MONTHYEARML24155A1992024-06-0303 June 2024 Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - NRC Meeting Summary ML24068A0742024-03-13013 March 2024 Summary of February 27, 2024, Pre Submittal Public Meeting with Pseg Nuclear Llc to Discuss Future Amendment Regarding Improved Technical Specification Conversion ML24068A0862024-03-13013 March 2024 February 27, 2024, Summary of Pre-Submittal Public Meeting with PSEG Nuclear LLC to Discuss Future Amendment Regarding 24 Month Fuel Cycle and Surveillance Interval Extension ML23300A0382023-11-0101 November 2023 Summary of Hope Creek Oct 24, 2023, Pre Submittal Public Meeting with PSEG Nuclear LLC to Discuss Future Amendments Regarding Improved TS Conversion 24 Month Fuel Cycle & Surveillance Interval Extension & Safety Relief Valve Lift Setpoint C ML23179A0012023-06-28028 June 2023 6/7/2023 - Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - Meeting Summary ML23146A1012023-05-31031 May 2023 Summary of May 25, 2023, Pre-Submittal Public Meeting with PSEG Nuclear LLC to Discuss Reduction of the Sites Exclusion Area Boundary ML22325A3052022-11-22022 November 2022 Summary of November 17, 2022, Pre Submittal Public Meeting with PSEG Nuclear LLC to Discuss Threshold Determination on Transferring Ownership of Portions of the Site ML22187A1462022-07-0606 July 2022 Joint Annual Assessment Meeting for Pa/Md/Nj/Ny Nuclear Power Plants - Meeting Summary ML21092A1502021-04-15015 April 2021 Summary of Pre-Submittal Public Meeting with PSEG Nuclear LLC to Discuss License Amendment Regarding Ultimate Heat Sink Technical Specification Changes ML21064A0962021-03-0909 March 2021 Summary of 3/4/2021 Pre-Submittal Public Meeting with PSEG Nuclear LLC to Discuss Adoption of ASME Section XI Code Cases N-878, N-879, and N-880 at Hope Creek Generating Station and Salem Nuclear Generating Station ML20308A3692020-11-19019 November 2020 Summary of Pre-Submittal Public Meeting with PSEG Nuclear LLC to Discuss Replacement of Source and Intermediate Range Neutron Monitors with Numac Wide Range Neutron Monitoring System ML19317E6762019-11-26026 November 2019 Summary of November 12, 2019, Pre-Submittal Public Meeting with PSEG Nuclear LLC to Discuss Proposed License Amendment to Adopt 10 CFR 50.69 ML19109A1282019-04-16016 April 2019 and Hope Creek Generating Station: Summary of Public Webinar Meeting on April 10, 2019 ML19045A4702019-02-15015 February 2019 Summary of Closed Teleconference Meeting with PSEG Nuclear LLC and General Electric-Hitachi Nuclear Energy to Discuss a General Electric Part 21 Issue ML18156A4242018-06-0505 June 2018 Annual Assessment Meeting, 5/30/18 Meeting Summary ML18044A9942018-02-26026 February 2018 Summary of Meeting with PSEG Nuclear LLC Regarding Planned Submittal of License Amendment Request to Revise Technical Specifications Regarding Extending the Allowed Outage Time for the Inverters ML18036A6142018-02-21021 February 2018 Generation Station-Summary of January 24, 2018, Meeting with PSEG Nuclear LLC on Planned Submittal of License Amendment Request to Revise Technical Specifications Regarding Diesel Generator Extended Allowed Outage Time ML17201A1012017-08-0404 August 2017 Summary of Meeting with PSEG Nuclear LLC to Discuss Potential License Amendment Request Technical Specification Task Force Traveler-542 for Hope Creek Generating Station ML17164A1742017-06-20020 June 2017 Summary of May 31, 2017, Meeting with PSEG Nuclear LLC to Discuss a Potential Measurement Uncertainty Recapture Power Uprate for Hope Creek Generating Station ML17102A7772017-04-10010 April 2017 Summary of Annual Assessment Meeting with PSEG ML16362A2022017-01-24024 January 2017 Summary of Meeting with PSEG Nuclear LLC Regarding Potential Measurement Uncertainty Recapture Power Uprate ML17023A1452017-01-23023 January 2017 Summary of Teleconference with PSEG Regarding Hope Creek HPCI ML16347A3932017-01-0505 January 2017 Summary of Teleconference with PSEG Nuclear LLC Regarding Planned License Amendment Request Regarding Change to the Salem Nuclear Generating Station-Hope Creek