IR 05000335/2008007
| ML081090249 | |
| Person / Time | |
|---|---|
| Site: | Saint Lucie, 07200061 |
| Issue date: | 04/18/2008 |
| From: | Division Reactor Projects II |
| To: | |
| Shared Package | |
| ML081090236 | List: |
| References | |
| IR-08-001, IR-08-007 | |
| Download: ML081090249 (46) | |
Text
ST LUCIE ISFSI PRE-OPERATIONAL TESTING AND FIRST LOADING (TABLE OF CONTENTS)
INSPECTOR NOTES Category Topic Page #
Crane Design Bridge and Trolley Brakes
Crane Design Bridge Bumpers
Crane Design Crane Support Structure
Crane Design Drum Safety Devices
Crane Design Emergency Stop Feature
Crane Design Hoist Control Brake Operation
Crane Design Hoist Holding Brake Location
Crane Design Hoist Holding Brake Operation
Crane Design Lamellar Tearing
Crane Design Overload Protection
Crane Design Provisions For Manual Operation
Crane Design Seismic Events During Cask Movement
Crane Design Seismically Induced Load Swing
Crane Design Trolley Bumpers
Crane Design Two-Block Protection
Crane Design Wire Rope Breaking Strength
Crane Design Wire Rope Configuration
Crane Inspection/Maintenance Crane Inspection - Frequent
Crane Inspection/Maintenance Crane Inspection - Periodic
Crane Inspection/Maintenance Crane Operational Testing
Crane Inspection/Maintenance Hoist Overload Testing
Crane Inspection/Maintenance Hoist Two-Block Testing - Limit Device Method
Crane Inspection/Maintenance Hoist Two-Block Testing - Strength Method
Crane Inspection/Maintenance Hook Inspections - Frequent
Crane Inspection/Maintenance Preventive Maintenance Program
Crane Inspection/Maintenance Welding
Crane Load Testing Cold Proof Testing
Crane Load Testing Dynamic Load Testing
Page 1 of 3 Attachment 2
Category Topic Page #
Crane Load Testing Hook Load Testing
Crane Load Testing Maximum Weight of Canister
Crane Load Testing Rated Load Marking
Crane Load Testing Static Load Testing
Crane Operation Minimum of Two Wraps of Rope
Crane Operation Qualification For Crane Operator
Crane Operation Warning Signals
Drying/Helium Backfill Drying Final Pressure
Drying/Helium Backfill Drying Time Limits - Procedure C
Drying/Helium Backfill Helium Backfill Final Pressure
Drying/Helium Backfill Helium Pressure Test
Drying/Helium Backfill Helium Purity
Emergency Planning Emergency Plan
Emergency Planning Emergency Plan Changes
Fire Protection Fire Protection Plan
Fire Protection Offsite Emergency Support
Fuel Selection/Verification Approved Contents
Fuel Selection/Verification Approved Spent Fuel Types
Fuel Selection/Verification Classifying Damaged Fuel
Fuel Selection/Verification Decay Heat Load
Fuel Selection/Verification Fuel Design Characteristics
Fuel Selection/Verification Loading Configurations
Fuel Selection/Verification Non-Fuel Assembly Hardware
Fuel Selection/Verification Spent Fuel Assembly Mis-Loading
General License Cask Design Compatible With Part 50
General License Dose to the Public - Normal Operations
General License Evaluation Report Changes
General License HSM - Storage Pad Soil Liquefaction
General License HSM Storage Arrays
General License Reactor Site Parameters - Fire and Explosion
General License Reactor Site Parameters - Flood Conditions
General License Reactor Site Parameters - Normal Temperatures
General License Reactor Site Parameters - Roof Snow Loading
Page 2 of 3 Attachment 2
Category Topic Page #
General License Reactor Site Parameters - Seismic Loads
General License Reactor Site Parameters - Temperature Extremes
General License Reactor Site Parameters - Tornado Wind Speeds
Heavy Loads Heavy Loads Safety Review
Heavy Loads Safe Load Paths
Procedures & Tech Specs Canister Gas Sampling During Unloading
Procedures & Tech Specs Canister Unloading - Reflooding
Procedures & Tech Specs Cask Maintenance - Annual Inspections
Procedures & Tech Specs Cask Operation
Procedures & Tech Specs Cask Surveillance - HSM Air Vent Inspections
Procedures & Tech Specs Criticality - Minimum Boron Concentration
Quality Assurance Approved QA Program
Quality Assurance Control of Measuring and Test Equipment
Quality Assurance Corrective Actions
Quality Assurance Handling and Storage Controls
Quality Assurance Nonconforming Material and Parts
Quality Assurance Procurement Controls
Radiation Protection ALARA Measures
Radiation Protection Contamination Survey of Canister
Radiation Protection Criticality - Monitoring and Alarm System
Radiation Protection HSM-H Dose Rate Evaluation
Radiation Protection Neutron Energies for Dosimetry
Training Approved Training Program
Training Cask System Overview
Training Cask System Procedures
Training Certification of Personnel
Training Dry Run Training Exercise
Page 3 of 3 Attachment 2
ST LUCIE ISFSI PRE-OPERATIONAL INSPECTION (INSPECTOR NOTES)
Category:
Crane Design Topic:
Bridge and Trolley Brakes Reference:
NUREG 0554, Section 5.1 Finding:
The bridge and trolley control and holding brakes are capable of applying a counter torque that is 100% of the maximum drive torque that can be developed at the point of applicatio The maximum torque capacity of the driving motor and gear reducer for both motions does not exceed the capacity of the gear train and brakes to stop either of the motions from the maximum speed with the design rated load attache The bridge and trolley motors are provided with spring set, electrically released holding brakes that are automatically applied when power is interrupte The holding brakes are electrically actuated and therefore, cannot be used as a foot operated slow down brak The crane does not employee drag brakes.
Documents Reviewed:
-American Crane & Equipment Corp. Report REP-19939-009 "NUREG 0554 Compliance Report for Fuel Cask Cranes Single Failure Proof Replacement Bridge Cranes at St. Lucie Units 1 & 2 Nuclear Generating Station," Revision 1 (Proprietary)
-American Crane & Equipment Corp. Report REP-19939-014 "NUREG 0554 Safety Analysis Report for Fuel Cask Cranes Single Failure Proof Replacement Bridge Cranes at St. Lucie Units 1 & 2 Nuclear Generating Station," Revision 1 (Proprietary)
Requirement: Bridge and trolley control and holding brakes should be: a) rated at 100% of maximum drive torque that can be developed at the point of application; and b) automatically actuate on interruption of power and overspee The holding brakes should be designed so that they cannot be used as foot-operated slowdown brake Drag brakes should not be used.
Category:
Crane Design Topic:
Bridge Bumpers Reference:
NUREG 0554, Sect 5.2; ASME B30.2, Section 2-1.8.2 Finding:
Compression bumpers, attached to the bridge, are provided to buffer contact with the end of trave The bridge bumpers were designed to withstand a speed of 40% of rated load as specified in Calculation CAL-19939-ME-425.
Documents Reviewed:
E-mail from Jeff Griesemer, American Crane to Ralph Russo, FPL dated Feb. 27, 2008 referencing Calculations CAL-19939-ME-325, Revision 2 and CAL-19939-ME-425, Revision 2 Requirement: A bridge shall be provided with bumpers, or other automatic means of equivalent effect, capable of stopping the bridge when traveling with power off in either direction at a speed of at least 40% of rated load speed.
Category:
Crane Design Topic:
Crane Support Structure Reference:
NUREG 0554, Sections 2.3 & 2.5 Requirement: The crane support structure should be designed to maintain structural integrity under Page 1 of 43 Attachment 2
Finding:
As part of the installation of the new single failure proof cranes at Unit 1 and Unit 2, the licensee replaced the crane support structure These structures are located outside the fuel handling building of each uni The crane runway support structure includes the columns, vertical bracing, runway girders and walkway platform truss syste In each unit, two columns of the crane runway support structure are supported by the fuel handling building roo The other columns are supported on reinforced concrete foundations at grade leve None of the structures affect the reactor safe shutdown system All of the crane support structures were included in the seismic analysis for the new crane The analysis used the seismic properties for the site based on the Part 50 Updated Final Safety Analysis Reports (UFSAR), Section (Additional information related to seismic design aspects of the crane are included in this inspection report under the Category: Crane Design - Topic: Seismic Events During Cask Movement.) The design life of the cranes was based on 40 years of outside servic This design included provisions for the chemical (salt) environment at the site, torrential rains, high winds to 120 mph produced by a hurricane, high winds to 360 mph produced by a tornado and pressure differentials that would be caused by a tornad During high wind situations, the crane will not be operated at wind speeds exceeding 50 mph.
Documents Reviewed:
-Updated Final Safety Analysis Report (UFSAR) for Saint Lucie Nuclear Power Station (Unit 1), Revision 22-Updated Final Safety Analysis Report (UFSAR) for Saint Lucie Nuclear Power Station (Unit 2), Revision 17-American Crane & Equipment Corp. Report REP-19939-009 "NUREG 0554 Compliance Report for Fuel Cask Cranes Single Failure Proof Replacement Bridge Cranes at St. Lucie Units 1 & 2 Nuclear Generating Station," Revision 1 (Proprietary)
normal operating conditions and seismic events.
Category:
Crane Design Topic:
Drum Safety Devices Reference:
NUREG 0554, Section 4.2 Finding:
The dual drums on the main hoist employ drum catching devices which prevent each of the two main hoist drums from disengaging from the emergency stop disk caliper braking syste The arrangement effectively locks the drum between a support frame and the brake and prevents disengagement of the braking syste The drum retaining devices are steel structures which ensure that a shaft or bearing failure will not allow the main hoist drums to disengage from the respective drum brakes.
Documents Reviewed:
-American Crane & Equipment Corp. Report REP-19939-009 "NUREG 0554 Compliance Report for Fuel Cask Cranes Single Failure Proof Replacement Bridge Cranes at St. Lucie Units 1 & 2 Nuclear Generating Station," Revision 1 (Proprietary)
-American Crane & Equipment Corp. Report REP-19939-014 "NUREG 0554 Safety Analysis Report for Fuel Cask Cranes Single Failure Proof Replacement Bridge Cranes at St. Lucie Units 1 & 2 Nuclear Generating Station," Revision 1 (Proprietary)
Requirement: The hoist drum should be provided with structural and mechanical safety devices to limit its drop during a shaft or bearing failur The devices should prevent disengaging from the holding brake.
Page 2 of 43 Attachment 2
Category:
Crane Design Topic:
Emergency Stop Feature Reference:
NUREG 0554, Sections 3.3, 6.1, and 6.6 Finding:
An emergency stop button is located on the radio transmitter and in the cab of the cran An electrical interlock is provided between the cab control and the radio contro A manual disconnect switch, located on the bridge, is provided to independently disconnect the power from the crane and runwa Power can also be disconnected from the crane using the breaker at the load center, though this breaker is not at ground leve Units 1 and 2 have similar design.
Documents Reviewed:
-American Crane & Equipment Corp. Report REP-19939-009 "NUREG 0554 Compliance Report for Fuel Cask Cranes Single Failure Proof Replacement Bridge Cranes at St. Lucie Units 1 & 2 Nuclear Generating Station," Revision 1 (Proprietary)
-American Crane & Equipment Corp. Report REP-19939-014 "NUREG 0554 Safety Analysis Report for Fuel Cask Cranes Single Failure Proof Replacement Bridge Cranes at St. Lucie Units 1 & 2 Nuclear Generating Station," Revision 1 (Proprietary)
-NUREG-0554 "Single Failure Proof Cranes for Nuclear Power Plants," dated May 1979 Requirement: An emergency stop feature should be installed at the control statio For cranes remotely operated using radio control stations, a second emergency stop feature should be provided at ground level to remove power from the crane, independent of the controlle Cranes that use more than one control station should be provided with electrical interlocks that permit only one control station to be operated at a time.
Category:
Crane Design Topic:
Hoist Control Brake Operation Reference:
NUREG 0554, Sect 4.9; ASME B30.2, Section 2-1.9.3 Finding:
The crane includes a main hoist control system utilizing dynamic braking as the power control braking system and two shoe type high speed holding brakes on the high speed shafting for the main hois Each of the two independent holding brake systems are designed with sufficient capacity to stop the full load of the hois The holding brakes are designed with large brake discs on each of the brakes to provide for heat dissipation to ensure damage will not occur during lowering of the load at minimum speed.
Documents Reviewed:
-American Crane & Equipment Corp. Report REP-19939-009 "NUREG 0554 Compliance Report for Fuel Cask Cranes Single Failure Proof Replacement Bridge Cranes at St. Lucie Units 1 & 2 Nuclear Generating Station," Revision 1 (Proprietary)
-American Crane & Equipment Corp. Report REP-19939-014 "NUREG 0554 Safety Analysis Report for Fuel Cask Cranes Single Failure Proof Replacement Bridge Cranes at St. Lucie Units 1 & 2 Nuclear Generating Station," Revision 1 (Proprietary)
.
Requirement: The minimum hoist braking system should included one power control brake (not mechanical or drag brake type) and two holding brake The power control brake may be regenerative, dynamic, counter-torque or eddy-current and shall be capable of maintaining controlled lowering speed The control brake shall have the thermal capacity required for the frequency of operation.
Page 3 of 43 Attachment 2
Category:
Crane Design Topic:
Hoist Holding Brake Location Reference:
NUREG 0554, Section 4.9; NUREG 0612, Pg C-3 (6)
Finding:
The holding brake system is single failure proo Each hoisting brake has dual brake One holding brake is on the gear train located on the moto The second holding brake is mounted on the hoisting dru Each holding brake is designated to stop the full load of the hoist.
Documents Reviewed:
-American Crane & Equipment Corp. Report REP-19939-009 "NUREG 0554 Compliance Report for Fuel Cask Cranes Single Failure Proof Replacement Bridge Cranes at St. Lucie Units 1 & 2 Nuclear Generating Station," Revision 1 (Proprietary)
-American Crane & Equipment Corp. Report REP-19939-014 "NUREG 0554 Safety Analysis Report for Fuel Cask Cranes Single Failure Proof Replacement Bridge Cranes at St. Lucie Units 1 & 2 Nuclear Generating Station," Revision 1 (Proprietary)
Requirement: When the hoisting system uses dual gear trains, a holding brake should be applied to each gear trai When the hoisting system uses a single gear train, one holding brake should be applied to the gear train and the second brake should be applied directly to the drum.
Category:
Crane Design Topic:
Hoist Holding Brake Operation Reference:
NUREG 0554, Section 4.9 Finding:
The crane includes a main hoist control system utilizing dynamic braking as the power control braking system and two shoe type high speed holding brakes on the high speed shafting for the main hois Each holding brake of the main hoist has been designed with a minimum capacity of 125% of the torque developed during the hoisting operation at the point of brake applicatio The holding brakes are fail safe, i.e. power released and spring actuate Each holding brake is designed to actuate should any hoisting fault be detected, including overspeed, overload or out of balance.
Documents Reviewed:
-American Crane & Equipment Corp. Report REP-19939-009 "NUREG 0554 Compliance Report for Fuel Cask Cranes Single Failure Proof Replacement Bridge Cranes at St. Lucie Units 1 & 2 Nuclear Generating Station," Revision 1 (Proprietary)
-American Crane & Equipment Corp. Report REP-19939-014 "NUREG 0554 Safety Analysis Report for Fuel Cask Cranes Single Failure Proof Replacement Bridge Cranes at St. Lucie Units 1 & 2 Nuclear Generating Station," Revision 1 (Proprietary)
Requirement: The minimum hoist braking system should included one power control braking system (not mechanical or drag brake type) and two holding brake Holding brakes should have a minimum brake capacity of 125% of the torque developed during the hoisting operation at the point of brake application, and should be automatically applied to the full holding position when power is off, and under overspeed condition and overload conditions.
