ML062510453

From kanterella
Jump to navigation Jump to search
NRC Inspection Report Nos. 05000317-06-012 and 05000318-06-012; Preliminary White Finding
ML062510453
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 09/08/2006
From: Christopher Cahill, Cheung L, Marlone Davis, Jack Giessner
Division Reactor Projects I, Division of Reactor Safety I
To:
References
IR-06-012
Download: ML062510453 (19)


See also: IR 05000317/2006012

Text

September 8, 2006

EA-06-198

Mr. James A. Spina, Vice President

Calvert Cliffs Nuclear Power Plant, Inc.

Constellation Generation Group, LLC

1650 Calvert Cliffs Parkway

Lusby, Maryland 20657-4702

SUBJECT:

CALVERT CLIFFS NUCLEAR POWER PLANT - NRC INSPECTION REPORT

NOS. 05000317/2006012 AND 05000318/2006012; PRELIMINARY WHITE

FINDING

Dear Mr. Spina:

On August 16, 2006, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection

at your Calvert Cliffs Nuclear Power Plant. The results of this inspection were discussed on

August 16, 2006, with you and other members of your staff.

The inspection examined activities conducted under your license as they relate to safety and

compliance with the Commissions rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and records, observed activities and interviewed

personnel. Specifically, this inspection focused on the 1A Emergency Diesel Generator (EDG)

at Calvert Cliffs Unit 1 and the activities performed by your staff in response to the unexpected

trip of an associated circuit breaker during a spring 2006 refueling outage surveillance test.

This report documents one finding related to the 1A EDG that appears to have low to

moderate safety significance. As described in Section 2 of this report, a circuit breaker which

normally supplies the EDG's support systems was found to have an incorrect trip setpoint. The

low over-current trip setpoint would have impacted the capability of the 1A EDG to perform its

intended safety function during certain design basis events. The self-revealing finding involved

inadequate design control during the establishment of the breaker's over-current trip setpoint.

While this issue did present a potential safety concern, the plant was shutdown at the time of

discovery and the requirements for onsite power systems were met. Actions were taken to

establish the proper circuit breaker settings prior to the end of the refueling outage and no

current safety concern exists.

This finding was assessed using the reactor safety Significance Determination Process (SDP)

and was preliminarily determined to be White for Unit 1 (i.e., a finding with some increased

importance to safety, which may require additional NRC inspection). The finding appears to

have low to moderate safety significance because the 1A EDG would not have been capable

of performing its intended safety function under all conditions for which it was designed.

This finding is an apparent violation of NRC requirements specified in 10 CFR 50, Appendix B,

Criterion III, "Design Control," and is being considered for escalated enforcement action in

accordance with the NRC Enforcement Policy. The current policy is included on the NRC's

website at http://www.nrc.gov; select What We Do, Enforcement, then Enforcement Policy.

We believe that we have sufficient information to make our final risk determination for the

performance issue involving the incorrect circuit breaker trip setpoints. However, before the

NRC makes a final decision on this matter, we are providing you an opportunity to: (1) present

to the NRC your perspective on the facts and assumptions used by the NRC to arrive at the

finding and its significance at a Regulatory Conference, or (2) submit your position on the

finding to the NRC in writing. If you request a Regulatory Conference, it should be held within

30 days of receipt of this letter and we encourage you to submit supporting documentation at

least one week prior to the conference in an effort to make the conference more efficient and

effective. If a Regulatory Conference is held, it will be open for public observation and a press

release will be issued to announce it. If you decide to provide a written response in lieu of the

Regulatory Conference, the submission should be sent to the NRC within 30 days of the receipt

of this letter.

Please contact Mr. Brian McDermott at (610) 337-5233 within 10 business days of the date of

this letter to notify the NRC of your intentions. If we have not heard from you within 10 days, we

will continue with our significance determination and enforcement decision, and you will be

advised by separate correspondence of the results of our deliberations on this matter. Since

the NRC has not made a final determination in this matter, no Notice of Violation is being issued

for the inspection finding at this time. In addition, please be advised that the characterization of

the apparent violation described in this letter may change as a result of further NRC review.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter

and its enclosure will be available electronically for public inspection in the NRC Public

Document Room or from the Publicly Available Records (PARS) component of NRC's document

system (ADAMS). ADAMS is accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Brian E. Holian, Director

Division of Reactor Projects

Docket No. 50-317, 50-318

License No. DPR-53, DRP-69

Enclosure:

Inspection Report 05000317/2006012 and 05000318/2006012

w/Attachments: A) Supplemental Information, B) Motor Control Center Loads

cc w/encl:

M. J. Wallace, President, Constellation Generation

J. M. Heffley, Senior Vice President and Chief Nuclear Officer

President, Calvert County Board of Commissioners

C. W. Fleming, Senior Counsel, Constellation Generation Group, LLC

Director, Nuclear Regulatory Matters

R. McLean, Manager, Nuclear Programs

K. Burger, Esquire, Maryland People's Counsel

State of Maryland (2)

Criterion III, "Design Control," and is being considered for escalated enforcement action in accordance with the NRC Enforcement

Policy. The current policy is included on the NRC's website at http://www.nrc.gov; select What We Do, Enforcement, then

Enforcement Policy.

We believe that we have sufficient information to make our final risk determination for the performance issue involving the incorrect

circuit breaker trip setpoints. However, before the NRC makes a final decision on this matter, we are providing you an opportunity

to: (1) present to the NRC your perspective on the facts and assumptions used by the NRC to arrive at the finding and its

significance at a Regulatory Conference, or (2) submit your position on the finding to the NRC in writing. If you request a Regulatory

Conference, it should be held within 30 days of receipt of this letter and we encourage you to submit supporting documentation at

least one week prior to the conference in an effort to make the conference more efficient and effective. If a Regulatory Conference

is held, it will be open for public observation and a press release will be issued to announce it. If you decide to provide a written

response in lieu of the Regulatory Conference, the submission should be sent to the NRC within 30 days of the receipt of this letter.

Please contact Mr. Brian McDermott at (610) 337-5233 within 10 business days of the date of this letter to notify the NRC of your

intentions. If we have not heard from you within 10 days, we will continue with our significance determination and enforcement

decision, and you will be advised by separate correspondence of the results of our deliberations on this matter. Since the NRC has

not made a final determination in this matter, no Notice of Violation is being issued for the inspection finding at this time. In addition,

please be advised that the characterization of the apparent violation described in this letter may change as a result of further NRC

review.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available

electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of

NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

Brian E. Holian, Director

Division of Reactor Projects

Docket No. 50-317, 50-318

License No. DPR-53, DRP-69

Enclosure:

Inspection Report 05000317/2006012 and 05000318/2006012

w/Attachments: A) Supplemental Information, B) Motor Control Center Loads

Distribution w/encl: (via E-mail)

S. Collins, RA

B. Holian, DRP

M. Dapas, DRA

B. Sosa, RI OEDO

R. Laufer, NRR

P. Milano, PM, NRR

R. Guzman, PM, NRR (Backup)

B. McDermott, DRP

A. Burritt, DRP

J. Giessner, DRP, Senior Resident Inspector (acting)

M. Davis, DRS

C. Cahill, DRS

D. Holody, ORA

L. Cheng, DRS

C. Newgent - Resident OA

Region I Docket Room (with concurrences)

ROPReports@nrc.gov

SUNSI Review Complete: ALB (Reviewers Initials)

DOCUMENT NAME:C:\\MyFiles\\Copies\\CC IR2006-012.wpd

After declaring this document An Official Agency Record it will/will not be released to the Public.

To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with

attachment/enclosure "N" = No copy

OFFICE RI/DRP

RI/DRP

RI/DRS

RI/ORA

RI/DRP

NAME

JGiessner/ALB

FOR

BMcDermott

CCahill

DHolody/RJS

FOR

BHolian

DATE

09/6/06

09/6/06

09/7/06

09/8/06

09/8/06

OFFICIAL RECORD COPY

Enclosure

U.S. NUCLEAR REGULATORY COMMISSION

REGION I

Docket Nos.

50-317, 50-318

License Nos.

DPR-53, DPR-69

Report Nos.

05000317/2006012 and 05000318/2006012

Licensee:

Constellation Generation Group, LLC

Facility:

Calvert Cliffs Nuclear Power Plant, Units 1 and 2

Location:

Lusby, MD

Dates:

July 10, 2006 through August 16, 2006

Inspectors:

John B. Giessner, Senior Resident Inspector (acting, DRP)

Christopher G. Cahill, Senior Reactor Analyst (DRS)

Leonard S. Chueng, Senior Inspector (DRS)

Marlone Davis, Resident Inspector (DRP)

Approved by:

Brian J. McDermott, Chief

Projects Branch 1

Division of Reactor Projects

Enclosure

ii

TABLE OF CONTENTS

SUMMARY OF FINDINGS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . iii

REPORT DETAILS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1

1.0

Description of Events . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1

2.0

Equipment Failures and Causes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2

