main Fuel Oil Storage Tank Completion Time2018-04-25025 April 2018 Request for License Amendment: Technical Specification 3.8.3, Diesel Fuel Oil, One-Time Extension of Main Fuel Oil Storage Tank Completion Time BSEP 18-0054, Response to Request for Additional Information Regarding Inservice Inspection Program Proposed Alternative ISI-09 in Accordance with 10 CFR 50.55a(z)(1) Regarding Reactor Pressure Vessel Circumferential.2018-04-24024 April 2018 Response to Request for Additional Information Regarding Inservice Inspection Program Proposed Alternative ISI-09 in Accordance with 10 CFR 50.55a(z)(1) Regarding Reactor Pressure Vessel Circumferential. BSEP 18-0048, Response to Request for Additional Information Regarding Inservice Inspection Program Proposed Alternative ISI-09 in Accordance with 10 CFR 50.55a(z)(1) Regarding Reactor Pressure Vessel Circumferential Shell Weld Examinations2018-04-11011 April 2018 Response to Request for Additional Information Regarding Inservice Inspection Program Proposed Alternative ISI-09 in Accordance with 10 CFR 50.55a(z)(1) Regarding Reactor Pressure Vessel Circumferential Shell Weld Examinations BSEP 18-0044, Application of Dissimilar Metal Weld Full Structural Overlay - Reactor Pressure Vessel Nozzles N4A and N4D2018-04-11011 April 2018 Application of Dissimilar Metal Weld Full Structural Overlay - Reactor Pressure Vessel Nozzles N4A and N4D BSEP 18-0046, Supplement to Response to Request for Additional Information SRXB-RAI-2 Regarding Request for License Amendment Regarding Core Flow Operating Range Expansion2018-04-10010 April 2018 Supplement to Response to Request for Additional Information SRXB-RAI-2 Regarding Request for License Amendment Regarding Core Flow Operating Range Expansion BSEP 18-0047, Supplement to Proposed Alternative in Accordance with 10 CFR 50.55a(z)(2) for End of Interval Leakage Test2018-04-0505 April 2018 Supplement to Proposed Alternative in Accordance with 10 CFR 50.55a(z)(2) for End of Interval Leakage Test BSEP 18-0041, Request for License Amendment to Revise the Technical Specifications to Relocate the Pressure-Temperature Limit Curves to a Pressure and Temperature Limits Report2018-04-0404 April 2018 Request for License Amendment to Revise the Technical Specifications to Relocate the Pressure-Temperature Limit Curves to a Pressure and Temperature Limits Report BSEP 18-0043, Application of Dissimilar Metal Weld Full Structural Overlay - Reactor Pressure Vessel Nozzles N4A and N4D2018-03-31031 March 2018 Application of Dissimilar Metal Weld Full Structural Overlay - Reactor Pressure Vessel Nozzles N4A and N4D BSEP 18-0035, Response to Request for Additional Information Regarding Request for License Amendment Regarding Core Flow Operating Range Expansion2018-03-29029 March 2018 Response to Request for Additional Information Regarding Request for License Amendment Regarding Core Flow Operating Range Expansion BSEP 18-0042, Cycle 22 Core Operating Limits Report (COLR)2018-03-27027 March 2018 Cycle 22 Core Operating Limits Report (COLR) BSEP 18-0040, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) for End of Interval Leakage Test2018-03-23023 March 2018 Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) for End of Interval Leakage Test BSEP 18-0039, Proposed In-Service Inspection Alternative for Application of Dissimilar Metal Weld Full Structural Overlay - Nozzles N4A and N4D2018-03-19019 March 2018 Proposed In-Service Inspection Alternative for Application of Dissimilar Metal Weld Full Structural Overlay - Nozzles N4A and N4D BSEP 18-0034, Corrected Affidavit Relating to the Request for License Amendment Regarding Core Flow Operating Range Expansion2018-03-16016 March 2018 Corrected Affidavit Relating to the Request for License Amendment Regarding Core Flow Operating Range Expansion BSEP 18-0032, Additional Testing Information Relating to the Request for License Amendment Regarding Core Flow Operating Range Expansion2018-03-14014 March 2018 Additional Testing Information Relating to the Request for License Amendment Regarding Core Flow Operating Range Expansion BSEP 18-0026, Additional Information Regarding Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) for Reactor Pressure Vessel Nozzle-to-Vessel Weld Examination2018-03-0707 March 2018 Additional Information Regarding Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) for Reactor Pressure Vessel Nozzle-to-Vessel Weld Examination BSEP 18-0014, Fifth 10-Year Inservice Testing Program Plan2018-02-19019 February 2018 Fifth 10-Year Inservice Testing Program