GNRO-2006/00014, Response to Generic Letter 2006-02, Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power

From kanterella
(Redirected from ML060950257)
Jump to navigation Jump to search
Response to Generic Letter 2006-02, Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power
ML060950257
Person / Time
Site: Grand Gulf Entergy icon.png
Issue date: 04/03/2006
From: Krupa M
Entergy Operations
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
GL-06-002, GNRO-2006/00014
Download: ML060950257 (26)


Text

Entergy Operatio is, Inc.

'Entergy Waterloo Rd.

P.O. Box 756 Port Gibson, MS 39150 Tel 601 437 6470 Michael A. Krupa Director Nuclear Safety Assurance GNRO-2006/00014 April 3, 2006 U.S. Nuclear Regulatory Commission Washington, DC 20555 Attention: Document Control Desk

SUBJECT:

Response to Generic Letter 2006-02, Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power Plant Name Grand Gulf Nuclear Station Docket No. 50-416 License No. NPF-29

REFERENCE:

NRC letter dated February 1, 2006, Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power (GNRI-2006/00005)

Dear Sir or Madam:

Per Reference 1, the NRC issued Generic Letter (GL) 2006-02 to request information for determining compliance with regulatory requirements governing electric power sources. Specifically, the NRC is requesting information regarding (1) use of protocols between the nuclear power plant (NPP) and the transmission system operator (TSO), independent system operator (ISO), or reliability coordinator/authority (RC/RA) including transmission load flow analysis tools, (2) use of NPP/TSO protocols and analysis tools by TSOs to assist NPPs in monitoring grid conditions for consideration in maintenance risk assessments; (3) offsite power restoration procedures in accordance with Section 2 of NRC Regulatory Guide (RG) 1.155, "Station Blackout;" and, (4) losses of offsite power caused by grid failures at a frequency equal to or greater than once in 20 site-years in accordance with RG 1.155. The requested information is being made under the requirements of 10 CFR 50.54(f).

GNRO-2006/00014 Page 2 of 2 The Grand Gulf Nuclear Station (GGNS) response to the requested information in GL 2006-02 is contained in attachment to this submittal. Responses to questions associated with the Entergy Transmission groups are outside the direct control of GGNS. However, they have been confirmed by the Transmission Organizations to the extent practical. Entergy is not making any commitments as a result of our response to this letter. If you have any questions or require additional information, please contact Eddie Hester at 601-437-6913.

I declare under penalty of perjury that the foregoing is true and correct.

Executed on April 3, 2006.

Sincerely, CAB/wba

Attachment:

Response to Generic Letter 2006-02 for GGNS cc: NRC Senior Resident Inspector Grand Gulf Nuclear Station Port Gibson, MS 39150 U. S. Nuclear Regulatory Commission ATTN: Dr. Bruce S. Mallet (w/2)

Regional Administrator, Region IV 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-4005 U. S. Nuclear Regulatory Commission ATTN: Mr. Bhalchandra Vaidya, NRR/DORL (w/2)

ATTN: ADDRESSEE ONLY ATTN: U. S. Postal Delivery Address Only Mail Stop OWFN/O-7D1A Washington, DC 20555-0001 Mr. D. E. Levanway (Wise Carter)

Mr. L. J. Smith (Wise Carter)

Mr. N. S. Reynolds Mr. J. N. Compton

Attachment to GNRO-2006/0001 4 Response to Generic Letter 2006-02 for GGNS

Attachment to GNRO -2006/00014 Page 1 of 23 Response to Generic Letter 2006-02 for GGNS Requested Information Use of protocols between the NPP licensee and the TSO, ISO, or RC/RA and the use of analysis tools by TSOs to assist NPP licensee in monitoring grid conditions to determine tho operability of offsite power systems under plant TS.

GDC 17, 10 CFR Part 50, Appendix A, requires that licensees minimize the probability of the loss of power from the transmission network given a loss of the power generated by the nuclear power unit(s).

NRC Request I - Use of protocols between the NPP licensee and the TSO, ISO, or RC/RA to assist the NPP licensee in monitoring grid conditions to determine the operability of offsile power systems under plant TS.

(a) Do you have a formal agreement orprotocol with your TSO?

ENS Response to Request 1(a):

Entergy Nuclear South (ENS) plants [i.e., Grand Gulf Nuclear Station, River Bend Nuclear Station, Waterford Steam Electric Station, Unit 3 (Waterford 3) and Arkansas Nuclear Orie]

utilize a combination of formal agreements, procedures, protocols and/or actions to have Entergy Transmission provide notification to each ENS plant if the predicted post-trip voltage does not meet the minimum value(s) specified in ENS procedure' ENS-DC-199, 'Offsite Power Supply Design Requirements". This procedure is an ENS controlled procedure that is jointly reviewed by both Entergy Transmission and ENS. It contains the specifics pertaining to preferred offsite sources, including acceptable voltage, frequency and power delivery requirements for each ENS plant. The formal agreement for GGNS is referred to as the Grand Gulf Nuclear Station Switchyard and Transmission Interface Agreement.

The formal agreements for each site provide a general framework for the establishment of procedures and processes that are deemed by each agreement to be of importance to the safe operation of the respective ENS site. Each agreement contains the requirement that respective ENS site be provided with an assured source of offsite power in accordance with procedures to be agreed upon by the respective ENS site and the Entergy Transmission organization.

The monitoring process used by Entergy Transmission to predict ENS plant post-trip voltages is contained in ENS procedure ENS-DC-201, 'ENS Transmission Grid Monitoring".

This procedure is an ENS controlled procedure that is jointly reviewed by both Entergy Transmission and ENS. This procedure contains the Transmission/ENS Off-Line Post Trip Voltage Analysis & Monitoring Process. This process is implemented by Entergy Traismission Procedures.

1 Compliance with GDC 17, as documented in the license basis and plant Technical Specifications for Entergy Nuclear South (ENS) plants, is not predicated on such agreements. Additionally, ENS plants are considered regulated, not de-regulated and ENS plants are part of vertically-integrated, Entergy Corporation utility operations.

Attachment to GNROQ-2006/00014 Page 2 of 23 These procedures collectively implement near-term advance (day-ahead) grid analysis specifically for ENS to use in determining the status of the Entergy Transmission grid, particularly near ENS plants. This monitoring uses PTI/PSSE analysis, performed for the neyt day, using daily cases representing that day of the month. These cases specifically consider the trip of each ENS unit and the application of design basis accident loads. These cases are also re-performed during the period of interest if previously identified specific contingencies occur or, if Entergy Transmission determines that system conditions have significantly changed during the period that could affect the offsite power source post-trip voltage availability for any ENS unit. This allows the analysis to remain bounding if system conditions change. The results of these analyses are then compared to the specific ENS' unit post-trip voltage requirements for each respective ENS site. If the results indicate the potential for ENS site specific requirements would not be met, Entergy Transmission determines if these requirements can be met for the period of interest by making changes to transmission system configuration/operation. If Entergy Transmission determines that the requirements cannot be met or are not being met, then notification to the affected plant is required. ENS plant compliance with GDC 17, as documented in the license basis and plant Technical Specifications for each ENS plant, is not predicated on such an agreement.

Compliance with GDC 17 as stated in NUREG 0800 is based on "each [offsite power] circuit has been sized with sufficient capacity to supply all connected loads" and "results of the grid stability analysis indicated that loss of the largest generating capacity being supplied to the grid, loss of largest load from the grid, loss of the most critical transmission line, or loss cf the unit itself will not cause grid instability." As confirmed in the definitions of Generic Letter 20C'6-02, for a given disturbance stability equates to maintaining a state of equilibrium, and not a specific voltage. However, Entergy Transmission is presently required by the applicable Regional Coordinating Council to perform periodic studies to ensure compliance with their grid stability criteria and planning standards. This criteria includes limits on the maximum allowable voltage deviation and duration of transients for a given grid disturbance.

This provides additional ENS plant offsite power (stability) assurance in addition to that required by GDC 17 for stability considerations.

(b) Describe any grid conditions that would trigger a notification from the TSO to the NPP licensee and if there is a time period required for the notification.

ENS Response to Request 1(b):

The! process described for the Entergy response to NRC Request 1(a) is a look-ahead analysis that covers the following day. As such, this process does not incorporate an explicit time period requirement for notification, because the period of interest is in the future (next day). This allows Entergy Transmission to evaluate the projected system conditions and provides an opportunity to possibly prevent the actual occurrence of grid conditions that would not meet ENS requirements. If, following such evaluations for the next day, or, following the occurrence of specific predetermined grid contingencies reevaluated during the present period, there are indications that ENS site specific requirements will not be met cr are not being met, notification to the affected plants is required. Likewise, should actual real-time conditions occur that are outside of ENS requirements, without projecting additional contingencies, then notification is also provided. While the present day re-evaluation and, if required, the real-time notifications do not have an explicit time requirement stated, it is expected by both parties that such communications would be performed commensurate with the severity of the situation. ENS procedures require

Attachment to GNRO-2006/0001 4 Page 3 of 23 Eniergy Transmission to receive periodic training by ENS on the importance of ENS offsite power to nuclear safety and the necessity of prompt resolution of such issues.

(c) Describe any grid conditions that would cause the NPP licensee to contact the TSO.

Describe the procedures associated with such a communication. If you do not have procedures, describe how you assess grid conditions that may cause the NPP licensee lb contact the TSO.

ENS Response to Request 1(c):

Grid conditions and status are the primary responsibility of Entergy Transmission for ENS plants. The observable parameters for the ENS plants include only voltage and frequenly, generator reactive output, breaker status, status of certain lines, and certain switchyard alarm points.

The Entergy Transmission organization has procedures and practices as indicated in the Entergy response to NRC Request 1(a), that require plant notification in the event that actual or projected ENS specific grid conditions are not met. As such, ENS does not explicitly dictate that the individual sites perform periodic inquiries of the Entergy Transmission organization for determination of grid status. However, this does not preclude ENS from performing a grid status check with Entergy Transmission if ENS deems such information to be beneficial in a given situation, using communications protocols provided in ENS procedures. Additionally, if the daily monitoring process is determined by Entergy Transmission to be unavailable, plant notification is required per ENS procedure DC-201, which is jointly reviewed by Entergy Transmission.

GG NS has procedural triggers for contacting the TSO in the 'Loss of AC Power" off-normal event procedure, in the Technical Specifications (Tech Spec) Bases and 'Control of Limiting Conditions for Operation" procedure prior to entering an extended Diesel Generator Outage, and before placing the Generator Voltage Regulator in manual per the "Main Generator and Auxiliaries" System Operating Instruction (SOI). In addition, the weekly Tech Spec Surveillance procedure has Licensed Operators contact the TSO. GGNS has Control Room Indications for the two 500 and the 115 kV GGNS offsite sources. Any indication cf a 500 or 115 kV line unplanned loss would trigger GGNS Operators to contact the TSO to determine the status of the grid and recovery actions/time periods until the line(s) could be restored. The GGNS Tech Specs require two of the three lines entering the 500/115 kV Switchyard to be Operable to satisfy the requirements for AC Power Sources in Modes 1, 2, and 3. These three lines are the GDC 17 credited offsite sources. If only one of the two required offsite sources is Operable, the Tech Spec LCO would be entered and the TSO would be contacted to determine the status of the grid within one hour and every 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> thereafter, until two offsite sources are operable.

Attachment to GNRO*-2006/00014 Page 4 of 23 (d) Describe how NPP operators are trained and tested on the use of the procedures or assessing grid conditions in question 1(c).

