MONTHYEARML11346A3012011-06-27027 June 2011 Declaration of Joseph R. Lynch, Lori Ann Potts, and Dr. Kevin R. O'Kula in Support of Entergy'S Answer Opposing Pilgrim Watch Request for Hearing on a New Contention Regarding Inadequacy of Environmental Report, Post-Fukushima ML1102503532011-01-0101 January 2011 Pilgrim Watch Reply to Entergy'S Request to Change the Hearing Date ML1100401252010-12-27027 December 2010 Entergy Answer Opposing Pilgrim Watch Request for Hearing on a New Contention ML1033403262010-11-22022 November 2010 Pilgrim Watch Reply to Order (October 26, 2010) - Questions from Board Majority Regarding the Mechanics of Computing Mean Consequences ML1030810622010-11-0303 November 2010 Response to Pilgrim Watch October 27 Letter Regarding Pilgrim Watch 6th and 7th Supplemental Disclosures ML1028711332010-10-0808 October 2010 Pilgrim Watch Reply to Entergy'S & NRC Staff'S Briefs Regarding Timeliness of Pilgrim Watch'S Raising Averaging Practice Concerns ML1027203992010-09-21021 September 2010 Entergy'S Response to Pilgrim Watch'S Memo Re Proposed Schedule ML1027307882010-09-21021 September 2010 Pilgrim Watch'S Reply to Entergy'S Response to Pilgrim Watch'S Memo Regarding Proposed Schedule ML1027307892010-09-21021 September 2010 Memo Regarding Proposed Schedule ML1021104482010-07-25025 July 2010 Pilgrim Watch Notice to Commission Regarding New and Significant Information Pertaining to Pilgrim Watch'S Petition for Review of LBP-06-848 ML1020900242010-07-19019 July 2010 Pilgrim Watch 2.206 Petition Regarding Inadequacy of Entergy'S Management of Non-Environmentally Qualified Inaccessible Cables & Wiring at Pilgrim Station ML1018000932010-06-28028 June 2010 NRC Staff'S Opposition to Pilgrim Watch'S Motion Requesting Leave to File Response to Judge Paul B. Abramson Decision on Recusal Motion (June 10, 2010) ML1018004862010-06-23023 June 2010 Entergy'S Opposition to Pilgrim Watch'S Motion Requesting Leave to File Response to Judge Abramson'S Decision on Recusal Motion ML1017301832010-06-16016 June 2010 Pilgrim Watch Response to Judge Paul B. Abramson Decision on Recusal Motion ML1014605742010-05-21021 May 2010 Entergy'S Opposition to Pilgrim Watch Motion to Disqualify Judge Abramson ML1014402032010-05-17017 May 2010 Entergy'S Reply to Pilgrim Watch'S Response to Aslb'S May 5, 2010 Order ML1015404212010-05-17017 May 2010 Pilgrim Watch'S Reply to Entergy'S Submission on Scope and Schedule for Remanded Hearing ML1014503232010-05-17017 May 2010 Pilgrim Watch'S Reply to NRC Staff'S Initial Brief to the Board'S Order (Regarding Deadlines for Submission of Parties) ML1014107452010-05-12012 May 2010 Pilgrim Watch Response to Aslb'S May 5, 2010 Order ML1014107432010-05-12012 May 2010 Entergy'S Submission on Scope and Schedule for Remanded Hearing ML1010504322010-04-15015 April 2010 NRC Staff'S Response in Opposition to Pilgrim Watch'S Motion for Reconsideration of CLI-10-11 ML1010408202010-04-0808 April 2010 Entergy'S Opposition to Pilgrim Watch'S Motion for Reconsideration of CLI-10-11 ML1010408192010-04-0707 April 2010 Entergy'S Opposition to Pilgrim Watch'S Motion to Reschedule Telephone Conference ML1010408212010-04-0707 April 2010 Entergy'S Opposition to Town of Plymouth'S Motion to Reschedule Telephone Conference ML1004808082010-02-0202 February 2010 Pilgrim Watch'S Reply to NRC Staff'S Response to Pilgrim Watch Notice to Commission Regarding New & Significant Information Pertaining to Pilgrim Watch'S Petition for Review of LBP-06-848 ML0823700122008-08-19019 August 2008 Pilgrim - Notice of Withdrawal of Appearance for James E. Adler ML0816402452008-05-15015 May 2008 2008/05/15-Supplemental Petition by Listed Companies for Additional Investigation and Correction of Deficiencies Regarding License Renewal Reviews, for Oyster Creek, Indian Point, Pilgrim, and Vermont Yankee Nuclear