Encl 2: BF1 Restart Master Tracking Forecast Schedule
ML063000007
Person / Time
Site: Browns Ferry Tennessee Valley Authority icon.png
Issue date: 10/20/2006
From:
Division of Reactor Safety II
To:
Shared Package
ML063000003 List:
References
Download: ML063000007 (2)


Text

BF1 RESTART MASTER TRACKING FORECAST SCHEDULE Days between TVA declares Readiness SPOC Complete = T0 0 day for Restart and Restart Date NRC SPOC Insp. Ends 14 days = 40 days TVA-Readiness for 21 days Operational Readiness Assmt Team 28 days 42 days Panel briefed on ORAT 43 days Panel recommends Restart 47 days RA/NRR recommend Restart 48 days Commission SECY- 50days RA authorizes Restart w/NRR 54 days Implement Communication Plan 59 days Startup Monitoring 60 days Mode Change to Mode 2 61 days Control Room 61 days 64 days Breaker Closure 81 days Power Ascension 81 days 95 days Full Power 95 days 0 25 50 75 100 DAYS LEGEND Region II TVA Oversight Panel NRR Revised 10/04/06 ENCLOSURE 2