Category:
Crane Design Topic:
Lamellar Tearing Reference:
NUREG 0554, Section 2.6 Requirement: Problems have been experienced with weld joints between rolled structural member Page 4 of 43 Attachment 2
Finding:
The trolley and bridge structures were fabricated primarily from plates and structural shapes rolled from carbon stee The bridge structures (girders, end trucks and end ties)
utilized plate thicknesses of 1-1/4" or less in highly restrained weld configurations to reduce the potential for lamellar tearin The trolley structure (end trucks, load girts and upper block) utilized plate thicknesses of 1" or less in highly restrained welded configuration For any load girts joint penetration welds in the base materials exceeding 1" plate thickness, ultrasonic testing was performe Most single failure point welds within the frame were eliminated by designing connections which transfer the force If the design could not eliminate a single failure point weld, the weld was welded with certified welders using certified filler material, visually inspected and magnetic particle or dye penetrant tested to ensure weld integrit All welds were visually inspected.
Documents Reviewed:
-American Crane & Equipment Corp. Report REP-19939-009 "NUREG 0554 Compliance Report for Fuel Cask Cranes Single Failure Proof Replacement Bridge Cranes at St. Lucie Units 1 & 2 Nuclear Generating Station," Revision 1 (Proprietary)
-American Crane & Equipment Corp. Report REP-19939-014 "NUREG 0554 Safety Analysis Report for Fuel Cask Cranes Single Failure Proof Replacement Bridge Cranes at St. Lucie Units 1 & 2 Nuclear Generating Station," Revision 1 (Proprietary)
Specifically, subsurface lamellar tearing has occurred at the weld joints during fabrication, and the through thickness strength of the material has been reduce When weld joints are carefully designed and fabricated, lamellar tearing is not expected to occu For certain weld joints, it may be necessary to examine the joint by radiography or ultrasonic inspection, as appropriate, to ensure the absence of lamellar tearing in the base metal and the soundness of the weld material.
Category:
Crane Design Topic:
Overload Protection Reference:
NUREG 0554, Section 4.5 Finding:
The main hoist is designed to safely handle a two-block situation without permanent deformation or damag In addition, two upper, redundant limit switches of different design and actuation are provided to prevent two-blockin A mechanical slip clutch is located between the gearbox and motor to disengage the rotating high speed kinetic energy from the system during two-blockin A load sensing system is included in the reeving system that will de-energize the hoist and stop motion when a load greater than 115% of the rated load is detecte The auxiliary hoist is not single failure proof and will not be used for critical lifts.
Documents Reviewed:
-American Crane & Equipment Corp. Report REP-19939-009 "NUREG 0554 Compliance Report for Fuel Cask Cranes Single Failure Proof Replacement Bridge Cranes at St. Lucie Units 1 & 2 Nuclear Generating Station," Revision 1 (Proprietary)
-American Crane & Equipment Corp. Report REP-19939-014 "NUREG 0554 Safety Analysis Report for Fuel Cask Cranes Single Failure Proof Replacement Bridge Cranes Requirement: The complete hoisting system should have the required strength to resist failure during load hang-u As an alternative the system design may include a load cell system in the drive train, a motor current-sensing device, or a mechanical load-limiting device that will de-energize the hoist drive motor and the main power supply under a load hang-up conditio The auxiliary hoist, if used for critical lifts, should also be equipped with overload protection.
Page 5 of 43 Attachment 2
at St. Lucie Units 1 & 2 Nuclear Generating Station," Revision 1 (Proprietary)
Category:
Crane Design Topic:
Provisions For Manual Operation Reference:
NUREG 0554, Sections 3.4; 4.9 Finding:
The main hoist has redundant brakes to allow portions of the hoist drive train to be repaired while retaining the loa In addition, the main hoist, trolley and bridge can each be moved independently under a loss of power event so that a load could be moved to a safe lay down location and then lowere The hydraulic drum brakes on the hoist can be manually modulated to lower the load in the event of hoisting equipment failure using a hand pump to cycle the brake The bridge and trolley have attachment points for manual operation by rigging to the crane structure and using the manual release on the brake system.
Documents Reviewed:
-American Crane & Equipment Corp. Report REP-19939-009 "NUREG 0554 Compliance Report for Fuel Cask Cranes Single Failure Proof Replacement Bridge Cranes at St. Lucie Units 1 & 2 Nuclear Generating Station," Revision 1 (Proprietary)
-American Crane & Equipment Corp. Report REP-19939-014 "NUREG 0554 Safety Analysis Report for Fuel Cask Cranes Single Failure Proof Replacement Bridge Cranes at St. Lucie Units 1 & 2 Nuclear Generating Station," Revision 1 (Proprietary)
Requirement: A crane that has been immobilized because of failure of controls or components while holding a critical load should be able to hold the load or set the load down while repairs or adjustments are mad This can be accomplished by inclusion of features that will permit manual operation of the hoisting system and the bridge and trolley transfer mechanisms by means of appropriate emergency devices.
Category:
Crane Design Topic:
Seismic Events During Cask Movement Reference:
NUREG 0554, Section 2.5 Finding:
The St. Lucie crane is designed to retain control of a 150-ton load for abnormal conditions including a broken rope, two-blocking, and load hang-up during a safe shutdown earthquake (SSE) and operating basis earthquake (OBE). The trolley and bridge structures are robust in nature and have low centers of gravit The design gives the structure very little upward thrust and lateral displacement during a seismic even The bridge and trolley are provided with seismic hold down lugs so that the bridge and trolley remain in place on their respective runways with their wheels prevented from leaving the rails with the brakes applie All crane brakes are set when the crane is not being operated or power is remove A three dimensional model of the crane support structure - fuel handling building (FHB) was developed to perform the seismic analysi The model included the crane runway girders, crane bridge girders, end trucks, the trolley, and the crane runway steel support structure connected to the FHB analytical mode Both Unit 1 and Unit 2 were modele The geometric, stiffness and weight properties of the FHB were in accordance with Figure 3.7-9 and Table 3.7-5 of the Unit 1 Requirement: The crane should be designed to retain control of and hold the load, and the bridge and trolley should be designed to remain in place on their respective runways with their wheels prevented from leaving the tracks during a seismic event.
Page 6 of 43 Attachment 2
Updated Final Safety Analysis Report (UFSAR) and Figure 3.7-34 and Table 3.7-8 of the Unit 2 UFSAR, respectivel The crane runway support steel structure included the columns, vertical bracing, runway girders and walkway platform truss syste In each unit, two columns of the crane runway support structure are supported on the FHB roo Other columns are supported on reinforced concrete foundations at grade leve The soil spring constants for the column foundations for the seismic analysis were calculated using the formulae in Section 3.7.1.5 of the Unit 1 UFSAR and Section 3.7.2.4 of the Unit 2 UFSAR, respectivel In the model, three trolley positions on the bridge girder were considered, i.e., end of the bridge, 1/4 span of the bridge and midspan of the bridg These trolley positions were in accordance with Table NOG-4153.7-The analysis determined that the bridge will remain on the runway and the trolley will remain on the bridge with brakes applied while holding the 150-ton load during a seismic event.
Documents Reviewed:
-American Crane & Equipment Corp. Report REP-19939-009 "NUREG 0554 Compliance Report for Fuel Cask Cranes Single Failure Proof Replacement Bridge Cranes at St. Lucie Units 1 & 2 Nuclear Generating Station," Revision 1 (Proprietary)
-American Crane & Equipment Corp. Report REP-19939-014 "NUREG 0554 Safety Analysis Report for Fuel Cask Cranes Single Failure Proof Replacement Bridge Cranes at St. Lucie Units 1 & 2 Nuclear Generating Station," Revision 1 (Proprietary)
-American Society of Mechanical Engineers (ASME) NOG-1 "Rules for Construction of Overhead and Gantry Cranes," 1998-Updated Final Safety Analysis Report (UFSAR) for Saint Lucie Nuclear Power Station (Unit 1), Revision 22-Updated Final Safety Analysis Report (UFSAR) for Saint Lucie Nuclear Power Station (Unit 2), Revision 17 Category:
Crane Design Topic:
Seismically Induced Load Swing Reference:
NUREG 0554, Section 2.5; Reg Guide 1.29 Finding:
The pendulum and swinging load effect of the 150-ton load was simulated in the seismic analysis model by a beam element, one end connected to the trolley beam with the suspended weights on the other en The equivalent stiffness of the beam with the suspended weight at its end was calculated such that its frequency was equal to the pendulum frequency of the suspended weigh Two suspended weight positions were considered, uppermost position and lowermost positio These seismically induced pendulum and swing load effects were included in the structural analysis for the crane support structure for both the operating basis earthquake (OBE) and the design basis earthquake (DBE).
Documents Reviewed:
-American Crane & Equipment Corp. Report REP-19939-009 "NUREG 0554 Compliance Report for Fuel Cask Cranes Single Failure Proof Replacement Bridge Cranes at St. Lucie Units 1 & 2 Nuclear Generating Station," Revision 1 (Proprietary)
-American Crane & Equipment Corp. Report REP-19939-014 "NUREG 0554 Safety Analysis Report for Fuel Cask Cranes Single Failure Proof Replacement Bridge Cranes at St. Lucie Units 1 & 2 Nuclear Generating Station," Revision 1 (Proprietary)
Requirement: The maximum critical load plus operational and seismically induced pendulum and swing load effects on the crane should be considered in the design of the trolley and should be added to the trolley weight for the design of the bridge.
Page 7 of 43 Attachment 2
Category:
Crane Design Topic:
Trolley Bumpers Reference:
NUREG 0554, Sect 5.2; ASME B30.2, Section 2-1.8.3 Finding:
Compression bumpers, attached to the trolley, are included for buffering contact with the end of the travel stop Positive mechanical end stops are installed on the runway for limiting the bridge travel and on the bridge girders for limiting the trolley trave The crane has both slow down and stop limit switches on both the trolley and bridg The slow down switches are programmed at 10% so that the trolley and bridge will slow down to 10% of rated speed before impacting the end of travel limit switc This set-up should stop the trolley or bridge prior to contacting the bumpers.
Documents Reviewed:
-American Crane & Equipment Corp. Report REP-19939-009 "NUREG 0554 Compliance Report for Fuel Cask Cranes Single Failure Proof Replacement Bridge Cranes at St. Lucie Units 1 & 2 Nuclear Generating Station," Revision 1 (Proprietary)
-American Crane & Equipment Corp. Report REP-19939-014 "NUREG 0554 Safety Analysis Report for Fuel Cask Cranes Single Failure Proof Replacement Bridge Cranes at St. Lucie Units 1 & 2 Nuclear Generating Station," Revision 1 (Proprietary)
Requirement: A trolley shall be provided with bumpers, or other automatic means of equivalent effect, capable of stopping the trolley when traveling with power off in either direction at a speed of at least 50% of rated load speed.
Category:
Crane Design Topic:
Two-Block Protection Reference:
NUREG 0554, Section 4.5 Finding:
The mechanical and structural components of the main hoist system have been designed to withstand a two-block event without permanent deformation or damag In addition, two upper, redundant limit switches of different design and actuation are used to prevent two-blockin The first limit switch interrupts power to the raising circuit which will stop the motion and set the holding brak The second upper limit switch activates if the first switch fail The second switch de-energizes the hoist motor power supply when the lower block lifts a weighted arm suspended from the fram This limit switch also stops all hoisting motion and sets the holding brak Should both limit switches fail, a mechanical slip clutch is located between the gear box and moto The auxiliary hoist is not designed as single failure proof and is not used for critical lifts.
Documents Reviewed:
-American Crane & Equipment Corp. Report REP-19939-009 "NUREG 0554 Compliance Report for Fuel Cask Cranes Single Failure Proof Replacement Bridge Cranes at St. Lucie Units 1 & 2 Nuclear Generating Station," Revision 1 (Proprietary)
-American Crane & Equipment Corp. Report REP-19939-014 "NUREG 0554 Safety Requirement: The complete hoisting system should have the required strength to resist failure during two-blockin As an alternative, a system of upper travel limit switches may be used to prevent two-blockin The system should include two independent travel limit devices of different designs and activated by separate mechanical mean These devices should de-energize the hoist drive motor and the main power suppl The auxiliary hoist, if used for critical lifts, should also be equipped with two independent travel limit switches to prevent two-blocking.
Page 8 of 43 Attachment 2
Analysis Report for Fuel Cask Cranes Single Failure Proof Replacement Bridge Cranes at St. Lucie Units 1 & 2 Nuclear Generating Station," Revision 1 (Proprietary)
Category:
Crane Design Topic:
Wire Rope Breaking Strength Reference:
NUREG 0554, Section 4.1 Finding:
The St. Lucie crane has dual (two) wire rope The wire ropes for the crane are 1-1/4" diameter, 9 x 25 class, EEIPS ropes supplied by Python Nationa The minimum break strength requirement specified by the crane manufacturer was 122.5 ton The commercial grade dedication plan developed by American Crane and Equipment Company and included in the QA Document Package FPL P.O. 00052828 specified the minimum 122.5-ton breaking strength and stated that the ropes did not have to be tested to failur The QA Document Package also included the Hessville Cable and Sling C Certificate of Testing for the two wire ropes used on the cran The wire ropes were pull tested to 245,710 lbs (122.8 tons) by Hessville Cable and Sling Company on December 27, 2002 and did not brea The crane has two ropes, with each rope carrying 75 tons under normal operation The ropes are configured using a 16-part reeve to carry the full load (i.e. 8 reeves per rope).
Therefore, each reeve would carry 75/8 = 9.375 ton Using the manufacturer's minimum break strength value of 122.5 tons, 10% would equate to 12.25 tons, which is greater than the 9.375-ton weight being carried by each reeve at full load.
Documents Reviewed:
-Quality Assurance Document Package FPL P.O. 00052828, ACECO W.O. # 19940
"Section 8: Main Hoist Wire Rope" Requirement: The maximum load (including static and inertia forces) on each individual wire rope in the dual reeving system with the maximum critical load attached should not exceed 10%
of the manufacturer's published breaking strength.
Category:
Crane Design Topic:
Wire Rope Configuration Reference:
NUREG 0554, Section 4.1 Finding:
The main hoist design used two drums each with one rope, with a balanced dual reeving system with each rope terminating on the drum it originated o The main hoist reeving system provided independent load balance of the head and load blocks through a configuration of ropes and rope equalizer The main hoist employed an equalizer rocker beam and hydraulic shock absorbers to balance and distribute the forces associated with the load transfe Each rope was capable of handling the entire 150-ton load such that if Requirement: A dual rope reeving system with individual attaching points and a load balancing system will permit either rope system to hold and transfer the critical load without excessive shock in case of failure of the other rope syste The dual reeving system may be a single rope from each end of the drum terminating at one of the blocks or equalizer with provisions for equalizing beam-type load and rope stretch, with each rope designated for the total loa Alternatively, a two-rope system may be used from each drum or separate drums using a sheave equalizer or beam equalizer or other combination that provides two separate and complete reeving systems.