Power Plants ML0814906102008-05-15015 May 2008 2008/05/15-Supplemental Petition by Collective Petitioners for Additional Investigation and Correction of Deficiencies Regarding License Renewal Reviews for Oyster Creek, Indian Point, Pilgrim, and Vermont Yankee Nuclear Power Plants ML0814306512008-05-15015 May 2008 Supplemental Petition by Nuclear Information and Resource Service: Jersey Shore Nuclear Watch, Inc.: Grandmothers, Mothers and More for Energy Safety: New Jersey Public Interest Research Group: New Jersey Sierra Club: New Jersey.. ML0808600962008-03-17017 March 2008 Pilgrim Watch Reply to NRC Staff'S Motion in Limine to Strike Exhibits and Testimony Filed by Pilgrim Watch, March 10, 2008 ML0808600952008-03-17017 March 2008 Pilgrim Watch Reply to Entergy'S Motion in Limine to Strike Exhibits and Testimony Filed by Pilgrim Watch, March 10, 2008 ML0807402022008-03-0707 March 2008 Entergy'S Eleventh Supplemental Disclosure ML0802904142008-01-18018 January 2008 2008/01/18-Answer of Entergy Nuclear Operation, Inc. Opposing Petition to Suspend License Renewal Reviews and Proceedings ML0802803052008-01-18018 January 2008 2008/01/18-NRC Staff Answer to Petition for Suspension of License Renewal Reviews Pending Investigation of NRC Staff License Renewal Process ML0735403732007-12-14014 December 2007 Entergy'S Eighth Supplemental Disclosure ML0726901592007-09-20020 September 2007 Entergy Nuclear Operations Inc. Answer Opposing Intervention Petition of Local 369, Utility Workers Union of America, AFL-CIO ML0726205402007-09-18018 September 2007 Motion to Intervene of Local 369, Utility Workers Union of America, AFL-CIO ML0721901912007-07-30030 July 2007 Pilgrim Watch'S Answer Opposing NRC Staff'S Motion Requesting That Pilgrim Watch'S Answer Opposing NRC Staff Support of Entergy'S Motion to Strike Pilgrim Watch'S Answer to Entergy'S Summary Disposition Motion Not Be Considered by the Board ML0721302252007-07-26026 July 2007 Pilgrim - Pilgrim Watch'S Answer Opposing NRC Staff'S Support of Entergy'S Motion to Strike Portions of Pilgrim Watch'S Answer Opposing Entergy'S Motion for Summary Disposition of Contention 3 ML0720501452007-07-17017 July 2007 Pilgrim - Pilgrim Watch'S Answer Opposing Entergy'S Motion to Strike Portions of Pilgrim Watch'S Answer Opposing Entergy'S Motion for Summary Disposition of Pilgrim Watch Contention 3 ML0718405682007-06-29029 June 2007 Pilgrim - Pilgrim Watch'S Answer Opposing Entergy'S Motion for Summary Disposition of Pilgrim Watch Contention 3 ML0718000592007-06-28028 June 2007 Pilgrim - NRC Staff Response to Entergy'S Motion for Summary Disposition of Pilgrim Watch Contention 1 ML0716303952007-06-0505 June 2007 Pilgrim - Entergy'S Sixth Supplemental Disclosure ML0715002992007-05-24024 May 2007 Pilgrim - Entergy'S Opposition to Pilgrim Watch Request to Extend Time to Respond to Summary Disposition of Pilgrim Watch Contention 3 ML0715201682007-05-22022 May 2007 Pilgrim - Notice of Appearance of Mary Elizabeth Lampert ML0711702672007-04-18018 April 2007 Pilgrim - Second Disclosure Statement by Pilgrim Watch ML0711702602007-04-16016 April 2007 Pilgrim - Entergy'S Fourth Supplemental Disclosure ML0708002172007-03-15015 March 2007 Pilgrim - Entergy'S Third Supplemental Disclosure ML0707301912007-03-0606 March 2007 Pilgrim - Letter to Judge Cole from S. Uttal, OGC Providing (Cd) Version of Safety Evaluation Report with Open Items ML0634803752006-12-0808 December 2006 Pilgrim- Entergy'S Comments on Proposed Schedule 2011-06-27
[Table view] Category:Responses and Contentions