4OA6 Meetings, Including Exits . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6

ATTACHMENTS: SUPPLEMENTAL INFORMATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6

SUPPLEMENTAL INFORMATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-1

KEY POINTS OF CONTACT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-1

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED . . . . . . . . . . . . . . . . . . . . . . . . . . . A-1

LIST OF DOCUMENTS REVIEWED . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-2

LIST OF ACRONYMS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-3

Enclosure

iii

SUMMARY OF FINDINGS

IR 05000317/2006012 and 05000318/2006012; 07/10/2006 - 08/16/2006; Calvert Cliffs Nuclear

Power Plant, Unit 1; Event Followup.

The report documents an event follow-up inspection focused on the 1A Emergency Diesel

Generator (EDG) at Calvert Cliffs Unit 1 and the followup activities performed by your staff in

response to the trip of an associated circuit breaker during a spring 2006 refueling outage

surveillance test. The inspection was conducted by regional and resident inspectors. One

apparent violation (AV) with potential low to moderate safety significance was identified

(Preliminary White). The significance of most findings is indicated by their color (Green, White,

Yellow, Red) using Inspection Manual Chapter (IMC) 0609, Significance Determination

Process (SDP). Findings for which the SDP does not apply may be Green or be assigned a

severity level after NRC management review. The NRC's program for overseeing the safe

operation of commercial nuclear power reactors is described in NUREG-1649, Reactor

Oversight Process, Revision 3, dated July 2000.

NRC-Identified and Self-Revealing Findings

Cornerstone: Mitigating Systems

Preliminary White: An apparent violation of 10 CFR 50, Appendix B, Criterion III

(Design Control) was identified involving the failure to ensure an adequate trip setpoint

for the electrical circuit breaker that supplies the 1A EDG support systems. An SDP

Phase 3 risk analysis determined that the failure to account for possible combinations of

1A EDG support equipment operation in the short-time over-current trip setpoint for the

supply breaker to 1MCC123 was preliminarily of low to moderate safety significance.

Specifically, the short-time over-current trip setpoint was set too low and it did not

account for the in-rush current associated with the possible combinations of equipment

that could start and operate to support the 1A EDG following a loss of offsite power

(LOOP). This low setpoint, combined with normal setpoint drift, resulted in substantial

periods where the 1A EDG would not have been able to perform its safety function,

because the support system supply circuit breaker would have tripped open

inappropriately. Calvert Cliffs took immediate action to correct the breaker setpoint and

evaluate other potential deficiencies of a similar nature. This issue was entered into the

corrective action program at Calvert Cliffs for resolution.

The finding was more than minor because it affected the Mitigating Systems

Cornerstone objective to ensure the availability and reliability of systems

(i.e., emergency AC power) that respond to initiating events to prevent undesirable

consequences, and its related attribute for design control. The "0C" Station Blackout

Diesel Generator (a non-safety related, but risk-important power source) and the breaker

for its support systems were similarly affected by the performance deficiency. SDP

Phase 1, Phase 2, and Phase 3 assessments were used to evaluate the risk

significance of this finding. The Phase 1 screening required performance of a Phase 2

evaluation because the finding represented a loss of safety function of a single train, for

greater than its allowed outage time. The Technical Specification (TS) allowed outage

time is 14 days for a single EDG. To assess the full significance both the Phase 2 and

Phase 3 analyzes assumed a 5407 hour exposure for the 1A EDG being unable to

Enclosure

iv

perform its safety function and an additional 6.7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br /> where both the 1A EDG and the

0C DG would not have been able to perform their required functions (the 0C EDG

had less instrument drift). The Region I senior reactor analyst (SRA) conducted a Phase

3 Risk Assessment, to refine the Phase 2 analysis and to incorporate external events

and recovery credit. The Phase 3 analysis for internal and external initiating events,

using the above assumptions and licensee risk information, determined a )CDF of

approximately 1 in 150,000 years of operation (mid E-6 per year range) for both internal

and external events, with no associated increase in large early release frequency

(LERF). The risk of the 1A EDG exposure time dominated the analysis by several

orders of magnitude over the risk of the concurrent 1A EDG and 0C DG exposure

time. A large fire in the turbine building, which causes a loss of offsite power, was the

dominating initiating event.