Plan BSEP 18-0021, Response to Request for Additional Information Regarding Request for License Amendment Regarding Core Flow Operating Range Expansion (CAC Nos. MF8864 and MF8865). Without Proprietary Enclosure2018-02-0505 February 2018 Response to Request for Additional Information Regarding Request for License Amendment Regarding Core Flow Operating Range Expansion (CAC Nos. MF8864 and MF8865). Without Proprietary Enclosure BSEP 18-0017, Revision to Radiological Emergency Response Plan and Implementing Procedure2018-01-30030 January 2018 Revision to Radiological Emergency Response Plan and Implementing Procedure BSEP 18-0015, Inservice Inspection Program Proposed Alternative ISI-09 in Accordance with 10 CFR 50.55a(z)(1) Regarding Reactor Pressure Vessel Circumferential Shell Weld Examinations2018-01-23023 January 2018 Inservice Inspection Program Proposed Alternative ISI-09 in Accordance with 10 CFR 50.55a(z)(1) Regarding Reactor Pressure Vessel Circumferential Shell Weld Examinations BSEP 18-0013, Supplement to Application to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control2018-01-23023 January 2018 Supplement to Application to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control BSEP 18-0001, Application to Revise Technical Specifications to Adopt TSTF-551, Revise Secondary Containment Surveillance Requirements2018-01-23023 January 2018 Application to Revise Technical Specifications to Adopt TSTF-551, Revise Secondary Containment Surveillance Requirements BSEP 18-0012, Application to Revise Technical Specifications to Adopt TSTF-208, Revision 0, Extension of Time to Reach Mode 2 in LCO 3.0.32018-01-23023 January 2018 Application to Revise Technical Specifications to Adopt TSTF-208, Revision 0, Extension of Time to Reach Mode 2 in LCO 3.0.3 BSEP 18-0009, 2017 Sea Turtle Annual Report2018-01-15015 January 2018 2017 Sea Turtle Annual Report BSEP 17-0098, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components (Sscs) for Nuclear Power Reactors2018-01-10010 January 2018 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components (Sscs) for Nuclear Power Reactors BSEP 17-0119, Snubber Program Plan for Fifth 10-Year Interval Inservice Testing Program2018-01-10010 January 2018 Snubber Program Plan for Fifth 10-Year Interval Inservice Testing Program BSEP 17-0115, Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control2018-01-0404 January 2018 Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control BSEP 17-0110, Seventh Six-Month Status Report in Response to June 6, 2013, Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions2017-12-20020 December 2017 Seventh Six-Month Status Report in Response to June 6, 2013, Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions BSEP 17-0121, Post-Examination Documentation and Comments for Operator Retake Initial Examination2017-12-14014 December 2017 Post-Examination Documentation and Comments for Operator Retake Initial Examination BSEP 17-0120, Withdrawal of Request for Risk-Informed Exigent License Amendment - Technical Specification 3.8.1, AC Sources - Operating, One-Time Extension of Emergency Diesel Generator Completion Times and Suspension..2017-12-12012 December 2017 Withdrawal of Request for Risk-Informed Exigent License Amendment - Technical Specification 3.8.1, AC Sources - Operating, One-Time Extension of Emergency Diesel Generator Completion Times and Suspension.. BSEP 17-0118, Supplement to Response to Request for Additional Information Regarding Request for Risk-Informed Exigent License Amendment - Technical Specification 3.8.1, AC Sources - Operating, One-Time Extension of Emergency Diesel..2017-12-0707 December 2017 Supplement to Response to Request for Additional Information Regarding Request for Risk-Informed Exigent License Amendment - Technical Specification 3.8.1, AC Sources - Operating, One-Time Extension of Emergency Diesel.. BSEP 17-0117, Response to Request for Additional Information (Probabilistic Risk Assessment and Human Performance Branches) Regarding Request for Risk-Informed Exigent License Amendment - Technical Specification 3.8.1 AC Sources..2017-12-0606 December 2017 Response to Request for Additional Information (Probabilistic Risk Assessment and Human Performance Branches) Regarding Request for Risk-Informed Exigent License Amendment - Technical Specification 3.8.1 AC Sources.. BSEP 17-0116, Response to Request for Additional Information Regarding Request for Risk- Informed Exigent License Amendment - Technical Specification 3.8.1, AC Sources - Operating, One-Time