E-mail from Klementowicz to Boland, Tritium Slides for Commissioner Merrifield
ML061460078
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 02/28/2005
From: Klementowicz S
Office of Nuclear Reactor Regulation
To: Boland A, Frye T, Peter Habighorst, Hackett E, Steven Orth, Richards S, Undine Shoop
NRC/RGN-II
References
FOIA/PA-2006-0130
Download: ML061460078 (3)


Text

,ne Boland - Tritiurn Slides for Commissioner Merrifield Page 1

,, * * (

Y1 0.L! '.L) U ,

From: Stephen Klementowicz To: Anne Boland; Edwin Hackett; Peter Habighorst; Steven Orth; Stuart Richards; Timothy Frye; Undine Shoop Date: 2/28/06 5:07PM

Subject:

Tritium Slides for Commissioner Merrifield Attached is a power point presentation on tritium. Also attached is our talking points for detailed information.

Steve K CC: Michael Case

..,u,.aauon in tis record was deleted inaccordance with the Freedom of, Information Act, U

Dresden Last month, a leak was identified in an underground pipe which carries tritiated water. (Line from the Condensate Storage Tank to the High Pressure Core Injection System)

The pipe is located onsite at the plant very near the reactor buildings themselves. (Approximate 1/4 mile to nearest site boundary)

The suspected pipe has been Isolated and drained. The leak appears to be associated with a pipe that similarly leaked in 2004 - the licensee only replaced the portion of.the pipe with the leak. Excavation has been put on hold to brace areas underneath the CST tank to ensure the ground does not collapse.

Replacement of the pipe will then proceed.

The leak was identified as a result of an existing onsite ground water monitoring

/

system -program. (On site levels have been up to approx. 600,000 pCi/I - as of February 24, 2006 levels in the two closest wells have stabilized between 20-50,000 pCi/I)

The leak is believed to be less than 1000 gallons and localized to an approximate 30 foot area.

Routine environmental wells were sampled in January and have indicated no change in tritium concentration due to the leak.