MONTHYEARLR-N24-0057, In-Service Inspection Activities2024-09-10010 September 2024 In-Service Inspection Activities LR-N24-0044, Relief Request VR-042024-08-0606 August 2024 Relief Request VR-04 LR-N24-0048, Invalid Primary Containment Integrated Leak Rate As-Found Test (ILRT)2024-07-0202 July 2024 Invalid Primary Containment Integrated Leak Rate As-Found Test (ILRT) LR-N24-0030, License Amendment Request to Revise Technical Specification Lift Settings for Reactor Coolant System Safety/Relief Valves2024-06-28028 June 2024 License Amendment Request to Revise Technical Specification Lift Settings for Reactor Coolant System Safety/Relief Valves LR-N24-0041, Stations, Revisions to Emergency Plan Document Nc EP-EP-ZZ-01102, Rev. 28, Emergency Coordinator Response2024-05-22022 May 2024 Stations, Revisions to Emergency Plan Document Nc EP-EP-ZZ-01102, Rev. 28, Emergency Coordinator Response LR-N24-0004, License Amendment Request – Revise Technical Specification to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle2024-05-20020 May 2024 License Amendment Request – Revise Technical Specification to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle LR-N24-0034, 2023 Annual Radioactive Effluent Release Report (ARERR)2024-04-30030 April 2024 2023 Annual Radioactive Effluent Release Report (ARERR) LR-N24-0035, 2023 Annual Radiological Environmental Operating Report (AREOR)2024-04-30030 April 2024 2023 Annual Radiological Environmental Operating Report (AREOR) LR-N24-0024, Response to Request for Additional Information Associated with License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary2024-04-26026 April 2024 Response to Request for Additional Information Associated with License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary LR-N24-0011, Supplemental Information to License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary2024-04-0505 April 2024 Supplemental Information to License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary LR-N24-0028, and Salem Generating Station - Notice of Intent to Pursue Subsequent License Renewal2024-03-28028 March 2024 and Salem Generating Station - Notice of Intent to Pursue Subsequent License Renewal LR-N24-0021, and Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums2024-03-20020 March 2024 and Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums LR-N24-0027, Inadvertent Main Turbine Control Valve Closure Caused Reactor Scram2024-03-19019 March 2024 Inadvertent Main Turbine Control Valve Closure Caused Reactor Scram LR-N24-0020, Generation Station and Salem Generating Station, Units 1 & 2 - Annual Property Insurance Status Report2024-03-0707 March 2024 Generation Station and Salem Generating Station, Units 1 & 2 - Annual Property Insurance Status Report LR-N24-0010, Technical Specification 6.9.1.5.b: 2023 Annual Report of SRV Challenges2024-02-22022 February 2024 Technical Specification 6.9.1.5.b: 2023 Annual Report of SRV Challenges LR-N23-0065, Submittal of 2023 Annual 10 CFR 50.46 Report2023-10-0202 October 2023 Submittal of 2023 Annual 10 CFR 50.46 Report LR-N23-0045, and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement2023-09-0808 September 2023 and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement LR-N23-0052, Retest Schedule for Drywell to Suppression Chamber Vacuum Breakers Per Technical Specification 4.6.2.12023-07-31031 July 2023 Retest Schedule for Drywell to Suppression Chamber Vacuum Breakers Per Technical Specification 4.6.2.1 LR-N23-0042, Spent Fuel Cask Registration2023-07-12012 July 2023 Spent Fuel Cask Registration LR-N23-0046, Emergency Plan Document Revisions Implemented June 28, 20232023-07-10010 July 2023 Emergency Plan Document Revisions Implemented June 28, 2023 LR-N23-0034, 2022 Annual Radiological Environmental Operating Report (AREOR) - Salem Nuclear Generating Station, Unit Nos. 1 and 2 and Hope Creek Generating Station2023-04-27027 April 2023 2022 Annual Radiological Environmental Operating Report (AREOR) - Salem Nuclear Generating Station, Unit Nos. 1 and 2 and Hope Creek Generating Station LR-N23-0035, 2022 Annual Radioactive Effluent Release Report (ARERR)2023-04-27027 April 2023 2022 Annual Radioactive Effluent Release Report (ARERR) LR-N23-0010, License Amendment Request Revision of Technical Specification (TS) to Delete TS Section 5.5 - Meteorological Tower Location2023-04-21021 April 2023 License Amendment Request Revision of Technical Specification (TS) to Delete TS Section 5.5 - Meteorological Tower Location LR-N23-0009, License Amendment Request (LAR) to Revise the Hope Creek Trip and Standby Auto-start Logic Associated with Safety Related Heating, Ventilation and Air Conditioning (HVAC) Trains2023-04-18018 April 2023 License Amendment Request (LAR) to Revise the Hope Creek Trip and Standby Auto-start Logic Associated with Safety Related Heating, Ventilation and Air Conditioning (HVAC) Trains LR-N23-0024, Submittal of Hope Creek Generating Station Technical Specification Bases Changes2023-03-29029 March 2023 Submittal of Hope Creek Generating Station Technical