Request for Additional Information, GL 2007-01, Inaccessible or Underground Power Cable Failures That Disable Accident Mitigation Systems or Cause Plant Transients
ML073110477
Person / Time
Site: San Onofre  
Issue date: 11/15/2007
From: Kalyanam N
NRC/NRR/ADRO/DORL/LPLIV
To: Rosenblum R
Southern California Edison Co
Kalyanam N, NRR/DORL/LPL4, 415-1480
References
GL-07-001, TAC MD4377, TAC MD4378
Download: ML073110477 (4)


Text

November 15, 2007 Mr. Richard M. Rosenblum Senior Vice President and Chief Nuclear Officer Southern California Edison Company San Onofre Nuclear Generating Station P.O. Box 128 San Clemente, CA 92674-0128

SUBJECT:

SAN ONOFRE NUCLEAR GENERATING STATION, UNITS 2 AND 3 -

REQUEST FOR ADDITIONAL INFORMATION ON THE NUCLEAR REGULATORY COMMISSION GENERIC LETTER 2007-01: INACCESSIBLE OR UNDERGROUND POWER CABLE FAILURES THAT DISABLE ACCIDENT MITIGATION SYSTEMS OR CAUSE PLANT TRANSIENTS (TAC NOS. MD4377 AND MD4378)

Dear Mr. Rosenblum:

The U.S. Nuclear Regulatory Commission (NRC) staff has received the cable failure history for San Onofre Nuclear Generating Station, Units 2 and 3, in response to Generic Letter (GL) 2007-01, "Inaccessible or Underground Power Cable Failures that Disable Accident Mitigation Systems or Cause Plant Transients." During its review, the licensee found no failures of inaccessible or underground power cables within the scope of Title 10 of the Code of Federal Regulations (10 CFR), Section 50.65, "Requirements for Monitoring the Effectiveness of Maintenance at Nuclear Power Plants" (Maintenance Rule (MR)). Please confirm that this history includes cable failures that occurred prior to July 10, 1996.

Paragraph (c) of 10 CFR 50.65 states, "[t]he requirements of this section shall be implemented by each licensee no later than July 10, 1996." The NRC staff is concerned that licensees may have excluded cable failures from the GL 2007-01 responses if the cable failures occurred prior to July 10, 1996 (or the licensee's implementation date of the MR). The NRC staff provided additional guidance on how licensees should determine which cable failures are within the scope of GL 2007-01 in the NRC letter dated April 13, 2007, from Michael J. Case (NRC) to James H. Riley (Nuclear Energy Institute) (Agencywide Documents Access and Management System (ADAMS) Accession No. ML070940311). This document stated to include cable failures that can be searched for in an electronic database, regardless of the actual date of the failure. If San Onofre's response to GL 2007-01 excluded cable failures that occurred prior to July 10, 1996, provide the data for these failures as requested in GL 2007-01.

R. M. Rosenblum Please provide the additional information requested within 30 days of the receipt of this letter.

If you have any questions, please contact me at (301) 415-1480.

Sincerely,

/RA/

N. Kalyanam, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-361 and 50-362 cc: See next page

ML073110477 NRR-088

  • No change from staff provided RAI OFFICE NRR/LPL4/PM NRR/LPL4/LA NRR/DE/EEEB*

NRR/LPL4/BC NAME NKalyanam:sp JBurkhardt GWilson THiltz DATE 11/13/07 11/9/07 11/15/07

October 2007 San Onofre Nuclear Generating Station Units 2 and 3 cc:

Mr. Raymond W. Waldo, Vice President, Nuclear Generation Southern California Edison Company San Onofre Nuclear Generating Station P.O. Box 128 San Clemente, CA 92674-0128 Mr. Douglas K. Porter, Esquire Southern California Edison Company 2244 Walnut Grove Avenue Rosemead, CA 91770 Dr. David Spath, Chief Division of Drinking Water and Environmental Management California Dept. of Health Services 850 Marina Parkway, Bldg P, 2nd Floor Richmond, CA 94804 Chairman, Board of Supervisors County of San Diego 1600 Pacific Highway, Room 335 San Diego, CA 92101 Mark L. Parsons Deputy City Attorney City of Riverside 3900 Main Street Riverside, CA 92522 Mr. Gary L. Nolff Assistant Director - Resources City of Riverside 3900 Main Street, 4th Floor Riverside, CA 92522 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064 Mr. Michael L. DeMarco San Diego Gas & Electric Company 8315 Century Park Ct. CP21G San Diego, CA 92123-1548 Director, Radiologic Health Branch State Department of Health Services P.O. Box 997414, MS 7610 Sacramento, CA 95899-7414 Resident Inspector San Onofre Nuclear Generating Station c/o U.S. Nuclear Regulatory Commission Post Office Box 4329 San Clemente, CA 92674 Mayor City of San Clemente 100 Avenida Presidio San Clemente, CA 92672 Mr. James T. Reilly Southern California Edison Company San Onofre Nuclear Generating Station P.O. Box 128 San Clemente, CA 92674-0128 Mr. James D. Boyd, Commissioner California Energy Commission 1516 Ninth Street (MS 31)

Sacramento, CA 95814 Brian Katz Southern California Edison Company San Onofre Nuclear Generating Station P.O. Box 128 San Clemente, CA 92764-0128 Mr. Steve Hsu Department of Health Services Radiologic Health Branch MS 7610, P.O. Box 997414 Sacramento, CA 95899-7414 Mr. A. Edward Scherer Southern California Edison Company San Onofre Nuclear Generating Station P.O. Box 128 San Clemente, CA 92674-0128