ENS Response to Request 1(d):

Plant operators receive training to ensure their understanding of the function and operation of the GGNS onsite and offsite electrical distribution system and components.- Training includes both initial and continuing training programs, which consist of a combination of classroom, and practical factors (e.g. qualification guides and job performance measures).

These methods provide instruction and administer testing to assess the proficiency and knowledge levels of operators in the use of procedures for basic operation of the electrical distribution system, assessing grid conditions, and responding to abnormal and/or emergency conditions. Training is provided in both the licensed and non-licensed training programs. Additionally, lessons learned from operating experience associated with offsite and onsite electrical distribution, such as Significant Operating Event Report (SOER) 99-01, are extensively incorporated into the training curriculum. Testing methods include written exams, and job performance measures.

(e) If you do not have a formal agreement or protocol with your TSO, describe why you believe you continue to comply with the provisions of GDC 17 as stated above, or describe what actions you intend to take to assure compliance with GDC 17.

ENS Response to Request 1(e):

ENS plants have a combination of formal agreements, procedures, protocols and practices as described in the response to NRC Request 1(a); therefore this question is not applicable.

(0 If youi have an existing formal interconnection agreement or protocol that ensures adequate communication and coordination between the NPP licensee and the TSO, describe whether this agreement or protocol requires that you be promptly notified when the conditions of the sun-ounding grid could result in degraded voltage (i.e., below TS nominal trip setpoint value requirements; including NPP licensees using allowable value in its TSs) or LOOP after a trip of the reactor unit(s).

ENS Response to Request 1(f):

As discussed under the response to NRC Request 1 (a), ENS plants utilize a combination of formal agreements, procedures, protocols and/or actions to have Entergy Transmission provide notification to each ENS plant if the predicted post-trip voltage does not meet the minimum value(s) specified in ENS procedure ENS-DC-199. This procedure is ENS controlled procedure that isjointly reviewed by both Entergy Transmission and ENS, and contains the specifics pertaining to preferred offsite sources, including acceptable voltage, frequency and power delivery requirements for each ENS plant.

If the analysis results indicate the potential for ENS site-specific requirements cannot be met, Entergy Transmission determines if these requirements can be met for the period of interest by making changes to transmission system configuration/operation. If Entergy Transmission determines that the requirements cannot be met or are not being met, then plant notification is required. While the present re-evaluations and, if required, the real-time

Attachment to GNRO*-2006/0001 4 Page 5 of 23 notifications do not have an explicit time requirement stated, it is expected by both parties thal such communications would be performed promptly. Entergy Transmission receives periodic training by ENS on the importance of ENS offsite power to Nuclear Safety and the necessity of prompt resolution of such issues.

ENS plans to implement an enhanced on-line monitoring system to be in service with Entergy Transmission during the summer of 2006. This system uses real-time models of the transmission grid and load flow analysis tools to determine if the transmission grid can meet the specific offsite power requirements for the ENS sites, while including the effects of a plant trip. This on-line enhanced system will include a notification time requirement if the requirements cannot be met.

(g) Describe the low switchyard voltage conditions that would initiate operation of plant degraded voltage protection.

ENS Response to Request 1(g):

GGNS receives its offsite power directly from the 500/115 kV Switchyards at all times. The Safety busses have 2 independent paths to the 500 kV Switchyard and a separate independent path to the 115 kV Switchyard.

At any time the 500 or 115 kV system voltage drops to allow the buss voltage on Division 1 or 2 to reach 90% nominal voltage for 9 seconds or 70% nominal voltage for 0.5 seconds (normal or LOCA), the busses will isolate from the Offsite Source. Division 3 buss will isolate from the Offsite Source when 88% of nominal voltage for 5 minutes and 4 seconds during non-LOCA scenarios (LOCA time is 4 seconds) or 73% nominal voltage for 2.3 seconds is met. The safety related busses will then connect to their associated Emergency Diesel Generator.

The minimum grid voltages are listed in ENS-DC-199.

Attachment to GNRO*-2006/00014 Page 6 of 23 NRC Request 2 - Use of criteria and methodologies to assess whether the offsite power system will become inoperable as a result of a trip of your NPP.

(a) Does your NPP's TSO use any analysis tools, an online analytical transmission system studies program, or other equivalent predictive methods to determine the grid conditions that would make the NPP offsite power system inoperable during various contingencies? If available to you, please provide a brief description of the analysis tool that is used by the TS0.

ENS Response to Request 2(a)

Yes., Entergy Transmission utilizes the PTI transmission analysis program as the analysis tool to predict ENS plant's offsite power voltages under various transmission grid contingencies. This transmission analysis program is one of the leading software programs used by electric utilities to perform detailed transmission grid studies. Using this program, Entergy Transmission performs detailed transmission studies for the next day, using daily cases representing that day of the month. These cases specifically consider the trip of each ENS unit and the application of design basis accident loads. These cases provide the advantage of the accuracy of a near term projection of expected loads and load flows, system generating unit status, expected transmission system elements in or out of service and specific site requirements, in a single analysis. These cases are also re-performed during the period of interest (i.e. present day) if previously identified specific contingencies occur or, if Entergy Transmission determines that system conditions have significantly changed during the period that could adversely affect the offsite power source post-trip voltage availability for any ENS unit. This allows the analysis to remain bounding if system conditions change. The results of these analyses are then compared to the post-trip voltage requirements for each respective ENS site. If the results indicate the potential for ENS site-specific requirements may not be met, Entergy Transmission then determines if these requirements can be met for the period of interest by making changes to transmission system configuration/operation. If Entergy Transmission determines that the requirements cannot be met or are not being met, then plant notification is required.

Per the unit-specific licensing basis for each ENS site and the requirements of ENS procedures, studies are performed on a periodicity as specified within the license basis to confirm that the offsite power system will remain operable following a trip of that unit. As a minimum, per ENS procedure DC-1 99, grid studies are performed at least every three years.

The! periodic analyses incorporate updated grid configurations and conditions, which are projected for a future period of interest and include such multiple contingencies as the ENS unit trip and design basis accident loading combined with significant other concurrent transmission/generation contingencies to confirm the adequacy of these sources to remain operable following such an event. This includes future projections for system load peaks and power transfers through the Entergy system, as determined by Entergy Transmission System Planning. Once submitted to ENS by Entergy Transmission, these analyses are reviewed by ENS Engineering personnel to confirm that the analyses provide the necessary assurance of the operability of the offsite power sources following a unit trip. This review is documented per the requirements of ENS procedure DC-1 99.

Attachment to GNRO-2006/00014 Page 7 of 23 (b) Does your NPP's TSO use an analysis tool as the basis for notifying the NPP licensee when such a condition is identified? If not, how does the TSO determine if conditions on the grid warrant NPP licensee notification?

ENS Response to Request 2(b):

Yes. Entergy Transmission uses the above analysis tools, in conjunction with procedures, as the basis for determining when conditions warrant ENS plant notification.

(c) If your TSO uses an analysis tool, would the analysis tool identify a condition in which a trip of the NPP would result in switchyard voltages (immediate and/or long-term) falling below TS nominal trip setpoint value requirements (including NPP licensees using allowable value in its TSs) and consequent actuation of plant degraded voltage protection? If not, discuss how such a condition would be identified on the grid.

ENS Response to Question 2(c):

Yes. As stated in 2(a) the day-ahead analysis tool would predict the voltage conditions that would result from an ENS plant trip well in advance of the actual condition and ENS plant notification would occur at that time.

(d) If your TSO uses an analysis tool, how frequently does the analysis tool program update'?

ENS Response to Request 2(d):

Entergy Transmission uses near-term advance (day-ahead) grid analysis specifically designed for ENS to notify plant sites of such a condition on the grid. These cases are also re-performed during the period of interest (i.e. present day) if previously identified specificS contingencies occur or, if Entergy Transmission determines that system conditions have significantly changed, during the period that could affect adversely the offsite power source post-trip voltage availability for any ENS unit. This allows the analysis to remain bounding if system conditions change.

(e) Provide details of analysis tool-identified contingency conditions that would trigger an NPP licensee notification from the TSO.

ENS Response to Request 2(e):

As stated in 2(a), Entergy Transmission provides notification to the ENS plant(s) if the predicted ENS plant post-trip voltage does not meet the minimum voltage values specified in ENS procedure DC-1 99 for that specific ENS plant. These post trip voltages are calculated by the PTI /PSSE software transmission analysis program, used by many utilities for extensive transmission studies. As stated in ENS procedure DC-201, if any transmission system element that is directly interconnected to the ENS plant switchyard/substation is lost, then the software analysis is re-performed to identify whether the post trip voltages are sl:ill acceptable. Additionally, if any transmission system contingency occurs that, in the opinion of Entergy Transmission may significantly impair the unit post-trip voltage performance for

Attachment to GNRO -2006/0001 4 Page 8 of 23 any ENS site, the software analysis is re-performed to identify whether the post trip voltage is still acceptable.

(f) If an interface agreement exists between the TSO and the NPP licensee, does it require that the NPP licensee be notified of periods when the TSO is unable to determine if offsite power voltage and capacity could be inadequate? If so, how does the NPP licensee determine that the offsite power would remain operable when such a notification is received?

ENS Response to Request 2(f):

Entergy Transmission uses near-term advance (day-ahead) grid analysis specifically designed to monitor ENS site grid conditions. If the near-term advance (day-ahead) monitoring process is determined by Entergy Transmission to be unavailable, ENS plant notification is required per ENS procedure DC-201 which is jointly reviewed and approved by Entergy Transmission. Per the requirements of ENS procedures, each affected ENS site will initiate a condition report for each daily case that results in an ENS notification by Entergy Transmission. This condition report will address Operability of the affected offsite power sources for such cases.

(g) After an unscheduled inadvertent trip of the NPP, are the resultant switchyard voltages verified by procedure to be bounded by the voltages predicted by the analysis tool?

ENS Response to Request 2(g):

Per the requirements of ENS procedure, DC-201, ENS Plant Engineering is required to coordinate with Entergy Transmission for a review of grid conditions that existed at the time of such an ENS unit trip to assess the accuracy of the analysis under known system conditions.

(h) If an analysis tool is not available to the NPP licensee's TSO, do you know if there are arny plans for the TSO to obtain one? If so, when?

ENS Response to Request 2(h):

Entergy Transmission uses an analysis tool; therefore this question is not applicable.

Attachment to GNRO-2006/00014 Page £ of 23 (i) If an analysis tool is not available, does your TSO perform periodic studies to verify that adequate offsite power capability, including adequate NPP post-trip switchyard voltages (immediate and/or long-term), will be available to the NPP licensee over the projected timeframe of the study?

(a) Are the key assumptions and parameters of these periodic studies translated into TSO guidance to ensure that the transmission system is operated within the bounds of the analyses?

(b) If the bounds of the analyses are exceeded, does this condition trigger the notification provisions discussed in question I above?

ENS Response to Request 2(i):

Entergy Transmission uses an analysis tool; therefore this question is not applicable.

a) If your TSO does not use, oryou do not have access to the results of an analysis tool, or your TSO does not perform and make available to you periodic studies that determine the adequacy of offsite power capability, please describe why you believe you comply with the provisions of GDC 17 as stated above, or describe what compensatory actions you intend to take to ensure that the offsite power system will be sufficiently reliable and remain operable with high probability following a trip of your NPP.