Specification Bases Changes LR-N23-0006, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-24024 March 2023 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations LR-N23-0019, and Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums2023-03-21021 March 2023 and Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums LR-N23-0016, and Salem Generating Station, Units 1 and 2 - Report of Changes, Tests, and Experiments2023-02-28028 February 2023 and Salem Generating Station, Units 1 and 2 - Report of Changes, Tests, and Experiments LR-N23-0018, Technical Specification 6.9.1.5.b - 2022 Annual Report of SRV Challenges2023-02-27027 February 2023 Technical Specification 6.9.1.5.b - 2022 Annual Report of SRV Challenges LR-N23-0012, Annual Property Insurance Status Report2023-02-24024 February 2023 Annual Property Insurance Status Report LR-N23-0014, Stations Submittal of 2022 Annual Report of Fitness for Duty Performance Data Per 10 CFR 26.203(e) and 10 CFR 26.7172023-02-23023 February 2023 Stations Submittal of 2022 Annual Report of Fitness for Duty Performance Data Per 10 CFR 26.203(e) and 10 CFR 26.717 LR-N23-0011, In-Service Inspection Activities - 90 Day Report: Twenty-Fourth Refueling Outage2023-01-19019 January 2023 In-Service Inspection Activities - 90 Day Report: Twenty-Fourth Refueling Outage LR-N22-0096, and Salem Generating Station, Units 1 and 2 - Request for Threshold Determination2023-01-0505 January 2023 and Salem Generating Station, Units 1 and 2 - Request for Threshold Determination LR-N22-0094, Emergency Plan Document Revisions Implemented November 21, 20222022-12-14014 December 2022 Emergency Plan Document Revisions Implemented November 21, 2022 LR-N22-0091, Independent Spent Fuel Storage Installation, Report of 10 CFR 72.48 Changes, Tests, and Experiments2022-12-0202 December 2022 Independent Spent Fuel Storage Installation, Report of 10 CFR 72.48 Changes, Tests, and Experiments LR-N22-0075, 2022 Annual 10 CFR 50.46 Report2022-09-30030 September 2022 2022 Annual 10 CFR 50.46 Report LR-N22-0074, Emergency Plan Evacuation Time Estimate2022-09-15015 September 2022 Emergency Plan Evacuation Time Estimate LR-N22-0051, License Amendment Request to Relocate Technical Specification Facility/Unit Staff Qualification Requirements to Quality Assurance Topical Report2022-06-22022 June 2022 License Amendment Request to Relocate Technical Specification Facility/Unit Staff Qualification Requirements to Quality Assurance Topical Report LR-N22-0044, Emergency Plan Document Revisions Implemented November, 20212022-05-19019 May 2022 Emergency Plan Document Revisions Implemented November, 2021 LR-N22-0040, 2021 Annual Radiological Environmental Operating Report2022-04-28028 April 2022 2021 Annual Radiological Environmental Operating Report LR-N22-0041, 2021 Annual Radioactive Effluent Release Report (Rerr)2022-04-28028 April 2022 2021 Annual Radioactive Effluent Release Report (Rerr) LR-N22-0039, Emergency Plan Document Revisions Implemented March 24, 20222022-04-21021 April 2022 Emergency Plan Document Revisions Implemented March 24, 2022 LR-N22-0023, Guarantees of Payment of Deferred Premiums2022-03-21021 March 2022 Guarantees of Payment of Deferred Premiums LR-N22-0017, Submittal of 2021 Annual Report of Fitness for Duty (FFD) Performance Data2022-02-25025 February 2022 Submittal of 2021 Annual Report of Fitness for Duty (FFD) Performance Data LR-N22-0019, Technical Specification 6.9.1.5.b 2021 Annual Report of SRV Challenges2022-02-24024 February 2022 Technical Specification 6.9.1.5.b 2021 Annual Report of SRV Challenges LR-N22-0016, Radiological Survey of Site Property to Be Used for Offshore Wind Port Facility2022-02-24024 February 2022 Radiological Survey of Site Property to Be Used for Offshore Wind Port Facility LR-N22-0011, Response to Request for Additional Information for License Amendment Request to Revise Technical Specification Limits for Ultimate Heat Sink2022-02-0101 February 2022 Response to Request for Additional Information for License Amendment Request to Revise Technical Specification Limits for Ultimate Heat Sink LR-N22-0005, Proposed Relief Request Associated with Reactor Pressure Vessel Water Level Instrumentation Partial Penetration Nozzle Repairs2022-01-0707 January 2022 Proposed Relief Request Associated with Reactor Pressure Vessel Water Level Instrumentation Partial Penetration Nozzle Repairs LR-N22-0007, Request for Exemption from Specific Requirements of 10 CFR Part 26, Fitness for Duty Programs2022-01-0505 January 2022 Request for Exemption from Specific Requirements of 10 CFR Part 26, Fitness for Duty Programs LR-N21-0087, Corrected Hope Creek 10 CFR 50.46 Reports2021-12-0202 December 2021 Corrected Hope Creek 10 CFR 50.46 Reports 2024-09-10
[Table view] |
Text
PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 Mr. Samuel Collins, Regional Administrator United States Nuclear Regulatory Commission Region I 475 Allendale Road King of Prussia, PA 19406-1415 ACTIONS TO CLOSE CAL 1-05-001 BREACTOR RECIRCULATION PUMP HOPE CREEK GENERATING STATION ..