Enclosure

REPORT DETAILS

1.0

Description of Events

On March 24, 2006, Operations personnel secured the 1A Emergency Diesel

Generator (1A EDG) at Calvert Cliffs Unit 1 during a refueling outage surveillance test,

based on the unexpected trip of an associated circuit breaker. Surveillance test

procedure (STP) O-004A-1, Unit 1 A-Train ESF Test, simulates a loss of the 4 kV

safety bus and initiates a fast start of the EDG. During the performance of the STP,

plant operators initially observed that the 1A EDG started and picked up the 4 kV bus

loads as expected. However, Operations subsequently noted that the 480 V feeder

breaker for Motor Control Center (MCC) 123 was tripped. This MCC supplies essential

EDG support systems such as radiator cooling fans, room ventilation cooling fans, and

other loads. Approximately twenty minutes after the EDG start, Operations aborted the

STP and secured the 1A EDG to prevent the engine from overheating due to the loss

of the cooling fans and room ventilation.

During the evaluation of this event, Calvert Cliffs determined that the 480 V feeder

breaker for MCC 123 tripped when the MCC was initially energized during loading of the

EDG. The feeder breaker tripped because the MCC 123 loads that immediately

energized exceeded the breaker's short-time over-current trip setpoint. The licensee

subsequently determined that the over-current trip setpoint was set too low due to a

design error that occurred when the EDG was installed in 1996.

Background

The safety related 1A EDG and the non-safety related 0C Station Blackout Diesel

Generator at Calvert Cliffs are French designed five megawatt dual diesel generators

(i.e., one diesel at each end with the generator in the middle). Each EDG is housed in

its own building, with a 125 V battery room and battery chargers. The 1A EDG is

cooled by six radiator fans and the building is cooled by a series of four ventilation fans.

The room ventilation fans start based on the diesel generator room temperature. One

building ventilation fan starts when the EDG starts, the other three fans start sequentially

based on the diesel generator room temperature. The ventilation system also includes

various heaters for temperature control during the winter months.

The 0C EDG (station blackout diesel) is a non-safety related, manual-start EDG that is

capable of being aligned to any one of the safety-related 4kV busses for either Unit 1 or

Unit 2 at Calvert Cliffs. The 0C EDG has a heating, ventilating and conditioning

(HVAC) design similar to the 1A EDG. The 0C EDG is important to plant risk and its

support system supply breaker setting was impacted, similar to the 1A EDG. As part of

the corrective actions for the issue discussed in this report, the licensee determined that

the Amptector setting for 0C EDG MCC supply breaker was also set too low. The

NRC's significance determination for the finding discussed in this report takes into

consideration the impact of the incorrect breaker settings for the 1A EDG and 0C

EDG.

2

Enclosure

2.0

Equipment Failures and Causes

Incorrect Setting of 1MCC123 Supply Breaker Over-current Trip Device

a.

Inspection Scope

The inspectors, as part of event follow-up, reviewed the events surrounding the breaker

trip and the existing design of the 1A EDG breakers and trip scheme. This review

included the related Updated Final Safety Analysis Report (UFSAR) sections and TSs,

diagrams, various design electrical analyses, discussion with site personnel, summaries

of testing results and various condition reports (CRs) related to the issue. The

inspectors reviewed the design modification which installed the 1A EDG and the testing

performed. In addition, the team reviewed the calculations and evaluations done to

assess the impact (probabilistic risk assessment) and past operability related to the

breaker tripping. This included a review of calculations, cause analysis, operator actions

and the overall thoroughness of the extent of condition. The extent of condition review

included the 0C EDG, the diesel generator with similar design. The inspectors also

reviewed Constellations immediate corrective action to address the issue, which

included the changes to the over-current setting to verify they were adequately set to

prevent inadvertent tripping, and to verify adequate breaker and bus protection. The

inspection included a review of CRs to ensure the scope of the licencees review was

adequate.

b.

Findings

Introduction: An apparent violation of 10 CFR 50, Appendix B, Criterion III (Design

Control) involving the licensee's failure to ensure an adequate trip setpoint for the

electrical circuit breaker that supplies the 1A EDG support systems was identified. A

SDP Phase 3 risk analysis determined that the failure to account for possible

combinations of 1A EDG support equipment operation in the short-time over-current

trip setpoint for the supply breaker to 1MCC123 was preliminarily of low to moderate

safety significance.

The inspectors verified that the condition of the short-time over-current trip setpoint

would not have been identifiable during normal monthly EDG surveillance testing.

When the 1A EDG is started for surveillance testing one room cooling fan and other

loads are already normally running and the other fans would start based on room

temperature alone (they would not simultaneously start as they do following a

loss-of-offsite power).

