Other: ML070390057, ML082630799, ML083100134, ULNRC-05476, One-Time Completion Time Extension for Essential Service Water (ESW) System, ULNRC-05482, Response to Questions Received on February 7, 2008 Regarding Amendment to Revise Technical Specifications for Essential Service Water, ULNRC-05520, One-Time Completion Time Extension for Essential Service Water (ESW) System, (OL1281), ULNRC-05534, One-Time Completion Time Extension for Essential Service Water (ESW) System, ULNRC-05542, Calculation 2007-16760, Rev. 0, Buried Hdpe Piping Stress Analysis, ULNRC-05563, One-Time Completion Time Extension for Essential Service Water System
|
MONTHYEARML0703900572007-02-21021 February 2007 BVPS Doc Table M Project stage: Other ML0725504882007-08-30030 August 2007 CFR 50.55a Request: Proposed Alternative to ASME Section XI Requirements for Replacement of Class 3 Buried Piping Project stage: Request 05000483/LER-2007-003, Regarding 1 OTDT Channel Inoperable for Greater than TS Allowable Time2007-08-30030 August 2007 Regarding 1 OTDT Channel Inoperable for Greater than TS Allowable Time Project stage: Request ULNRC-05445, One-Time Completion Time Extension for Essential Service Water (ESW) System2007-10-31031 October 2007 One-Time Completion Time Extension for Essential Service Water (ESW) System Project stage: Request ML0800400232008-01-0808 January 2008 Forthcoming Meeting with Union Electric Company on the Callaway Plant Relief and Amendment Requests Dated August 3 and October 31, 2007. (Tac No. MD6792 and MD7252) Project stage: Meeting ML0802504052008-01-23023 January 2008 Licensee Handout for Meeting with Union Electric Company on the Callaway Plant Relief Request I3R-10 to Use Plastic Pipe in the Safety-Related Essential Service Water (ESW) System Project stage: Meeting ML0803802882008-02-0707 February 2008 Preliminary Request for Additional Information Project stage: RAI ULNRC-05476, One-Time Completion Time Extension for Essential Service Water (ESW) System2008-02-21021 February 2008 One-Time Completion Time Extension for Essential Service Water (ESW) System Project stage: Other ML0803806472008-02-29029 February 2008 Summary of Meeting with Union Electric Company Callaway Plant, Unit 1, 8/30/2007 Relief Request and 10/31/2007 License Amendment Request Applications Related to Replacement of Essential Service Water Piping (Tac No. MD6792 and MD7252) Project stage: Meeting ULNRC-05482, Response to Questions Received on February 7, 2008 Regarding Amendment to Revise Technical Specifications for Essential Service Water2008-03-0707 March 2008 Response to Questions Received on February 7, 2008 Regarding Amendment to Revise Technical Specifications for Essential Service Water Project stage: Other ML0808800122008-03-31031 March 2008 Request for Additional Information Related to LAR to Revise TS 3.7.8, Essential Service Water System, and TS 3.8.1, AC Sources - Operating, for One-time Completion Time Extension Re Underground Piping Project stage: RAI ULNRC-05434, CFR50.55a Request: Proposed Alternative to ASME Section X1 Requirements for Replacement of Class 3 Buried Piping2008-04-17017 April 2008 CFR50.55a Request: Proposed Alternative to ASME Section X1 Requirements for Replacement of Class 3 Buried Piping Project stage: Request ULNRC-05500, Response to Request for Additional Information One-Time Completion Time Extension for Essential Service Water (ESW) System2008-05-0606 May 2008 Response to Request for Additional Information One-Time Completion Time Extension for Essential Service Water (ESW) System Project stage: Response to RAI ML0815800112008-06-10010 June 2008 Request for Additional Information, Relief Request No. 13R-10 and License Amendment Request to Revise TS 3.7.8, Essential Service Water System, and TS 3.8.1, AC Sources - Operating, for One-time CT Extension Underground Piping Project stage: RAI ML0817506442008-06-24024 June 2008 Forthcoming Meeting with Union Electric Company on the Callaway Plant to Discuss the Licensees Responses to NRC Request for Additional Information Relief and License Amendment Requests Project stage: RAI