ENS Response to Request 20):

Entergy Transmission uses an analysis tool. ENS plants have access to the results of an analysis tool used by Entergy Transmission and Entergy Transmission makes periodic studies available to ENS to determine the adequacy of offsite power capability. Therefore, this question is not applicable.

NRC Request 3. - Use of criteria and methodologies to assess whether the NPP's offsite power system and safety-related components will remain operable when switchyard voltages are inadequate.

(a) If the TSO notifies the NPP operator that a trip of the NPP, or the loss of the most critical transmission line or the largest supply to the grid would result in switchyard voltages (immediate and/or long-term) below TS nominal trip setpoint value requirements (including NP.P licensees using allowable value in its TSs) and would actuate plant degraded voltage protection, is the NPP offsite power system declared inoperable under the plant TSs? If not, why not?

Entergy Note GL 2006-02 uses the term 'Operable' in several locations with regard to postulated offsite power conditions and for showing compliance with GDC 17. Operability is based on uthe capability of performing its specified safety function(s)." This is a current capability, not a.

postulated capability after other events not analyzed in the Safety Analysis Report.

Declaring offsite circuits inoperable due to projected switchyard voltages (except in combination with a plant trip) would require a plant shutdown per the TS. A premature plant

Attachment to GNRO*-2006/00014 Page 10 of 23 shutdown would contribute to the actual degraded voltage condition. Entering the TS required action statement potentially worsens the situation that the Generic Letter was intended to avoid. Therefore, as discussed in the following responses, Entergy applies offsite power system Operability with actual or immediate conditions consistent with other Limiting Conditions for Operation within the GGNS TS.

Additionally, GL 2006-02 also appears to equate meeting GDC 17 with the Operability of the offsite circuits. As stated in Regulatory Information Summary (RIS) 2005-20, Operability Determination Process, Appendix C.1, Relationship Between the General Design Criteria and the Technical Specifications, "The General Design Criteria (GDC) and the TS differ in that the GDC specify requirements for the design of nuclear power reactors, whereas the TS specify requirements for the operation of nuclear reactors." Therefore, failure to meet a General Design Criteria is considered a degraded or nonconforming condition and an operability determination is required to determine if the associated equipment is inoperable.

ENS Response to Request 3(a):

Per the requirements of ENS procedures, plant notification is required if the transmission grid cannot be maintained or is not within the values required by ENS procedure DC-1 99.

These values represent the acceptable ranges to demonstrate that a given offsite source! will remain capable of powering the required onsite loads under design basis conditions. Per the requirements of ENS procedures, if such notification is made, ENS will initiate a condition report and evaluate operability. If this evaluation demonstrates the inability to power required onsite loads from a given offsite source, that offsite source would be declared inoperable.

The ENS plant would declare the offsite power source inoperable for the situation where the loss; of an ENS unit would result in inadequate switchyard voltages that would actuate plant degraded voltage protection. The ENS plants do not declare the offsite power inoperable for the situation where the loss of the most critical transmission line or the largest supply to the grid would result in inadequate switchyard voltages. The loss of the facility would have to already occur before any action would be taken. If predicting a most critical line loss or loss of the largest supply would predict a voltage below the degraded voltage protection setpoint, the ENS plant would take preparatory actions without entering a Limiting Condition for Operation (LCO), since ENS plants do not enter into an LCO until an event happens.

(b) If onsite safety-related equipment (e.g., emergency diesel generators or safety-related motors) is lost when subjected to a double sequencing (LOCA with delayed LOOP event) as a result of the anticipated system performance and is incapable of performing its safety functions as a result of responding to an emergency actuation signal during this condition, is the equipment considered inoperable? If not, why not?

ENS Response to Request 3(b):

If a SSC is lost or determined to be unable to perform its design basis safety function, then it is declared inoperable and actions are taken (as governed by plant Technical Specifications). However, double sequencing is not a design basis condition.

Attachment to GNRO*-2006/00014 Page 11 of 23 (c) Describe your evaluation of onsite safety-related equipment to determine whether it will operate as designed during the condition described in question 3(b).

ENS Response to Request 3(c):

As stated in our above response 3(b) this double sequencing is not a design basis analyzed event.

(d) If the NPP licensee is notified by the TSO of other grid conditions that may impair the capability or availability of offsite power, are any plant TS action statements entered? If so, please identify them.

ENS Response to Request 3(d):

As discussed in response to NRC Request 3(a), plant notification is required, if the transmission grid cannot be maintained or is not within the values required by ENS procedures. If a required offsite source is declared inoperable, then the appropriate Technical Specification LCO Action Statement(s) would be entered. However, GGNS Technical Specification LCOs are not entered for grid conditions that might occur (i.e.,

tornados, forest fires, severe weather events).

(e) If you believe your plant TSs do not require you to declare your offsite power system or saf9ty-related equipment inoperable in any of these circumstances, explain why you believe you comply with the provisions of GDC 17 and your plant TSs, or describe what compensatory actions you intend to take to ensure that the offsite power system and safety-related components will remain operable when switchyard voltages are inadequate.

ENS Response to Request 3(e):

ENS believes that certain cases could result in the affected equipment being declared inoperable as described in response to NRC Requests 3(a) and 3(b). Therefore, this question is not applicable to ENS.

(f) Describe if and how NPP operators are trained and tested on the compensatory actions mentioned in your answers to questions 3(a) through (e).

ENS Response to Request 3(f):

ENS did not specify any "compensatory" actions in the ENS responses to NRC Request 3(a) through 3(e). All actions described by ENS within these responses are governed by plant procedures. Therefore, there are no applicable "compensatory" actions stated for ENS operators to be trained or tested on.

Attachment to GNRO-.2006/00014 Page 12 of 23 NRC Request 4 - Use of criteria and methodologies to assess whether the offsite power system will remain operable following a trip of your NPP.

(a) Do the NPP operators have any guidance orprocedures in plant TS bases sections, the final safety analysis report, or plant procedures regarding situations in which the condition of plant-controlled or-monitored equipment (e.g., voltage regulators, auto tap changing transformers, capacitors, static VAR compensators, main generator voltage regulators) can adversely affect the operability of the NPP offsite power system? If so, describe how the operators are trained and tested on the guidance and procedures.

ENS Response to Request 4(a):

As stated in NRC Request 1(C), GGNS has procedural triggers to notify the TSO prior to placing the Generator Voltage Regulator in manual per "Main Generator and Auxiliaries" SOL. No transformers connected to the offsite source have load tap changers, and GGNS does not have any voltage regulators, capacitors, or static VAR compensators.

Entergy Transmission has also incorporated the allowable voltage ranges as specified in ENS' procedures into Entergy Transmission Energy Management System (EMS) alarms for the transmission system operators. These alarms provide an independent means to detect adverse effects on ENS offsite power sources due to main generator voltage regulator deviations, if such deviations are of sufficient magnitude to cause the offsite source to be!

outside of the allowable range as determined by ENS procedures, when the turbine generator is connected to the grid (i.e. before the postulated DBA).

As discussed in the response to Request 1(d), GGNS operators are trained in normal, off-normal, and emergency operations including the potential for impact from loss of both onsite and offsite power sources.

(b) If your TS bases sections, the final safety analysis report, and plant procedures do not provide guidance regarding situations in which the condition of plant-controlled or -

monitored equipment can adversely affect the operability of the NPP offsite power system, explain why you believe you comply with the provisions of GDC 17 and the plant TSs, or describe what actions you intend to take to provide such guidance or procedures.

ENS Response to Request 4(b):

The above listed documents support determination of operability of the offsite power system. Therefore, compliance with GDC 17 and plant Tech Specs is assured.

Use of NPP licensee/TSO protocols and analysis tool by TSOs to assist NPP licensees in monitoring grid conditions for consideration in maintenance risk assessments The Maintenance Rule (10 CFR 50. 65(a)(4)) requires that licensees assess and manage the increase in risk that may result from proposed maintenance activities before performing them.

Attachment to GNRO*2006/00014 Page 13 of 23 NRC Request 5 Performance of grid reliability evaluations as part of the maintenance risk assessments required by 10 CFR 50.65(a)(4).

(a) Is a quantitative or qualitative grid reliability evaluation performed at your NPP as part of the maintenance risk assessment required by 10 CFR 50. 65(a)(4) before performing grid-risk-sensitive maintenance activities? This includes surveillances, post-maintenance testing, and preventive and corrective maintenance that could increase the probability of a plant trip or LOOP or impact LOOP or SBO coping capability, for example, before taking a risk-significant piece of equipment (such as an EDG, a battery, a steam-driven pump, an alternate AC power source) out-of-service?

ENS Response to Request 5(a):

Coordination of both grid and plant major maintenance to minimize plant risk is performed by the ENS and Transmission functions, although the primary responsibility and oversight functions for these actions is performed by the ENS site organization. The site work control processes factor in scheduled switchyard activities as part of the risk evaluation process, as well as any emergent items. The site's "Switchyard and Transmission Interface Agreement",

the site's specific implementing procedure for these interfaces Management Standard 21 (MS,-21), and NMM procedure PL-158, uSwitchyard and Transmission Interface Requirements" are used to define responsibilities between the Transmission and ENS organizations for this purpose.

As stated in 10CFR50.65 (a)(4), 'Before performing maintenance activities (including but not limited to surveillance, post-maintenance testing, and corrective and preventive maintenance), the licensee shall assess and manage the increase in risk that may result from the proposed maintenance activities. The scope of the assessment may be limited 1:o structures, systems, and components that a risk-informed evaluation process has shown to be significant to public health and safety".

GGNS Administrative Procedure "Risk Assessment of Maintenance Activities", provides procedural guidance to meet IOCFR50.65 (a)(4) in assessing the overall impact of plant maintenance on plant risk, and manage the risk associated with equipment unavailability.

GGNS includes all major switchyard components and incoming transmission lines to the switchyard in the EOOS (Equipment Out of Service) risk model. Per the Switchyard Interface Agreement that was signed in 1999, Entergy Mississippi will coordinate activities directly affecting the off-site power supply to GGNS. These activities include, but are nol:

limited to:

a. Removing from service any transmission line terminating in the Switchyard
b. Breaker switching which can affect power supply to GGNS [e.g., switching of lines identified in item (a) above]
c. Maintenance activities that can affect power supply to GGNS.

(b) Is grid status monitored by some means for the duration of the grid-risk-sensitive maintenance to confirm the continued validity of the risk assessment and is risk reassessed when warranted? If not, how is the risk assessed during grid-risk-sensitive maintenance?

Attachment to GNRO-2006/00014, Page 14 of 23 ENS Response to Request 5(b):

Entergy Transmission grid status is monitored by Entergy Transmission as described in the ENS response to question 1.

Yes. NUMARC 93-01 does not define "grid-risk-sensitive maintenance", so there is no unique guidance for such activities. The following guidance is included in Section 11.3.2.8:

Emergent conditions may result in the need for action prior to conducting an assessment, or could change the conditions of a previously performed assessment. Examples include plant configuration or mode changes, additional SSCs out of service due to failures, or significant changes in external conditions (weather, offsite power availability). The following guidance applies to this situation:

  • The safety assessment should be performed (or re-evaluated) to address the changed plant conditions on a reasonable schedule commensurate with the safety significance of the condition. Based on the results of the assessment, ongoing or planned maintenance activities may need to be suspended or re-scheduled, and SSCs may need to be returned to service.
  • Performance (or re-evaluation) of the assessment should not interfere with, or delay, the operator and/or maintenance crew from taking timely actions to restore the equipment to service or take compensatory actions.
  • If the plant configuration is restored prior to conducting or re-evaluating the assessment, the assessment need not be conducted, or re-evaluated if already performed.

