Text
Dominion Resources Services, Inc.
~(I(1(1 Dominion Boulevard, elen Allen, VA 2,Of,:
\\\\'cb Address: www.dom.com Attention: Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville Pike Rockville, MD 20852 May 8,2008 Serial No.
08-0013A NL&OSITJS R3 Docket Nos. 50-280,281 50-338,339 50-336,423 50-305 License Nos. DPR-32, 37 NPF-4,7 DPR-65 NPF-49 DPR-43 VIRGINIA ELECTRIC AND POWER COMPANY DOMINION NUCLEAR CONNECTICUT, INC.
DOMINION ENERGY KEWAUNEE, INC.
SURRY POWER STATION UNITS 1 AND 2 NORTH ANNA POWER STATION UNITS 1 AND 2 MILLSTONE POWER STATION UNITS 2 AND 3 KEWAUNEE POWER STATION GENERIC LETTER 2008-01, MANAGING GAS ACCUMULATION IN EMERGENCY CORE COOLING, DECAY HEAT REMOVAL, AND CONTAINMENT SPRAY SYSTEMS THREE-MONTH RESPONSE CONTAINING ALTERNATIVE ACTIONS Generic Letter (GL) 2008-01 requires a nine-month written response providing the information requested in the GL.
A three-month written response is required if a licensee proposes an alternative course of action, including schedule considerations.
In a telephone conversation between the NRC (Mr. J. S. Wermiel) and Dominion (Mr. D. A. Sommers) on April 3, 2008, the NRC staff agreed to a thirty-day extension (i.e., until May 11,2008) for Dominion to submit the GL 2008-01 three-month response in order to address evolving positions on confirmatory walkdowns.
A letter confirming this agreed upon extension was transmitted to the NRC on April 7,2008 (Dominion Serial No. 08-0013).
The purpose of this letter is to inform the NRC that a portion of the Dominion fleet will not complete all the activities that will be discussed in the nine-month response to GL 2008-01 before the required nine-month response date (i.e., October 10, 2008).
All the activities requested by the Generic Letter will be complete by the required response date with the exception of confirmatory walkdowns inside containment. Specifically, Dominion's completion of walkdowns to confirm gas accumulation management plans on associated systems are needed in fall 2008 and spring 2009 refueling outages at four units in the Dominion fleet.
These unit outages are not aligned with the requested response schedule for GL 2008-01, and are as follows:
Millstone Power Station Unit 3 (MPS-3):
North Anna Power Station Unit 2 (NAPS-2):
North Anna Power Station Unit 1 (NAPS-i):
Surry Power Station Unit 1 (SPS-1):
fall 2008 fall 2008 spring 2009 spring 2009
Serial No. 08-0013A Docket Nos. 50-280/281, 338/339, 336/423, 305 Page 2 of 3 Dominion will provide a response to GL 2008-01, consistent with the Generic Letter's requested schedule by October 10, 2008 that will address the required aspects of the Generic Letter for the Dominion fleet. However, Dominion requests additional time after completion of the confirmatory walkdowns in the falll 2008 and spring 2009 outages to submit supplemental responses. The first supplemental response (containing information on MPS-3 and NAPS-2) will be submitted by January 15, 2009 and the second supplemental response (containing information on NAPS-1 and SPS-1) will be submitted by July 15, 2009.
Please contact Mr. David A. Sommers at (804) 273-2823 if you have any questions or require additional information.
Sincerely,
~?~~?a~6 Vice President Nuclear Engineering Virginia Electric and Power Company Dominion Nuclear Connecticut, Inc.
Dominion Energy K.ewaunee, Inc.
COMMONWEALTH OF VIRGINIA COUNTY OF HENRICO The foregoing document was acknowledged before me, in and for the County and Commonwealth aforesaid, today by Gerald T
Bischof, who is ViCI~ President -
Nuclear Engineering of Virginia Electric and Power Company, Dominion Nuclear Connecticut, Inc. and Dominion Energy Kewaunee, Inc. He has affirmed before me that he is duly authorized to execute and file the foregoing document in behalf of that company, and that the statements in the document are true to the best of his knowledge and belief.
MARGARET B. BENNETT Notary Public $ 5'c.f.:3 () :J,..
Commonweattt11 of Virginia
~
My Commllilan Expltr** Aug 31. 2008
- Attachments: None, Commitments made in this letter:
Acknowledged before me this~ day of~
2008.
My Commission Expires: WIf"P* ~~ 2Jvo8.
~~p'~~
1.
Provide supplemental response to GL 2008-01 by January 15, 2009 for MPS-3 and NAPS-2.
2.
Provide supplemental response to GL 2008-01 by July 15, 2009 for NAPS-1 and SPS-1.
Serial No. 08-0013A Docket Nos. 50-280/281, 338/339, 336/423, 305 Page 3 of 3 cc:
U. S. Nuclear Regulatory Commission Region I 475 Allendale Road King of Prussia, PA 19406-1415 U. S. Nuclear Regulatory Commission Region II Sam Nunn Atlanta Federal Center 61 Forsyth Street, S.W., Suite 23T85 Atlanta, GA 30303-8931 U. S. Nuclear Regulatory Commission Region III 2443 Warrenville Road, Suite 210 Lisle, IL 60532-4352 NRC Senior Resident Inspector Surry Power Station NRC Senior Resident Inspector North Anna Power Station NRC Senior Resident Inspector Millstone Power Station NRC Senior Resident Inspector Kewaunee Power Station Mr. J. D. Hughey NRC Project Manager Millstone U. S. Nuclear Regulatory Commission, Mail Stop OWFN 0-8 83 One White Flint North 11555 Rockville Pike Rockville, MD 20852-2738 Mr. S. P. Lingam NRC Project Manager North Anna and Surry U. S. Nuclear Regulatory Commission, Mail Stop OWFN 0-8 G9A One White Flint North 11555 Rockville Pike Rockville, MD 20852-2738 Ms. M. H. Chernoff NRC Senior Project Manager Kewaunee U. S. Nuclear Regulatory Commission, Mail Stop OWFN 0-8 H4A One White Flint North 11555 Rockville Pike Rockville, MD 20852-2738