Description: The 1A EDG was manually secured during testing when it was

determined that the circuit breaker that feeds 1MCC123 had tripped. Since the EDG

would not be able to perform its design functions with its support loads de-energized, the

licensee promptly declared the EDG inoperable and started an investigation. The cause

for the loss of 1MCC123 was due to the feeder breaker short-time over-current

exceeding its trip setpoint, resulting in a trip of the feeder breaker. Attachment B of this

report has a detailed description of the MCC loads and their design ratings.

The original short-time over-current of the Amptector (trip device) for the supply breaker

was set at 2400 amps. The setpoint was based on providing coordination with the

3

Enclosure

upstream breaker; and the starting of the single largest motor, and the MCC supplying

all other loads, as documented in Calculation D-E-94-001, dated August 26,1994. The

combined current from the assumed loading was increased by a factor of two to account

for the direct-current (DC) off-set current and the large uncertainty of the breaker tripping

setpoint (i.e., including calibration tolerance, setpoint drift and the inherent inaccuracy of

the Amptector). However, the setpoint did not account for all the loads that can

simultaneously start after an undervoltage event. The setpoint was inadequate because

once the 1A EDG started and 1MCC123 energized, more than one motor can start

instantly. At the design room temperature of 105°F, all four room ventilation fans would

start simultaneously. Fifteen motors and other breaker loads could start simultaneously,

resulting in a combined in-rush current of more than 2600 amps. In addition, with the

tripping setpoint uncertainty, setpoint drift of up to 10%, and DC off-set current, the in-

rush current could be much higher than the original setpoint. During an extent of

condition review, Constellation determined that the 0C EDG also had an inadequate

short-time over-current setpoint for its equivalent breaker and that the breaker would trip

open prematurely under certain conditions.

The inspectors determined that Calvert Cliffs did not verify and check the adequacy of

the short-time over-current setting of 1MCC123 Amptector for the simultaneous starting

of all loads that would be expected under design basis conditions. Instead,

Constellation used a design standard which only included the largest single load starting

with other loads already running. This standard was not appropriate for the 1MCC 123

supply breaker setting. This issue was most likely not identified in previous surveillance

tests because the setpoint had not drifted as low and because the testing was

conducted during the months when the normal ambient temperature was too low to

require additional ventilation fans to start.

The licensee, prior to plant startup on Unit 1, reset the 1MCC123 breaker trip to 3600

amps to address the issue. The Amptector setpoints are calibrated once every two

years. The calibration procedure allowed the technicians a +/- 2% as-left setpoint

tolerance and the allowable as-found setpoint deviation can be +/- 10%. The inspectors

have reviewed the new short-time over-current setting and have found it acceptable.

The licensee also corrected the setpoint of the equivalent breaker which supplies the

support systems for the 0C EDG.

Analysis: The performance deficiency involved the failure to provide adequate design

control, as required by 10 CFR 50 Appendix B, Criteria III, for the 1A EDG support

system supply circuit breaker short-time over-current trip setpoint. The setpoint was too

low, it did not account for the in-rush current associated with the possible combinations

of equipment that could start and operate to support the 1A EDG following a LOOP.

This low setpoint and normal setpoint drift resulted in substantial periods where the 1A

EDG would not have been able to perform its safety function, because the support

system supply circuit breaker would have tripped open inappropriately.

The inspectors determined, by reviewing licensee data concerning setpoint drift and

outside air temperatures that the 1A EDG would not have been able to perform its

safety function for an exposure period of approximately 5407 hours0.0626 days <br />1.502 hours <br />0.00894 weeks <br />0.00206 months <br /> over the last year of

reactor operation. The setpoint drift contributed approximately 5046 hours0.0584 days <br />1.402 hours <br />0.00834 weeks <br />0.00192 months <br /> when outside

air temperature was below 85 °F (one room cooling fan start) and the low setpoint

contributed approximately 361 hours0.00418 days <br />0.1 hours <br />5.968915e-4 weeks <br />1.373605e-4 months <br /> when outside air temperature was at or above 85

4

Enclosure

°F(more than one room cooling fan start). The finding was more than minor because it is

associated with the Mitigating Systems Cornerstone attribute of design control and

affected the cornerstone objective to ensure the availability and reliability of systems

(i.e., emergency AC power) that respond to initiating events to prevent undesirable

consequences.

The 0C EDG (station blackout diesel) support system supply circuit breaker short-time

over-current trip was similarly affected by this performance deficiency, however, the

as-found setting was not as low as that found on the 1A EDG. The inspectors verified

licensee data that indicated that the 0C EDG would not have been able to perform its

required function when outside air temperature was at or above 95 °F (more than two

room cooling fans start). It was estimated that this exposure period was 6.7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br />.