In addition, GGNS Tech Specs require the offsite source to be assessed, in part by contacting the TSO, every 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> during EDG outages or times when onsite or offsite AC power requirements are not met. This assessment is performed per surveillance procedure that confirms reliability of onsite and offsite power systems. GGNS Licensed Operators perform this surveillance every 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> when the LCO Action Statement has been entered.

(c) Is there a significant variation in the stress on the grid in the vicinity of your NPP site caused by seasonal loads or maintenance activities associated with critical transmission elements?

Is there a seasonal variation (or the potential for a seasonal variation) in the LOOP frequency in the local transmission region? If the answer to either question is yes, discuss the time of year when the variations occur and their magnitude.

ENS Response to Request 5(c):

No. Within the context of the definition provided for 'Grid Stress or a Stressed Grid" for this generic letter, Entergy Transmission system loads typically reach annual maximums within the summer months, however Entergy Transmission System Operators continually account for such loads when balancing these loads with available generation and power import/export and load flow capability.

Attachment to GNRO-2006/00014 Page 15 of 23 Major transmission lines near the ENS site that might affect the viability of the Offsite Power System and/or the nuclear generation, have their maintenance outages scheduled away from the summer or peak load times or during plant outages to avoid grid stress in the vicinity of the plant. GGNS has not experienced a total loss of offsite power (LOOP) caused by grid.

Enlergy Transmission maintains grid stability with an automatic load shedding system. This system sheds up to 30% of the system load in three successive increments of degrading grid frequency. Entergy Transmission also maintains a stable grid by shedding selective!

load if necessary after potential re-dispatch solutions are exhausted to ensure continued grid reliability. Thus, two goals exist: Grid Reliability and Service Reliability. The residential and commercial customers may experience electrical outages at the distribution level while the grid is unaffected. Hence, offsite power continues to be available to ENS plants.

Additionally, EPRI TR-101 1759, dated December 2005, has shown that there is no statistically significant seasonal-regional variation in recorded LOOP events from 1997 to 200)4.

(d) Are known time-related variations in the probability of a LOOP at yourplant site considered in the grid-risk-sensitive maintenance evaluation? If not, what is your basis for not considering them?

ENS Response to Request 5(d):

Yes. The GGNS online risk model [Equipment Out Of Service] is based on the guidance of NUMARC 93-01, which states that [risk] assessments should consider the impact of maintenance activities on availability of electrical power. Specifically, the assessments for maintenance activities involving the switchyard and transformer yard should consider thE, impact on offsite power availability. The GGNS EOOS model incorporates the ability to adjust the frequency of LOOP probability due to adverse weather conditions such as severe weather and potential tornado conditions. In addition, the frequency of LOOP probability can also be adjusted based on the work in the switchyard.

(e) Do you have contacts with the TSO to determine current and anticipated grid conditions as part of the grid reliability evaluation performed before conducting grid-risk-sensitive maintenance activities?

ENS Response to Request 5(e):

Yes, ENS plant contacts Entergy Transmission at any time necessary, using communications protocols provided in ENS procedures.

As discussed in the response to Request 5(a), the GGNS "Switchyard Work Control" Standard (MS-21) provides detailed scheduling and coordination requirements associated with work in the switchyard. This procedure includes a list of maintenance exceptions that have been evaluated to have no impact on the plant. These activities typically do not require impact statements. For all other activities, component and plant impact statements are prepared to assess the possible impact on the plant. These activities, once approved,

Attachment to GNRO -2006/00014 Page 16 of 23 are also placed on the integrated plant schedules. These processes assure that the work is thoroughly evaluated for its impact on the plant.

(f) Describe any formal agreement or protocol that you have with your TSO to assure that you are promptly alerted to a worsening grid condition that may emerge during a maintenance activity.

ENS Response to Request 5(f):

As discussed in the Response to NRC Request 1(a), ENS plants utilize a combination of formal agreements, procedures, protocols and/or actions to have Entergy Transmission provide notification to each ENS plant if the predicted post-trip voltage does not meet the minimum value(s) specified in ENS procedures. This is a ENS controlled procedure that is jointly reviewed by both Entergy Transmission and ENS. It contains the specifics pertaining to preferred offsite sources, including acceptable voltage, frequency and power delivery requirements for each ENS plant.

If analysis results indicate the potential for ENS site-specific requirements are not being met, Entergy Transmission determines if these requirements can be met for the period of interest by making changes to transmission system configuration/operation. If Entergy Transmission determines that the requirements cannot be met or are not being met, then ENS plant notification is required. Per the requirements of ENS-DC-201, if such notification is made, ENS will initiate a condition report and evaluate operability. Thus, ENS plant operations will be made aware of worsening grid conditions that could result in the inability to meet the ENS site post-trip design basis accident load requirements from the offsite power source.

(g) Do you contact your TSO periodically for the duration of the grid-risk-sensitive maintenance activities?

ENS Response to Request 6(g):

Yes. GGNS Tech Spec 3.8.1 requires the offsite source to be assessed, in part by contacting the TSO, every 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> during EDG outages or times when onsite or offsite AC power requirements are not met. This assessment is performed per surveillance procedure that confirms reliability of onsite and offsite power systems. GGNS Licensed Operators perform this surveillance every 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> when the LCO Action Statement has been entered.

(h) If you have a formal agreement or protocol with your TSO, describe how NPP operators and maintenance personnel are trained and tested on this formal agreement or protocol.

ENS Response to Request 5(h):

GGNS operators and maintenance personnel receive training, as described in the answer to question 1(d), to ensure their understanding of the function and operation of the GGNS offsite electrical distribution system and components. This training includes the GGNS

'Switchyard and Transmission Interface Agreement" as well as the GGNS "Switchyard Work Control" Standard, MS-21.

Attachment to GNRO*-2006/00014 Page 17 of 23 (i) If your grid reliability evaluation, performed as part of the maintenance risk assessment required by 10 CFR 50.65(a) (4), does not consider or rely on some arrangement for communication with the TSO, explain why you believe you comply with 10 CFR 50.65(a)(4).

ENS Response to Request 5(i):

As previously discussed, risk sensitive maintenance activities are communicated with Entergy Transmission and changes in risk during the maintenance evolution are similarly communicated as required. Therefore, this question is not applicable to GGNS.

U) If risk is not assessed (when warranted) based on continuing communication with the TSC throughout the duration of grid-risk-sensitive maintenance activities, explain why you believe you have effectively implemented the relevant provisions of the endorsed industry guidance associated with the maintenance rule.

ENS Response to Request 5(j):

As previously discussed, risk sensitive maintenance activities are communicated with Entergy Transmission and changes in risk during the maintenance evolution are similarly communicated as required. Therefore, this question is not applicable to GGNS.

(k) Wt)h respect to questions 5(i) and 50), you may, as an alternative, describe what actions you intend to take to ensure that the increase in risk that may result from proposed grid-risk-sensitive activities is assessed before and during grid-risk-sensitive maintenance activities, respectively.

ENS Response to Request 5(k):

Since GGNS maintains communication with offsite Entergy Transmission for risk-sensitive maintenance, no alternative communications are considered necessary.

NRC Request 6. Use of risk assessment results, including the results of grid reliability evaluations, in managing maintenance risk, as required by 10 CFR 50.65(a)(4).

(a) Does the TSO coordinate transmission system maintenance activities that can have an impact on the NPP operation with the NPP operator?

ENS Response to Request 6(a):

Entergy Transmission maintenance is classified as either planned maintenance or emergent maintenance. Additionally, ENS has an added tool where planned Entergy Transmission system outages, that are relevant to ENS sites, are posted on an Entergy Intranet web page.

Planned maintenance activities with the potential to affect ENS operation are incorporated into the near-term advance (day-ahead) grid analysis specifically for ENS to use in determining the status of the Entergy Transmission grid, particularly near ENS plants.

Attachment to GNRO..2006/00014 Page 18 of 23 Emergent maintenance activities and planned maintenance activities with the potential to affect ENS operation are required to be coordinated with the affected ENS site per the formal agreements indicated in this response for each respective ENS site.

(b) Do you coordinate NPP maintenance activities that can have an impact on the transmission system with the TSO?

ENS Response to Request 6(b):

Scheduled and unscheduled ENS unit outages and ENS unit power reductions are communicated between ENS units, Entergy System Planning and Operation and Entergy Transmission for transmission security purposes. Also, see response to Request 5(a).

(c) Do you consider and implement, if warranted, the rescheduling of grid-risk-sensitive maintenance activities (activities that could (i) increase the likelihood of a plant trip, (ii) increase LOOP probability, or (iii) reduce LOOP or SBO coping capability) under existing, imminent, or worsening degraded grid reliability conditions?

ENS Response to Request 6(c):

Yes. Degraded grid reliability conditions would require a condition report to be initiated and an Dperability determination to be performed. Grid-risk-sensitive maintenance would be rescheduled to such a time that the grid has recovered and the EOOS risk was acceptalle to the plant.

GGNS Management Standard 21 designates the responsibilities of the Point of Contact (PC)C) who is responsible for coordination of grid maintenance and testing. The POC facilitates preparation and review of these impact statements with assistance from GGN';

Operations. These activities, once approved, are placed on the integrated plant schedules.

These processes assure that the work is thoroughly evaluated for its impact on the plant. In addition, by adding the activities to the integrated plant schedules, they are evaluated to assure there are no conflicts with other in-house activities, thus maintaining adequate defense-in-depth. GGNS Operations personnel are involved, via the impact statements and integrated schedule, to insure that grid activities are coordinated with in-house activities so that adequate electrical diversity is maintained at all times. The POC works closely with Operations and Entergy Transmission in communication and coordination of these activities.

Note: Per the GGNS Switchyard and Transmission Interface Agreement, GGNS has maintenance responsibility (including necessary repair or replacement) for the GGNS support transformers, main output transformers, and any other equipment to the point of the defined power transmission interface. Based on this agreement, GGNS currently has maintenance responsibility for the Service Transformers, as well as, the 34.5 kV Switchyard.

All Dther equipment located in the switchyard is maintained by Entergy Transmission.

Attachment to GNRO*2006/00014 Page 19 of 23 (d) If there is an overriding need to perform grid-risk-sensitive maintenance activities under existing or imminent conditions of degraded grid reliability, or continue grid-risk-sensitive maintenance when grid conditions worsen, do you implement appropriate risk management actions? If so, describe the actions that you would take. (These actions could include alternate equipment protection and compensatory measures to limit or minimize risk.)

ENS Response to Request 6(d):

Yes, when time allows an assessment of risk is preformed prior to switchyard related maintenance [MS-21]. As discussed in the response to Request 5(d), GGNS has clear guidance on ensuring the risk is minimized where grid sensitive maintenance could occur.

However, as discussed in the response to 5(b), emergent conditions may result in the need for action prior to conduct of the assessment, or could change the conditions of a previously performed assessment. Examples include plant configuration or mode changes, additional SS-s out of service due to failures, or significant changes in external conditions (weather, offsite power availability). Irrespective, GGNS applies the most appropriate risk and deterministic tools available to ensure plant and grid protection. If maintenance must be performed during grid-sensitive periods, the in-plant risk directive limits all other maintenance activities that would worsen the risk to the plant or the grid. If additional actions are needed, then compensatory measures will be taken to the extent practical. All grid-sensitive maintenance requires control room management approval prior to work being performed.