Generating Station Emergency Action Levels (MF8875, MF8876, and MF8877) ML16201A0292016-08-15015 August 2016 Summary of June 21, 2016, Teleconference with PSEG Nuclear LLC on the Upgrade of the Hope Creek Generating Station Power Range Neutron Monitoring System to a Digital Power Range Neutron Monitoring System ML16217A4552016-08-15015 August 2016 Summary of July 19, 2016, Teleconference with PSEG Nuclear LLC on the Upgrade of Hope Creek Generating Station'S Power Range Neutron Monitoring System ML16141A2402016-06-16016 June 2016 Summary of April 19, 2016, Teleconference with PSEG Nuclear LLC on the Upgrade of Hope Creek Generating Stations'S Power Range Neutron Monitoring System to a Digital Power Range Neutron Monitoring System ML16113A3962016-04-29029 April 2016 Summary of Teleconference with PSEG Nuclear LLC on the Upgrade of Hope Creek Generating Station'S Power Range Neutron Monitoring System to a Digital Power Range Neutron Monitoring System ML16096A2222016-04-0505 April 2016 March 30, 2016, Summary of Annual Assessment Meeting with PSEG - Salem Nuclear Generating Station & Hope Creek Generating Station ML16064A0052016-03-22022 March 2016 Summary of Teleconference with PSEG Nuclear LLC on the Upgrade of Hope Creek Generating Station'S Power Range Neutron Monitoring System to a Digital Power Range Neutron Monitoring System ML16116A2352016-03-15015 March 2016 Meeting Summary for Public Teleconference Between PSEG LLC and the Nuclear Regulatory Commission, Hope Creek Generating Station - Power Range Neutron Monitoring System Digital Upgrade LAR HCGS Numac Upgrade - Open Item DOC-0006-2118 Ri ML15104A1492015-04-14014 April 2015 Hope, Summary of Annual Assessment Meeting with PSEG ML15043A2392015-03-24024 March 2015 January 29, 2015, Summary of Pre-licensing Meeting with PSEG Regarding Digital Upgrade of Power Range Neutron Monitor (Prnm) ML14224A1332014-08-26026 August 2014 Summary of August 12, 2014, Pre-Licensing Meeting with PSEG Regarding Digital Upgrade of Power Range Neutron Monitor ML14100A0242014-04-10010 April 2014 Salem and Hope Creek - Summary of Annual Assessment Meeting with PSEG ML13364A2422014-02-0404 February 2014 9/11/2013 - Summary of Pre-Licensing Meeting with PSEG Regarding Digital Upgrade of Power Range Neutron Monitor ML13099A3242013-04-0909 April 2013 Salem & Hope Creek - Summary of Annual Assessment Meeting with PSEG ML12144A3312012-05-23023 May 2012 Summary of Meeting at the PSEG to Discuss the Nrc'S Assessment of Pseg'S Safety Performance at Salem & Hope Creek for 2011 ML1129700652011-10-21021 October 2011 Summary of PSEG Drop-in Visit, 9-28-2011 and Slides ML11292A1612011-10-20020 October 2011 Summary of Meeting with Beyond Nuclear Regarding Their 10 CFR 2.206 Petition to Suspend Operating Licenses of General Electric Mark I Boiling Water Reactors ML11181A1772011-06-30030 June 2011 June 29, 2011 Summary of Public Meeting to Discuss Observations and Lessons Learned During the Hope Creek Nuclear Generating Station Application of the Nuclear Energy Institute'S Nuclear Safety Culture Assessment Process ML11166A1342011-06-22022 June 2011 Meeting Summary with the Beyond Nuclear Petitioners Regarding Their 2.206 Petition to Suspend Operating Licenses (Ols) of General Electric (GE) Boiling Water Reactors (Bwrs) Mark I (Bwrs) ML11138A3212011-06-0808 June 2011 May 9, 2011, Summary of Telephone Conference Call Held Between NRC and PSEG Nuclear, LLC, Concerning Status of Hope Creek Drywell Air Gap Drains ML11137A0762011-06-0202 June 2011 Summary of Telephone Conference Call Held on May 11, 2011, Between the U.S. Nuclear Regulatory Commission and PSEG Nuclear, LLC, Concerning the Hope Creek License Condition for the Drywell ML1114002132011-05-20020 May 2011 Summary of Annual Assessment Meeting for Salem and Hope Creek ML11105A0372011-05-0404 May 2011 Summary of Telephone Conference Call Held on March 25, 2011, Between the U.S. Nuclear Regulatory Commission and PSEG Nuclear, LLC, Concerning Findings on the Hope Creek Generating Station Gas Turbine ML1100700302011-03-25025 March 2011 Summary