ULNRC-05517, CFR50.55a Request: Proposed Alternative to ASME Section XI Requirements for Replacement of Class 3 Buried Piping2008-07-10010 July 2008 CFR50.55a Request: Proposed Alternative to ASME Section XI Requirements for Replacement of Class 3 Buried Piping Project stage: Request ULNRC-05520, One-Time Completion Time Extension for Essential Service Water (ESW) System, (OL1281)2008-07-10010 July 2008 One-Time Completion Time Extension for Essential Service Water (ESW) System, (OL1281) Project stage: Other ULNRC-05529, CFR50.55a Request: Proposed Alternative to ASME Section XI Requirements for Replacement of Class 3 Buried Piping2008-07-24024 July 2008 CFR50.55a Request: Proposed Alternative to ASME Section XI Requirements for Replacement of Class 3 Buried Piping Project stage: Request ULNRC-05534, One-Time Completion Time Extension for Essential Service Water (ESW) System2008-08-13013 August 2008 One-Time Completion Time Extension for Essential Service Water (ESW) System Project stage: Other ML0826307992008-09-0505 September 2008 Calculation 2007-13241, Rev. 1, Minimum Wall Thickness for ESW Buried Hdpe Piping Project stage: Other ULNRC-05542, Calculation 2007-16760, Rev. 0, Buried Hdpe Piping Stress Analysis2008-09-12012 September 2008 Calculation 2007-16760, Rev. 0, Buried Hdpe Piping Stress Analysis Project stage: Other ML0826307982008-09-15015 September 2008 Transmittal of Callaway, Unit 1, Additional Information Regarding 10CFR50.55a Request: Proposed Alternative to ASME Section XI Requirements for Replacement of Class 3 Buried Piping Project stage: Request ML0829000272008-10-0909 October 2008 Follow-up Information Regarding 10CFR50.55a Request: Proposed Alternative to ASME Section XI Requirements for Replacement of Class 3 Buried Piping (TAC No. MD67920) Project stage: Request ML0826400072008-10-31031 October 2008 Relief Request I3R-10 for Use of Polyethylene Pipe in Lieu of Carbon Steel Pipe in Buried Essential Service Water Piping System Project stage: Approval ML0828106432008-10-31031 October 2008 Issuance of Amendment No. 186, Revise TS 3.7.8, Essential Service Water System, and TS 3.8.1, AC Sources - Operating, for One-time Completion Time Extension Re Underground Piping Project stage: Approval ML0831001342008-11-0606 November 2008 Correction to Amendment No. 186 Approving One-Time Extension of Completion Time for Inoperable Essential Service Water System and Emergency Diesel Generators Project stage: Other ML0831002882008-11-0707 November 2008 Relief Request 13R-10 Approved on October 31, 2008, for Third 10-Year Inservice Inspection Interval for Use of Polyethylene Pipe in Lieu of Carbon Steel Pipe in Buried Essential Service Water Piping System Project stage: Approval ULNRC-05563, One-Time Completion Time Extension for Essential Service Water System2008-12-0101 December 2008 One-Time Completion Time Extension for Essential Service Water System Project stage: Other ML0834503272008-12-19019 December 2008 Summary of Meeting with Representatives of Union Electric Company, Licensee for Callaway Plant, Unit 1 Second Round of Requests for Information, Extension of Completion Time for Essential Service Water Systems (TAC Nos. MD6792 & MD7252) Project stage: Meeting ULNRC-06115, CFR 50.55a Request: Proposed Alternative to ASME Section XI Alternative Technical Requirements for Class 3 Buried Piping2014-06-10010 June 2014 CFR 50.55a Request: Proposed Alternative to ASME Section XI Alternative Technical Requirements for Class 3 Buried Piping Project stage: Request 2008-02-07
[Table View] |
Text
From:
Mohan Thadani To:
Internet:smaglio@ameren.com Date:
2/7/2008 9:53:40 AM
Subject:
PRELIMINARY REQUEST FOR ADDITIONAL INFORMATION-TAC NO. MD7252 Scott:
The NRC staff has reviewed the Ameren UE request regarding one-time AOT extension for EDGs for Callaway plant. The NRC staff has identified a need for additional information. Attached is a preliminary request for additional information. A formal letter request will follow. I request that Ameren respond to the subject request within 30 days, to facilitate timely completion of the requested action.
