Request for Extension of the Three-Month Response to NRC Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal and
ML081000362
Person / Time
Site: Hatch, Vogtle, Farley  Southern Nuclear icon.png
Issue date: 04/08/2008
From: David Jones
Southern Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
GL-08-001, NL-08-0574
Download: ML081000362 (2)


Text

David H. Jones Southern Nuclear Vice President Operating Company, Inc.

Engineering 40 Inverness Center Parkway Birmingham. Alabama 35242 Tel 205.992.5984 Fax 205.992.0341 SOUTHERNA COMPANY April 8, 2008 Energy to Serve :YourWorld'"

Docket Nos.: 50-321 50-348 50-424 NL-08-0574 50-366 50-364 50-425 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555-0001 Edwin I. Hatch Nuclear Plant Joseph M. Farley Nuclear Plant Vogtle Electric Generating Plant Request for Extension of the Three-Month Response to NRC Generic Letter 2008-01, "Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal. and Containment Spray Systems" Ladies and Gentlemen:

The Nuclear Regulatory Commission (NRC) issued Generic Letter (GL) 2008-01 to request that each licensee evaluate the licensing basis, design, testing, and corrective action programs for the emergency core cooling, decay heat removal, and the containment spray systems, to ensure that gas accumulation is maintained less than the amount that challenges operability of these systems, and that appropriate action is taken when conditions adverse to quality are identified.

The NRC requested that if a licensee cannot meet the requested response date, the licensee "shall provide a response within 3 months of the date of this GL."

Based on an April 7, 2008 telecon between Southern Nuclear Operating Company (SNC) Nuclear Licensing and Jared Wermiel of the NRC, a verbal approval for an extension of the three-month response was given and the new due date for the response is no later than May 30, 2008.

The date extension for the response was requested and approved based on:

  • The short time frame between receipt of the NEI three-month response template and the due date of the response.
  • To allow the SNC plants time to identify the actions which will be completed both prior to and after nine-months from the issuance date of the generic letter.
  • The three-month response will be submitted no later than May 30, 2008.

U. S. Nuclear Regulatory Commission NL-08-0574 Page 2 Mr. D. H. Jones states he is a Vice President of Southern Nuclear Operating Company, is authorized to execute this oath on behalf of Southern Nuclear Operating Company and to the best of his knowledge and belief, the facts set forth in this letter are true.

This letter contains no NRC commitments. If you have any questions, please advise.

Respectfully submitted, NUCLEAR OPERATING COMPANY D. H. Jone Vice President - Engineering before me this ~yof..,...+-,A.L..#-!1-..:...-'&...L.."_L=--_-_, 2008.

Notary Public i~,-r~ Notary Public Slate of Florida

  • Eduardo Rosello

'l(. ~ ~ My ~ommi..ion 00785897 My commission expires: 03/?g,~o/J.

....".. Expwes 0312812012

~~~I'V\\;"VV~~~

DHJ/~ILS/daj cc:

Southern Nuclear Operating Company Mr. J. T. Gasser, Executive Vice President Mr. J. R. Johnson, Vice President - Farley Mr. D. R. Madison, Vice President - Hatch Mr. T. E. Tynan, Vice President - Vogtle RType: CFA04.054; CHA02.004; CVC7000; LC# 14748 U. S. Nuclear Regulatory Commission Mr. V. M. McCree, Acting Regional Administrator Mr. R. A. Jervey, NRR Project Manager - Farley Mr. R. E. Martin, NRR Project Manager - Hatch Mr. R. A. Jervey, NRR Project Manager - Vogtle Mr. E. L. Crowe, Senior Resident Inspector - Farley Mr. J. A. Hickey, Senior Resident Inspector - Hatch Mr. G. J. McCoy, Senior Resident Inspector - Vogtle Alabama Department of Public Health Dr. D. E. Williamson, State Health Officer State of Georgia Mr. N. Holcomb, Commissioner - Department of Natural Resources