(e) Describe the actions associated with questions 6(a) through 6(d) above that would be taken, state whether each action is governed by documented procedures and identify the procedures, and explain why these actions are effective and will be consistently accomplished.

ENS Response to Request 6(e):

All actions described in the responses to Requests 6(a) through 6(d), are directed by either Entergy Transmission agreements and/or GGNS specific procedures. These agreements and procedures are not new to Entergy Transmission or GGNS and have been exercised on a routine basis. GGNS believes that the specific requirements of the procedures discussed are effective and repeatable to ensure grid-sensitive maintenance is reduced to a minimum.

(f) Describe how NPP operators and maintenance personnel are trained and tested to assure they can accomplish the actions described in your answers to question 6(e).

ENS Response to Request 6(f):

As discussed in the answer to question 5(h) above, training is provided on a GGNS specific management standard, which provides controls for switchyard activities. The procedure assigns responsibilities and establishes interfaces for coordination of scheduled and unscheduled maintenance. Risk factors and impacts of specific work activities are identified and evaluated in accordance with the guidance of this procedure and a decision making process is provided to determine if specific maintenance activities are to be allowed.

Attachment to GNRO -2006/00014 Page 20 of 23 (g) If there is no effective coordination between the NPP operator and the TSO regarding transmission system maintenance or NPP maintenance activities, please explain why you believe you comply with the provisions of 10 CFR 50.65(a)(4).

ENS Response to Request 6(g):

ENS believes that there is effective coordination between ENS operators and Entergy Transmission maintenance activities; therefore, this question is not applicable.

(h) If you do not consider and effectively implement appropriate risk management actions during the conditions described above, explain why you believe you effectively addressed the relevant provisions of the associated NRC-endorsed industry guidance.

ENS Response to Request 6(h):

ENS believes that there is effective coordination between ENS operators and Entergy Transmission maintenance activities; therefore, this question is not applicable.

(i) You may, as an alternative to questions 6(g) and 6(h) describe what actions you intend to take to ensure that the increase in risk that may result from grid-risk-sensitive maintenance activities is managed in accordance with 10 CFR 50.65(a)(4).

ENS Response to Request 6(i):

No alternate actions are considered necessary and therefore, this question is not applicable to GGNS.

Offsite power restoration procedures in accordance with 10 CFR 50.63 as developed in Section 2 of RG 1.155*

Pursuant to 10 CFR 50.63, the NRC requires that each NPP licensed to operate be able to withstand an SBO for a specified duration and recover from the SBO. NRC RG 1.155 gives licensees guidance on developing their approaches for complying with 10 CFR 50.63.

NRC Request 7. Procedures for identifying local power sources that could be made available to resupply your plant following a LOOP event.

Note: Section 2, Offsite Power," of RG 1.155 (ADAMS Accession No. MLOO3740034) states:

Procedures should include the actions necessary to restore offsite power and use nearby power sources when offsite power is unavailable. As a minimum, the following potential causes for loss of offsite power should be considered:

- Grid undervoltage and collapse

- Weather-induced power loss

- Preferred power distribution system faults that could result in the loss of normal power to essential switchgear buses

Attachment to GNRO*-2006/00014 Page 21 of 23 (a) Briefly describe any agreement made with the TSO to identify local power sources that could be made available to resupply power to your plant following a LOOP event.

ENS Response to Request 7(a):

Formal agreements previously described between ENS plants and Entergy Transmission dictate priority restoration of offsite power to these units. Entergy Transmission maintains restoration plans for the Entergy Transmission system:The plans include the use of system black-start capable generation, where available. Such restoration plans consider all available Entergy Transmission restoration options, including but not limited to use of other local-area generation for re-supply of ENS plants. Restoration of off site power to ENS facilities has the highest restoration priority. Grid operators train on this procedure annually per NERC training requirements. Entergy Transmission is not responsible for the use of any onsite generation sources under site control.

(b) Are your NPP operators trained and tested on identifying and using local power sources to resupply your plant following a LOOP event? If so, describe how.

ENS Response to Request 7(b):

ENS operators are responsible for the use of ENS onsite resources under ENS control, only.

Entergy Transmission is responsible for the use of Entergy system resources, including, but not limited to, use of local-area (offsite) generation to re-supply ENS plants following a LOOP event and such re-supply is designated as a priority activity within Entergy Transmission restoration plans, as previously described.

GGNS has an off-normal event procedure, "Loss of AC Power", which covers both LOOP and station blackout conditions. The GGNS Emergency Diesel Generator SOI procedure provides guidance for normal and abnormal EDG operation.

(c) If you have not established an agreement with your plant's TSO to identify local power sources that could be made available to resupplypower to yourplant following a LOOP event, explain why you believe you comply with the provisions of 10 CFR 50.63, or desc,-ibe what actions you intend to take to establish compliance.

ENS Response to Request 7(c):

ENS has agreements previously described between ENS plants and Entergy Transmission that dictate priority restoration of offsite power to ENS units. Entergy Transmission maintains restoration plans for the Entergy Transmission system. The plans include the use of system black-start capable generation, where available. Such restoration plans consider all available Entergy Transmission restoration options, including but not limited to use of other (offsite) local-area generation for re-supply of ENS plants. Therefore, this question is not applicable.

Attachment to GNRO-2006/0001 4 Page 22 of 23 Losses of offsite power caused by grid failures at a frequency of equal to or greater than once in 20 site.-years in accordance with Table 4 of Regulatory Guide 1.155 for complying with 10 CFR 50.63.

Pursuant to 10 CFR 50.63, the NRC requires that each NPP licensed to operate be able to withstand an SBO for a specified duration and recover from the SBO. NRC RG 1.155 gives licensees guidance on developing their approaches for complying with 10 CFR 50.63.

NRC Request 8. Maintaining SBO coping capabilities in accordance with 10 CFR 50.63.

(a) Has your NPP experienced a total LOOP caused by grid failure since the plant's coping duration was initially determined under 10 CFR 50.63?

ENS Response to Request 8(a):

GGNS has not experienced a total loss of offsite power or a grid failure that would have initiated a station blackout.

(b) If so, have you reevaluated the NPP using the guidance in Table 4 of RG 1.155 to determine if your NPP should be assigned to the P3 offsite power design characteristic group?

ENS Response to Request 8(b):

This question is not applicable to GGNS.

(c) If so, what were the results of this reevaluation, and did the initially determined coping duration for the NPP need to be adjusted?

ENS Response to Request 8(c):

This question is not applicable to GGNS.

(d) If your NPP has experienced a total LOOP caused by grid failure since the plant's coping duration was initially determined under 10 CFR 50.63 and has not been reevaluated using the guidance in Table 4 of RG 1.155, explain why you believe you comply with the provisions of 10 CFR 50.63 as stated above, or describe what actions you intend to take to ensure that the NPP maintains its SBO coping capabilities in accordance with 10 CFR 50.63.

ENS Response to Request 8(d):

This question is not applicable to GGNS.

Attachment to GNRO-2006/00014 Page 23 of 23 Actions to ensure compliance NRC Request 9. If you determine that any action is warranted to bring your NPP into compliance with NRC regulatory requirements, including TSs, GDC 17, 10 CFR 50.65(a) (4),

10 CFR 50.63, 10 CFR 55.59 or 10 CFR 50.120, describe the schedule for implementing it.

ENS Response to Request 9 Entergy believes that GGNS is in compliance with NRC regulatory requirements and no further actions are necessary.

Text

Entergy Operatio is, Inc.

'Entergy Waterloo Rd.

P.O. Box 756 Port Gibson, MS 39150 Tel 601 437 6470 Michael A. Krupa Director Nuclear Safety Assurance GNRO-2006/00014 April 3, 2006 U.S. Nuclear Regulatory Commission Washington, DC 20555 Attention: Document Control Desk

SUBJECT:

Response to Generic Letter 2006-02, Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power Plant Name Grand Gulf Nuclear Station Docket No. 50-416 License No. NPF-29

REFERENCE:

NRC letter dated February 1, 2006, Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power (GNRI-2006/00005)

Dear Sir or Madam:

Per Reference 1, the NRC issued Generic Letter (GL) 2006-02 to request information for determining compliance with regulatory requirements governing electric power sources. Specifically, the NRC is requesting information regarding (1) use of protocols between the nuclear power plant (NPP) and the transmission system operator (TSO), independent system operator (ISO), or reliability coordinator/authority (RC/RA) including transmission load flow analysis tools, (2) use of NPP/TSO protocols and analysis tools by TSOs to assist NPPs in monitoring grid conditions for consideration in maintenance risk assessments; (3) offsite power restoration procedures in accordance with Section 2 of NRC Regulatory Guide (RG) 1.155, "Station Blackout;" and, (4) losses of offsite power caused by grid failures at a frequency equal to or greater than once in 20 site-years in accordance with RG 1.155. The requested information is being made under the requirements of 10 CFR 50.54(f).

GNRO-2006/00014 Page 2 of 2 The Grand Gulf Nuclear Station (GGNS) response to the requested information in GL 2006-02 is contained in attachment to this submittal. Responses to questions associated with the Entergy Transmission groups are outside the direct control of GGNS. However, they have been confirmed by the Transmission Organizations to the extent practical. Entergy is not making any commitments as a result of our response to this letter. If you have any questions or require additional information, please contact Eddie Hester at 601-437-6913.

I declare under penalty of perjury that the foregoing is true and correct.

Executed on April 3, 2006.

Sincerely, CAB/wba

Attachment:

Response to Generic Letter 2006-02 for GGNS cc: NRC Senior Resident Inspector Grand Gulf Nuclear Station Port Gibson, MS 39150 U. S. Nuclear Regulatory Commission ATTN: Dr. Bruce S. Mallet (w/2)

Regional Administrator, Region IV 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-4005 U. S. Nuclear Regulatory Commission ATTN: Mr. Bhalchandra Vaidya, NRR/DORL (w/2)

ATTN: ADDRESSEE ONLY ATTN: U. S. Postal Delivery Address Only Mail Stop OWFN/O-7D1A Washington, DC 20555-0001 Mr. D. E. Levanway (Wise Carter)

Mr. L. J. Smith (Wise Carter)

Mr. N. S. Reynolds Mr. J. N. Compton

Attachment to GNRO-2006/0001 4 Response to Generic Letter 2006-02 for GGNS

Attachment to GNRO -2006/00014 Page 1 of 23 Response to Generic Letter 2006-02 for GGNS Requested Information Use of protocols between the NPP licensee and the TSO, ISO, or RC/RA and the use of analysis tools by TSOs to assist NPP licensee in monitoring grid conditions to determine tho operability of offsite power systems under plant TS.

GDC 17, 10 CFR Part 50, Appendix A, requires that licensees minimize the probability of the loss of power from the transmission network given a loss of the power generated by the nuclear power unit(s).

NRC Request I - Use of protocols between the NPP licensee and the TSO, ISO, or RC/RA to assist the NPP licensee in monitoring grid conditions to determine the operability of offsile power systems under plant TS.

(a) Do you have a formal agreement orprotocol with your TSO?