of Telephone Conference Call Held on August 30, 2010, Between the U.S. Nuclear Regulatory Commission and PSEG Nuclear, LLC, Concerning Questions Pertaining to the Hope Creek Generating Station License Renewal Application ML1034909292011-02-0909 February 2011 Summary of Telephone Conference Call Held on November 18, 2010, Between the U.S. Nuclear Regulatory Commission and PSEG Nuclear, LLC, Concerning Findings on the Hope Creek Generating Station Recent Outage ML1100501592011-02-0909 February 2011 September 15, 2010 Summary of Telephone Conference Call Held Between the U.S. Nuclear Regulatory Commission and PSEG Nuclear, LLC, Concerning Questions Pertaining to the Hope Creek Generating Station License Renewal Application ML1031907452010-11-19019 November 2010 Summary of Telephone Conference Call Held on 10/21/10 Btw the USNRC and PSEG Nuclear, LLC, Concerning Hope Creek Generating Station, License Renewal Application, Environmentally Assisted Fatigue Analysis ML1025903832010-11-0202 November 2010 September 09, 2010, Summary of Telephone Conference Call Held Between NRC & PSEG Concerning a LRA Supplement Pertaining to the Hope Creek Generating Station, License Renewal Application 2024-06-03
[Table view] |
Text
May 1, 2006 LICENSEE: PSEG NUCLEAR, LLC.
FACILITY: HOPE CREEK GENERATING STATION
SUBJECT:
SUMMARY
OF MARCH 29, 2006, CATEGORY 1 MEETING WITH PSEG NUCLEAR LLC, REGARDING PLANNED APPLICATION FOR EXTENDED POWER UPRATE FOR HOPE CREEK GENERATING STATION (TAC MD0510)
On March 29, 2006, the Nuclear Regulatory Commission (NRC) staff met with representatives of PSEG Nuclear LLC (PSEG), the licensee for the Hope Creek Generating Station (Hope Creek), to discuss PSEGs plans to apply for an extended power uprate (EPU) for Hope Creek.
The NRC staff considers an EPU to be any uprate in excess of approximately 8%, and typically involving major plant modifications to achieve the higher power level.
As background, PSEG had applied for an EPU at Hope Creek on November 7, 2005. The NRC staff performed an acceptance review, in accordance with its procedures, using its experience with previous EPU applications and the guidance in RS-001, Review Standard for Extended Power Uprates. The NRC staff determined that the application did not contain sufficient information regarding the effects of higher flow rates that result from the higher power level, particularly with respect to the steam dryer. The NRC staff and PSEG discussed these concerns on December 20, 2005. On February 2, 2006, the NRC staff explained that it did not find the application acceptable due to the amount of work required to address the issues.
PSEG withdrew the amendment by letter dated February 10, 2006.
During the meeting, the licensee discussed its plans for evaluating the effect of higher flow rates. The licensee discussed the susceptibility review that was being performed on all plant equipment. Equipment that is determined to be susceptible to degradation due to higher flow rates will be further evaluated for acceptability or corrective actions.
The majority of the meeting was spent discussing the licensees evaluation of the steam dryers.
PSEG discussed the combination of computational fluid dynamics, acoustic circuit models, and finite element analyses that would be used to predict the loads and stresses on the steam dryer, and how online measurements would be used to verify the predictions. PSEG compared and contrasted their approach to similar EPU applications, and discussed their treatment of uncertainty in the models.
The meeting notice indicated that a portion of the meeting would be closed to discuss proprietary information related to the acoustic circuit model, but no proprietary information was discussed.
The licensee also discussed other items, such as the license condition related to feedwater temperature reduction and the NRC staffs plans to perform audit calculations.
A list of meeting attendees is enclosed. No handouts or presentation materials were used at the meeting.
Please direct any inquiries to me at 301-415-1321 or snb@nrc.gov.
