July 3, 2007 MEMORANDUM TO: Harold K. Chernoff, Chief Plant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation FROM: Richard B. Ennis, Senior Project Manager /RA/

Plant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

SUBJECT:

SALEM NUCLEAR GENERATING STATION, UNIT NOS. 1 AND 2, DRAFT REQUEST FOR ADDITIONAL INFORMATION (TAC NOS. MD4843 AND MD4844)

The attached draft request for information (RAI) was transmitted on July 3, 2007, to Mr. Jamie Mallon of PSEG Nuclear LLC (the licensee). This information was transmitted to facilitate an upcoming conference call in order to clarify the licensees amendment request for Salem Nuclear Generating Station (Salem), Unit Nos. 1 and 2, dated March 16, 2007. The proposed amendment would add new Technical Specification (TS) requirements for the response times associated with a steam generator feedwater pump (SGFP) trip and feedwater isolation valve (FIV) closure. The amendment would also revise the TS requirements for the containment fan cooler unit (CFCU) cooling water flow rate. These changes are associated with a revised containment response analysis that credits a SGFP trip and FIV closure (on a feedwater regulator valve failure) to reduce the mass/energy release to the containment during a main steam line break (MSLB). The containment analysis also credits a reduced heat removal capability for the CFCUs, allowing a reduction in the required service water (SW) flow to the CFCUs.

This memorandum and the attachment do not convey or represent an NRC staff position regarding the licensee's request.

Docket Nos. 50-272 and 50-311

Attachment:

Draft RAI

July 3, 2007 MEMORANDUM TO: Harold K. Chernoff, Chief Plant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation FROM: Richard B. Ennis, Senior Project Manager Plant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

SUBJECT:

SALEM NUCLEAR GENERATING STATION, UNIT NOS. 1 AND 2, DRAFT REQUEST FOR ADDITIONAL INFORMATION (TAC NOS. MD4843 AND MD4844)

The attached draft request for information (RAI) was transmitted on July 3, 2007, to Mr. Jamie Mallon of PSEG Nuclear LLC (the licensee). This information was transmitted to facilitate an upcoming conference call in order to clarify the licensees amendment request for Salem Nuclear Generating Station (Salem), Unit Nos. 1 and 2, dated March 16, 2007. The proposed amendment would add new Technical Specification (TS) requirements for the response times associated with a steam generator feedwater pump (SGFP) trip and feedwater isolation valve (FIV) closure. The amendment would also revise the TS requirements for the containment fan cooler unit (CFCU) cooling water flow rate. These changes are associated with a revised containment response analysis that credits a SGFP trip and FIV closure (on a feedwater regulator valve failure) to reduce the mass/energy release to the containment during a main steam line break (MSLB). The containment analysis also credits a reduced heat removal capability for the CFCUs, allowing a reduction in the required service water (SW) flow to the CFCUs.

This memorandum and the attachment do not convey or represent an NRC staff position regarding the licensee's request.

Docket Nos. 50-272 and 50-311

Attachment:

Draft RAI DISTRIBUTION PUBLIC RidsNrrDorlLpl1-2 PDI-2 Reading RidsNrrPMREnnis RidsNrrDorlDpr JFair ACCESSION NO.: ML071860475 OFFICE PDI-2/PM NAME REnnis DATE 07/03/07 OFFICIAL RECORD COPY

DRAFT REQUEST FOR ADDITIONAL INFORMATION REGARDING PROPOSED LICENSE AMENDMENT STEAM GENERATOR FEEDWATER PUMP TRIP, FEEDWATER ISOLATION VALVE CLOSURE RESPONSE TIMES, AND CONTAINMENT FAN COIL UNIT COOLING WATER FLOW RATE SALEM NUCLEAR GENERATING STATION, UNIT NOS. 1 AND 2 DOCKET NOS. 50-272 AND 50-311 By letter dated March 16, 2007, PSEG Nuclear LLC (PSEG or the licensee) submitted an amendment request for Salem Nuclear Generating Station (Salem), Unit Nos. 1 and 2. The proposed amendment would add new Technical Specification (TS) requirements for the response times associated with a steam generator feedwater pump (SGFP) trip and feedwater isolation valve (FIV) closure. The amendment would also revise the TS requirements for the containment fan cooler unit (CFCU) cooling water flow rate. These changes are associated with a revised containment response analysis that credits a SGFP trip and FIV closure (on a feedwater regulator valve failure) to reduce the mass/energy release to the containment during a main steam line break (MSLB). The containment analysis also credits a reduced heat removal capability for the CFCUs, allowing a reduction in the required service water (SW) flow to the CFCUs.

The NRC staff has reviewed the information the licensee provided that supports the proposed amendment and would like to discuss the following issues to clarify the submittal.

EMCB-1: PSEGs letter dated May 8, 1998, provided a response to an NRC staff request for additional information (RAI) regarding Generic Letter (GL) 96-06. The GL RAI response indicated that, for Salem Unit 2 penetrations M22A, M27, and M45, relief valves would be installed to protect these penetrations from thermally-induced pressurization. However, based on the discussion in Section 6.8 of Enclosure 2 to PSEGs application dated March 16, 2007, regarding the impact of the proposed amendment on these penetrations, it does not appear that relief valves were installed. Please clarify if these penetrations are protected by relief valves as indicated in the submittal dated May 8, 1998.

Attachment