Page 9 of 43 Attachment 2
one rope breaks, the remaining intact reeving system would not be loaded to more than 40% of the braking strength of the wire rope, including the dynamic effects of the load transfe Each rope had an eight-part reeve such that each reeve would carry 150/8 =
18.75 tons should only one rope be available to carry the full 150-ton loa The rope strength was specified by the manufacturer as a minimum of 122.5 ton Forty percent of this value would be 122.5 x 0.4 = 49 tons, well above the required 18.75-ton strength needed to carry the full loa The design of the crane used one right-and one left-hand lay rop The Quality Assurance Package FPL PO 00052828 was reviewed concerning the specifications of the wire ropes for the cran Specifications for both a right regular lay rope and a left regular lay rope were included along with a picture showing the proper installation of the rope on the drums as to which drum would be wound with right lay and which would be wound with left la The specifications called for a 9 x 25 wire rope with diameter 1.250 to 1.313 inches and a minimum length of 980 fee The wire rope breaking strength was specified as a minimum of 122.5 ton The ropes were purchased from Python National and manufactured in German The certificate from the German company specified the dimensions of the wire rope as 1 1/4" with strand construction of 9 x 2 Documentation was provided in FPL PO 00052828 confirming the rope diameter was within specifications through actual measurements of the ropes.
Documents Reviewed:
-American Crane & Equipment Corp. Report REP-19939-009 "NUREG 0554 Compliance Report for Fuel Cask Cranes Single Failure Proof Replacement Bridge Cranes at St. Lucie Units 1 & 2 Nuclear Generating Station," Revision 1 (Proprietary)
-American Crane & Equipment Corp. Report REP-19939-014 "NUREG 0554 Safety Analysis Report for Fuel Cask Cranes Single Failure Proof Replacement Bridge Cranes at St. Lucie Units 1 & 2 Nuclear Generating Station," Revision 1 (Proprietary)
-Quality Assurance Document Package FPL P.O. 00052828, ACECO W.O. # 19940
"Section 8: Main Hoist Wire Rope" Category:
Crane Inspection/Maintenance Topic:
Crane Inspection - Frequent Reference:
ASME B30.2; Section 2-2.1.2 Finding:
The crane was classified by FPL as a Class A crane (Standby or Infrequent Service).
The licensee and the crane manufacturer (ACECO) inspect the crane and its components following Procedures MMP-74.02 and EMP-74.04.
Documents Reviewed:
-Procedure MMP-74.02 "Spent Fuel Cask Handling Crane Inspection," Revision 1A-Procedure EMP-74.04 "Cask Crane Annual Inspection," Revision 0 Requirement: Cranes in regular use shall be subjected to a frequent crane inspection monthly during normal service, weekly to monthly during heavy service, and daily to weekly during severe servic The frequent inspection points should include: a) operating mechanisms for proper operation; b) leakage in lines, tanks, valves, pumps, and other parts of the air or hydraulic systems; c) hooks for cracks, more than 15% of normal throat opening, or more than 10 degrees of twist; d) hook latches for proper operation; e) hoist ropes including end clamps; and e) the rope reeving syste All limit switches should be checked at the beginning of each work shift by inching, or running at slow speeds, each motion into its limit switch.
Page 10 of 43 Attachment 2
-Weekly and Daily Operational Checks or Inspections performed on February 11, 2008, February 18, 2008, and February 25, 2008.
Category:
Crane Inspection/Maintenance Topic:
Crane Inspection - Periodic Reference:
ASME B30.2; Section 2-2.1.3 Finding:
The licensee and the crane manufacturer (ACECO) inspect the crane and its components (e.g., hook) following Procedures MMP-74.02 and EMP-74.0 Among the items included in the annual inspection of the crane were: a) deformed, cracked or corroded members; b) loose bolts and rivets; c) cracked or worn sheaves and drums; d) worn, cracked or distorted pins, shafts, and rollers; e) excessive brake system wear; and f)
weigh scale and wind speed display damage or loose connection Procedure EMP-74.04 was used to test the operation of various electrical components of the crane including push buttons and limit switches.
Documents Reviewed:
-Procedure MMP-74.02 "Spent Fuel Cask Handling Crane Inspection," Revision 1A-Procedure EMP-74.04 "Cask Crane Annual Inspection, " Revision 0 Requirement: Cranes in regular use shall be subjected to a periodic crane inspection annually during normal and heavy service, and quarterly during severe servic The periodic inspection includes checking for: a) deformed, cracked or corroded members; b) loose bolts or rivets; c) cracked or worn sheaves and drums; d) worn, cracked or distorted pins, bearings, shafts, gears, and rollers; e) excessive brake system wear; f) load, wind, and other indicators over their full range for any significant inaccuracies; g) gasoline, diesel, electric, or other power plants for improper performance; h) excessive drive chain sprocket wear and chain stretch; i) deterioration of controllers, master switches, contacts, limit switches and pushbutton stations.
Category:
Crane Inspection/Maintenance Topic:
Crane Operational Testing Reference:
ASME B30.2; Sect 2-2.2.1 Finding:
The crane manufacturer performed an initial functional and load test (both 110% and 125%) on the trolley at its facility prior to shipping to the sit Crane operational tests, including 100% and 125% load tests, were performed at St. Lucie after the Unit 1 and Unit 2 cranes were installe This testing program was documented in Work Order Task 32016943-05, REP-19939-019 and REP 19939-020 for Unit 1 and Work Order Task 32016815-04, REP-19939-035, and REP-19939-036 for Unit The tests conducted on the new cranes were performed in 2003 and were significantly more extensive than required by ASME B3 The acceptance tests included the trolley, bridge, main hoist Requirement: Prior to initial use, all new, reinstalled, altered, extensively repaired or modified cranes shall be tested to ensure compliance with ASME B30.2 including the following: (a)
hoisting and lowering, (b) trolley travel, (c) bridge travel, (d) limit switches, and (e)
locking and safety device The trip setting of the hoist devices shall be determined by tests with an empty hook traveling in increasing speeds up to the maximum spee The actuating mechanism of the limit device shall be located so that it will trip the device under all conditions in sufficient time to prevent contact of the hook or load block with any part of the trolley or crane.
Page 11 of 43 Attachment 2
and auxiliary hoist and involved verification of the operability of the various safety features, indicating devices, crane controls, limit switches, brakes and holding device This included verification that the limit switches would operate properly to prevent the hook or load block from contacting the trolley or cran A 100% load test and 125%
load test were conducted on both the main hook and auxiliary hook and included moving the trolley and bridge through their entire ranges of motion while loade Post load test hook inspections were performed including magnetic particle nondestructive testing of the hooks after the 125% load tests.
The brakes drums were replaced in June 2006 and the crane vendor (American Crane Equipment Corporation) performed a functional test per REP-19939-04 Licensees staff stated that the wind speed instrument had been replaced and that Belfort Instrument Company, Cat. No. 120 and 122, Instruction Book No. 509754 was used to perform the operational/functional test.
Documents Reviewed:
-Procedure QI-3-PSL-1 "Design Control St. Lucie Plant," Appendix F "Implementer Turnover Package (ITOP)," Revision 13-Work Order Task No. 32016815-04 "Unit 2 Crane Load Test," dated May 11, 2004-Work Order Task No. 32016943-05 "Unit 1 Crane Load Test," dated June 15, 2004-REP-19939-019 "Site Acceptance Test Plan for Unit 1 Fuel Cask Crane," Revision 2-REP-19939-020 "Site Load Test Plan for Unit 1 Fuel Cask Crane," Revision 1-REP 19939-035 "Site Acceptance Test Plan for Unit 2 Fuel Cask Crane," Revision 2-REP-19939-036 "Site Load Test Plan for Unit 2 Fuel Cask Crane," Revision 1-REP-19939-045 "Test Plan for Torque Testing Main Hoist Electric Shoe Brakes,"
Revision 0-Work Order Task No. 34016024 05 "Defect Request: U1: CRN 135/R/R Brakes Drums"
-Work Order Task No. 34016024 08 "Defect Request: Wind Speed"
-Belfort Instrument Company, Catalog No. 120 and 122, Instruction Book No. 509754-ASME B30.2 "Overhead and Gantry Cranes," dated 1976 Category:
Crane Inspection/Maintenance Topic:
Hoist Overload Testing Reference:
NUREG 0554, Section 8.3; NUREG 0612, C-4, (9)
Finding:
The crane design employs an energy controlling device between the load and head block This device was tested as described in Section 8.3 of NUREG 055 The crane's design also used the NUREG 0554 alternative redundant upper limit switch design for defense in depth to prevent two-blockin The limit switches were field tested under load and calibrated to trip at 110% of the 150-ton loa During the 125% load test for the Unit 1 & 2 cranes, a jumper wire was installed within the main control circuit to allow the main hoist to lift the 125% loa After the load was lifted, the brakes tested, and the load lowered, the jumper wire was removed and an attempt made to lift the loa Verification was made that the hoisting motion in the up direction was disabled and the Requirement: If the hoisting system is designed with adequate strength to resist failure during load hang-up, the hoisting system should be tested by securing the load-block-attaching points to a fixed anchor and applying the maximum critical loa Alternately, if a load cell system, a motor current-sensing device, or a mechanical load-limiting device is provided to prevent load hang-up, the device(s) should be tested to verify operability.
Page 12 of 43 Attachment 2
hoist would only operate in the down directio For the Unit 2 crane, this test was conducted November 4, 200 For the Unit 1 crane, the test was conducted November 7, 2003.
Documents Reviewed:
-American Crane & Equipment Corp. Report REP-19939-009 "NUREG 0554 Compliance Report for Fuel Cask Cranes Single Failure Proof Replacement Bridge Cranes at St. Lucie Units 1 & 2 Nuclear Generating Station," Revision 1 (Proprietary)
-American Crane & Equipment Corp. Report REP-19939-014 "NUREG 0554 Safety Analysis Report for Fuel Cask Cranes Single Failure Proof Replacement Bridge Cranes at St. Lucie Units 1 & 2 Nuclear Generating Station," Revision 1 (Proprietary)
-NUREG-0554 "Single Failure Proof Cranes for Nuclear Power Plants," dated May 1979-Work Order Task No. 32016943-05 "Unit 1 Crane Load Test," dated June 15, 2004-REP-19939-019 "Site Acceptance Test Plan for Unit 1 Fuel Cask Crane," Revision 2-REP-19939-020 "Site Load Test Plan for Unit 1 Fuel Cask Crane," Revision 1-Work Order Task No. 32016815-04 "Unit 2 Crane Load Test," dated May 11, 2004-REP 19939-035 "Site Acceptance Test Plan for Unit 2 Fuel Cask Crane," Revision 2-REP-19939-036 "Site Load Test Plan for Unit 2 Fuel Cask Crane," Revision 1 Category:
Crane Inspection/Maintenance Topic:
Hoist Two-Block Testing - Limit Device Method Reference:
NUREG 0612, C-4, (8)
Finding:
The main hoist limit switch was tested as part of the crane operational testing after the new cranes were installed in 2003 and is documented in Section III.F.4 of the two respective Acceptance Test Plan The main hoist was run in the up direction until the limit switch tripped the hois Verification was made that two-blocking did not occur and that hoist motion was disable The crane fault pilot lit and the main hoist paddle limit pilot light properly lit.
Documents Reviewed:
-REP-19939-019 "Site Acceptance Test Plan for Unit 1 Fuel Cask Crane," Revision 2-REP 19939-035 "Site Acceptance Test Plan for Unit 2 Fuel Cask Crane," Revision 2 Requirement: If the hoisting system is provided with a system of upper travel limit switches to prevent two-blocking, the travel limit switches should be tested to verify operabilit If the crane is equipped with a load limiter (strain gage, etc.) the load limiter should be tested to verify operability.
Category:
Crane Inspection/Maintenance Topic:
Hoist Two-Block Testing - Strength Method Reference:
NUREG 0554, Section 8.3; NUREG 0612, C-3 (8)
Finding:
The crane design employs an energy controlling device between the load and head Requirement: If the hoisting system is equipped with an energy-controlling device between the load and head blocks, the complete hoisting machinery should be allowed to two-block during the hoisting test (load block limit and safety device are bypassed). This test, conducted at low speed without load, should provide assurance of the integrity of the design, the equipment, the controls and the overload protection device The test should demonstrate that the maximum torque that can be developed by the driving system, including the inertia of the rotating parts at the over torque condition, will be absorbed or controlled during two-blocking or load hang-up.
Page 13 of 43 Attachment 2
block A two-block test of the main hoist was successfully performed during factory functional testing in accordance with Section 8.3 of NUREG 0554.
Documents Reviewed:
-American Crane & Equipment Corp. Report REP-19939-009 "NUREG 0554 Compliance Report for Fuel Cask Cranes Single Failure Proof Replacement Bridge Cranes at St. Lucie Units 1 & 2 Nuclear Generating Station," Revision 1 (Proprietary)
-American Crane & Equipment Corp. Report REP-19939-014 "NUREG 0554 Safety Analysis Report for Fuel Cask Cranes Single Failure Proof Replacement Bridge Cranes at St. Lucie Units 1 & 2 Nuclear Generating Station," Revision 1 (Proprietary)
-NUREG-0554 "Single Failure Proof Cranes for Nuclear Power Plants," dated May 1979 Category:
Crane Inspection/Maintenance Topic:
Hook Inspections - Frequent Reference:
ASME B30.10, Sections 10-1.4.2 and 10-1.4.6 Finding:
The licensee and the crane manufacturer (ACECO) inspected the crane and its components in accordance with Procedure MMP-74.0 This procedure included steps in which the operators share inspection results with the maintenance supervisor to determine if inspection results are acceptabl In accordance with Work Order Task N, the licensee also follows OSHA regulations 29 CFR 1910.179, "Overhead and Gantry Cranes," when scheduling cranes and hook inspection Requirements in 29 CFR 1910.179 are in general agreement with ASME B30.10, Section 10-1.4.2 and 10-1.4.6.
Documents Reviewed:
-Procedure MMP-74.02, "Spent Fuel Cask Handling Crane Inspection," Revision 1A-Work Order Task No. 37006249 01, "Fuel Handling Building Spent Fuel Cask Handling Crane: Inspection," (12 months)
Requirement: Hooks shall be inspected monthly during normal service, weekly to monthly during heavy service and daily to weekly during severe servic Hooks shall be inspected for: a)
distortion such as bending, twisting or increased throat opening; b) cracks, severe nicks, or gouges; c) damaged or malfunctioning latch (if provided); and d) hook attachment and securing mean Hooks having any of the following deficiencies shall be removed from service unless a qualified person approves their continue use and initiates corrective action: a) cracks; b) wear exceeding 10% of the original sectional dimension; c) bend or twist exceeding 10 degrees from the plane of an unbent hook; and d) an increase in throat opening of 15% (for hooks without latches).
Category:
Crane Inspection/Maintenance Topic:
Preventive Maintenance Program Reference:
ASME B30.2; Section 2-2.3.1 Finding:
In general, the licensee has incorporated the manufacturers recommendations in its preventive maintenance program for the fuel building cranes and has addressed discrepancies between the manufacturers recommendations and the St. Lucies preventive maintenance program through several condition report The licensee incorporated the preventive maintenance bases (PMB) in Passports softwar The preventive maintenance bases contained the preventive maintenance scope and its Requirement: A preventive maintenance program should be established based on the crane manufacturer's or a qualified persons recommendations.
Page 14 of 43 Attachment 2
required/suggested frequenc Licensee staff stated that preventive maintenance on the cranes would be performed weekly during fuel movement campaigns and monthly when fuel loading is not underwa Procedure MMP-74.02 is used to perform operational checks prior to using the crane.
