MONTHYEARML24303A2822024-10-29029 October 2024 License Termination Plan Supplemental Submittal for Technical Bases Documents ML24284A1972024-10-10010 October 2024 Cover Letter Oyster Creek, License Termination Plan Acceptance Review ML24269A0462024-10-0404 October 2024 Cover Letter for Oyster Creek Nuclear Generating Station, License Amendment Request, License Termination Plan, Acceptance Review Request for Additional Information ML24274A0822024-09-25025 September 2024 Independent Spent Fuel Storage Installation Security Plan, Training Qualification Plan, Safeguards Contingency Plan, Revisions 1 and 2 ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status IR 05000219/20240022024-09-0505 September 2024 – NRC Inspection Report 05000219/2024002 and 07200015/2024001 PNP 2024-030, Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 02024-08-0202 August 2024 Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 0 ML24214A0372024-08-0101 August 2024 License Amendment Request to Revise Renewed Facility Operating License to Add License Condition 2.C.(18) to Include License Termination Plan Requirements ML24179A1842024-07-23023 July 2024 June 20, 2024, Clarification Call on Preapplication Readiness Assessment of the Holtec Decommissioning International License Termination Plan ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities IR 05000219/20240012024-05-14014 May 2024 Decommissioning Intl, LLC Oyster Creek Nuclear Generating Station - NRC Inspection Report No. 05000219/2024001 L-24-009, HDI Annual Occupational Radiation Exposure Data Reports - 20232024-04-29029 April 2024 HDI Annual Occupational Radiation Exposure Data Reports - 2023 ML24120A0402024-04-29029 April 2024 Annual Radioactive Effluent Release Report for 2023 ML24120A0412024-04-29029 April 2024 Annual Radioactive Environmental Operating Report for 2023 ML24094A2142024-04-19019 April 2024 Preapplication Readiness Assessment of the Holtec Decommissioning International License Termination Plan ML24089A2492024-03-29029 March 2024 Reply to Notice of Violation EA-2024-024 L-24-007, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI)2024-03-29029 March 2024 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI) ML24085A7902024-03-28028 March 2024 – Preapplication Readiness Assessment of the License Termination Plan ML24081A2882024-03-21021 March 2024 Request Preliminary Review and Feedback on Chapter 6 of the Draft License Termination Plan ML24046A1242024-02-29029 February 2024 – NRC Inspection Report 05000219/2023003 ML24033A3272024-02-0202 February 2024 Request Preliminary Review and Feedback on Chapter 5 of the Draft License Termination Plan ML23342A1162024-01-0909 January 2024 Independent Spent Fuel Storage Installation Security Inspection Plan L-23-019, Proof of Financial Protection 10 CFR 140.152023-12-18018 December 2023 Proof of Financial Protection 10 CFR 140.15 IR 05000219/20230022023-11-0909 November 2023 EA-23-076 Oyster Creek Nuclear Generating Station - Notice of Violation and Proposed Imposition of Civil Penalty - $43,750 - NRC Inspection Report No. 05000219/2023002 ML23286A1552023-10-13013 October 2023 Defueled Safety Analysis Report (DSAR) ML23249A1212023-09-0606 September 2023 NRC Inspection Report 05000219/2023002, Apparent Violation (EA-23-076) ML23242A1162023-08-30030 August 2023 Biennial 10 CFR 50.59 and 10 CFR 72.48 Change Summary Report January 1, 2021 Through December 31, 2022 ML23214A2472023-08-22022 August 2023 NRC Inspection Report 05000219/2023002 IR 05000219/20230012023-05-31031 May 2023 NRC Inspection Report No. 05000219/2023001 IR 07200015/20234012023-05-16016 May 2023 NRC Independent Spent Fuel Storage Installation Security Inspection Report 07200015/2023401 L-23-004, HDI Annual Occupational Radiation Exposure Data Reports - 20222023-04-24024 April 2023 HDI Annual Occupational Radiation Exposure Data Reports - 2022 ML23114A0912023-04-24024 April 2023 Annual Radioactive Effluent Release Report for 2022 ML23114A0872023-04-24024 April 2023 Annual Radioactive Environmental Operating Report for 2022 L-23-003, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-31031 March 2023 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23088A0382023-03-29029 March 2023 Stations 1, 2, & 3, Palisades Nuclear Plant, and Big Rock Point - Nuclear Onsite Property Damage Insurance ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities IR 05000219/20220022023-02-0909 February 2023 NRC Inspection Report No. 05000219/2022002 ML23031A3012023-02-0808 February 2023 Discontinuation of Radiological Effluent Monitoring Location in the Sewerage System ML23033A5052023-02-0202 February 2023 First Use Notification of NRC Approved Cask RT-100 ML23025A0112023-01-24024 January 2023 LLRW Late Shipment Investigation Report Per 10 CFR 20, Appendix G ML22347A2732022-12-21021 December 2022 Independent Spent Fuel Storage Installation Security Inspection Plan Dated December 21, 2022 ML22297A1432022-12-15015 December 2022 Part 20 App G Exemption Letter L-22-042, Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.152022-12-14014 December 2022 Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.15 IR 07200015/20224012022-12-0606 