ENS Response to Request 1(a):

Entergy Nuclear South (ENS) plants [i.e., Grand Gulf Nuclear Station, River Bend Nuclear Station, Waterford Steam Electric Station, Unit 3 (Waterford 3) and Arkansas Nuclear Orie]

utilize a combination of formal agreements, procedures, protocols and/or actions to have Entergy Transmission provide notification to each ENS plant if the predicted post-trip voltage does not meet the minimum value(s) specified in ENS procedure' ENS-DC-199, 'Offsite Power Supply Design Requirements". This procedure is an ENS controlled procedure that is jointly reviewed by both Entergy Transmission and ENS. It contains the specifics pertaining to preferred offsite sources, including acceptable voltage, frequency and power delivery requirements for each ENS plant. The formal agreement for GGNS is referred to as the Grand Gulf Nuclear Station Switchyard and Transmission Interface Agreement.

The formal agreements for each site provide a general framework for the establishment of procedures and processes that are deemed by each agreement to be of importance to the safe operation of the respective ENS site. Each agreement contains the requirement that respective ENS site be provided with an assured source of offsite power in accordance with procedures to be agreed upon by the respective ENS site and the Entergy Transmission organization.

The monitoring process used by Entergy Transmission to predict ENS plant post-trip voltages is contained in ENS procedure ENS-DC-201, 'ENS Transmission Grid Monitoring".

This procedure is an ENS controlled procedure that is jointly reviewed by both Entergy Transmission and ENS. This procedure contains the Transmission/ENS Off-Line Post Trip Voltage Analysis & Monitoring Process. This process is implemented by Entergy Traismission Procedures.

1 Compliance with GDC 17, as documented in the license basis and plant Technical Specifications for Entergy Nuclear South (ENS) plants, is not predicated on such agreements. Additionally, ENS plants are considered regulated, not de-regulated and ENS plants are part of vertically-integrated, Entergy Corporation utility operations.

Attachment to GNROQ-2006/00014 Page 2 of 23 These procedures collectively implement near-term advance (day-ahead) grid analysis specifically for ENS to use in determining the status of the Entergy Transmission grid, particularly near ENS plants. This monitoring uses PTI/PSSE analysis, performed for the neyt day, using daily cases representing that day of the month. These cases specifically consider the trip of each ENS unit and the application of design basis accident loads. These cases are also re-performed during the period of interest if previously identified specific contingencies occur or, if Entergy Transmission determines that system conditions have significantly changed during the period that could affect the offsite power source post-trip voltage availability for any ENS unit. This allows the analysis to remain bounding if system conditions change. The results of these analyses are then compared to the specific ENS' unit post-trip voltage requirements for each respective ENS site. If the results indicate the potential for ENS site specific requirements would not be met, Entergy Transmission determines if these requirements can be met for the period of interest by making changes to transmission system configuration/operation. If Entergy Transmission determines that the requirements cannot be met or are not being met, then notification to the affected plant is required. ENS plant compliance with GDC 17, as documented in the license basis and plant Technical Specifications for each ENS plant, is not predicated on such an agreement.

Compliance with GDC 17 as stated in NUREG 0800 is based on "each [offsite power] circuit has been sized with sufficient capacity to supply all connected loads" and "results of the grid stability analysis indicated that loss of the largest generating capacity being supplied to the grid, loss of largest load from the grid, loss of the most critical transmission line, or loss cf the unit itself will not cause grid instability." As confirmed in the definitions of Generic Letter 20C'6-02, for a given disturbance stability equates to maintaining a state of equilibrium, and not a specific voltage. However, Entergy Transmission is presently required by the applicable Regional Coordinating Council to perform periodic studies to ensure compliance with their grid stability criteria and planning standards. This criteria includes limits on the maximum allowable voltage deviation and duration of transients for a given grid disturbance.

This provides additional ENS plant offsite power (stability) assurance in addition to that required by GDC 17 for stability considerations.

(b) Describe any grid conditions that would trigger a notification from the TSO to the NPP licensee and if there is a time period required for the notification.

ENS Response to Request 1(b):

The! process described for the Entergy response to NRC Request 1(a) is a look-ahead analysis that covers the following day. As such, this process does not incorporate an explicit time period requirement for notification, because the period of interest is in the future (next day). This allows Entergy Transmission to evaluate the projected system conditions and provides an opportunity to possibly prevent the actual occurrence of grid conditions that would not meet ENS requirements. If, following such evaluations for the next day, or, following the occurrence of specific predetermined grid contingencies reevaluated during the present period, there are indications that ENS site specific requirements will not be met cr are not being met, notification to the affected plants is required. Likewise, should actual real-time conditions occur that are outside of ENS requirements, without projecting additional contingencies, then notification is also provided. While the present day re-evaluation and, if required, the real-time notifications do not have an explicit time requirement stated, it is expected by both parties that such communications would be performed commensurate with the severity of the situation. ENS procedures require

Attachment to GNRO-2006/0001 4 Page 3 of 23 Eniergy Transmission to receive periodic training by ENS on the importance of ENS offsite power to nuclear safety and the necessity of prompt resolution of such issues.

(c) Describe any grid conditions that would cause the NPP licensee to contact the TSO.

Describe the procedures associated with such a communication. If you do not have procedures, describe how you assess grid conditions that may cause the NPP licensee lb contact the TSO.

ENS Response to Request 1(c):

Grid conditions and status are the primary responsibility of Entergy Transmission for ENS plants. The observable parameters for the ENS plants include only voltage and frequenly, generator reactive output, breaker status, status of certain lines, and certain switchyard alarm points.

The Entergy Transmission organization has procedures and practices as indicated in the Entergy response to NRC Request 1(a), that require plant notification in the event that actual or projected ENS specific grid conditions are not met. As such, ENS does not explicitly dictate that the individual sites perform periodic inquiries of the Entergy Transmission organization for determination of grid status. However, this does not preclude ENS from performing a grid status check with Entergy Transmission if ENS deems such information to be beneficial in a given situation, using communications protocols provided in ENS procedures. Additionally, if the daily monitoring process is determined by Entergy Transmission to be unavailable, plant notification is required per ENS procedure DC-201, which is jointly reviewed by Entergy Transmission.

GG NS has procedural triggers for contacting the TSO in the 'Loss of AC Power" off-normal event procedure, in the Technical Specifications (Tech Spec) Bases and 'Control of Limiting Conditions for Operation" procedure prior to entering an extended Diesel Generator Outage, and before placing the Generator Voltage Regulator in manual per the "Main Generator and Auxiliaries" System Operating Instruction (SOI). In addition, the weekly Tech Spec Surveillance procedure has Licensed Operators contact the TSO. GGNS has Control Room Indications for the two 500 and the 115 kV GGNS offsite sources. Any indication cf a 500 or 115 kV line unplanned loss would trigger GGNS Operators to contact the TSO to determine the status of the grid and recovery actions/time periods until the line(s) could be restored. The GGNS Tech Specs require two of the three lines entering the 500/115 kV Switchyard to be Operable to satisfy the requirements for AC Power Sources in Modes 1, 2, and 3. These three lines are the GDC 17 credited offsite sources. If only one of the two required offsite sources is Operable, the Tech Spec LCO would be entered and the TSO would be contacted to determine the status of the grid within one hour and every 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> thereafter, until two offsite sources are operable.

Attachment to GNRO*-2006/00014 Page 4 of 23 (d) Describe how NPP operators are trained and tested on the use of the procedures or assessing grid conditions in question 1(c).

ENS Response to Request 1(d):

Plant operators receive training to ensure their understanding of the function and operation of the GGNS onsite and offsite electrical distribution system and components.- Training includes both initial and continuing training programs, which consist of a combination of classroom, and practical factors (e.g. qualification guides and job performance measures).

These methods provide instruction and administer testing to assess the proficiency and knowledge levels of operators in the use of procedures for basic operation of the electrical distribution system, assessing grid conditions, and responding to abnormal and/or emergency conditions. Training is provided in both the licensed and non-licensed training programs. Additionally, lessons learned from operating experience associated with offsite and onsite electrical distribution, such as Significant Operating Event Report (SOER) 99-01, are extensively incorporated into the training curriculum. Testing methods include written exams, and job performance measures.

(e) If you do not have a formal agreement or protocol with your TSO, describe why you believe you continue to comply with the provisions of GDC 17 as stated above, or describe what actions you intend to take to assure compliance with GDC 17.

ENS Response to Request 1(e):

ENS plants have a combination of formal agreements, procedures, protocols and practices as described in the response to NRC Request 1(a); therefore this question is not applicable.

(0 If youi have an existing formal interconnection agreement or protocol that ensures adequate communication and coordination between the NPP licensee and the TSO, describe whether this agreement or protocol requires that you be promptly notified when the conditions of the sun-ounding grid could result in degraded voltage (i.e., below TS nominal trip setpoint value requirements; including NPP licensees using allowable value in its TSs) or LOOP after a trip of the reactor unit(s).

ENS Response to Request 1(f):

As discussed under the response to NRC Request 1 (a), ENS plants utilize a combination of formal agreements, procedures, protocols and/or actions to have Entergy Transmission provide notification to each ENS plant if the predicted post-trip voltage does not meet the minimum value(s) specified in ENS procedure ENS-DC-199. This procedure is ENS controlled procedure that isjointly reviewed by both Entergy Transmission and ENS, and contains the specifics pertaining to preferred offsite sources, including acceptable voltage, frequency and power delivery requirements for each ENS plant.

If the analysis results indicate the potential for ENS site-specific requirements cannot be met, Entergy Transmission determines if these requirements can be met for the period of interest by making changes to transmission system configuration/operation. If Entergy Transmission determines that the requirements cannot be met or are not being met, then plant notification is required. While the present re-evaluations and, if required, the real-time

Attachment to GNRO*-2006/0001 4 Page 5 of 23 notifications do not have an explicit time requirement stated, it is expected by both parties thal such communications would be performed promptly. Entergy Transmission receives periodic training by ENS on the importance of ENS offsite power to Nuclear Safety and the necessity of prompt resolution of such issues.

ENS plans to implement an enhanced on-line monitoring system to be in service with Entergy Transmission during the summer of 2006. This system uses real-time models of the transmission grid and load flow analysis tools to determine if the transmission grid can meet the specific offsite power requirements for the ENS sites, while including the effects of a plant trip. This on-line enhanced system will include a notification time requirement if the requirements cannot be met.

(g) Describe the low switchyard voltage conditions that would initiate operation of plant degraded voltage protection.

ENS Response to Request 1(g):

GGNS receives its offsite power directly from the 500/115 kV Switchyards at all times. The Safety busses have 2 independent paths to the 500 kV Switchyard and a separate independent path to the 115 kV Switchyard.

At any time the 500 or 115 kV system voltage drops to allow the buss voltage on Division 1 or 2 to reach 90% nominal voltage for 9 seconds or 70% nominal voltage for 0.5 seconds (normal or LOCA), the busses will isolate from the Offsite Source. Division 3 buss will isolate from the Offsite Source when 88% of nominal voltage for 5 minutes and 4 seconds during non-LOCA scenarios (LOCA time is 4 seconds) or 73% nominal voltage for 2.3 seconds is met. The safety related busses will then connect to their associated Emergency Diesel Generator.

The minimum grid voltages are listed in ENS-DC-199.

Attachment to GNRO*-2006/00014 Page 6 of 23 NRC Request 2 - Use of criteria and methodologies to assess whether the offsite power system will become inoperable as a result of a trip of your NPP.

(a) Does your NPP's TSO use any analysis tools, an online analytical transmission system studies program, or other equivalent predictive methods to determine the grid conditions that would make the NPP offsite power system inoperable during various contingencies? If available to you, please provide a brief description of the analysis tool that is used by the TS0.