MONTHYEARML11346A3012011-06-27027 June 2011 Declaration of Joseph R. Lynch, Lori Ann Potts, and Dr. Kevin R. O'Kula in Support of Entergy'S Answer Opposing Pilgrim Watch Request for Hearing on a New Contention Regarding Inadequacy of Environmental Report, Post-Fukushima ML1102503532011-01-0101 January 2011 Pilgrim Watch Reply to Entergy'S Request to Change the Hearing Date ML1100401252010-12-27027 December 2010 Entergy Answer Opposing Pilgrim Watch Request for Hearing on a New Contention ML1033403262010-11-22022 November 2010 Pilgrim Watch Reply to Order (October 26, 2010) - Questions from Board Majority Regarding the Mechanics of Computing Mean Consequences ML1030810622010-11-0303 November 2010 Response to Pilgrim Watch October 27 Letter Regarding Pilgrim Watch 6th and 7th Supplemental Disclosures ML1028711332010-10-0808 October 2010 Pilgrim Watch Reply to Entergy'S & NRC Staff'S Briefs Regarding Timeliness of Pilgrim Watch'S Raising Averaging Practice Concerns ML1027203992010-09-21021 September 2010 Entergy'S Response to Pilgrim Watch'S Memo Re Proposed Schedule ML1027307882010-09-21021 September 2010 Pilgrim Watch'S Reply to Entergy'S Response to Pilgrim Watch'S Memo Regarding Proposed Schedule ML1027307892010-09-21021 September 2010 Memo Regarding Proposed Schedule ML1021104482010-07-25025 July 2010 Pilgrim Watch Notice to Commission Regarding New and Significant Information Pertaining to Pilgrim Watch'S Petition for Review of LBP-06-848 ML1020900242010-07-19019 July 2010 Pilgrim Watch 2.206 Petition Regarding Inadequacy of Entergy'S Management of Non-Environmentally Qualified Inaccessible Cables & Wiring at Pilgrim Station ML1018000932010-06-28028 June 2010 NRC Staff'S Opposition to Pilgrim Watch'S Motion Requesting Leave to File Response to Judge Paul B. Abramson Decision on Recusal Motion (June 10, 2010) ML1018004862010-06-23023 June 2010 Entergy'S Opposition to Pilgrim Watch'S Motion Requesting Leave to File Response to Judge Abramson'S Decision on Recusal Motion ML1017301832010-06-16016 June 2010 Pilgrim Watch Response to Judge Paul B. Abramson Decision on Recusal Motion ML1014605742010-05-21021 May 2010 Entergy'S Opposition to Pilgrim Watch Motion to Disqualify Judge Abramson ML1014402032010-05-17017 May 2010 Entergy'S Reply to Pilgrim Watch'S Response to Aslb'S May 5, 2010 Order ML1015404212010-05-17017 May 2010 Pilgrim Watch'S Reply to Entergy'S Submission on Scope and Schedule for Remanded Hearing ML1014503232010-05-17017 May 2010 Pilgrim Watch'S Reply to NRC Staff'S Initial Brief to the Board'S Order (Regarding Deadlines for Submission of Parties) ML1014107452010-05-12012 May 2010 Pilgrim Watch Response to Aslb'S May 5, 2010 Order ML1014107432010-05-12012 May 2010 Entergy'S Submission on Scope and Schedule for Remanded Hearing ML1010504322010-04-15015 April 2010 NRC Staff'S Response in Opposition to Pilgrim Watch'S Motion for Reconsideration of CLI-10-11 ML1010408202010-04-0808 April 2010 Entergy'S Opposition to Pilgrim Watch'S Motion for Reconsideration of CLI-10-11 ML1010408192010-04-0707 April 2010 Entergy'S Opposition to Pilgrim Watch'S Motion to Reschedule Telephone Conference ML1010408212010-04-0707 April 2010 Entergy'S Opposition to Town of Plymouth'S Motion to Reschedule Telephone Conference ML1004808082010-02-0202 February 2010 Pilgrim Watch'S Reply to NRC Staff'S Response to Pilgrim Watch Notice to Commission Regarding New & Significant Information Pertaining to Pilgrim Watch'S Petition for Review of LBP-06-848 ML0823700122008-08-19019 August 2008 Pilgrim - Notice of Withdrawal of Appearance for James E. Adler ML0816402452008-05-15015 May 2008 2008/05/15-Supplemental Petition by Listed Companies for Additional Investigation and Correction of Deficiencies Regarding License Renewal Reviews, for Oyster Creek, Indian Point, Pilgrim, and Vermont Yankee Nuclear Power Plants ML0814906102008-05-15015 May 2008 2008/05/15-Supplemental Petition by Collective Petitioners for Additional Investigation and Correction of Deficiencies Regarding License Renewal Reviews for Oyster Creek, Indian Point, Pilgrim, and Vermont Yankee Nuclear Power Plants