December 2022 NRC Independent Spent Fuel Storage Installation Security Inspection Report 07200015/2022401 (Letter & Enclosure 1) ML22280A0762022-11-0202 November 2022 Us NRC Analysis of Holtec Decommissioning Internationals Funding Status Report for Oyster Creek, Indian Point and Pilgrim Nuclear Power Station ML22276A1762022-10-24024 October 2022 Decommissioning International Proposed Revisions to the Quality Assurance Program Approval Forms for Radioactive Material Packages ML22286A1402022-10-13013 October 2022 NRC Confirmatory Order EA-21-041 IR 05000219/20220012022-08-11011 August 2022 NRC Inspection Report 05000219/2022001 ML22215A1772022-08-0303 August 2022 Decommissioning International (HDI) Proposed Revisions to the Quality Assurance Program Approval Forms for Radioactive Material Packages ML22214A1732022-08-0202 August 2022 Request for Exemption from 10 CFR 20, Appendix G, Section Iii.E 2024-09-05
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 475 ALLENDALE ROAD KING OF PRUSSIA, PENNSYLVANIA 19406-1415 September 13, 2007 Mr. David Lochbaum Union of Concerned Scientists 1707 H Street, NW, Suite 600 Washington, D.C. 20006
Dear Mr. Lochbaum:
I am responding to your letter of July 18, 2007, which raised concerns related to the Oyster Creek Nuclear Generating Station plant scram that occurred on July 17, 2007. Your concerns related to whether operator actions were appropriate including whether the plant should have scrammed and whether the consequences of the event were expected (e.g., main steam isolation valve closure and containment spray). Although you did not request a written response, we are providing this response to emphasize the importance we place on event response.
Event response is a key priority for the U.S. Nuclear Regulatory Commission (NRC). The NRC has various processes in place to ensure effective event response. For this event, the resident inspectors promptly responded to the control room and provided timely communication of plant status to NRC regional management. Additional inspection was considered in accordance with the criteria outlined in NRC Inspection Manual Chapter (IMC) 0309, Reactive Inspection Decision Basis for Reactors (ML070860410). Based on review of the event conditional risk, detailed information gathered through prompt onsite inspection, and consultation with regional specialist inspectors, we determined that a special team inspection was not warranted.
Accordingly, we initiated a baseline event follow-up inspection to more fully assess plant equipment and operator response.
Throughout the event, there was frequent communication between the resident inspectors, NRC regional management, and NRC headquarters staff to assess licensee performance and plant conditions. Specialist inspection support to address various technical questions and issues was provided, where needed. Additionally, a Preliminary Notification of Event or Unusual Occurrence (PN) (PNO-I-07-006) was issued to communicate the event to external stakeholders. Close communications have continued between NRC regional management and the inspection staff throughout our follow-up inspection. We will include our conclusions on this matter in our next periodic resident inspection report, which will be issued no later than November 15, 2007.
We expect our inspection to determine the significance and impact of licensee performance during this event, and we will forward a copy of the resident inspection report to you once it is issued. Our inspection scope includes independent verification that event-related performance deficiencies, if any occurred, are identified and addressed through the licensees formal corrective action program. We expect this inspection to address your questions.
Mr. D. Lochbaum 2 I trust that this letter has been responsive to your concern. If you have any further questions or concerns in this matter, please contact Ronald Bellamy at 610-337-5200.
Sincerely,
/RA/
David C. Lew, Director Division of Reactor Projects Docket No. 50-219 License No. DPR-16
Mr. D. Lochbaum 2 I trust that this letter has been responsive to your concern. If you have any further questions or concerns in this matter, please contact Ronald Bellamy at 610-337-5200.
Sincerely,
/RA/
David C. Lew, Director Division of Reactor Projects Docket No. 50-219 License No. DPR-16 Distribution w/encl:
S. Collins, RA M. Dapas, DRA D. Lew, DRP J. Clifford, DRP R. Bellamy, DRP S. Barber, DRP M. Ferdas, DRP, Sr Resident Inspector R. Treadway, DRP, Resident Inspector J. DeVries, DRP, Resident OA R. Laufer, RI OEDO H. Chernoff, NRR J. Lubinski, NRR E. Miller, PM, NRR J. Hughey, NRR, Backup G. Matakas, ORA Region I Docket Room (with concurrences)
Response Letter ADAMS Accession Number: ML072560803 Incoming Letter ADAMS Accession Number: ML072220387 SUNSI Review Complete: GSB (Reviewers Initials)
DOCUMENT NAME: C:\FileNet\ML072560803.wpd After declaring this document An Official Agency Record it will be released to the Public.
To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRP RI/DRP RI/DRP RI/DRP NAME SBarber/SB MFerdas/SB for RBellamy/RRB DLew/DCL DATE 08/08/07 08/08/07 09/12/07 09/12/07 OFFICIAL RECORD COPY