ENS Response to Request 2(a)

Yes., Entergy Transmission utilizes the PTI transmission analysis program as the analysis tool to predict ENS plant's offsite power voltages under various transmission grid contingencies. This transmission analysis program is one of the leading software programs used by electric utilities to perform detailed transmission grid studies. Using this program, Entergy Transmission performs detailed transmission studies for the next day, using daily cases representing that day of the month. These cases specifically consider the trip of each ENS unit and the application of design basis accident loads. These cases provide the advantage of the accuracy of a near term projection of expected loads and load flows, system generating unit status, expected transmission system elements in or out of service and specific site requirements, in a single analysis. These cases are also re-performed during the period of interest (i.e. present day) if previously identified specific contingencies occur or, if Entergy Transmission determines that system conditions have significantly changed during the period that could adversely affect the offsite power source post-trip voltage availability for any ENS unit. This allows the analysis to remain bounding if system conditions change. The results of these analyses are then compared to the post-trip voltage requirements for each respective ENS site. If the results indicate the potential for ENS site-specific requirements may not be met, Entergy Transmission then determines if these requirements can be met for the period of interest by making changes to transmission system configuration/operation. If Entergy Transmission determines that the requirements cannot be met or are not being met, then plant notification is required.

Per the unit-specific licensing basis for each ENS site and the requirements of ENS procedures, studies are performed on a periodicity as specified within the license basis to confirm that the offsite power system will remain operable following a trip of that unit. As a minimum, per ENS procedure DC-1 99, grid studies are performed at least every three years.

The! periodic analyses incorporate updated grid configurations and conditions, which are projected for a future period of interest and include such multiple contingencies as the ENS unit trip and design basis accident loading combined with significant other concurrent transmission/generation contingencies to confirm the adequacy of these sources to remain operable following such an event. This includes future projections for system load peaks and power transfers through the Entergy system, as determined by Entergy Transmission System Planning. Once submitted to ENS by Entergy Transmission, these analyses are reviewed by ENS Engineering personnel to confirm that the analyses provide the necessary assurance of the operability of the offsite power sources following a unit trip. This review is documented per the requirements of ENS procedure DC-1 99.

Attachment to GNRO-2006/00014 Page 7 of 23 (b) Does your NPP's TSO use an analysis tool as the basis for notifying the NPP licensee when such a condition is identified? If not, how does the TSO determine if conditions on the grid warrant NPP licensee notification?

ENS Response to Request 2(b):

Yes. Entergy Transmission uses the above analysis tools, in conjunction with procedures, as the basis for determining when conditions warrant ENS plant notification.

(c) If your TSO uses an analysis tool, would the analysis tool identify a condition in which a trip of the NPP would result in switchyard voltages (immediate and/or long-term) falling below TS nominal trip setpoint value requirements (including NPP licensees using allowable value in its TSs) and consequent actuation of plant degraded voltage protection? If not, discuss how such a condition would be identified on the grid.

ENS Response to Question 2(c):

Yes. As stated in 2(a) the day-ahead analysis tool would predict the voltage conditions that would result from an ENS plant trip well in advance of the actual condition and ENS plant notification would occur at that time.

(d) If your TSO uses an analysis tool, how frequently does the analysis tool program update'?

ENS Response to Request 2(d):

Entergy Transmission uses near-term advance (day-ahead) grid analysis specifically designed for ENS to notify plant sites of such a condition on the grid. These cases are also re-performed during the period of interest (i.e. present day) if previously identified specificS contingencies occur or, if Entergy Transmission determines that system conditions have significantly changed, during the period that could affect adversely the offsite power source post-trip voltage availability for any ENS unit. This allows the analysis to remain bounding if system conditions change.

(e) Provide details of analysis tool-identified contingency conditions that would trigger an NPP licensee notification from the TSO.

ENS Response to Request 2(e):

As stated in 2(a), Entergy Transmission provides notification to the ENS plant(s) if the predicted ENS plant post-trip voltage does not meet the minimum voltage values specified in ENS procedure DC-1 99 for that specific ENS plant. These post trip voltages are calculated by the PTI /PSSE software transmission analysis program, used by many utilities for extensive transmission studies. As stated in ENS procedure DC-201, if any transmission system element that is directly interconnected to the ENS plant switchyard/substation is lost, then the software analysis is re-performed to identify whether the post trip voltages are sl:ill acceptable. Additionally, if any transmission system contingency occurs that, in the opinion of Entergy Transmission may significantly impair the unit post-trip voltage performance for

Attachment to GNRO -2006/0001 4 Page 8 of 23 any ENS site, the software analysis is re-performed to identify whether the post trip voltage is still acceptable.

(f) If an interface agreement exists between the TSO and the NPP licensee, does it require that the NPP licensee be notified of periods when the TSO is unable to determine if offsite power voltage and capacity could be inadequate? If so, how does the NPP licensee determine that the offsite power would remain operable when such a notification is received?

ENS Response to Request 2(f):

Entergy Transmission uses near-term advance (day-ahead) grid analysis specifically designed to monitor ENS site grid conditions. If the near-term advance (day-ahead) monitoring process is determined by Entergy Transmission to be unavailable, ENS plant notification is required per ENS procedure DC-201 which is jointly reviewed and approved by Entergy Transmission. Per the requirements of ENS procedures, each affected ENS site will initiate a condition report for each daily case that results in an ENS notification by Entergy Transmission. This condition report will address Operability of the affected offsite power sources for such cases.

(g) After an unscheduled inadvertent trip of the NPP, are the resultant switchyard voltages verified by procedure to be bounded by the voltages predicted by the analysis tool?

ENS Response to Request 2(g):

Per the requirements of ENS procedure, DC-201, ENS Plant Engineering is required to coordinate with Entergy Transmission for a review of grid conditions that existed at the time of such an ENS unit trip to assess the accuracy of the analysis under known system conditions.

(h) If an analysis tool is not available to the NPP licensee's TSO, do you know if there are arny plans for the TSO to obtain one? If so, when?

ENS Response to Request 2(h):

Entergy Transmission uses an analysis tool; therefore this question is not applicable.

Attachment to GNRO-2006/00014 Page £ of 23 (i) If an analysis tool is not available, does your TSO perform periodic studies to verify that adequate offsite power capability, including adequate NPP post-trip switchyard voltages (immediate and/or long-term), will be available to the NPP licensee over the projected timeframe of the study?

(a) Are the key assumptions and parameters of these periodic studies translated into TSO guidance to ensure that the transmission system is operated within the bounds of the analyses?

(b) If the bounds of the analyses are exceeded, does this condition trigger the notification provisions discussed in question I above?

ENS Response to Request 2(i):

Entergy Transmission uses an analysis tool; therefore this question is not applicable.

a) If your TSO does not use, oryou do not have access to the results of an analysis tool, or your TSO does not perform and make available to you periodic studies that determine the adequacy of offsite power capability, please describe why you believe you comply with the provisions of GDC 17 as stated above, or describe what compensatory actions you intend to take to ensure that the offsite power system will be sufficiently reliable and remain operable with high probability following a trip of your NPP.

ENS Response to Request 20):

Entergy Transmission uses an analysis tool. ENS plants have access to the results of an analysis tool used by Entergy Transmission and Entergy Transmission makes periodic studies available to ENS to determine the adequacy of offsite power capability. Therefore, this question is not applicable.

NRC Request 3. - Use of criteria and methodologies to assess whether the NPP's offsite power system and safety-related components will remain operable when switchyard voltages are inadequate.

(a) If the TSO notifies the NPP operator that a trip of the NPP, or the loss of the most critical transmission line or the largest supply to the grid would result in switchyard voltages (immediate and/or long-term) below TS nominal trip setpoint value requirements (including NP.P licensees using allowable value in its TSs) and would actuate plant degraded voltage protection, is the NPP offsite power system declared inoperable under the plant TSs? If not, why not?

Entergy Note GL 2006-02 uses the term 'Operable' in several locations with regard to postulated offsite power conditions and for showing compliance with GDC 17. Operability is based on uthe capability of performing its specified safety function(s)." This is a current capability, not a.

postulated capability after other events not analyzed in the Safety Analysis Report.

Declaring offsite circuits inoperable due to projected switchyard voltages (except in combination with a plant trip) would require a plant shutdown per the TS. A premature plant

Attachment to GNRO*-2006/00014 Page 10 of 23 shutdown would contribute to the actual degraded voltage condition. Entering the TS required action statement potentially worsens the situation that the Generic Letter was intended to avoid. Therefore, as discussed in the following responses, Entergy applies offsite power system Operability with actual or immediate conditions consistent with other Limiting Conditions for Operation within the GGNS TS.

Additionally, GL 2006-02 also appears to equate meeting GDC 17 with the Operability of the offsite circuits. As stated in Regulatory Information Summary (RIS) 2005-20, Operability Determination Process, Appendix C.1, Relationship Between the General Design Criteria and the Technical Specifications, "The General Design Criteria (GDC) and the TS differ in that the GDC specify requirements for the design of nuclear power reactors, whereas the TS specify requirements for the operation of nuclear reactors." Therefore, failure to meet a General Design Criteria is considered a degraded or nonconforming condition and an operability determination is required to determine if the associated equipment is inoperable.

ENS Response to Request 3(a):

Per the requirements of ENS procedures, plant notification is required if the transmission grid cannot be maintained or is not within the values required by ENS procedure DC-1 99.

These values represent the acceptable ranges to demonstrate that a given offsite source! will remain capable of powering the required onsite loads under design basis conditions. Per the requirements of ENS procedures, if such notification is made, ENS will initiate a condition report and evaluate operability. If this evaluation demonstrates the inability to power required onsite loads from a given offsite source, that offsite source would be declared inoperable.

The ENS plant would declare the offsite power source inoperable for the situation where the loss; of an ENS unit would result in inadequate switchyard voltages that would actuate plant degraded voltage protection. The ENS plants do not declare the offsite power inoperable for the situation where the loss of the most critical transmission line or the largest supply to the grid would result in inadequate switchyard voltages. The loss of the facility would have to already occur before any action would be taken. If predicting a most critical line loss or loss of the largest supply would predict a voltage below the degraded voltage protection setpoint, the ENS plant would take preparatory actions without entering a Limiting Condition for Operation (LCO), since ENS plants do not enter into an LCO until an event happens.

(b) If onsite safety-related equipment (e.g., emergency diesel generators or safety-related motors) is lost when subjected to a double sequencing (LOCA with delayed LOOP event) as a result of the anticipated system performance and is incapable of performing its safety functions as a result of responding to an emergency actuation signal during this condition, is the equipment considered inoperable? If not, why not?

ENS Response to Request 3(b):

If a SSC is lost or determined to be unable to perform its design basis safety function, then it is declared inoperable and actions are taken (as governed by plant Technical Specifications). However, double sequencing is not a design basis condition.

Attachment to GNRO*-2006/00014 Page 11 of 23 (c) Describe your evaluation of onsite safety-related equipment to determine whether it will operate as designed during the condition described in question 3(b).

ENS Response to Request 3(c):

As stated in our above response 3(b) this double sequencing is not a design basis analyzed event.

(d) If the NPP licensee is notified by the TSO of other grid conditions that may impair the capability or availability of offsite power, are any plant TS action statements entered? If so, please identify them.