Extension of ..2017-12-0404 December 2017 Response to Request for Additional Information Regarding Request for Risk- Informed Exigent License Amendment - Technical Specification 3.8.1, AC Sources - Operating, One-Time Extension of .. BSEP 17-0104, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) for Reactor Pressure Vessel Nozzle-to-Vessel Weld Examination2017-11-29029 November 2017 Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) for Reactor Pressure Vessel Nozzle-to-Vessel Weld Examination BSEP 17-0111, Request for Risk-Informed Exigent License Amendment - Technical Specification 3.8.1, AC Sources Operating, One-Time Extension of Emergency Diesel Generator Completion Times and Suspension of Surveillance Requirements2017-11-28028 November 2017 Request for Risk-Informed Exigent License Amendment - Technical Specification 3.8.1, AC Sources Operating, One-Time Extension of Emergency Diesel Generator Completion Times and Suspension of Surveillance Requirements BSEP 17-0109, Response to Request for Additional Information Regarding Request for Emergency License Amendment - Technical Specification 3.8.1, AC Sources - Operating, One-Time Extension of Emergency Diesel Generator Completion Times And.2017-11-24024 November 2017 Response to Request for Additional Information Regarding Request for Emergency License Amendment - Technical Specification 3.8.1, AC Sources - Operating, One-Time Extension of Emergency Diesel Generator Completion Times And. BSEP 17-0108, Request for Emergency License Amendment - Technical Specification 3.8.1, AC Sources - Operating, One-Time Extension of Emergency Diesel Generator Completion Times and Suspension of Surveillance Requirements2017-11-22022 November 2017 Request for Emergency License Amendment - Technical Specification 3.8.1, AC Sources - Operating, One-Time Extension of Emergency Diesel Generator Completion Times and Suspension of Surveillance Requirements BSEP 17-0017, Submittal of Request for License Amendment for Performance-Based Fire Protection Alternative for Thermal Insulation Material2017-11-15015 November 2017 Submittal of Request for License Amendment for Performance-Based Fire Protection Alternative for Thermal Insulation Material BSEP 17-0100, Fifth 10-Year Inservice Testing Interval2017-11-0202 November 2017 Fifth 10-Year Inservice Testing Interval BSEP 17-0089, Updates to Request for License Amendment Regarding Core Flow Operating Range Expansion2017-11-0101 November 2017 Updates to Request for License Amendment Regarding Core Flow Operating Range Expansion BSEP 17-0093, Response to Request for Additional Information Regarding Request for License Amendment Regarding Core Flow Operating Range Expansion2017-11-0101 November 2017 Response to Request for Additional Information Regarding Request for License Amendment Regarding Core Flow Operating Range Expansion BSEP 17-0078, Request for License Amendment - DC Sources - Operating Surveillance Requirement (SR) 3.8.4.52017-10-0303 October 2017 Request for License Amendment - DC Sources - Operating Surveillance Requirement (SR) 3.8.4.5 BSEP 17-0076, Registration for Use of General License Spent Fuel Casks2017-09-0606 September 2017 Registration for Use of General License Spent Fuel Casks BSEP 17-0081, Revision to Radiological Emergency Response Plan Implementing Procedures2017-09-0505 September 2017 Revision to Radiological Emergency Response Plan Implementing Procedures BSEP 17-0039, Submittal of Response to Inspection Report 05000324/2015404 and 05000325/2015404, Dated March 30, 2015, Inspection of Interim Cyber Security Milestones 1-7 and Target Set Requirements2017-08-15015 August 2017 Submittal of Response to Inspection Report 05000324/2015404 and 05000325/2015404, Dated March 30, 2015, Inspection of Interim Cyber Security Milestones 1-7 and Target Set Requirements BSEP 17-0071, ISFSI - Registration for Use of General License Spent Fuel Casks2017-08-15015 August 2017 ISFSI - Registration for Use of General License Spent Fuel Casks BSEP 17-0064, Application of Dissimilar Metal Weld Full Structural Overlay on Reactor Pressure Vessel Nozzle N92017-07-10010 July 2017 Application of Dissimilar Metal Weld Full Structural Overlay on Reactor Pressure Vessel Nozzle N9 BSEP 17-0060, Application to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control.2017-06-29029 June 2017 Application to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control. 2019-01-17
[Table view] |
Text
Progress EnergyViceenai Benjamin C.Waidrep P .Wlrpresident Brunswick Nuclear Plant Progress Energy Carolinas, Inc.