Documents Reviewed:
-Procedure 0010431 "Preventive Maintenance Program," Revision 35-REP-19939-037 "Annual Preventative Maintenance Plan for 150/25-Ton Unit 1 Cask Handling Crane Florida Power & Light St. Lucie Station (PSL)," American Crane &
Equipment Corporation, dated July 11, 2003 REP-19939-038 "Annual Preventative Maintenance Plan for 150/25-Ton Unit 2 Cask Handling Crane Florida Power & Light St. Lucie Station (PSL)," American Crane &
Equipment Corporation, dated July 11, 2003-Procedure MMP-74.02 "Spent Fuel Cask Handling Crane Inspection," Revision 1A-Procedure EMP-74.04 "Cask Crane Annual Inspection," Revision 0-Condition Report (CR) 2006-21936 "U 1 Cask Crane PM Discrepancies"
-PCR-06-3762, "Bring into Line with ACECO PM and Incorporate Improvements Identified in CR-2006-21936" Category:
Crane Inspection/Maintenance Topic:
Welding Reference:
NUREG 0554, Section 2.8; NUREG 0612, C-3 (3)
Finding:
This requirement was not relevant to the crane support structures due to all on-site crane connections being bolted and not welde The crane was brought to the site and assembled in large modules with bolts alleviating the need to weld structural joints which could lead to a failure involving a critical load.
Documents Reviewed:
Requirement: All welding on load-sustaining members shall be in accordance with American Welding Society (AWS) structural welding code AWS D1.1, except as modified by AWS D1 All critical welds (joints whose failure could result in a drop of a critical load) should be post weld heat treated in accordance with AWS D1.1, Subarticle As a substitute for post weld heat treatment of crane structures already built or in operation, the critical welds should be nondestructively examined to ascertain that the weldments are acceptable.
Category:
Crane Load Testing Topic:
Cold Proof Testing Reference:
NUREG 0554, Section 2.4; NUREG 0612, C-2 (8)
Requirement: Minimum operating temperatures for the crane should be specified to reduce the possibility of brittle fracture of the ferritic load-carrying members of the cran The minimum temperature can be determined by: 1) a drop weight test per ASTM E-208, 2)
a Charpy test per ASTM A-370 or 3) a 125% cold proof tes If the crane is made of low alloy steel such as ASTM A514, cold proof testing should be don If cold proof testing is omitted, the default minimum crane operating temperature is 70 degrees For crane operation at temperatures below 70 degrees F, cold proof testing must be performed and the ambient temperature at which the testing is conducted becomes the minimum crane operating temperature.
Page 15 of 43 Attachment 2
Finding:
The minimum operating temperature was determined through Charpy tests by the crane and yoke manufacture The Charpy tests were performed at -2 degree F for crane components and at 0 degree F for the yok A review of site weather conditions in the Updated Final Safety Analysis Report for Unit 2, Section 2.3.2.1.2, "Temperature and Atmospheric Water Vapor," determined that the lowest temperature that has been recorded at the St. Lucie site was 28 degree F, well above the Charpy Test temperature Based on the Charpy test results, the St. Lucie cranes would be operable year round for cask loading activities.
Documents Reviewed:
-Work Order 20016 "American Crane and Equipment Corporation Commercial Grade Dedication Evaluation, Project: Palo Verde Units 1 and 2 (SFP Trolleys)"
-Purchase Order L27746 "Certificate of Compliance (10 CFR Part 50, Appendix B Orders, 10 CFR Applies), Certified Test Report MUS001-02-07-16889"
-Purchase Order L27743 "Certificate of Compliance (10 CFR Part 50, Appendix B Orders, 10 CFR Applies), Certified Test Report MUS001-02-07-16887"
-Purchase Order L27741 "Certificate of Compliance (10 CFR Part 50, Appendix B Orders, 10 CFR Applies), Certified Test Report MUS001-02-07-16890"
-Purchase Order L35526 "Certificate of Compliance (10 CFR Part 50, Appendix B Orders, 10 CFR Applies), Certified Test Report MUS001-02-10-24742"
-Purchase Order 20070093-1 "Certified Test Report CPS001-07-05-14575-1"
-Purchase Order 20070093-2,3 "Certified Test Report CPS001-07-05-12809-1"
-Material Test Report 0000032258 "Heavy Hexagonal Nut"
-Material Test Report 0000032268 "Heavy Hexagonal Structural Bolt"
-Material Test Report 0000032259 "Heavy Hexagonal Nut"
-Material Test Report 0000032267 "Heavy Hexagonal Structural Bolt"
-Updated Final Safety Analysis Report (UFSAR) for Saint Lucie Nuclear Power Station (Unit 1), Revision 22-Updated Final Safety Analysis Report (UFSAR) for Saint Lucie Nuclear Power Station (Unit 2), Revision 17-American Crane & Equipment Corp. Report REP-19939-009 "NUREG 0554 Compliance Report for Fuel Cask Cranes Single Failure Proof Replacement Bridge Cranes at St. Lucie Units 1 & 2 Nuclear Generating Station," Revision 1 (Proprietary)
-ND-2226.4-ND-2311, ND-2311 "Material for Which Impact Testing is Required," 1986 Edition.
-ND-2226.4-ND-2331, ND-2331 "Pressure Retaining Material Other Than Bolting,"
1986 Edition.-Purchase Order Category:
Crane Load Testing Topic:
Dynamic Load Testing Reference:
NUREG 0554, Section 8.2 Finding:
The trolley was static load tested at 125% load at the factor At the site, the 100% load Requirement: After the 125% static load test, the crane should be given a full performance test with 100% of the maximum critical load attached, for all speeds and motions for which the system is designe This should include verifying all limiting and safety control device The features provided for manual lowering of the load and manual movement of the bridge and trolley during an emergency should be tested with the maximum critical load attached.
Page 16 of 43 Attachment 2
test was performed first, followed by the 125% load tes Both the 100% load test and 125% load test included testing the brakes, moving the load across the entire span of the bridge and moving the bridge the full length of the runwa During the 100% load test, manual lowering of the load was performed for a distance of 4 feet using the hand pump and manual control knob on the hydraulic brake power unit.
Documents Reviewed:
-American Crane & Equipment Corp. Report REP-19939-014 "NUREG 0554 Safety Analysis Report for Fuel Cask Cranes Single Failure Proof Replacement Bridge Cranes at St. Lucie Units 1 & 2 Nuclear Generating Station," Revision 1 (Proprietary)
-REP-19939-020 "Site Load Test Plan for Unit 1 Fuel Cask Crane," Revision 1-REP-19939-036 "Site Load Test Plan for Unit 2 Fuel Cask Crane," Revision 1 Category:
Crane Load Testing Topic:
Hook Load Testing Reference:
NUREG 0554, Sect 4.3; ASME B30.10, Sect 10-1.1.2 Finding:
Prior to delivery to St. Lucie, a 200% (300 ton) static load test was performed on each load attaching point, the hook prongs, and pin hole for the main hois Measurements of the geometric configuration of each hook was made before and after the tes Hook nondestructive testing was performed including an ultrasonic testing of the base material prior to load testing followed by magnetic particle (MT) testing of the surface after the 200% load tes During the 100% load test and 125% load test at the St. Lucie site, the hook throat opening was monitored. The main hook, for both the Unit 1 and Unit 2 hooks, had a throat opening measurement of 15.5" before each tes The opening size did not change after the load test After the 125% load test, a magnetic particle nondestructive test was performed on both hooks on November 11, 200 The acceptance criteria listed in Section II.K.3 of REP-19939-020 and REP-19939-036 were no linear indications parallel to the hook contour greater than 1/8 inch long whose length is equal to or greater than 3 times its widt Indications transverse to the hook contour and/or cracks were not acceptabl The results of the magnetic particle tests were attached to REP-19939-020 for Unit 1 and REP-19939-036 for Unit The hooks were found to meet the acceptance criteria.
Documents Reviewed:
-American Crane & Equipment Corp. Report REP-19939-009 "NUREG 0554 Compliance Report for Fuel Cask Cranes Single Failure Proof Replacement Bridge Cranes at St. Lucie Units 1 & 2 Nuclear Generating Station," Revision 1 (Proprietary)
-American Crane & Equipment Corp. Report REP-19939-014 "NUREG 0554 Safety Analysis Report for Fuel Cask Cranes Single Failure Proof Replacement Bridge Cranes at St. Lucie Units 1 & 2 Nuclear Generating Station," Revision 1 (Proprietary)
Requirement: A 200% static load test should be performed for each load-attaching hoo For a duplex (sister) hook, the proof load shall be shared by the two sisters unless the hook is designed for unbalanced loadin Measurements of the geometric configuration of the hooks should be made before and after the test and the acceptance criteria is no permanent increase in throat opening in excess of 0.5% or 0.010 inches (0.25 mm). The load testing should be followed by a nondestructive examination that should consist of volumetric and surface examinations to verify the soundness of fabrication and ensure integrity of the hooks.
Page 17 of 43 Attachment 2
-REP-19939-020 "Site Load Test Plan for Unit 1 Fuel Cask Crane," Revision 1-REP-19939-036 "Site Load Test Plan for Unit 2 Fuel Cask Crane," Revision 1 Category:
Crane Load Testing Topic:
Maximum Weight of Canister Reference:
N/A Finding:
The spent fuel cask crane was rated for 150 tons with a yoke rated for 125 ton Table 3.2.2 of the CoC 72-1030 FSAR lists the weight of an OS187H transfer cask loaded with spent fuel as 114.3 ton At St. Lucie, the heavy lift of a loaded cask from the spent fuel building to the cask handling facility involved a fully loaded transfer cask filled with wate During the lift of the first loaded cask, the load cell on the crane indicated a reading of 119.5 ton The load cell weight included the added weight of the yoke, rope and water in the canister.
Documents Reviewed:
Certificate of Compliance 72-1030, Final Safety Analysis Report (FSAR), Revision 1 Requirement: The maximum weight of the transfer cask containing the canister filled with water and fuel (including dynamic loads) that will be lifted by the crane is to be verified to be within the crane's rated capacity.
Category:
Crane Load Testing Topic:
Rated Load Marking Reference:
NUREG 0554, Section 8.5; ASME B30.2, Sect 2-1.1.1 Finding:
The 150-ton crane rating was properly labeled on the crane.
Documents Reviewed:
N/A Requirement: The rated load shall be marked on each side of the crane and, if the crane has more than one hoisting unit, each hoist shall have its rated load marked on it or on its load bloc This marking shall be legible from the ground or floor.
Category:
Crane Load Testing Topic:
Static Load Testing Reference:
NUREG 0554, Section 8.2 Finding:
An extensive load test program was established to test the new Unit 1 and Unit 2 spent fuel building crane This included pre-operational inspections of the crane's electrical, hydraulic and structural components; inspection of the rope, hook and yoke, including measurements of the hook throat openings; inspection of the brakes and safety systems; and the full range of movements of the trolley, bridge and hoo The 125% load test for the Unit 1 crane was conducted on November 7, 2003 using a test load of 376,014 lbs (188 tons). This met the 125% load test requirement (i.e. 125% x 150 tons = 18 tons). The Unit 2 crane was tested on November 4, 2003 using a 375,800 lb (187.9 ton)
test weigh The trolley and bridge were moved through their full range of motions that would be experienced during the fuel cask movement activities.
Requirement: The crane should be static load tested at 125% of the maximum critical loa The test should be conducted at all positions generating maximum strain in the bridge and trolley structures and other positions as recommended by the designer or manufacturer.
Page 18 of 43 Attachment 2
Documents Reviewed:
-REP-19939-019 "Site Acceptance Test Plan for Unit 1 Fuel Cask Crane," Revision 2-REP-19939-020 "Site Load Test Plan for Unit 1 Fuel Cask Crane," Revision 1-REP 19939-035 "Site Acceptance Test Plan for Unit 2 Fuel Cask Crane," Revision 2-REP-19939-036 "Site Load Test Plan for Unit 2 Fuel Cask Crane," Revision 1 Category:
Crane Operation Topic:
Minimum of Two Wraps of Rope Reference:
ASME B30.2, Section 2-3.2.3 (h)
Finding:
Verification that at least two full wraps of rope were left on the drum was performed during the crane acceptance testing in 200 This was documented in REP-19939-019 for Unit 1 and REP-19939-035 for Unit 2 during the main hoist low-low limit key switch test.
Documents Reviewed:
-REP-19939-019 "Site Acceptance Test Plan for Unit 1 Fuel Cask Crane," Revision 2-REP 19939-035 "Site Acceptance Test Plan for Unit 2 Fuel Cask Crane," Revision 2 Requirement: The load shall not be lowered below the point where two wraps of rope remain on each anchorage of the hoisting drum unless a lower-limit device is provided, in which case no less than one wrap shall remain.
Category:
Crane Operation Topic:
Qualification For Crane Operator Reference:
ASME B30.2, Sections 2-3.1.2 and 2-3.1.6 Finding:
Procedure 0010438, Section 8.1, "Crane Operator Qualification," stated that operators eye exam would be successful with a vision of at least 20/40 in both eyes, with or without corrective lenses and physically fit without evidence of heart problems or seizure The requirement for vision of 20/40 was not consistent with the ASME 2 requirement of 20/30 Snelling in one eye and 20/50 in the othe The physical examination criteria for the crane operators used by the FPLs clinic referenced ASME B3 The licensee issued Condition Report (CR) 2008-6488 to address consistency between Procedure 0010438, the physical examination criteria for the crane operators, and the ASME B30.2 standar The other requirements in ASME B30.2 were adequately incorporated into the licensee's procedure.
Documents Reviewed:
-Physician Examination Criteria," FPL Medical Clinic," dated August 22, 2006-Procedure 0010438 "Control of Heavy Loads," Revision 45-Plant Training Material-IM No. 1302060, "Control of Heavy Loads," dated 3/9/2007.
-Learning Management System Output, "Learner Curriculum Item Status" (Crane Operators Qualifications)
Requirement: Qualification to operate a cab-operated or remote-operated crane requires the operator to pass a written or oral examination and a practical operating examination specific to the type of crane to be operate In addition, the operator shall: a) have vision of at least 20/30 Snellon in one eye and 20/50 in the other with or without corrective lenses; b) be able to distinguish colors regardless of their position; c) have sufficient hearing capability for the specific operation with or without hearing aids; d) have sufficient strength, endurance, agility, coordination and reaction speed for the specific operation; e) not be subject to seizures, loss of control or dizziness; and f) have normal field of vision and depth perception.
Page 19 of 43 Attachment 2
-Condition Report (CR) 2008-6488 "AP-0010438, Control of Heavy Loads, Section 8.1.A, Annual Physical and Eye Exam"
-ASME B30.2 "Overhead and Gantry Cranes," dated 1976 Category:
Crane Operation Topic:
Warning Signals Reference:
ASME B30.2, Section 2-3.1.7 (e)
Finding:
The crane provides intermittent beeping whenever the crane was travelin The crane was also equipped with a red light and a blue ligh The red light was illuminated when the "load" was lifted and the operator was in the ca The blue light was illuminated when the "load" was lifted and the operator was using the remote control During the dry run demonstrations, the area under the lift was roped off to keep personnel not involved with the lift out of the work area.
Documents Reviewed:
Direct observation Requirement: If a warning device is furnished. It shall be activated each time before traveling, and intermittently when approaching workpersons.
Category:
Drying/Helium Backfill Topic:
Drying Final Pressure Reference:
CoC 1030, Tech Spec 3.1.1 Finding:
Procedure MMP-116.12, Step 6.11.13 required a final vacuum drying pressure of less than 2000 mtorr for 30 minute This is more conservative than the required 3 torr (3000 mtorr) in the technical specification to account for instrument error on the measuring devices.