ML0814306512008-05-15015 May 2008 Supplemental Petition by Nuclear Information and Resource Service: Jersey Shore Nuclear Watch, Inc.: Grandmothers, Mothers and More for Energy Safety: New Jersey Public Interest Research Group: New Jersey Sierra Club: New Jersey.. ML0808600962008-03-17017 March 2008 Pilgrim Watch Reply to NRC Staff'S Motion in Limine to Strike Exhibits and Testimony Filed by Pilgrim Watch, March 10, 2008 ML0808600952008-03-17017 March 2008 Pilgrim Watch Reply to Entergy'S Motion in Limine to Strike Exhibits and Testimony Filed by Pilgrim Watch, March 10, 2008 ML0807402022008-03-0707 March 2008 Entergy'S Eleventh Supplemental Disclosure ML0802904142008-01-18018 January 2008 2008/01/18-Answer of Entergy Nuclear Operation, Inc. Opposing Petition to Suspend License Renewal Reviews and Proceedings ML0802803052008-01-18018 January 2008 2008/01/18-NRC Staff Answer to Petition for Suspension of License Renewal Reviews Pending Investigation of NRC Staff License Renewal Process ML0735403732007-12-14014 December 2007 Entergy'S Eighth Supplemental Disclosure ML0726901592007-09-20020 September 2007 Entergy Nuclear Operations Inc. Answer Opposing Intervention Petition of Local 369, Utility Workers Union of America, AFL-CIO ML0726205402007-09-18018 September 2007 Motion to Intervene of Local 369, Utility Workers Union of America, AFL-CIO ML0721901912007-07-30030 July 2007 Pilgrim Watch'S Answer Opposing NRC Staff'S Motion Requesting That Pilgrim Watch'S Answer Opposing NRC Staff Support of Entergy'S Motion to Strike Pilgrim Watch'S Answer to Entergy'S Summary Disposition Motion Not Be Considered by the Board ML0721302252007-07-26026 July 2007 Pilgrim - Pilgrim Watch'S Answer Opposing NRC Staff'S Support of Entergy'S Motion to Strike Portions of Pilgrim Watch'S Answer Opposing Entergy'S Motion for Summary Disposition of Contention 3 ML0720501452007-07-17017 July 2007 Pilgrim - Pilgrim Watch'S Answer Opposing Entergy'S Motion to Strike Portions of Pilgrim Watch'S Answer Opposing Entergy'S Motion for Summary Disposition of Pilgrim Watch Contention 3 ML0718405682007-06-29029 June 2007 Pilgrim - Pilgrim Watch'S Answer Opposing Entergy'S Motion for Summary Disposition of Pilgrim Watch Contention 3 ML0718000592007-06-28028 June 2007 Pilgrim - NRC Staff Response to Entergy'S Motion for Summary Disposition of Pilgrim Watch Contention 1 ML0716303952007-06-0505 June 2007 Pilgrim - Entergy'S Sixth Supplemental Disclosure ML0715002992007-05-24024 May 2007 Pilgrim - Entergy'S Opposition to Pilgrim Watch Request to Extend Time to Respond to Summary Disposition of Pilgrim Watch Contention 3 ML0715201682007-05-22022 May 2007 Pilgrim - Notice of Appearance of Mary Elizabeth Lampert ML0711702672007-04-18018 April 2007 Pilgrim - Second Disclosure Statement by Pilgrim Watch ML0711702602007-04-16016 April 2007 Pilgrim - Entergy'S Fourth Supplemental Disclosure ML0708002172007-03-15015 March 2007 Pilgrim - Entergy'S Third Supplemental Disclosure ML0707301912007-03-0606 March 2007 Pilgrim - Letter to Judge Cole from S. Uttal, OGC Providing (Cd) Version of Safety Evaluation Report with Open Items ML0634803752006-12-0808 December 2006 Pilgrim- Entergy'S Comments on Proposed Schedule 2011-06-27
[Table view] |
Text
May 24, 2007 DOCKETED USNRC UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION May 24, 2007 (4:12pm)
OFFICE OF SECRETARY Before the Atomic Safety and Licensing Board Panel RULEMAKINGS AND ADJUDICATIONS STAFF In the Matter of )
)
Entergy Nuclear Generation Company and ) Docket No. 50-293-LR Entergy Nuclear Operations, Inc. ) ASLBP No. 06-848-02-LR
)
(Pilgrim Nuclear Power Station) )
ENTERGY'S OPPOSITION TO PILGRIM WATCH REQUEST TO EXTEND TIME TO RESPOND TO
SUMMARY
DISPOSITION OF PILGRIM WATCH CONTENTION 3 Applicants Entergy Nuclear Generation Company and Entergy Nuclear Operations, Inc.