May 9, 2008 SERIAL: BSEP 08-0060 10 CFR 50.54(f)
U. S. Nuclear Regulatory Commission ATTN: Document Control Desk 11555 Rockville Pike Rockville, MD 20852
Subject:
Brunswick Steam Electric Plant, Unit Nos. 1 and 2 Docket Nos. 50-325 and 50-324/License Nos. DPR-71 and DPR-62 Three-month Response to Generic Letter 2008-01, "Managing Gas Accumulation in Emergency Core Cooling; Decay Heat Removal, and Containment Spray Systems"
References:
- 1. Generic Letter 2008-01, "Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems,"
dated January 11, 2008 (ADAMS Accession Number ML072910759)
- 2. Letter from J. Paul Fulford to the U.S. Nuclear Regulatory Commission (Serial: PE&RAS-08-025), "Request for Extension of 3-Month Response to Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems," dated April 8, 2008 (ADAMS Accession Number ML081080038)
Ladies and Gentlemen:
On January 11, 2008, the NRC issued Generic Letter (GL) 2008-01 requesting that each licensee evaluate its Emergency Core Cooling Systems (ECCS), Decay Heat Removal System, and Containment Spray System licensing basis, design, testing, and corrective actions to ensure that gas accumulation is maintained less than the amount that challenges operability of these systems, and that appropriate action is taken when conditions adverse to quality are identified. The results of these evaluations are requested to be reported within nine months of the date of the GL pursuant to 10 CFR 50.54(f). The GL goes on to state that licensees who do not believe they can complete the requested evaluations within the nine-month period are to inform the NRC, within three months of the date of the GL, of proposed alternative actions including the basis for the acceptability of the proposed alternative course of action. As documented in Reference 2, Carolina Power & Light Company (CP&L), now doing business as Progress Energy Carolinas, Inc., received a 30 day extension to the three-month response requirement.
PO. Box 10429 Southport, NC28461 T> 910.457.3698
Document Control Desk BSEP 08-0060 / Page 2 Enclosure I provides CP&L's three-month response to GL 2008-01 for the Brunswick Steam Electric Plant (BSEP), Unit Nos. 1 and 2.
Regulatory commitments associated with this submittal are documented in Enclosure 2.
Please refer any questions regarding this submittal to Mr. Randy C. Ivey, Manager - Support Services, at (910) 457-2447.
I declare, under penalty of perjury, that the foregoing is true and correct. Executed on May 9, 2008.