Documents Reviewed:
Procedure MMP-116.12 "ISFSI Dry Shielded Canister Sealing Operations," Revision 0 Requirement: The 32PTH canister vacuum drying pressure shall be sustained at or below 3.0 torr (3 mm Hg) absolute for a period of at least 30 minutes following evacuation.
Category:
Drying/Helium Backfill Topic:
Drying Time Limits - Procedure C Reference:
CoC 1030, Tech Spec 3.1.1 Finding:
Procedure MMP-116.12 specified the use of Technical Specification LCO 3.1.1,
"Procedure C," which is implemented by using a helium cover gas to facilitate the pumpdown and maintain the transfer cask annulus temperature below 180 degree F until such time that the transfer cask annulus is drained to facilitate canister heatup for vacuum dryin Procedure C specifies that for canisters with a heat load of less than 22.4 kW, there was no time limit for completing vacuum dryin For canisters over 2 kW, there was a 42-hour limit after the canister is drained or a 28-hour limit when the transfer cask cavity/annulus was drained, which ever was more limitin Procedure Requirement: Technical Specification 3.1.1 establishes vacuum drying time limits for the canister based on the cask heat load, water temperature (180 degree limit) in the transfer casks, and when water is drained from the transfer cask cavity/annulu Three situations are described and designated as Procedure A, B, or C with different criteria than can be selected by the licensee.
Page 20 of 43 Attachment 2
MMP-116.12 contained actions within Step 6.8, "Removing DSC Bulk Water using Pumpdown Method," to determine the vacuum drying time limitation based on the technical specification requirement and the heat load for each caniste Since the total heat load for each of the canisters being loaded in this initial loading campaign was less than 22.4 kW (see Table 4 of Calculation PSL-1FJF-07-002), the technical specification did not require a time limit for vacuum drying the canisters currently being loade For the first canister loaded (DSC-2) at St. Lucie, the drying time was approximately 26 hour3.009259e-4 days <br />0.00722 hours <br />4.298942e-5 weeks <br />9.893e-6 months <br /> The water in the transfer cask annulus was measured on an hourly basis throughout the time water was present and documented on Appendix B "Transfer Cask Annulus Water Temperature Control" to Procedure MMP-116.1 Initial water temperature was 90 degree Over the 80-hour period, the temperature eventually peaked at 136 degree A very slow rate of temperature increase was observed, averaging about 0.5 degree F/hour.
Documents Reviewed:
-Procedure MMP-116.12 "ISFSI Dry Shielded Canister Sealing Operations," Revision 0-Calculation PSL-1FJF-07-002 "St. Lucie Unit 1 - Irradiated Fuel Assembly Selection for Initial Dry Cask Loading Campaign," Revision 1 Category:
Drying/Helium Backfill Topic:
Helium Backfill Final Pressure Reference:
CoC 1030, Tech Spec 3.1.2 Finding:
Procedure MMP-116.12, Steps 6.15.6 through 6.15.12 established the helium backfill pressure requirement as 2.5 psig +/- 0.5 psig, stable for 30 minutes after filling.
Documents Reviewed:
Procedure MMP-116.12 "ISFSI Dry Shielded Canister Sealing Operations," Revision 4 Requirement: The 32PTH helium backfill pressure shall be 1.5 to 3.5 psig and stable for 30 minutes after filling after completion of vacuum drying.
Category:
Drying/Helium Backfill Topic:
Helium Pressure Test Reference:
FSAR 1030, Section 8.1.1.3.19a Finding:
Procedure MMP-116.12, Steps 6.12.13, 6.12.14 and 6.12.15, required the canister to be backfilled with helium to a pressure of 16.75 to 17.75 psig for 10 minutes.
Documents Reviewed:
Procedure MMP-116.12 "ISFSI Dry Shielded Canister Sealing Operations," Revision 0 Requirement: Following initial evacuation, backfill the canister with helium to 16.5 to 18.0 psig and hold for 10 minutes.
Category:
Drying/Helium Backfill Topic:
Helium Purity Reference:
FSAR 1030, Section 8.1.1.3.14 Finding:
The license purchased standard grade helium from a vendor for use in backfilling the canister The licensee had the purity of the helium confirmed using an independent analytical laboratory using gas chromatography and other analytical techniques against Requirement: All helium used in backfilling operations shall be at least 99.99% pure.
Page 21 of 43 Attachment 2
certified standard The Certificate of Analysis from the independent laboratory for three helium cylinders was reviewe The analysis for all three cylinders confirmed the helium gas exceeded 99.999% purity.
Documents Reviewed:
-Matheson Tri-Gas, Purchase Order 00110686 "Certificate of Analysis," dated March 6, 2008-FPL/FPLE QA Surveillance 08.06.MTGIL.08.1(A) of Mathison Tri-Gas dated March 6, 2008 Category:
Emergency Planning Topic:
Emergency Plan Reference:
Finding:
The St. Lucie Radiological Emergency Plan identified the ISFSI in Table 3-1
"Emergency Classification Table." Emergency Plan Implementing Procedure - 01, Sections 4.2, "Emergency Classes," and Section 4.3, "Classification Table," described the Emergency Action Levels (EALs) for the St. Lucie sit An EAL for an Unusual Event was included for ISFSI-related accidents.
Documents Reviewed:
-Radiological Emergency Plan, Revision 52-Emergency Plan Implementing Procedure - 01, Revision 15 Requirement: For an ISFSI that is located on the site of a nuclear power plant licensed for operation, the Emergency Plan required by 10 CFR 50.47 shall be deemed to satisfy the requirements of this section.
Category:
Emergency Planning Topic:
Emergency Plan Changes Reference:
Finding:
The licensee complied with 10 CFR 50.4, which requires a change to the emergency plan be submitted to the NRC within thirty day Compliance with 10 CFR 50.4 satisfies the requirements of 10 CFR 72.44(f). Revisions 51 of the St. Lucie Radiological Emergency Plan was reviewe Revision 51 was implemented on December 27, 200 The change was submitted to the NRC via letter dated January 15, 2008, well within the 30-day requiremen Revision 52 was recently issued and the submittal to the NRC was scheduled to be transmitted to the NRC by April, 3, 2008, within the 30-day requirement of 10 CFR 50.4.
Documents Reviewed:
Radiological Emergency Plan, Revision 52 Requirement: Within six months of any changes made to the emergency plan, the licensee shall submit a report containing a description of the changes to the appropriate regional office and headquarters.
Category:
Fire Protection Topic:
Fire Protection Plan Reference:
Requirement: Each operating nuclear power plant must have a fire protection plan that satisfies Criterion 3 of Appendix A to Part 5 This fire protection plan must describe the overall Page 22 of 43 Attachment 2
Finding:
Fire protection planning for St. Lucie, Unit 2 was described in Administrative Procedure 2-180002 Appendix I included planning for response to a fire associated with ISFSI activities and movement of a loaded cask between the cask handling building and the ISFS During the dry run activates observed by the NRC, the licensee stationed personnel along the transport route with instructions to keep vehicles and personnel away from the cask during transpor This ensured that no unanalyzed combustionable sources were introduced to the transport route due to other site activitie Arrangements were established for emergency personnel to have access to the ISFSI are Annual training, site tours and fire drills related to the ISFSI operations had been coordinated with offsite fire department.
Documents Reviewed:
- Administrative Procedure 2-1800023 "Unit 2 Fire Fighting Strategies," Revision 28
- St. Lucie Plant Training Report "Local Fire Department Overview of Plant ISFSI Facility and Site Location," dated Feb. 18, 2008, Feb. 19, 2008, and Feb. 20, 2008
- Annual Fire Drill with St. Lucie County Fire Department, dated September 6, 2007 fire protection program for the facility.
Category:
Fire Protection Topic:
Offsite Emergency Support Reference:
Finding:
The licensee's plans for responding to an emergency at the site, including the ISFSI and during transport of a loaded cask to the ISFSI, included arrangements for notifying offsite emergency response organizations (i.e. ambulance and fire department) and for response personnel to have access to the ISFSI are Administrative Procedure 2-1800023, Appendix I described the emergency response plans related to the ISFS Annual training, site tours and fire drills related to the ISFSI operations have included coordination with offsite response organizations.
Documents Reviewed:
- Administrative Procedure 2-1800023 "Unit 2 Fire Fighting Strategies," Revision 28
- St. Lucie Plant Training Report "Local Fire Department Overview of Plant ISFSI Facility and Site Location," dated February 18, 2008, February 19, 2008, and February 20, 2008
- Annual Fire Drill with St. Lucie County Fire Department, dated September 6, 2007 Requirement: Structures systems and components important to safety must be designed for emergencie The design must provide accessibility to emergency equipment, facilities and services such as hospitals, fire and police departments, ambulance services, and other emergency agencies.
Category:
Fuel Selection/Verification Topic:
Approved Contents Reference:
CoC 1030, Tech Spec 2.1.d Finding:
The limit of 16 damaged fuel assemblies per canister was specified in Engineering Package PC/M 07130 and was verified in the loading patterns described in Attachment 1 to PC/M 07130 and Calculation PSL-1FJF-07-002.
Requirement: The 32PTH canister is authorized for storage of 32 intact fuel assemblies, or up to 16 damaged fuel assemblies with the balance being intact assemblies.
Page 23 of 43 Attachment 2
Documents Reviewed:
-Engineering Package (EP) - PC/M 07130 "Fuel Selection and Initial Dry Cask Loading Campaign at St. Lucie Unit 1," Revision 6-Calculation PSL-1FJF-07-002 "St. Lucie Unit 1 - Irradiated Fuel Assembly Selection for Initial Dry Cask Loading Campaign," Revision 1 Category:
Fuel Selection/Verification Topic:
Approved Spent Fuel Types Reference:
CoC 1030, Tech Spec 2.1.b Finding:
The fuel-related specifications in Table 1 of Calculation PSL-1FJF-07-002, were reviewed and were found to reflect the requirements of Tables 1 and 2 referenced in Technical Specification 2.1.b.
Documents Reviewed:
Calculation PSL-1FJF-07-002 "St. Lucie Unit 1 - Irradiated Fuel Assembly Selection for Initial Dry Cask Loading Campaign," Revision 1 Requirement: Spent fuel assemblies authorized for storage in the 32PTH are limited to the fuel types specified in Table Equivalent reload fuel assemblies that are enveloped by the fuel assembly design characteristics listed in Table 2 for a given fuel assembly class are also acceptable for storage.
Category:
Fuel Selection/Verification Topic:
Classifying Damaged Fuel Reference:
Interim Staff Guidance ISG-1 Finding:
Table 3 of Calculation PSL-1FJF-07-002 classified each of the 192 assemblies, identified as candidates for loading, as either "intact" or "damaged." The classification of each
"intact" assembly was based on post-discharge sipping and/or post-discharge ultrasonic testing or by reactor coolant system chemistry analysi These methods were consistent with the guidance in ISG-The first canister loaded at St. Lucie included only intact fuel assemblies.
Documents Reviewed:
-Calculation PSL-1FJF-07-002 "St. Lucie Unit 1 - Irradiated Fuel Assembly Selection for Initial Dry Cask Loading Campaign," Revision 1-NRC Interim Staff Guidance (ISG) - 1 "Damaged Fuel," Revision 1 Requirement: The process for classifying spent fuel as intact or damaged should be consistent with Interim Staff Guidance ISG-Fuel assemblies discharged from operating cycles with no chemistry indications of cladding breaches may be classified as intact without further evaluatio Fuel assemblies discharged from operating cycles with chemistry indications of cladding breaches shall be classified as damaged, pending fuel sipping or ultrasonic testing results confirming the fuel assembly has not experienced cladding failur Fuel assemblies with visible cladding breaches shall be classified as damaged.
Category:
Fuel Selection/Verification Topic:
Decay Heat Load Reference:
CoC 1030, Tech Spec 2.1.c Requirement: The maximum heat load for a single fuel assembly, including insert components, is k The maximum heat load for a 32PTH canister is 33.8 kW for CE 14 X 14 fuel assemblies.
Page 24 of 43 Attachment 2
Finding:
Engineering Package PC/M 07130 established the conditions for St. Lucie Unit 1's first loading campaign which will consist of six-PTH type C canisters loaded with both intact or damaged CE 14 x 14 fuel assemblie Calculation PSL-1FJF-07-002 verified that the calculated maximum heat load for each individual assembly selected for this first loading campaign was below 1.5 k Attachment 1 "Fuel Loading Pattern - DSC" listed each individual assembly showing their calculated heat loa Table 4 documented the calculated total heat load for each of the six canister to be loaded in this first campaig All canisters were below the Technical Specification limit of 33.8 k Procedure 1-NOP-116.01 was used by the licensee to load the first canister (DSC-2) on March 10, 200 The heat load for the 32 spent fuel assemblies loaded in canister DSC-2 ranged from 0.3982 kW to 0.5969 k The total heat load of the canister was 15.517 kW.
Documents Reviewed:
-Procedure 1-NOP-116.01 "Dry Shielded Canister Fuel Loading, St. Lucie Unit 1,"
Revision 2-Engineering Package (EP) - PC/M 07130 "Fuel Selection and Initial Dry Cask Loading Campaign at St. Lucie Unit 1," Revision 6-Calculation PSL-1FJF-07-002 "St. Lucie Unit 1 - Irradiated Fuel Assembly Selection for Initial Dry Cask Loading Campaign," Revision 1 Category:
Fuel Selection/Verification Topic:
Fuel Design Characteristics Reference:
CoC 1030, Tech Spec 2.1.e Finding:
The dimensions and weights specified in Table 2 of Technical Specification 2.1.e were verified to be the limiting characteristics incorporated in Calculation PSL-1FJF-07-002.
Documents Reviewed:
Calculation PSL-1FJF-07-002 "St. Lucie Unit 1 - Irradiated Fuel Assembly Selection for Initial Dry Cask Loading Campaign," Revision 1 Requirement: Spent fuel assemblies authorized for storage in the 32PTH are limited to the design characteristics (dimensions and weights) specified in Table 2.
Category:
Fuel Selection/Verification Topic:
Loading Configurations Reference:
CoC 1030, Tech Spec 2.1.b and c Finding:
Engineering Package PC/M 07130 established the technical specification heat load zone requirements and used the fuel burnup, cooling time, and enrichment limits in Table 4 of the technical specifications for the selection of the assemblies to be inserted into each load zon The specific loading patterns for each canister were established in the Calculation PSL-1FJF-07-00 The criteria used was consistent with the requirements in Technical Specification 2.1.b and c including heat load, fuel burnup, cooling time, enrichment limits, and a prohibition on loading fuel assemblies with non-fuel assembly hardwar The loading pattern used for the loading of the first canister on March 10, 2008, as identified in Data Sheet #2 "DSC Loading Diagram" and Data Sheet #6 "Fuel Requirement: Fuel assemblies may be qualified for four (4) heat load zones designated as Zones 1a, 1b, 2, and Figure 2 shows the heat load zone location Table 4 identifies the acceptable combinations of enrichment, burnup and cooling times for each heat load zone.
Page 25 of 43 Attachment 2
Movement Data Sheet" of completed Procedure 1-NOP-116.01 was compared to the fuel loading pattern specified in PC/M 07130, Attachment 1 "Fuel Loading Pattern-DSC2" and was found to be consistent.