To assess the full significance of the performance deficiency, both Phase 2 and Phase 3

analyses were based on the 5400 hour0.0625 days <br />1.5 hours <br />0.00893 weeks <br />0.00205 months <br /> exposure for the 1A EDG being unable to

perform its safety function and additional 6.7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br /> where both the 1A EDG and the

0C EDG would not have been able to perform their required functions.

The finding was evaluated in accordance with IMC 0609, Appendix A, "Significance

Determination of Reactor Inspection Findings for At-Power Situations," using Phase 1,

Phase 2, and Phase 3 SDP analyses. The Phase 1 screening required performance of

a Phase 2 evaluation because the finding represented a loss of safety function of a

single train, for greater than its allowed outage time. The TS allowed outage time is 14

days for a single EDG. A Licensee Event Report (LER) was written on this issue.

The internal events Phase 2 analysis, conducted using the Risk-informed Inspection

Notebook for Calvert Cliffs Nuclear Power Plant Units 1 and 2, revision 2, dated

September 30, 2005 and with IMC 0609, Appendix H, Containment Integrity SDP,

determined that the finding could have substantial safety significance based on )CDF

with no associated change in LERF.

The Region I SRA conducted a Phase 3 Risk Assessment, to refine the Phase 2

analysis and to incorporate external events and recovery credit. The analysis used an

updated Calvert Cliffs SPAR model, Rev 3 plus, dated October 28, 2005. Since the

finding only affected the 1A EDG and the 0C DG, the emergency power system

common cause factors were adjusted to more accurately reflect the physical differences

between the site EDGs. Additionally, the shutdown risk was evaluated and considered

to be small compared to the operational risk.

The final assessment results indicate that the finding had low to moderate safety

significance and was determined to be WHITE for Unit 1 based on )CDF of

approximately 1 in 150,000 years of operation (mid E-6 per year range) for both internal

and external events, with no associated increase in LERF. The Phase 3 internal events

analysis resulted in an increase in )CDF of in the low E-6 range for the 5407-hour

exposure period. The dominant internal event core damage sequence was a station

blackout with a successful reactor shutdown along with a failure to recover the EDGs

and restore offsite power in four hours. A LOOP was the second dominant internal

event sequence with a successful reactor shutdown and the EDGs powering a safety

bus with auxiliary feedwater (AFW) and failure of once through cooling. The SRA

determined, based on information from the licensee, that the dominate external event

5

Enclosure

was a large turbine building fire which causes a LOOP and challenges AFW and failure

of once through cooling. The contribution in )CDF from external events was in the mid

E-6 range. The SRA reviewed the licensees risk assessment which included at-power

internal and external events, shutdown and LERF. Using similar assumptions to those

used in the Phase 3 analysis, the licensee estimated the )CDF to be similarly in the mid-

E-6 range. The risk of the 1A EDG exposure time dominated the analysis by several

orders of magnitude over the risk of the concurrent 1A EDG and 0C EDG exposure

period.

Old Design Issue Considerations: As defined in NRC Inspection Manual Chapter (IMC) 0305, issued date 06/22/06, an old design issue is an inspection finding involving a past

design-related problem in the engineering calculations or analysis, associated operating

procedure or installation of plant equipment that does not reflect a performance

deficiency associated with existing licensee programs, policy, or procedures. As

discussed in IMC 0305 Section 06.06.a, some old design issues may not be considered

in the assessment program.

This issue was self-revealed during the performance of a two-year surveillance test

which is associated with an existing licensee program. Section 06.06.a.1 states, in part,

that the NRC may refrain from considering safety significant inspection findings in the

assessment program for a design-related finding in engineering calculations or analysis,

associated operating procedure or installation of plant equipment that meets all four

criteria listed in IMC 0305, Section 06.06.a.1, Treatment of Old Design Issues in the

Assessment Process. The first criterion states that the finding was licensee-identified as

a result of a voluntary initiative such as a design basis reconstitution. This section

further states that for the purpose of this manual chapter, self-revealing issues are not

considered to be licensee-identified. In this case, the design issue (incorrect short-time

over-current setting of 1MCC123 Amptector) was identified as the result of a

self-revealing event and the licensee had a previous opportunity to identify the issue

during the EDG installation. Therefore, this design-related finding will not be treated as

an old design issue.