Sincerely, Benjamin aldrep MAT/mat
Enclosures:
- 1. Three-month Response to Generic Letter 2008-01
- 2. List of Regulatory Commitments
Document Control Desk BSEP 08-0060 / Page 3 cc (with enclosures):
U. S. Nuclear Regulatory Commission, Region II ATTN: Mr. Victor M. McCree, Regional Administrator (Acting)
Sam Nunn Atlanta Federal Center 61 Forsyth Street, SW, Suite 23T85 Atlanta, GA 30303-8931 U. S. Nuclear Regulatory Commission ATTN: Mr. Joseph D. Austin, NRC Senior Resident Inspector 8470 River Road Southport, NC 28461-8869 U. S. Nuclear Regulatory Commission (Electronic Copy Only)
ATTN: Mrs. Farideh E. Saba (Mail Stop OWFN 8G9A) 11555 Rockville Pike Rockville, MD 20852-2738 Chair - North Carolina Utilities Commission P.O. Box 29510 Raleigh, NC 27626-0510
BSEP 08-0060 Enclosure 1 Page 1 of 3 Three-month Response to Generic Letter 2008-01
Background
On January 11, 2008, the NRC issued Generic Letter (GL) 2008-01 requesting that each licensee evaluate its Emergency Core Cooling Systems (ECCS), Decay Heat Removal System, and Containment Spray System licensing basis, design, testing, and corrective actions to ensure that gas accumulation is maintained less than the amount that challenges operability of these systems, and that appropriate action is taken when conditions adverse to quality are identified. The results of these evaluations are requested to be reported within nine months of the date of the GL (i.e.,
October 11, 2008) pursuant to 10 CFR 50.54(f). The GL goes on to state that licensees who do not believe they can complete the requested evaluations within the nine month period are to inform the NRC, within three months of the date of the GL, of proposed alternative actions including the basis for the acceptability of the proposed alternative course of action.
Alternative Schedule Carolina Power & Light Company (CP&L), now doing business as Progress Energy Carolinas, Inc., will complete detailed walkdowns and any necessary ultrasonic examinations of inaccessible piping at locations potentially susceptible to gas accumulation for systems within the scope of GL 2008-01 for Brunswick Steam Electric Plant (BSEP), Units 1 and 2 prior to startup from each unit's next refueling outage (i.e., B 118R1 for Unit 1, currently scheduled to begin on February 27, 2010, and B219R1 for Unit 2, currently scheduled to begin on February 28, 2009).
Supplemental responses to GL 2008-01 will be provided within three months following the completion of the B 118R1 and B219R 1 refueling outages. The supplemental responses will describe any changes to the nine-month response resulting from walkdowns and ultrasonic examination of inaccessible piping.
Basis for Alternative Schedule CP&L expects to be able to complete the GL requested actions involving evaluation of licensing basis, design, testing, and corrective actions for both Unit 1 and 2 to a significant extent.
However, the GL requested evaluations also necessitate detailed physical walkdowns of the subject piping systems to confirm pertinent design details (e.g., locations of high point vents),
confirm as-built configuratioIns (e.g., pipe elevations and slope), and ultrasonic examinations at locations potentially susceptible to gas accumulation. Portions of the subject piping systems are inaccessible during power operation due to one or more of the following reasons:
" The piping is in an area where dose rates are substantially higher during normal operation as compared to during plant shutdown conditions.
" The piping is in the drywell, the main steam tunnel, or the suppression pool.
BSEP 08-0060 Enclosure 1 Page 2 of 3
- Insulation removal may be required to fully characterize relevant geometry and insulation removal is not practical.
- Scaffolding may be needed to access the piping to fully characterize relevant geometry and installation of scaffolding could jeopardize operability of adjacent equipment.
BSEP Unit 1 recently completed a refueling outage (i.e., B117R1) during which physical walkdowns of inaccessible piping within the scope of GL 2008-01 were performed to confirm as-built configurations (e.g., pipe elevations and slope), at locations potentially susceptible to gas accumulation. Pipe insulation was not removed during these inspections. Because adequate time was not available between issuance of GL 2008-01 on January 11, 2008, and the start of the B117R1 outage on March 15, 2008, to determine what actions are required, additional inspections or other actions may be warranted during the B118R1 outage.