(collectively "Entergy") hereby file their opposition to the May 22, 2007 "Request by Pilgrim Watch for Extension of Time to Reply to Entergy's Motion for Summary Disposition" of Pilgrim Watch Contention 3. Pilgrim Watch has not justified its request to essentially double the response time, and provides no explanation why, eight months after the admission of this contention, it is unprepared to respond to Entergy's motion. Further, Pilgrim Watch did not consult with counsel for Entergy prior to filing its request for an extension of time, as required by 10 C.F.R. §2.323(b). Therefore, Pilgrim Watch's motion should be denied.
The Commission has made clear that a license applicant is "entitled to a prompt resolution of disputes" concerning its application and that extension of times are to be granted "only when warranted by unavoidable and extreme circumstances." Statement of Policy on Conduct of Adjudicatory Proceedings, CLI-98-12, 48 NRC 18, 19, 21 (1998). The Commission has cautioned parties to heed this guidance, Hydro Resources, Inc., 49 NRC 1, 5 n.2 (1999), and
-T-r= E-.7 '8 .3 -?
both the Commission and the licensing boards have applied this standard in denying motions for extensions of time. See, e.g., Combustion Engineering (Windsor Site), 2002 WL 1009297, at
- 1 (NRC May 10, 2002) (denying motion for extension of time arguing that intervenor is "a state agency with limited resources"); Entergy Nuclear Vermont Yankee LLC (Vermont Yankee Nuclear Power Station), 2006 NRC LEXIS 72, at *9 (NRC ASLB March 24, 2006) (denying motion for extension of time arguing that intervenor inadvertently wrote the wrong deadline in a calendar); Florida Power and Light Company (Turkey Point, Units 3 and 4), 2000 WL 1911658, at *3-*4 (NRC ASLB Dec. 15, 2000) (denying motion for extension of time arguing that intervenor has work and family commitments); Carolina Power & Light Company (Shearon Harris Nuclear Power Plant), 2000 NRC LEXIS 112, at *4-*5 (NRC ASLB Oct. 19, 2000)
(denying motion for extension of time arguing that intervenor's access to agency documents was delayed and that applicant did not promptly provide documents to intervenor). The Licensing Board should apply this well established precedent here and reject Pilgrim Watch's request for an extension of time to respond to Entergy's motion for summary disposition of Pilgrim Watch Contention 3.
Entergy filed its motion for summary disposition on May 17, 2007 and under applicable Commission regulations, 10 C.F.R. § 2.1205(b), responses are due within 20 days or by June 6, 2007. Furthermore, by electronic mail of May 8, 2007 - nine days prior to filing the motion -
counsel for Entergy advised then counsel for Pilgrim Watch, Ms. Bartlett, of Entergy's intent to request summary disposition on Pilgrim Watch Contention 3. At the same time, counsel for Entergy provided Ms. Bartlett by electronic mail acopy of the expert report, "Radiological Dispersion and Consequence Analysis Supporting Pilgrim Nuclear Power Station Severe Accident Mitigation Alternative Analysis, Revision 0 (May 2007)" which serves as the primary
basis for Entergy's summary disposition motion.' Thus, Pilgrim Watch has known for two weeks of Entergy's intention to move for summary disposition on Pilgrim Watch Contention 3 and has known of Entergy's bases for the motion. Also, as required by 10 C.F.R. §2.323(b),
counsel for Entergy and Ms. Bartlett subsequently communicated about the potential motion. No mention was made as part of these communications of her potential unavailability as counsel to Pilgrim Watch to respond to the motion.
As stated in the Commission's 1998 policy statement, an applicant is entitled to expeditious action and extension of times are to be granted only in unavoidable and extreme circumstances. Pilgrim Watch is seeking more than a three week extension of time to respond the motion - more than twice that allowed by Commission regulation not taking into account the Entergy's pre-notification of it intent and technical basis for the motion. The request for extension of time does not elucidate any extreme and compelling circumstances of why withdrawal of counsel necessitates this additional time to prepare what should essentially be a factual response based on Pilgrim Watch's preparation of its case as intended under the NRC's rules of practice.