Sincerely,
/RA/
Stewart N. Bailey, Sr. Project Manager Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-354
Enclosure:
- 1. Attendee List cc w/enclosure: See next page
A list of meeting attendees is enclosed. No handouts or presentation materials were used at the meeting.
Please direct any inquiries to me at 301-415-1321 or snb@nrc.gov.
Sincerely,
/RA/
Stewart N. Bailey, Sr. Project Manager Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-354
Enclosure:
- 1. Attendee List cc w/enclosure: See next page DISTRIBUTION:
PUBLIC LPL1-2 Reading RidsNrrDorlLplb RidsNrrPMSBailey RidsNrrLACRaynor RidsOgcRp RidsAcrsAcnwMailCenter R. Jasinski, NRR RidsNrrDeEemb RidsNrrDssSnpb TScarbrough, NRR JWu, NRR RidsNrrPMCSanders RidsNrrPMFSaba MRazzaque, NRR CBoyd, RES R. Caruso, ACRS B. Sosa, EDO Region I RidsRgnIMailCenter Accession No.: ML061180052 OFFICE LPL1-2/PM LPL1-2/LA LPL1-2/BC NAME SBailey CRaynor DRoberts DATE 4/28/06 4/28/06 5/01/06 OFFICIAL RECORD COPY
ATTENDEE LIST MARCH 29, 2006, PREAPPLICATION MEETING ON EXTENDED POWER UPRATE HOPE CREEK GENERATING STATION Name Organization S. Bailey NRC/NRR/ADRO/DORL/LPL1-2 R. Ennis NRC/NRR/ADRO/DORL/LPL1-2 D. Roberts NRC/NRR/ADRO/DORL/LPL1-2 F. Saba NRC/NRR/ADRO/DORL/LPL1-2 C. Sanders NRC/NRR/ADRO/DORL/LPL1-2 K. Manoly NRC/NRR/DE/EEMB J. Wu NRC/NRR/DE/EEMB T. Scarbrougn NRC/NRR/DCI/
F. Akstulewicz NRC/NRR/DSS/SNPB M. Rozzaque NRC/NRR/DSS/SPLB C. Boyd NRC/RES/DRASP R. Caruso ACRS L. Curran PSEG T. DelGaizo PSEG P. Duke PSEG K. Hutko PSEG F. Safin PSEG H. Trenka PSEG J. Mallon Exelon A. Bilanin Continuum Dynamics (PSEG Contractor)
J. Humphries New Jersey Department of Environmental Protection (by phone)
D. Horner McGraw-Hill Enclosure
Hope Creek Generating Station cc:
Mr. William Levis Jeffrie J. Keenan, Esquire Senior Vice President & Chief Nuclear PSEG Nuclear - N21 Officer P.O. Box 236 PSEG Nuclear LLC - N09 Hancocks Bridge, NJ 08038 Post Office Box 236 Hancocks Bridge, NJ 08038 Township Clerk Lower Alloways Creek Township Mr. Dennis Winchester Municipal Building, P.O. Box 157 Vice President - Nuclear Assessments Hancocks Bridge, NJ 08038 PSEG Nuclear P.O. Box 236 Mr. Paul Bauldauf, P.E., Asst. Director Hancocks Bridge, NJ 08038 Radiation Protection Programs NJ Department of Environmental Mr. George P. Barnes Protection and Energy Site Vice President - Hope Creek CN 415 PSEG Nuclear Trenton, NJ 08625-0415 P.O. Box 236 Hancocks Bridge, NJ 08038 Mr. Brian Beam Board of Public Utilities Mr. George H. Gellrich 2 Gateway Center, Tenth Floor Plant Support Manager Newark, NJ 07102 PSEG Nuclear P.O. Box 236 Regional Administrator, Region I Hancocks Bridge, NJ 08038 U.S. Nuclear Regulatory Commission 475 Allendale Road Mr. Michael J. Massaro King of Prussia, PA 19406 Plant Manager - Hope Creek PSEG Nuclear Senior Resident Inspector P.O. Box 236 Hope Creek Generating Station Hancocks Bridge, NJ 08038 U.S. Nuclear Regulatory Commission Drawer 0509 Mr. Darin Benyak Hancocks Bridge, NJ 08038 Director - Regulatory Assurance PSEG Nuclear - N21 P.O. Box 236 Hancocks Bridge, NJ 08038 Mr. James Mallon Manager - Locensing 200 Exelon Way - KSA 3-E Kennett Square, PA 19348