BSEP Units 1 and 2 do not currently have a planned refueling outage to conduct the walkdowns and perform ultrasonic examinations of inaccessible piping within the nine month period requested by the GL (i.e., by October 11, 2008). The next Unit 1 refueling outage (i.e., B118R1) is currently planned to begin on February 27, 2010. The next Unit 2 refueling outage (i.e.,
B219R1) is currently planned to begin on February 28, 2009. The nine-month response to GL 2008-01 will include evaluations of non-accessible piping based on the existing BSEP Unit 1 and 2 as-built design drawings, as well as system operating experience, and any previously performed walkdown information, including the physical walkdowns of inaccessible BSEP Unit 1 piping completed during the spring 2008 B 117R1 outage.
Supplemental responses to GL 2008-01 will be provided within 90 days following the completion of the B 118R 1 and B219R1 refueling outages. These supplemental responses will describe any changes to the nine-month response resulting from walkdowns and ultrasonic examination of inaccessible piping.
CP&L has confidence that the BSEP Units 1 and 2 ECCS, Decay Heat Removal, and Containment Spray Systems can fulfill their required design functions, based upon the following:
" The majority of inaccessible piping is on the pump discharge where potential impact of gas accumulation is generally less than for pump suction piping.
- Based on reviews completed to date, no historical examples of events related to gas accumulation have been identified for the inaccessible piping.
- Successful performance of surveillance requirements, such as periodic venting and pump testing. 1 Note that on April 29, 2008, the Unit I High Pressure Coolant Injection system experienced a main pump seal failure during surveillance testing to establish operability. Preliminary investigations have determined that the seal failure was due to inadequate venting of the pump after seal replacement and not a result of gas accumulation in inaccessible piping. The final root cause and corrective actions associated with this event have not been completed.
BSEP 08-0060 Enclosure 1 Page 3 of 3 CP&L will complete the GL 2008-01 actions for BSEP Units 1 and 2, with the exception of the final verification walkdowns of the pipe segments requiring a refueling outage to access.
Preliminary evaluations of inaccessible piping will provide a high degree of confidence that these systems will perform their design functions. The outage walkdowns are expected to be validation activities of these design reviews.
Based upon the above, completing detailed walkdowns, ultrasonic examinations, and subsequent revisions to preliminary evaluations of inaccessible piping outside the requested nine-month period, but no later than startup from the next refuel outage, is an acceptable alternative course of action.
BSEP 08-0060 Enclosure 2 Page 1 of I List of Regulatory Commitments The following table identifies those actions committed to by Carolina Power & Light Company (CP&L), now doing business as Progress Energy Carolinas, Inc., in this document. Any other statements in this submittal are provided for information purposes and are not considered to be regulatory commitments. Please direct questions regarding these commitments to the Manager - Support Services at the Brunswick Steam Electric Plant.
Commitment Schedule
- 1. CP&L will complete detailed walkdowns and any necessary Prior to startup from the ultrasonic examinations of inaccessible piping at locations B219R1 refueling potentially susceptible to gas accumulation for systems within the outage, currently scope of Generic Letter (GL) 2008-01 for Brunswick Steam scheduled to begin on Electric Plant (BSEP) Unit 2, prior to startup from the next February 28, 2009.
refueling outage (i.e., B219R1).
- 2. CP&L will submit a supplemental response to GL 2008-01 within Within 90 days 90 days following the completion of the B219R1 refueling following the outage. The supplemental response will describe any changes to completion of the the nine-month response resulting from walkdowns and ultrasonic B219R1 refueling examination of inaccessible BSEP Unit 2 piping. outage, currently scheduled to end on April 11, 2009.
- 3. CP&L will complete any necessary ultrasonic examinations or Prior to startup from the additional inspections of inaccessible piping at locations B 118R 1 refueling potentially susceptible to gas accumulation for systems within the outage, currently scope of GL 2008-01 for BSEP Unit 1 prior to startup from the scheduled to begin on next refueling outage (i.e., BI 18R 1). February 27, 2010.
- 4. CP&L will submit a supplemental response to GL 2008-01 within Within 90 days 90 days following the completion of the B 118R1 refueling following the outage. The supplemental response will describe any changes to completion of the the nine-month response resulting from walkdowns and ultrasonic B118RI refueling examination of inaccessible BSEP Unit 1 piping. outage, currently scheduled to end on April 5, 2010.