Documents Reviewed:
-Engineering Package (EP) - PC/M 07130 "Fuel Selection and Initial Dry Cask Loading Campaign at St. Lucie Unit 1," Revision 6-Calculation PSL-1FJF-07-002 "St. Lucie Unit 1 - Irradiated Fuel Assembly Selection for Initial Dry Cask Loading Campaign," Revision 1-Procedure 1-NOP-116.01 "Dry Shielded Canister Fuel Loading," Revision 2 Category:
Fuel Selection/Verification Topic:
Non-Fuel Assembly Hardware Reference:
CoC 1030, Tech Spec 2.1.b Finding:
Technical Specification 2.1.b does not allow CE 14 x 14 fuel assemblies to be stored with non-fuel assembly hardware (NFAH). Engineering Package PC/M 07130 did not allow non-fuel assembly hardware in any of the 192 fuel assemblies selected to be loaded into the six canisters planned for the initial loading campaig The Engineering Package stated that lumped burnable absorber rods (LBAR) displaced fuel rods in certain St. Lucie reload batches and therefore were not considered non-fuel assembly hardwar This was established in Calculation PSL-1FJF-07-002 where the implication of loading CE 14 x 14 fuel assemblies containing lumped burnable absorber rods was evaluate The calculation stated that another calculation, performed by Transnuclear, found that the effects of loading 32 CE-type assemblies, each containing 16 lumped burnable absorber rods, was insignificant relative to the Safety Analysis Report evaluation of criticality, shielding and internal canister pressur Therefore, Calculation PSL-1FJF-07-002 concluded that the existing analyses and analysis assumptions in the Safety Analysis Report remain valid and that the St. Lucie Unit 1 fuel remains bounded by the Safety Analysis Report for CoC 1030 as long as the total number of lumped burnable absorber rods per canister remained below 512 (16 lumped burnable absorber rods/assembly x 32 assemblies/canister). Calculation PSL-1FJF-07-002 stated that the storage pattern for the initial Unit 1 cask loading campaign conformed to the limit of 512 lumped burnable absorber rods per canister.
Documents Reviewed:
-Engineering Package (EP) - PC/M 07130 "Fuel Selection and Initial Dry Cask Loading Campaign at St. Lucie Unit 1," Revision 6-Calculation PSL-1FJF-07-002 "St. Lucie Unit 1 - Irradiated Fuel Assembly Selection for Initial Dry Cask Loading Campaign," Revision 1
.
Requirement: Non-Fuel Assembly Hardware (NFAH) stored integral to the assemblies shall be limited to Burnable Poison Rod Assemblies (BPRAs), Thimble Plug Assemblies (TPAs), and Vibration Suppressor Inserts (VPIs). The NFAH stored shall have acceptable combinations of burnup and cooling time described in Table CE 14 X 14 fuel assemblies are stored without NFAH.
Page 26 of 43 Attachment 2
Category:
Fuel Selection/Verification Topic:
Spent Fuel Assembly Mis-Loading Reference:
FSAR 1030, Sect 8.1.1.2.7; CoC 1030, TS Spec 2.2 Finding:
The requirement to perform post loading verification of the assemblies was implemented in Steps 6.2.10 and 6.2.11 of Procedure 1-NOP-116.0 The requirement for notification of a mis-loading was incorporated into Administrative Procedure 0010721, Appendix K
"ISFSI Related Non-Routine Reports." This appendix included the requirement to place the affected fuel assemblies in a safe condition if a functional or operational limit of Technical Specification 2.1 was discovere The 24-hour notification to the NRC as an ENS notification and a 30-day written notification were specified.
Documents Reviewed:
-Procedure 1-NOP-116.01 "Dry Shielded Canister Fuel Loading, St. Lucie Unit 1,"
Revision 2-Administrative Procedure 0010721 "NRC Required Non-Routine Notifications and Reports," Revision 62 Requirement: After all assemblies have been placed in the canister, verify their identitie If any functional or operating limit of Technical Specification 2.1, "Fuel To Be Stored In The 32PTH Canister", is violated, the following actions shall be completed: a) the affected fuel assemblies shall be placed in a safe condition, b) within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, notify the NRC Operations Center, c) within 30 days, submit a special report which describes the cause of the violation and the actions taken to restore compliance and prevent recurrence.
Category:
General License Topic:
Cask Design Compatible With Part 50 Reference:
Finding:
Section 4.5 of the 72.212 evaluation report documented the performance of 10 CFR 50.59 evaluations for spent fuel movement associated with Unit The 50.59 evaluation concluded that no Part 50 technical specification change was required nor was a licenses amendment require The 50.59 evaluation, PSL-ENG-ISFS-08-001, was reviewed and no concerns were identified with the analysis.
Documents Reviewed:
-PSL-ENG-ISFS-08-002 "72.212 Evaluation Report For The St. Lucie Nuclear Plant ISFSI Units 1&2," Revision 0-PSL-ENG-ISFS-08-001 "ISFSI Dry Cask Storage Loading and Unloading Operations" Requirement: Prior to use of the general license, determine whether activities related to storage of spent fuel involve a change in the facility technical specifications or require a license amendment for the facility pursuant to Part 50.59(c)(2). Results of this determination must be documented in the 10 CFR 72.212 Evaluation Report.
Category:
General License Topic:
Dose to the Public - Normal Operations Reference:
10 CFR 72.212(b)(2)(i)(C); 10 CFR 72.104(a)
Requirement: The general licensee shall perform a written evaluation that establishes that the requirements of 10 CFR 72.104, "Criteria for Radioactive Materials in Effluents and Direct Radiation from an ISFSI", have been me CFR 72.104 requires the annual dose equivalent to any real individual located beyond the controlled area must not exceed 25 mrem to the whole body during normal operations and anticipated occurrences.
Page 27 of 43 Attachment 2
Finding:
Section 4.3 of the 72.212 evaluation report addressed the issue of compliance with 10 CFR 72.104 criteria and concluded that the St. Lucie ISFSI complies with all requirements.
After the first canister was placed in the ISFSI, dose rate measurements were taken around the ISFSI fence at numerous location The typical dose rate measured was 0.006 mR/hr (6 microR/hr) at the fence boundary, which is background level The highest reading was 0.015 mR/hr, which is 0.009 mR/hr over background.
Documents Reviewed:
-PSL-ENG-ISFS-08-002 "72.212 Evaluation Report For The St. Lucie Nuclear Plant ISFSI Units 1&2," Revision 0-HP Survey Form-170 "ISFSI," completed March 15, 2008 Category:
General License Topic:
Evaluation Report Changes Reference:
Finding:
The above-referenced document addressed the performance of 10 CFR 72.212 evaluation Step 5.5 of the procedure addressed the need to perform a 72.48 review for changes made to the 72.212 evaluation after initial issuance.
Documents Reviewed:
ENG-QI 2.10 "10 CFR 72.212 Evaluation," Revision 0 Requirement: Changes to the approved 72.212 evaluation report shall be made using the requirements of 72.48(c). A copy of the completed 72.48 evaluation shall be retained until spent fuel is no longer stored under the general license issued.
Category:
General License Topic:
HSM - Storage Pad Soil Liquefaction Reference:
CoC 1030, Tech Spec 4.2.2 Finding:
Section 4.2.4 of the 72.212 evaluation report addressed the issue of liquefactio Based on a specific analysis for liquefaction potential at the ISFSI, it was concluded that the engineered soil column (upon which the ISFSI pad sits) is not liquefiable.
Documents Reviewed:
PSL-ENG-ISFS-08-002 "72.212 Evaluation Report For The St. Lucie Nuclear Plant ISFSI Units 1&2," Revision 0 Requirement: For sites for which soil-structure interaction is considered important, the license is to perform site-specific analysis considering the effects of soil structure interaction (SSI).
Amplified seismic spectra at the location of the HSM-H center of gravity (CG) is to be developed based on the SSI response The storage pad location shall have no potential for liquefaction at the site-specific level earthquake.
Category:
General License Topic:
HSM Storage Arrays Reference:
CoC 1030, Tech Spec 4.6.1 Requirement: HSM-Hs are placed together in single rows or in back-to-back array An end shield wall is placed on the outside of any loaded outside HSM-A rear shield wall is placed on the rear of any single row loaded HSM-H.
Page 28 of 43 Attachment 2
Finding:
Attachment 1, CoC Section 4.6.1, of the 72.212 evaluation report, stated that the ISFSI was comprised of back-to-back arrays and therefore utilized end shield wall Physical inspection by the inspector of the HSM-Hs placed to-date on the ISFSI pad verified that the back-to-back array configuration was the one in use and that end shield walls were in place.
Documents Reviewed:
PSL-ENG-ISFS-08-002 "72.212 Evaluation Report For The St. Lucie Nuclear Plant ISFSI Units 1&2," Revision 0 Category:
General License Topic:
Reactor Site Parameters - Fire and Explosion Reference:
CoC 1030, TS 4.6.3.6; FSAR 1030, Sect 4.1.1.1 Finding:
Engineering evaluations for the fire/explosion hazards analyses were detailed and used a systematic approach to evaluate all potential fixed and transient fire/explosion hazard Conservative and appropriate assumptions involving administrative controls were placed in the appropriate ISFSI operating procedures.
Documents Reviewed:
-PSL-ENG-ISFS-08-002 "72.212 Evaluation Report For The St. Lucie Nuclear Plant ISFSI Units 1&2," Revision 0-Calculation FPL009-CALC-011 "Explosion Hazard Calculation for the PSL ISFSI Cask Hauling and Storage," Revision 0-Calc FPL009-CALC-010 "Fire Hazards Evaluation for the St. Lucie ISFSI Cask Hauling and Storage," Revision 0-Procedure MMP-116.14 "ISFSI DSC Transport from CHF to HSM," Revision 1 Requirement: The potential for fires and explosions shall be addressed, based on site-specific consideration The bounding condition assumed in the fire accident analysis is a 300-gallon diesel fuel fire engulfing the transfer cask for 15 minutes at a temperature of 1,475 degrees The bounding condition assumed in the explosion analysis is a blast force of less than 1.0 ps The general license shall determine whether the site fire and explosion hazards are enveloped by the cask design basi This determination must be documented in the 72.212 evaluation report.
Category:
General License Topic:
Reactor Site Parameters - Flood Conditions Reference:
CoC 1030, Tech Spec 4.6.3.2; 10 CFR 72.212(b)(2)
Finding:
Section 4.4.2 of the 72.212 evaluation report addressed the issue of floodin The ISFSI pad surface was located at approximately 18 fee The maximum surge height of water from a hurricane was 17.2 fee Although refracted waves from the intake canal would reach the ISFSI pad at an elevation about 2.5 inches above the ISFSI pad surface, the stillwater elevation was still below the ISFSI pad surface, and any resulting water surge was not sufficient to block the HSM vents.
Documents Reviewed:
PSL-ENG-ISFS-08-002 "72.212 Evaluation Report For The St. Lucie Nuclear Plant Requirement: The NUHOMS HD System is certified for use at reactor sites with maximum flood levels of 50 feet, and maximum water velocities of 15 feet per secon The user shall verify the site-specific maximum flood levels and water velocities are within the limits of the certification, and shall document that verification in the 72.212 evaluation report.
Page 29 of 43 Attachment 2
ISFSI Units 1&2," Revision 0 Category:
General License Topic:
Reactor Site Parameters - Normal Temperatures Reference:
CoC 1030, Tech Spec 4.6.3.4; 10 CFR 72.212(b)(2)
Finding:
Section 4.4.8 of the 72.212 evaluation report addressed the issue of ambient air temperature limits at the sit The NUHOMS HD ambient temperature requirements bound those of the site.
Documents Reviewed:
PSL-ENG-ISFS-08-002 "72.212 Evaluation Report For The St. Lucie Nuclear Plant ISFSI Units 1&2," Revision 0 Requirement: The NUHOMS HD System is certified for use at reactor sites with normal ambient temperature ranges of 0 degrees F to 100 degrees The user shall verify the site-specific normal temperatures are within the range of the certification and shall document that verification in the 72.212 evaluation report.
Category:
General License Topic:
Reactor Site Parameters - Roof Snow Loading Reference:
CoC 1030, Tech Spec 4.6.3.3; 10 CFR 72.212(b)(2)
Finding:
Section 4.4.4 of the 72.212 evaluation report documented that no significant snow fall has ever occurred at the site and therefore will not exceed the NUHOMS HD design value for snow loadin Also, any accumulation of ice that may occur in winter periods will not challenge the design value.
Documents Reviewed:
PSL-ENG-ISFS-08-002 "72.212 Evaluation Report For The St. Lucie Nuclear Plant ISFSI Units 1&2," Revision 0 Requirement: The NUHOMS HD System is certified for use at reactor sites where the roof snow loading will not exceed 110 pounds per square foo The user shall verify the site-specific 100 year roof snow loading is within the limits of the certification, and shall document that verification in the 72.212 evaluation report.
Category:
General License Topic:
Reactor Site Parameters - Seismic Loads Reference:
CoC 1030, Tech Spec 4.6.3.8; 10 CFR 72.212(b)(2)
Finding:
Section 4.4.3 of the 72.212 evaluation report addressed the issue of earthquake at the ISFS Evaluation revealed that the verified acceleration value exceeded the HSM-H design value (0.2g) for the ISFSI pad; however, further seismic evaluation concluded that the HSM-H and DSC are qualified to the site-specific accelerations.
Documents Reviewed:
PSL-ENG-ISFS-08-002 "72.212 Evaluation Report For The St. Lucie Nuclear Plant ISFSI Units 1&2," Revision 0 Requirement: The NUHOMS HD System is certified for use at reactor sites with peak horizontal seismic acceleration loads of 0.30gs and peak vertical seismic acceleration loads of 0.20g The user shall verify the site-specific seismic acceleration loads are within the limits of the certification, and shall document that verification in the 72.212 evaluation report.
Page 30 of 43 Attachment 2
Category:
General License Topic:
Reactor Site Parameters - Temperature Extremes Reference:
CoC 1030, Tech Spec 4.6.3.5; 10 CFR 72.212(b)(2)
Finding:
Attachment 1, CoC Section 4.6.3.5, of the 72.212 evaluation report, documents that the extreme high temperature recorded at the St. Lucie site was 99.8 degrees F and the extreme low was 28.4 degrees These values are bounded by the NUHOMS HD design temperature limits of -20 degree F and plus 115 degree F.
Documents Reviewed:
PSL-ENG-ISFS-08-002 "72.212 Evaluation Report For The St. Lucie Nuclear Plant ISFSI Units 1&2," Revision 0 Requirement: The NUHOMS HD System is certified for use at reactor sites with off-normal ambient temperature extremes of minus 20 degrees F without solar insolation and plus 115 degrees F with full solar insolatio The user shall verify the site-specific off-normal ambient temperature extremes are within the limits of the certification, and shall document that verification in the 72.212 evaluation report.
Category:
General License Topic:
Reactor Site Parameters - Tornado Wind Speeds Reference:
CoC 1030, Tech Spec 4.6.3.1; 10 CFR 72.212(b)(2)
Finding:
Section 4.4.1 of the 72.212 evaluation report documented that the reactor site tornado parameters of 360 mph (300 mph rotational and 60 mph translational) are bounded by the NUHOMS HD design parameters of 360 mph (290 mph rotational and 70 mph translational).
Documents Reviewed:
PSL-ENG-ISFS-08-002 "72.212 Evaluation Report For The St. Lucie Nuclear Plant ISFSI Units 1&2," Revision 0 Requirement: The NUHOMS HD System is certified for use at reactor sites with maximum tornado wind speeds of 290 mph rotational and 70 mph translationa The user shall verify the site-specific maximum tornado wind speeds are within the limits of the certification, and shall document that verification in the 72.212 evaluation report.