rc rt FACILITY OPERATING LICENSE NO. NPF-57 0 h)
DOCKET NO. 50-354
References:
- 1) PSEG letter LR-N05-0017 from C. Bakken to S. Collins, dated January 9,2005
- 2) NRC Confirmatory Action Letter (CAL) (1-05-OOI), dated January II, 2005
Dear Mr. Collins:
As discussed in References 1 and 2 above, PSEG committed to and has implemented a vibration-monitoring program to continuously monitor the B Reactor Recirculation Pumps primary and secondary harmonic parameters (total amplitude, 1X and 2X amplitude, and 1X and 2X phase angle). As stated in Reference 1, PSEG procedures HC.OP-AB.RPV-O003(Q), HC.ER-AP.66-0001(Z), and HC.OP-AR.ZZ-O008(Q) Attachment E-4 fulfill this commitment.
Prior to implementing any changes to the vibration monitoring procedures, PSEG committed to notify the NRC and provide sufficient time for the NRC to complete a review of the proposed changes. Further, PSEG committed to replace the B Reactor Recirculation Pumps shaft and inspect the pumps rotating assembly and pressure boundary components (such as the pump casing and cover) at the earlier of the next refueling outage or during an outage of sufficient duration to accomplish pump replacement. PSEG has scheduled the replacement of the B Reactor Recirculation Pumps rotating assembly during the upcoming 13h Refueling Outage (RFOI 3) in April 2006.
95-2168 REV. 7/99
Mr. Samuel Collins 2 LR-N06-0053 To complete the actions specified in Reference 2 and committed by PSEG in Reference 1, PSEG intends to perform the following activities during RFOl3.
The B Reactor Recirculation pump rotating assembly will be replaced with a new rotating assembly. The replacement is being performed as a design change since the rotating assembly being installed is the new 4thgeneration assembly that is no longer susceptible to the shaft thermal cracking phenomenon of the early generation assemblies. The rotating assembly replacementwill be performed during RF013 and per the current schedule, the replacement is expected to begin on April 16h.It is PSEGs understanding that the NRC may be present during the rotating assembly removal so PSEG will keep the NRC verbally informed of any schedule changes.
During the removal of the rotating assembly, a visual inspection of the assembly will be performed by the pump vendor (Flowserve). The visual inspection will be performed as the assembly is transported from the pump casing to a shielded storage container. The Flowserve personnel will inspect the rotating assembly for the following conditions; general conditions of the visual portions of the exterior of the pump assembly, general conditions of the visual portions of the impeller, any noticeable dents or scratches, any shining metal indicating possible interaction with the pump wearing ring, and any abnormalities outside of previous reactor recirculation pump experience. Upon removal, the rotating assembly will be placed in its shielded storage container and will remain onsite pending final disposition.
Following the inspection of the rotating assembly, an inspection of the pressure boundary components will be performed. The pressure boundary components will be inspected in accordance with ASME Section XI Acceptance Criteria I WB-35 19.
As required by Section 182 of the Atomic Energy Act, 42 U.S.C. 2232, PSEG will inform the NRC in writing when the actions addressed in the CAL have been completed (i.e., B Reactor Recirculation pump shaft replaced, rotating assembly and pressure boundary components inspected). In order to support start-up activities following RFOl3, PSEG requests that NRC provide verbal notification, in advance of NRC written correspondence, that the CAL actions have been satisfied as allowed by Section 4.7.7 of the NRC Enforcement Manual. PSEG also understands that upon confirmation by the NRC that the actions addressed in the CAL have been completed, future changes to PSEG procedures HC.OP-AB.RPV-O003(Q), HC.ER-AP.BB-0001(Z), and HC.OP-AR.ZZ-O008(Q) Attachment E-4 will be controlled in accordance with PSEGs administrative processes and the need for NRC approval prior to implementation will be determined in accordance with 10CFR50.59.
-. 3 Mr. Samuel Collins LR-N06-0053 Should you have any further questions please contact James Barstow at 856-339-1384.
Siny r e l y ,
George P. Barnes Site Vice President - Hope Creek
Mr. Samuel Collins
. I 4
LR-N06-0053 C Mr. S. Bailey, Project Manager Salem & Hope Creek U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 08B2 I1555 Rockville Pike Rockville, MD 20852 Mr. J. White, Chief, Materials & Structural Engineering Branch United States Nuclear Regulatory Commission Region I 475 Allendale Road King of Prussia, PA 19406-1415 USNRC Senior Resident Inspector - HC (X24)
Mr. K. Tosch, Manager IV Bureau of Nuclear Engineering PO Box 415 Trenton, NJ 08625 USNRC Document Control Desk Washington, DC 20555