Enforcement: Title 10 CFR Part 50, Appendix B, Criterion III, Design Control, requires,

in part, that design control measures shall provide for verifying or checking the adequacy

of design, such as by the performance of design reviews, by the use of alternate or

simplified calculational methods or by the performance of a suitable testing program.

Contrary to the above, in 1996, Calvert Cliffs did not verify or check the adequacy of the

short-time over-current setting of the 1MCC123 Amptector when the 1A EDG was

installed. This issue was entered into the corrective action program at Calvert Cliffs

(IRE-013-237) for resolution. Corrective actions included changes to the over-current

trip setting (AV 50-317/20060012-01, Failure to Adequately Control the Design of the

1A EDG Feeder Breaker for Essential EDG Support Systems).

6

Enclosure

4OA6 Meetings, Including Exits

Exit Meeting

On August 16, 2006, the inspectors presented the inspection results to yourself and

other members of your staff, who acknowledged the findings. The inspectors asked

Constellation whether any materials examined during the inspection should be

considered proprietary. No proprietary information was identified.

ATTACHMENTS:

SUPPLEMENTAL INFORMATION

MOTOR CONTROL CENTER LOADS

A-1

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee

J. Spina

Site Vice President

J. Pollock

Plant General Manager

P. Furio

Licencing Supervisor

J. Mills

System Engineering General Supervisor

M. Simpson

Supervisor, Electrical and Controls System Engineering

A. Julka

Director Fleet PRA

J. Stone

Principal Engineer

A. Simpson

Sr. Licensing Engineer

L. Larragoite

Director Fleet Licensing

M. Flaherty

Manager - Engineering

S. Loeper

EDG system manager

R. Stark

Design Engineer

J. Boggs

Design Engineer

A. Julka

Director, PRA

J. Wynn

System Engineer

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened

05000317/2006012-01

AV

Failure to Adequately Control the Design of the

Setpoints for 1A EDG Feeder Breaker for

Essential EDG Support Systems (Section 2)

Closed

None

Discussed

None

A-2

LIST OF DOCUMENTS REVIEWED

Procedures and Documents

STP O-004A-1, Unit 1A Train Engineered Safety Features Test, Revision 25

FTE-29, Acceptance Test and Calibration of Amptectors, Revision 8

York 507-40053, Direct Digital Control System for 0C-AHU-1 & 0C-AHU-2

Calculations and Studies

Calculation D-E-94-001, Bechtel Design Calculation for SACM Diesel Project, Revision 7

Calvert Cliffs Nuclear Power Plant Risk Evaluation for the 1A DG MCC Feeder Breaker Trip on

3/24/2006 and 7/25/2006

ES 200400160, Equivalency Evaluation for New Westector Trip Devices in Place of

Westinghouse Amptectors, Revision 0

ES 200600156, Engineering Evaluation for Breaker Short Time Over-current Settings 52-1703

(of MCC 123) and 52-0703 (MCC 023)

Condition Reports/Evaluations

IRE-013-237, 1MCC123 Feeder Breaker tripped, 3/27/2006

Action Item Tracking (AIT) IR200600072, Apparent Cause for 1MCC123 Feeder Breaker

Tripping, Revision 1

Drawings

61001SH0001, Electrical Main Single Line Diagram

61-027-E, Diesel Generator Project Single Line Diagram, Diesel Generator 1A, SH1, Rev. 2

61-085-C, Diesel Generator Project Schematic Diagram, 1A Emergency DG HVAC System

Preheat Duct Heater DH-4, Sh 106, Revision 2

62429SH0001, HVAC System P & ID, Diesel Generator Building 1, Revision 5

60-626-B, Logic Diagram, DG Building 2, Switchgear Room Air Handling Unit 0C-AHU-2,

SH004, Revision 1

60-626-B, Logic Diagram, DG Room Exhaust Fans 0C-F-1 Thru OC-F-4, Sh 48, Revision 1

61085SH0077, Schematic Diagram Diesel Generator 1A Building Supply Fan F-10, Revision 5

Work Orders (WO)