Category:
Heavy Loads Topic:
Heavy Loads Safety Review Reference:
CoC 1030, Condition 5 Finding:
St. Lucie, Unit 1 and 2, certified their spent fuel cask cranes as single-failure proof in accordance with NUREG-0612 and NUREG-0554 in a letter to the NRC on December 11, 200 The cranes were manufactured by American Crane and Equipment Company (ACECO), rated for a maximum critical load of 150 tons with an auxiliary hoist rated at 25 ton The 25-ton auxiliary hoists are not designated as single-failure proo The new cranes were installed in the fourth quarter of 200 The cranes are located outside the fuel buildings, supported by a superstructure above the north end of the respective unit's Requirement: Each lift of the canister and transfer cask must be made within the existing heavy loads requirements and procedures of the licensed facility at which the lift is mad A plant-specific safety review (under 10 CFR 50.59 or 10 CFR 72.48, if applicable) is required to show operational compliance with existing plant-specific heavy loads requirements.
Page 31 of 43 Attachment 2
fuel handling buildin The cranes' function is to transfer shielded casks containing spent fuel between the cask pit area in the fuel handling building and the outside laydown are The St. Lucie cranes are similar in design as single-failure proof cranes installed at Oyster Creek and Palo Verd St. Lucie completed a 10 CFR 50.59 safety evaluation for the crane installation and developed a matrix demonstrating compliance with NUREG-055 The safety evaluation and the NUREG-0554 matrix were reviewed during this inspectio The licensee had completed a thorough review of the crane design against the single-failure proof crane requirements listed in NUREG-0554.
Documents Reviewed:
-Letter # L-2003-309 from St. Lucie to the NRC dated December 11, 2003 (ML033490185)
-Letter # L-2002-111 from St. Lucie to the NRC dated July 18, 2002 (ML022040006)
-NUREG-0612 "Control of Heavy Loads at Nuclear Power Plants," dated January 1980-NUREG-0554 "Single Failure Proof Cranes for Nuclear Power Plants," dated May 1979 Category:
Heavy Loads Topic:
Safe Load Paths Reference:
NUREG 0612, Section 5.1.1 (1)
Finding:
The requirement to analysis a safe load path does not apply to the use of the new cranes installed at St. Lucie Units 1 and 2 because they are single failure proo However, the removal of the old cranes in 2003 involved the use of a mobile crane during dismantlement of the trolley, bridge, cab and crane structure Because this work effort was near the fuel building and underground cables, and the removal effort involved the heavy lifts of the trolley (90,100 lbs) and bridge (106,890 lbs), the licensee performed an analysis to determine if any impact would occur on safety-related structures, systems and components (SSC). The analysis determined that underground cabling could be impacted from a drop during the dismantlement effor Each of the cables was analyzed to determine the impact of opening or shorting the cable The analysis showed that no safe shutdown function would be adversely affected during the demolition activities.
Documents Reviewed:
Minor Engineering Package (MEP)-PC/M 02061M "Unit 2 Cask Crane Demolition and Site Preparation," dated October 31, 2002 Requirement: Safe load paths should be defined for the movement of heavy loads to minimize the potential for heavy loads, if dropped, to impact irradiated fuel in the reactor vessel and in the spent fuel pool, or to impact safe shutdown equipmen The path should follow, to the extent practical, structural floor members, beams, etc., such that if the load is dropped, the structure is more likely to withstand the impact.
Category:
Procedures & Tech Specs Topic:
Canister Gas Sampling During Unloading Reference:
FSAR 1030, Section 8.2.2.12 Finding:
Procedure MMP 116.13 "ISFSI DSC Lid Removal," Steps 6.3.4 and 6.3.27 required gas sampling of the canister atmosphere during canister unloading operations once the vent and drain port cover plates are remove Acceptable hydrogen concentrations were Requirement: Once the vent and drain port cover plates are removed, obtain a sample of the canister atmospher Confirm acceptable hydrogen concentration and check for presence of fission gas indicative of degraded fuel cladding.
Page 32 of 43 Attachment 2
specified in Step 6.3.4 as less than 2.4% hydroge For fission gases, Step 6.3.27 of the procedure required a gamma analysis of the collected gas to determine if any fission products were present.
Documents Reviewed:
Procedure MMP-116.13 "ISFSI DSC Lid Removal," Revision 0 Category:
Procedures & Tech Specs Topic:
Canister Unloading - Reflooding Reference:
FSAR 1030, Section 8.2.2.14 Finding:
Procedure MMP-116.13 "ISFSI DSC Lid Removal," established the process for canister re-floodin Step 3.3 required the spent fuel pool ventilation system to be in operation and the Note prior to Step 6.4.20 established the process to re-flood the canister, including filling from the drain port with the vent port ope The vented steam is routed to the spent fuel poo Gases from the spent fuel pool are captured by the ventilation system which exhausts through the fuel handling building vent stack, after passing through a prefilter, a HEPA filter bank, and charcoal absorber The vent pressure is monitored by the vent port pressure gaug Step 6.4.20 specified the 15 psig limit on the canister pressure.
Documents Reviewed:
Procedure MMP-116.13 "ISFSI DSC Lid Removal," Revision 0 Requirement: Fill the canister with water through the drain port with the vent port ope The vented steam and gas should be routed though a monitored and filtered pathwa Monitor the vent pressure and regulate the fill rate to ensure canister pressure does not exceed 15 psig.
Category:
Procedures & Tech Specs Topic:
Cask Maintenance - Annual Inspections Reference:
CoC 1030, Condition 2; FSAR 1030, Section 9.2 Finding:
The transfer cask is leased from Transnuclear and will be leaving the site after the first loading campaig Therefore, the licensee stated that FPL is not required to perform the annual transfer cask inspections described in the Certificate of Compliance and Final Safety Analysis Report.
Documents Reviewed:
Transnuclear Lease Agreement with Florida Power and Light Co. for NUHOMS Transfer and Auxiliary Equipment.
.
Requirement: Written procedures shall be prepared for cask maintenanc The procedures shall require performance of the following transfer cask inspections within one year of each loading or unloading campaign: a) dye penetrant examination of the top trunnion bearing surfaces and accessible welds; b) leak testing of the transfer cask lid, ram access cover, vent and drain cover o-rings, vent and drain quick-connect fittings and neutron shield fitting If bubble leak testing is performed, no leak indication is allowe If pressure drop or helium leak testing is used, the maximum allowable leak rate for each component is X 10(-3) ref-cc/sec.
Page 33 of 43 Attachment 2
Category:
Procedures & Tech Specs Topic:
Cask Operation Reference:
CoC 1030, Condition 2; Tech Spec 5.2.2 Finding:
Fuel qualification and loading was performed in accordance with the methodology in Calculation PSL-1FJF-07-00 Rigging and handling was performed in accordance with Procedures MMP-116.07 and MMP-116.0 Loading 0perations were performed in accordance with Procedures 1-NOP-116.0 Unloading operations were performed in accordance with Procedure 1-NOP-116.0 Auxiliary equipment operation was performed in accordance with procedures above and Procedures MMP-116.03, MMP-116.04, MMP-116.11, MMP-116.12, MMP-116.13, and MMP-116.1 Transfer operations were performed in accordance with Procedures MMP-116.11 and MMP-116.1 Radiation Protection was performed in accordance with procedure HPP-8 Off-normal conditions, accident conditions, responses and corrective actions were performed in accordance with Procedure MMP-116.15.
Documents Reviewed:
-Calculation PSL-1FJF-07-002 "St. Lucie Unit 1 - Irradiated Fuel Assembly Selection for Initial Dry Cask Loading Campaign," Revision 1-Procedure 1-NOP-116.01 "Dry Shielded Canister Fuel Loading," Revision 2-Procedure 1-NOP-116.03 "Dry Shielded Canister Fuel Off-Load"
-Procedure MMP 116-03 "ISFSI TC/DSC Handling Operations for Fuel Off-Loading,"
Revision 0-Procedure MMP 116-04 "ISFSI DSC Upending and Cold Fit Test," Revision 0A-Procedure MMP-116.07 "ISFSI TC and DSC Preparation for Loading"
-Procedure MMP-116.08 "ISFSI TC/DSC Handling Operations for Fuel Loading,"
Revision 3-Procedure MMP 116.11 "ISFSI Transport DSC from HSM to CHF," Revision 0-Procedure MMP-116.12 "ISFSI Dry Shielded Canister Sealing Operations," Revision 0-Procedure MMP-116.13 "ISFSI DSC Lid Removal," Revision 0-Procedure MMP-116.14 "ISFSI DSC Transport from CHF to HSM," Revision 1-Procedure MMP-116.15 "ISFSI Contingency Plan," Draft 2/28/08-Procedure HPP-85 "ISFSI Radiological Controls," Revision 1 Requirement: Written procedures shall be prepared for cask handling, loading, and movemen The procedures shall control: a) fuel qualification and loading; b) rigging and handling; c)
loading operations; d) unloading operations; e) auxiliary equipment operation; f)
transfer operations; g) radiation protection; and h) off-normal and accident conditions, responses and corrective actions.
Category:
Procedures & Tech Specs Topic:
Cask Surveillance - HSM Air Vent Inspections Reference:
CoC 1030 Condition 6; TS 5.2.5.b; FSAR, Sect 4.4.2 Finding:
Procedure 1-OSP-100.01 contained daily steps to visually inspect the loaded HSM-Hs to ensure the inlet and outlet air vents were not blocked and to clean the screens (within 34 hours3.935185e-4 days <br />0.00944 hours <br />5.621693e-5 weeks <br />1.2937e-5 months <br />) if there is a blockage.
Requirement: Written procedures shall be prepared for cask surveillanc Site personnel shall conduct a daily visual inspection of the air vents to ensure that the HSM air vents are not blocked for more than 34 hours3.935185e-4 days <br />0.00944 hours <br />5.621693e-5 weeks <br />1.2937e-5 months <br />, and that blockage will not exist for longer than the 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> assumed in the safety analysis.
Page 34 of 43 Attachment 2
Documents Reviewed:
Procedure 1-OSP-100.01 "Schedule of Periodic Tests, Checks, and Calibrations Week 1, St. Lucie Unit 1," Revision 31 Category:
Procedures & Tech Specs Topic:
Criticality - Minimum Boron Concentration Reference:
CoC 1030, Tech Spec 3.2 Finding:
The fuel selected for the first loading campaign was CE Type 14 x 14 fuel assemblies in a Type C DSC basket with a maximum average initial enrichment of 3.65 wt. % U-23 For this configuration, Technical Specification Table 7 required a minimum boron concentration of 2000 pp During the loading of the first canister, the boron concentration in the spent fuel pool and in the water added to the basket was 2216 ppm.
Procedure MMP 116.08, Step 6.1.11 required the boron concentration to be determined within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> prior to commencing loading operations and Step 6.1.12 required boron samples 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> thereafter while water is in the caniste Procedure 1-NOP-116.01, Step 6.2, required this determination to be made by two independent measurements.
For unloading of a canister, Step 6.4.2 of Procedure MMP 116.13, required the boron concentration to be determined within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> prior to flooding the canister during unloading operations and Step 6.1.6 required the boron concentration to be determined 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> thereafter while water is in the caniste Step 6.4.2 required this determination to be made by two independent measurement Also, Step 4.14 of Procedure 1-NOP-116.03 contained the same requirement.
Documents Reviewed:
- Procedure MMP-116.08 "ISFSI TC/DSC Handling Operations for Fuel Loading,"
Revision 3
- Procedure MMP-116.13 "ISFSI DSC Lid Removal," Revision 0
- Procedure 1-NOP-116.01 "Dry Shielded Canister Fuel Loading," Revision 2
- Procedure 1-NOP-116.03 "Dry Shielded Canister Fuel Off-Load," Revision 0 Requirement: The dissolved boron concentration of the spent fuel pool water and the water added to the cavity of a loaded canister shall be at least the boron concentration shown in Table 7 for the basket type and fuel enrichment selecte The boron concentration will be determined within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> prior to commencing LOADING operations and 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> thereafter while water is in the caniste The boron concentration will be determined within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> prior to flooding the canister during UNLOADING operations and 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> thereafter while water is in the caniste All boron concentrations shall be determined by two independent measurements.
Category:
Quality Assurance Topic:
Approved QA Program Reference:
Requirement: A Quality Assurance program previously approved by the Commission as satisfying the requirements of Appendix B to Part 50 will be accepted as satisfying the requirements of Part 7 In filing the description of the QA program required by Part 72.140(c), each licensee shall notify the NRC of it's intent to apply it's previously approved QA program to ISFSI activitie The notification shall identify the previously approved QA program by date of submittal, docket number and date of Commission approval.
Page 35 of 43 Attachment 2
Finding:
The licensee is using its NRC-approved Part 50 QA program for the ISFS Florida Power & Light Company notified the NRC on October 11, 2006, of its intent to apply its previously approved Part 50 QA program to the ISFSI program in a letter from J.A. Stall to the Director of the Spent Fuel Project Office.
Documents Reviewed:
Letter from J.A. Stall, Florida Power & Light Company to Director, Spent Fuel Project Office, NRC entitled "Notification of Intent to Apply Previously Approved 10 CFR 50 Appendix B Quality Assurance Program to Independent Spent Fuel Storage Activities,"
dated October 11, 2006.
Category:
Quality Assurance Topic:
Control of Measuring and Test Equipment Reference:
10 CFR 72.164 Finding:
Procedure QI-12-PR/PSL-1 defined the requirements for the control and calibration of measuring and test equipment and calibration standard "ISFSI Test Equipment for Technical Specification Measurements" listed test equipment required to demonstrate conformance with the technical specifications and specified range and accuracy requirement Calibration certificates for a sample of equipment were found to be current.
Documents Reviewed:
-Quality Assurance Topical Report FPL-1-Procedure QI-12-PR/PSL-1 "Control and Calibration of Measuring and Testing Equipment (MT&E)"
-ISFSI Test Equipment for Technical Specification Measurements Requirement: The licensee shall establish measures to ensure that tools, gauges, instruments and other measuring and testing devices used in activities affecting quality are properly controlled, calibrated, and adjusted at specific periods to maintain accuracy within necessary limits.
Category:
Quality Assurance Topic:
Corrective Actions Reference:
10 CFR 72.172 Finding:
Procedure NAP-204 provided the process for identifying and resolving conditions adverse to qualit The Station Issue Tracking & Information System (SITRIS) was used to document and track significant conditions adverse to quality (SCAQ) and conditions adverse to quality (CAQ). NAP-204 required that significant conditions adverse to quality receive root cause analysis and identify corrective actions to prevent recurrence, and be reported to the Chief Nuclear Officer and direct reports.
The licensee maintained a status of condition reports pertaining the ISFSI and identified condition reports requiring resolution prior to fuel loadin A sample of condition reports was reviewed and no discrepancies were noted.
Requirement: The licensee shall establish measures to ensure that conditions adverse to quality, such as failures, malfunctions, deficiencies, deviations, defective material and equipment, and nonconformances are promptly identified and correcte In the case of significant conditions adverse to quality, the measures must ensure that the cause of the condition is determined and corrective action taken to preclude repetitio This must be documented and reported to appropriate levels of management.
Page 36 of 43 Attachment 2
Documents Reviewed:
-Quality Assurance Topical Report FPL-1-Procedure NAP-204 "Condition Reporting" Category:
Quality Assurance Topic:
Handling and Storage Controls Reference:
10 CFR 72.166 Finding:
Procedure MMP-116.01 provided storage requirements for HSM component Procedure MMP-116.04 provided storage requirements for the DSC and associated DSC components.