Thanks.
Mohan REQUEST FOR ADDITIONAL INFORMATION AMERENUE Callaway Plant Docket No. 50-483
- 1)
Describe the safety margins that are being credited in the license amendment request section titled, Evaluation of Safety Margins. Also, demonstrate that the safety margins for the events analyzed in the Callaway Plant Final Safety Analysis Report will not be impacted during the implementation proposed change.
- 2)
Based on previously approved diesel generator (DG) Technical Specification (TS) Completion Time (CT) extension requests, the staff has found that certain compensatory measures, in the form of regulatory commitments, need to be implemented during the extended DG CT. These regulatory commitments help ensure continued safe operation of the plant. The following compensatory measures are provided as examples of regulatory commitments that other licensees have provided in support of obtaining DG CT extensions. Provide a discussion as to how you will address each of the following compensatory measures for the Callaway Plant.
No maintenance or testing that affects the reliability of the train associated with the OPERABLE DG will be scheduled during the extended CT. If any testing and maintenance activities must be performed while the extended CT is in effect, an evaluation will be performed in accordance with Title 10 to the Code of Federal Regulations (10 CFR) Section 50.65(a)(4).
An alternate power source with capacity equal to or greater than the capacity of the inoperable DG will be available as a backup to the inoperable DG. After entering the extended CT, this source will be verified available every 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> and treated as protected equipment.
The scheduling of DG preplanned maintenance will be avoided during seasons when the probability of severe weather or grid stress conditions are high or forecasted to be high.
The system load dispatcher will be contacted once per day to
ensure no significant grid perturbations are expected during the extended CT.
Also, the system load dispatcher should inform the plant operator if conditions change during the extended CT (e.g., unacceptable voltages could result due to a trip of the nuclear unit).
Component testing or maintenance of safety systems and important non-safety equipment including offsite power systems (auxiliary and startup transformers) that increase the likelihood of a plant transient or loss-of-offsite power (LOOP) will be avoided. In addition, no discretionary switchyard maintenance will be allowed.
TS requirements of verification that the required systems, subsystems, trains, components, and devices that depend on the remaining DG(s) are operable and positive measures will be provided to preclude subsequent testing or maintenance activities on these systems, subsystems, trains, components, and devices.
Turbine driven auxiliary feedwater pump will be controlled as protected equipment, and will not be taken out of service for planned maintenance while a DG is out of service for extended maintenance.
- 3)
In accordance with the defense-in-depth philosophy, describe how the remaining systems will be capable of performing the function of the safety system that is being removed from service.
- 4)
If the DG on the affected train continues to be functional but not OPERABLE, describe the loading capabilities of the functional DG. Also describe how the functional DG would respond if called upon (e.g., a LOOP event).
Mail Envelope Properties (47AB1B74.3C3 : 23 : 35106)
Subject:
PRELIMINARY REQUEST FOR ADDITIONAL INFORMATION-TAC NO. MD7252 Creation Date 2/7/2008 9:53:40 AM From:
Mohan Thadani Created By:
MCT@nrc.gov Recipients ameren.com smaglio (Internet:smaglio@ameren.com)
Post Office Route ameren.com Internet Files Size Date & Time MESSAGE 881 2/7/2008 9:53:40 AM RAI_ML0803601840.doc 33280 2/7/2008 9:51:08 AM