WO 0200402727, Inspect 52-0703 (MCC 023 Feed) Per FTE-077

WO 1200403460, Inspect 52-1703 (MCC 123 Feed) Per FTE-077

WO 0200002152, Inspect 52-0703 (MCC 023 Feed) Per FTE-077 and Calibrate the Amptector

per FTE 29

WO 1200601442, Replace Amptector 52-1703 and Calibrate the Amptector per FTE 29

A-3

LIST OF ACRONYMS

ADAMS

Agency Document Access and Management System

AFW

Auxiliary Feed Water

AIT

Action Item Tracking

AV

Apparent Violation

CR

Condition Report

DC

Direct Current

DS

Diesel Generator

EDG

Emergency Diesel Generator

HVAC

Heating, ventilating and air-conditioning

IMC

Inspection Manual Chapter

LER

Licensee Event Report

LERF

Large Early Release Frequency

LOOP

Loss of Offsite Power

MCC

Motor Control Center

NRC

Nuclear Regulatory Commission

PARS

Publicly Available Records System

SDP

Significance Determination Process

SRA

Senior Reactor Analyst

STP

Surveillance Test Procedure

TS

Technical Specification

UFSAR

Updated Final Safety Analysis Report

WO

Work Order

B-1

MOTOR CONTROL CENTER (MCC) LOADS

1MCC123 supplies power to all essential 480 VAC components for the operation of the

1A EDG at Calvert Cliffs Unit 1. The MCC is fed from the 4.16kV safety-related bus 11

that is powered from the 1A EDG output or the offsite power supply. A step down

transformer reduces the voltage to 480 VAC and supplies the power to 1MCC123 and

another MCC (MCC124). The loads connected to the 480 VAC 1MCC123 are as

follows:

a.

Six radiator fans (40 HP with an estimated inrush current of 247.5 amps each)

b.

Two ventilation fans (F10 &F12, 40 HP with an estimated inrush current of 283

amps each)

c.

Two fuel oil feed pump motors (P11 and P12, 5 HP with an estimated inrush

current of 12.76 amps each

d.

One battery room exhaust fan (F8, 1.5 HP with an estimated inrush current of

20.37 amps)

e.

One battery charger (estimated inrush current of 6.17 amps)

f.

One distribution panel (1P23 with estimated inrush current of 1.44 amps)

g.

Four room ventilation fans (F1, F2, F3, and F4, 20 HP with an estimated inrush

current of 148.1 amps each)

h.

One intake duct heater (DH-4, 70 KW with steady state current of 79 amps)

i.

One battery room unit heater with fan (estimated inrush current of 21 amps)

j.

Two pre-lube pumps (not expected to be running during EDG operation)

The operation of the above components is such that when the 1A EDG starts and

energizes the 4.16kV Safety Bus 17, it in turn energizes the 480 VAC 1MCC123, items

a through f and at least one fan of item g starts immediately (regardless of the diesel

room temperature). The other three fans of item g will start, sequentially, when the

room temperature exceeds 85°F, 95°F, and 105°F. If the diesel room temperature is

above 105°F when the 1MCC123 is energized then all four room fans listed in item "g"

will start simultaneously. Item i is set at 78°F to maintain the battery room at or above

the temperature setting.

Item h is controlled through two silicon controlled rectifiers (SCRs), which responds to

a thermister (a resistance temperature sensor) in the outdoor air inlet duct, and is set at

40°F. It is controlled with a control band of 10°F that is fully heated at 35°F and has no

heat at 45°F. However, the current design will always energize the heater initially (for

about 2 seconds) when power is restored to the bus. This heater design led to an overall

increase in the in-rush current the breaker will experience when power is restored to the

bus.

[NRC FORM 665S

U.S. NUCLEAR REGULATORY COMMISSION (4-2002)

Single Document

ADAMS DOCUMENT SUBMISSION

ORIGINATED BY

TELEPHONE

MAIL STOP

LAN ID

DATE

John B. Giessner

410-495-4683

RI

jbg

DOCUMENT NO.

DOCUMENT TITLE OR ACCESSION NO.

NRC INSPECTION REPORT: Calvert Cliffs Unit 1

U Is this a brief title that can be changed by DPC according to template instructions?

Is this an exact title formatted according to template instructions that should not be

changed by DPC?

Document AVAILABILITY (select

one)

Document SENSITIVITY (select one)

U Publicly Available

Sensitive

U Non-Sensitive

(Indicate release date)

Sensitive-Copyright

Non-Sensitive Copyright

Immediate Release

U Normal Release

Document SECURITY ACCESS LEVEL (select one)

Delay Release Until

X

Document Processing Center

= Owner

U NRC Users

= Viewer

Date

Limited Document Security (Defined by User)

= Viewer

Non-Publicly Available

= Viewer

= Viewer

ADAMS TEMPLATE NO.

RIDS CODE (IF APPLICABLE)

OTHER IDENTIFIERS

SPECIAL INSTRUCTIONS

SUBMITTED BY

TELEPHONE

MAIL STOP

LAN ID

DATE SUBMITTED TO DPC