Documents Reviewed:
-Quality Assurance Topical Report FPL-1-Procedure MMP-116.01 "ISFSI HSM Material Identification, Control and Storage,"
Revision 2-Procedure MMP-116.04 "ISFSI DSC Upending and Cold Fit," Revision 0A Requirement: The licensee shall establish measures to control, in accordance with work and inspection instructions, the handling, storage, and preservation of material and equipment to prevent damage or deterioratio When necessary for particular products, special protective environments, such as inert gas atmosphere and specific moisture content and temperature levels must be specified and provided.
Category:
Quality Assurance Topic:
Nonconforming Material and Parts Reference:
10 CFR 72.170 Finding:
Procedure QI-15-PSL-1 established the requirements, mechanisms, and responsibilities for documentation, control, evaluation, and disposition of nonconforming items or services.
Documents Reviewed:
-Quality Assurance Topical Report FPL-1-Procedure QI-15-PSL-1 "Control of Nonconforming Materials, Parts, Components and Services for St. Lucie Plant" Requirement: The licensee shall establish measures to control materials, parts or components that do not conform to their requirements in order to prevent their inadvertent use or installatio These measures must include procedures for identification, documentation, segregation, disposition and notification to affected organization Nonconforming items must be reviewed and accepted, rejected, repaired, or reworked in accordance with documented procedures.
Category:
Quality Assurance Topic:
Procurement Controls Reference:
10 CFR 72.154(a)/(b)/(c)
Finding:
Procurement of ISFSI materials was done under existing St. Lucie procedure Requirement: The licensee shall establish measures to ensure that purchased material, equipment, and services conform to procurement document These measures must include provisions for source evaluation and selection, objective evidence of quality furnished by the contractor/subcontractor, inspection at the contractor/subcontractor source and examination of product on delivery.
Page 37 of 43 Attachment 2
Procedure QI-4-PSL-1 provided the method for material procurement and the control of material procurement document Two sample purchase orders for material to be used on the ISFSI project were reviewe One purchase order was for the calibration of four display and transducer sets and the other was for calibrated digital pressure gauge No discrepancies were noted.
Documents Reviewed:
-Quality Assurance Topical Report FPL-1-Procedure QI-4-PSL-1 "Procurement of Materials"
-Purchase Order 00082306-Purchase Order 00110076 Category:
Radiation Protection Topic:
ALARA Measures Reference:
Finding:
Operational restrictions were established in Procedure HHP-85 to meet ALARA objectives for direct radiation levels associated with ISFSI operation These restrictions included performing radiological surveys; using special procedural cautions for specific activities; using-extender type survey instruments and temporary shielding; and decontaminating the transfer cask, tools, equipment, and work area The first canister loaded had a heat load of 15.5 k The total estimated radiation dose received during the loading was 0.128 manre The final manrem dose may be revised once the TLD badges are processed and results are receive This is a low radiation level compared to many other reactor sites which have loaded canister The licensee contributes this low number to the fact the annulus and transfer cask water jackets were kept filled, thereby providing extra shieldin The NRC also noted that many of the workers had previous experience at other sites loading canisters and were more efficient in getting tasks completed than would be the case for individuals with less experience.
Documents Reviewed:
Procedure HHP-85 "ISFSI Radiological Controls," Revision 1 Requirement: Operational restrictions shall be established to meet ALARA objectives for direct radiation levels associated with ISFSI operations.
Category:
Radiation Protection Topic:
Contamination Survey of Canister Reference:
CoC 1030, Tech Spec 5.2.4.d Finding:
The licensee had established more conservative smearable contamination limits than required by Technical Specification 5.2. Procedure HHP-85, Steps 6.3.7.A and 6. established acceptable contamination limits as less than 1000 disintegrations per minute (dpm) per 100 square cm from beta and gamma emitting sources and less than 20 dpm/100 square cm from alpha emitting sources. Step 6.3.11 of Health Physics Procedure - 85 required the contamination smear to be taken on the outer top 1 foot Requirement: Following placement of each loaded transfer cask into the cask decontamination area and prior to transfer to the ISFSI, the smearable surface contamination levels on the outer top 1 foot surface of the canister shall be less than 2,200 disintegrations per minute (dpm)
per 100 square cm from beta and gamma emitting sources and less than 220 dpm/100 square cm from alpha emitting source The contamination limits are based on the allowed removable external radioactive contamination specified in 49 CFR 173.443.
Page 38 of 43 Attachment 2
surface of the canister prior to any decontamination of that are During the first cask loading, smearable contamination levels were measured at less than 1000 dpm beta/gamma per 100 square cm and less that 20 dpm alpha per 100 square cm.
Documents Reviewed:
Procedure HHP-85 "ISFSI Radiological Controls," Revision 1 Category:
Radiation Protection Topic:
Criticality - Monitoring and Alarm System Reference:
10 CFR 72.124.c Finding:
Two area radiation monitors (ARMs) are located in the fuel building to provide a warning to workers should an accidental criticality occur One is on the south wall and one on the north wall at the 62 foot leve These ARMs readout in the control roo During the dry run, testing of the south wall ARM provided a noticeable alarm leve For the cask handling facility, Procedure HPP-85, Step 4.20 stated, "A criticality monitor shall be in operation in the cask handling facility while working with a spent fuel loaded dry shielded canister." According to members of the cask handling facility crew, the criticality monitoring system emits a clearly audible alarm signal easily heard by the workers in the area.
Documents Reviewed:
-Procedure MMP-116.12 "ISFSI Dry Shielded Canister Sealing Operations," Revision 2B-Procedure HHP-85, "ISFSI Radiological Controls," Revision 1 Requirement: A criticality monitoring system shall be maintained in each area where special nuclear material is handled, used, or stored which will energize clearly audible alarm signals if accidental criticality occur Underwater monitoring is not required, nor is monitoring of dry storage areas where special nuclear material is packaged in its stored configuratio The NRC has defined "packaged" to begin when the canister lid closure weld is complete.
Category:
Radiation Protection Topic:
HSM-H Dose Rate Evaluation Reference:
CoC 1030, Tech Specs 5.4.1 through 5.4.3 Finding:
Procedure HHP-85, Attachment A, Table 3 established the dose rate limits for the horizontal storage modules (HSMs) as 752 mrem/hour at the front bird screen, mrem/hour on the door centerline, and 1.4 mrem/hour on the end shield wall exterio These limits are within the limits established in the technical specificatio After the first canister (DSC-2) was placed in the ISFSI, surveys were conducted of HSM-2 on March 15, 2008 to confirm compliance with the technical specification Survey results were documented on Procedure MMP-116.14, Section 6.19 and on HP Survey Form-17 Dose rates on HSM-2 measured 25-32 mR/hr beta/gamma and 6.6 mrem/hr neutron on contact at the bird screen for a total of 36.6 mrem/h The dose rate at the HSM door Requirement: The licensee shall perform an analysis to confirm that the limits of 10 CFR Part 20 and 10 CFR 72.104 will be satisfied under actual site conditions, assuming a fully loaded ISFS On the basis of the analysis, the licensee shall establish dose rate limits for the HSM-H front surface, door centerline, and end shield wall exterio The dose rate limits established based on the analysis shall not exceed 800 mrem/hour at the front bird screen, 2 mrem/hour on the door centerline, and 2 mrem/hour on the end shield wall exterior.
Page 39 of 43 Attachment 2
centerline was 0.4 mrem/h The dose rate at the end shield wall exterior was mrem/h No smearable contamination was detected.
Documents Reviewed:
-Procedure HHP-85 "ISFSI Radiological Controls," Revision 0-Procedure MMP-116.14 "ISFSI DSC Transport from CHF to HSM," Revision 2-HP Survey Form -170 "ISFSI," completed March 15, 2008-HP Survey Form-181 "ISFSI Horizontal Storage Modules Front View," completed March 15, 2008 Category:
Radiation Protection Topic:
Neutron Energies for Dosimetry Reference:
FSAR 1030, Table 5-13 Finding:
The licensee had established a special program to asses the neutron dose to workers when the water was removed from the canister and a higher energy spectrum would result in the areas near the cas Special neutron dosimeters were used that were sensitive to the higher neutron energies using a CR39 badge, which would be energy independent for intermediate and fast neutrons between 150 keV to 10 Me The higher energy neutron dosimeters were color coded differently than the normal neutron dosimetry worn at the plan A REM 500 Tissue Equivalent Proportional Counter was used to measure the neutron fields around the cas In addition, several neutron badges were placed on the ISFSI pad fence line to assess the neutron dose After six casks are placed in the horizontal storage modules (HSM), the dosimeters will be collected and analyzed.
Documents Reviewed:
-Certificate of Compliance 1030, Final Safety Analysis Report, Revision 1-Condition Report 2008-8058 "ISFSI Neutron Pilot Monitoring Project," dated March 7, 2008-FPL Memo from B.K. Mouring "ISFSI Neutron Pilot Monitoring Plan White Paper,"
dated March 5, 2008 Requirement: FSAR Section 5.4.7.1 states that 85% of the neutron spectrum from the spent fuel will be represented by spontaneous fission of Cm-24 While water is in the cask, the neutrons will be adequately thermalized similar to the neutron energy levels typically encountered in the plan However, once the water is removed from the cask, a higher neutron energy spectrum will be emitted from the cas FSAR Table 5-13 provides the design basis neutron energy spectrum for the caniste Since the neutron energy will be higher when the water has been removed from the cask during drying, helium backfill and transport to the ISFSI pad, than the normal thermal energies of neutrons found in work areas of the plant, calibration considerations should be made for personnel monitoring of neutrons at these higher energies.
Category:
Training Topic:
Approved Training Program Reference:
Finding:
The training and certification of personnel for ISFSI activities was conducted under the Requirement: The licensee shall have a training program in effect that covers the training and certification of personnel that meet the requirements of Subpart I before the licensee receives spent fuel at the ISFSI.
Page 40 of 43 Attachment 2
licensee's Part 50 training progra The Nuclear Projects Group was responsible for ensuring training was developed, planned, scheduled, and conducted for personnel involved in the ISFSI projec The ISFSI training program was described in the "S Lucie Plant Training ISFSI Program for NUHOMS HD CoC 1030."
Documents Reviewed:
St. Lucie Plant Training ISFSI Program for NUHOMS HD CoC 1030 Category:
Training Topic:
Cask System Overview Reference:
CoC 1030, Tech Spec 5.2.2 Finding:
The "St. Lucie Plant Training ISFSI Program for NUHOMS HD CoC 1030" addressed, and Lesson Plan PSL OPS SYS 208A LPC provided overview training for the NUHOMS-HD system design; ISFSI facility design, structures, systems and components (SSCs) important to safety; NUHOMS-HD System final safety analysis report (FSAR),
and the NRC safety evaluation report (SER). The lesson plan also included more specific training on the certificate of compliance (CoC) conditions, NUHOMS-HD system technical specifications, applicable regulatory reviews and operating experience.
Documents Reviewed:
-St. Lucie Plant Training ISFSI Program for NUHOMS HD CoC 1030-Lesson Plan PSL OPS SYS 208A LPC "Independent Spent Fuel Storage Installation" Requirement: Training modules shall be developed to include an overview of the NUHOMS-HD system design, ISFSI facility design, Systems, Structures and Components (SSCs)
Important To Safety, NUHOMS-HD System FSAR and the NRC SE The modules shall include more specific training on the Certificate of Compliance (CoC) conditions, NUHOMS-HD system technical specifications, applicable regulatory requirements, required instrumentation and use, and operating experience reviews.
Category:
Training Topic:
Cask System Procedures Reference:
CoC 1030, Tech Spec 5.2.2 Finding:
The ISFSI Training Program was developed using a systematic approach to training and was described in the "St. Lucie Plant Training ISFSI Program for NUHOMS HD CoC 1030." The program identified operations requiring training and a training group matrix of applicabilit Lesson Plan PSL OPS SYS 208A LPC provided overview training that was tailored to each training group based on need and covered all the required training topics.
Documents Reviewed:
-St. Lucie Plant Training ISFSI Program for NUHOMS HD CoC 1030-Lesson Plan PSL OPS SYS 208A LPC "Independent Spent Fuel Storage Installation" Requirement: Training modules shall be developed for the operation and maintenance of the NUHOMS-HD System and the ISFS These modules shall include the procedures used for: a) fuel loading; b) rigging and handling; c) loading operations as described in Chapter 8 of the FSAR; d) unloading operations including reflooding; e) auxiliary equipment operation; f) transfer operations; g) surveillance operations; h) radiation protection; i) maintenance as described in Section 9.2 of the FSAR; and j) off-normal and accident conditions responses and corrective actions.
Page 41 of 43 Attachment 2
Category:
Training Topic:
Certification of Personnel Reference:
10 CFR 72.190 Finding:
Procedure MMP 116.07 required that only certified personnel or personnel under the direct supervision of a certified person may operate equipment important to safet The TriVis personnel and supervisors that will perform cask loading operations had completed classroom training and were in the process of completing the On-Job Training (OJT) and Task Performance Evaluation (TPE) requirements at the time of the dry run demonstration.
Documents Reviewed:
-St. Lucie Plant Training ISFSI Program for NUHOMS HD CoC 1030-Learning Management System Database-Procedure MMP-116.07 "ISFSI TC and DSC Preparation for Loading," Draft Revision B6 Requirement: Operations of equipment and controls that have been identified as important to safety in the SAR and in the license must be limited to trained and certified personnel or be under the direct visual supervision of an individual with training and certification in the operatio Supervisory personnel who personally direct the operation of equipment and controls that are important to safety must also be certified in such operations.
Category:
Training Topic:
Dry Run Training Exercise Reference:
CoC 1030, Condition 8 Finding:
Two dry run training exercises were completed by the licensee in preparation for the first loading operation During the week of December 17-21, 2007, an inspection of portions of the ISFSI dry run work was conducted at the TriVis, Inc. headquarters in Pelham, Alabam The inspection included canister sealing via welding and the associated non-destructive examinations (NDE); canister drying and backfilling operations via dewatering, drying, vacuuming, and helium gas inputting; and mechanical cutting of a mockup of the Transnuclear NUHOMS-HD 32PTH Type 1 caniste These activities were documented in Section 4OA5.5 of NRC Inspection Report 05000335/2007005, 05000389/200700 During the week of February 25-29, 2008, an inspection of on-site dry run activities was conducte The operations reviewed included canister retrieval from the horizontal storage module (HSM); canister transport from the HSM to the cask handling facility, including upending from the transport trailer via the overhead crane; flooding the canister; opening the canister; and fuel loading using a dummy fuel assembly. These activities were inspected to confirm the adequacy of procedures, personnel training
/qualification, and equipmen Although the inspectors did not observe the specific Requirement: A dry run training exercise of the loading, closure, handling, unloading and transfer of the NUHOMS-HD System shall be conducted by each licensee prior to first use of the system to load spent nuclear fuel assemblie The loading operations shall include: a)
fuel loading; b) canister sealing; c) drying and backfilling operations; d) transfer cask downending and transport to the ISFSI; and e) canister transfer into the HSM-The unloading operations shall include: a) canister retrieval from the HSM-H; b) flooding the canister; and c) opening the canister.
Page 42 of 43 Attachment 2
activities of transfer cask downending and transport to the ISFSI, or canister transfer into the HSM, the activities which were reviewed were deemed to be equivalent or more difficult to complete.
Documents Reviewed:
NRC Inspection Report 05000335/2007005, 05000389/2007005, dated February 1, 2008 (Adams Document # ML080350408)
Page 43 of 43 Attachment 2