Indeed, Pilgrim Watch states that its Director, Mary Lampert, will now be representing Pilgrim Watch pro se going forward. Thus, Pilgrim Watch's request does not involve any need to obtain new legal representation. Further, Ms. Lampert has been involved in this proceeding from its inception, so Pilgrim Watch's request does not involve bringing in a new representative who is unfamiliar with the case. Further, the fact that Ms. Lampert is now representing Pilgrim Entergy filed Revision 1 of the report in support of its summary disposition motion, but as noted in the motion (at page 2 n. 2) Revision 1 only made corrections and incorporated some minimal changes to Revision 0 of the Report that had been previously provided to NRC Staff and Pilgrim Watch as part of Entergy's Fifth Supplemental Disclosure.
3
Watch pro se provides no basis for an extension. See e.g., Entergy Nuclear, 2006 NRC LEXIS at *9 (holding a pro se party to the. same "unavoidable and extreme circumstances" standard as represented parties). The only conclusion to be drawn is that Pilgrim Watch is seeking additional time because it had no basis for its original contention and has not made any subsequent effort to prepare a case. Such dalliance is not permitted under Commission rule or policy which places obligations upon the parties to proceed expeditiously in the resolution of contested issues.
Accordingly, Pilgrim Watch's request to more than double its time to respond to Entergy's motion for summary disposition of Pilgrim Watch 3 should be denied.
Respectfully Submitted, David R. Lewis Paul.A. Gaukler PILLSBURY WINTHROP SHAW PITTMAN LLP 2300 N Street, N.W.
Washington, DC 20037-1128 Tel. (202) 663-8000 Counsel for Entergy Dated: May 24, 2007 4
May 24, 2007 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION Before the Atomic Safety and Licensing Board In the Matter of )
)
Entergy Nuclear Generation Company and ) Docket No. 50-293-LR Entergy Nuclear Operations, Inc. ) ASLBP No. 06-848-02-LR
~)
(Pilgrim Nuclear Power Station) )
CERTIFICATE OF SERVICE I hereby certify that copies of"Entergy's Opposition to Pilgrim Watch Request to Extend Time to Respond to Summary Disposition of Pilgrim Watch Contention 3" dated May 24, 2007, were served on the persons listed below by deposit in the U.S. Mail, first class, postage prepaid, and where indicated by an asterisk by electronic mail, this 24th day of May, 2007.
- Administrative Judge *Administrative Judge Ann Marshall Young, Esq., Chair Dr. Richard F. Cole Atomic Safety and Licensing Board Atomic Safety and Licensing Board Mail Stop T-3 F23 Mail Stop T-3 F23 U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Washington, D.C. 20555-0001 amy(anrc. gov rfc 1 inrc. gov
- Administrative Judge *Secretary Paul B. Abramson Att'n: Rulemakings and Adjudications Staff Atomic Safety and Licensing Board Mail Stop 0-16 C1 Mail Stop T-3 F23 U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Washington, D.C. 20555-0001 secy@nrc.gov, hearingdocket(ýnrc.gov pba(anrc.gov I
Office of Commission Appellate Atomic Safety and Licensing Board Adjudication Mail Stop T-3 F23 Mail Stop 0-16 C I U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Washington, D.C. 20555-0001
- Susan L. Uttal, Esq. *Mr. Mark D. Sylvia
- Marian L. Zobler, Esq. Town Manager Office of the General Counsel Town of Plymouth Mail Stop 0- 15 D21 11 Lincoln St.
U.S. Nuclear Regulatory Commission Plymouth MA, 02360 Washington, D.C. 20555-0001 msvlvia(&townhall.plvrnouth.ma.us slu@nrc.gov; mlz@n(rc.gov
- Ms. Mary Lampert *Richard R. MacDonald 148 Washington Street Town Manager Duxbury, MA 02332 878 Tremont Street lampert(cadelphia.net Duxbury, MA 02332 mnacdonald(dtown.duxbury.ma.us
- Sheila Slocum Hollis, Esq. *Chief Kevin M. Nord Duane Morris LLP Fire Chief and Director, Duxbury Emergency 1667 K Street, N.W. Management Agency Suite 700 688 Tremont Street Washington, D.C. 20006 P.O. Box 2824 sshollis(aduanemorris.com Duxbury, MA 02331 nord@a~town.duxbury.ma.us Paul A. Gaukler 2