ENS Response to Request 3(d):

As discussed in response to NRC Request 3(a), plant notification is required, if the transmission grid cannot be maintained or is not within the values required by ENS procedures. If a required offsite source is declared inoperable, then the appropriate Technical Specification LCO Action Statement(s) would be entered. However, GGNS Technical Specification LCOs are not entered for grid conditions that might occur (i.e.,

tornados, forest fires, severe weather events).

(e) If you believe your plant TSs do not require you to declare your offsite power system or saf9ty-related equipment inoperable in any of these circumstances, explain why you believe you comply with the provisions of GDC 17 and your plant TSs, or describe what compensatory actions you intend to take to ensure that the offsite power system and safety-related components will remain operable when switchyard voltages are inadequate.

ENS Response to Request 3(e):

ENS believes that certain cases could result in the affected equipment being declared inoperable as described in response to NRC Requests 3(a) and 3(b). Therefore, this question is not applicable to ENS.

(f) Describe if and how NPP operators are trained and tested on the compensatory actions mentioned in your answers to questions 3(a) through (e).

ENS Response to Request 3(f):

ENS did not specify any "compensatory" actions in the ENS responses to NRC Request 3(a) through 3(e). All actions described by ENS within these responses are governed by plant procedures. Therefore, there are no applicable "compensatory" actions stated for ENS operators to be trained or tested on.

Attachment to GNRO-.2006/00014 Page 12 of 23 NRC Request 4 - Use of criteria and methodologies to assess whether the offsite power system will remain operable following a trip of your NPP.

(a) Do the NPP operators have any guidance orprocedures in plant TS bases sections, the final safety analysis report, or plant procedures regarding situations in which the condition of plant-controlled or-monitored equipment (e.g., voltage regulators, auto tap changing transformers, capacitors, static VAR compensators, main generator voltage regulators) can adversely affect the operability of the NPP offsite power system? If so, describe how the operators are trained and tested on the guidance and procedures.

ENS Response to Request 4(a):

As stated in NRC Request 1(C), GGNS has procedural triggers to notify the TSO prior to placing the Generator Voltage Regulator in manual per "Main Generator and Auxiliaries" SOL. No transformers connected to the offsite source have load tap changers, and GGNS does not have any voltage regulators, capacitors, or static VAR compensators.

Entergy Transmission has also incorporated the allowable voltage ranges as specified in ENS' procedures into Entergy Transmission Energy Management System (EMS) alarms for the transmission system operators. These alarms provide an independent means to detect adverse effects on ENS offsite power sources due to main generator voltage regulator deviations, if such deviations are of sufficient magnitude to cause the offsite source to be!

outside of the allowable range as determined by ENS procedures, when the turbine generator is connected to the grid (i.e. before the postulated DBA).

As discussed in the response to Request 1(d), GGNS operators are trained in normal, off-normal, and emergency operations including the potential for impact from loss of both onsite and offsite power sources.

(b) If your TS bases sections, the final safety analysis report, and plant procedures do not provide guidance regarding situations in which the condition of plant-controlled or -

monitored equipment can adversely affect the operability of the NPP offsite power system, explain why you believe you comply with the provisions of GDC 17 and the plant TSs, or describe what actions you intend to take to provide such guidance or procedures.

ENS Response to Request 4(b):

The above listed documents support determination of operability of the offsite power system. Therefore, compliance with GDC 17 and plant Tech Specs is assured.

Use of NPP licensee/TSO protocols and analysis tool by TSOs to assist NPP licensees in monitoring grid conditions for consideration in maintenance risk assessments The Maintenance Rule (10 CFR 50. 65(a)(4)) requires that licensees assess and manage the increase in risk that may result from proposed maintenance activities before performing them.

Attachment to GNRO*2006/00014 Page 13 of 23 NRC Request 5 Performance of grid reliability evaluations as part of the maintenance risk assessments required by 10 CFR 50.65(a)(4).

(a) Is a quantitative or qualitative grid reliability evaluation performed at your NPP as part of the maintenance risk assessment required by 10 CFR 50. 65(a)(4) before performing grid-risk-sensitive maintenance activities? This includes surveillances, post-maintenance testing, and preventive and corrective maintenance that could increase the probability of a plant trip or LOOP or impact LOOP or SBO coping capability, for example, before taking a risk-significant piece of equipment (such as an EDG, a battery, a steam-driven pump, an alternate AC power source) out-of-service?

ENS Response to Request 5(a):

Coordination of both grid and plant major maintenance to minimize plant risk is performed by the ENS and Transmission functions, although the primary responsibility and oversight functions for these actions is performed by the ENS site organization. The site work control processes factor in scheduled switchyard activities as part of the risk evaluation process, as well as any emergent items. The site's "Switchyard and Transmission Interface Agreement",

the site's specific implementing procedure for these interfaces Management Standard 21 (MS,-21), and NMM procedure PL-158, uSwitchyard and Transmission Interface Requirements" are used to define responsibilities between the Transmission and ENS organizations for this purpose.

As stated in 10CFR50.65 (a)(4), 'Before performing maintenance activities (including but not limited to surveillance, post-maintenance testing, and corrective and preventive maintenance), the licensee shall assess and manage the increase in risk that may result from the proposed maintenance activities. The scope of the assessment may be limited 1:o structures, systems, and components that a risk-informed evaluation process has shown to be significant to public health and safety".

GGNS Administrative Procedure "Risk Assessment of Maintenance Activities", provides procedural guidance to meet IOCFR50.65 (a)(4) in assessing the overall impact of plant maintenance on plant risk, and manage the risk associated with equipment unavailability.

GGNS includes all major switchyard components and incoming transmission lines to the switchyard in the EOOS (Equipment Out of Service) risk model. Per the Switchyard Interface Agreement that was signed in 1999, Entergy Mississippi will coordinate activities directly affecting the off-site power supply to GGNS. These activities include, but are nol:

limited to:

a. Removing from service any transmission line terminating in the Switchyard
b. Breaker switching which can affect power supply to GGNS [e.g., switching of lines identified in item (a) above]
c. Maintenance activities that can affect power supply to GGNS.

(b) Is grid status monitored by some means for the duration of the grid-risk-sensitive maintenance to confirm the continued validity of the risk assessment and is risk reassessed when warranted? If not, how is the risk assessed during grid-risk-sensitive maintenance?

Attachment to GNRO-2006/00014, Page 14 of 23 ENS Response to Request 5(b):

Entergy Transmission grid status is monitored by Entergy Transmission as described in the ENS response to question 1.

Yes. NUMARC 93-01 does not define "grid-risk-sensitive maintenance", so there is no unique guidance for such activities. The following guidance is included in Section 11.3.2.8:

Emergent conditions may result in the need for action prior to conducting an assessment, or could change the conditions of a previously performed assessment. Examples include plant configuration or mode changes, additional SSCs out of service due to failures, or significant changes in external conditions (weather, offsite power availability). The following guidance applies to this situation:

  • The safety assessment should be performed (or re-evaluated) to address the changed plant conditions on a reasonable schedule commensurate with the safety significance of the condition. Based on the results of the assessment, ongoing or planned maintenance activities may need to be suspended or re-scheduled, and SSCs may need to be returned to service.
  • Performance (or re-evaluation) of the assessment should not interfere with, or delay, the operator and/or maintenance crew from taking timely actions to restore the equipment to service or take compensatory actions.
  • If the plant configuration is restored prior to conducting or re-evaluating the assessment, the assessment need not be conducted, or re-evaluated if already performed.

In addition, GGNS Tech Specs require the offsite source to be assessed, in part by contacting the TSO, every 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> during EDG outages or times when onsite or offsite AC power requirements are not met. This assessment is performed per surveillance procedure that confirms reliability of onsite and offsite power systems. GGNS Licensed Operators perform this surveillance every 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> when the LCO Action Statement has been entered.

(c) Is there a significant variation in the stress on the grid in the vicinity of your NPP site caused by seasonal loads or maintenance activities associated with critical transmission elements?

Is there a seasonal variation (or the potential for a seasonal variation) in the LOOP frequency in the local transmission region? If the answer to either question is yes, discuss the time of year when the variations occur and their magnitude.

ENS Response to Request 5(c):

No. Within the context of the definition provided for 'Grid Stress or a Stressed Grid" for this generic letter, Entergy Transmission system loads typically reach annual maximums within the summer months, however Entergy Transmission System Operators continually account for such loads when balancing these loads with available generation and power import/export and load flow capability.

Attachment to GNRO-2006/00014 Page 15 of 23 Major transmission lines near the ENS site that might affect the viability of the Offsite Power System and/or the nuclear generation, have their maintenance outages scheduled away from the summer or peak load times or during plant outages to avoid grid stress in the vicinity of the plant. GGNS has not experienced a total loss of offsite power (LOOP) caused by grid.

Enlergy Transmission maintains grid stability with an automatic load shedding system. This system sheds up to 30% of the system load in three successive increments of degrading grid frequency. Entergy Transmission also maintains a stable grid by shedding selective!

load if necessary after potential re-dispatch solutions are exhausted to ensure continued grid reliability. Thus, two goals exist: Grid Reliability and Service Reliability. The residential and commercial customers may experience electrical outages at the distribution level while the grid is unaffected. Hence, offsite power continues to be available to ENS plants.

Additionally, EPRI TR-101 1759, dated December 2005, has shown that there is no statistically significant seasonal-regional variation in recorded LOOP events from 1997 to 200)4.

(d) Are known time-related variations in the probability of a LOOP at yourplant site considered in the grid-risk-sensitive maintenance evaluation? If not, what is your basis for not considering them?

ENS Response to Request 5(d):

Yes. The GGNS online risk model [Equipment Out Of Service] is based on the guidance of NUMARC 93-01, which states that [risk] assessments should consider the impact of maintenance activities on availability of electrical power. Specifically, the assessments for maintenance activities involving the switchyard and transformer yard should consider thE, impact on offsite power availability. The GGNS EOOS model incorporates the ability to adjust the frequency of LOOP probability due to adverse weather conditions such as severe weather and potential tornado conditions. In addition, the frequency of LOOP probability can also be adjusted based on the work in the switchyard.

(e) Do you have contacts with the TSO to determine current and anticipated grid conditions as part of the grid reliability evaluation performed before conducting grid-risk-sensitive maintenance activities?

ENS Response to Request 5(e):

Yes, ENS plant contacts Entergy Transmission at any time necessary, using communications protocols provided in ENS procedures.

As discussed in the response to Request 5(a), the GGNS "Switchyard Work Control" Standard (MS-21) provides detailed scheduling and coordination requirements associated with work in the switchyard. This procedure includes a list of maintenance exceptions that have been evaluated to have no impact on the plant. These activities typically do not require impact statements. For all other activities, component and plant impact statements are prepared to assess the possible impact on the plant. These activities, once approved,

Attachment to GNRO -2006/00014 Page 16 of 23 are also placed on the integrated plant schedules. These processes assure that the work is thoroughly evaluated for its impact on the plant.

(f) Describe any formal agreement or protocol that you have with your TSO to assure that you are promptly alerted to a worsening grid condition that may emerge during a maintenance activity.

ENS Response to Request 5(f):

As discussed in the Response to NRC Request 1(a), ENS plants utilize a combination of formal agreements, procedures, protocols and/or actions to have Entergy Transmission provide notification to each ENS plant if the predicted post-trip voltage does not meet the minimum value(s) specified in ENS procedures. This is a ENS controlled procedure that is jointly reviewed by both Entergy Transmission and ENS. It contains the specifics pertaining to preferred offsite sources, including acceptable voltage, frequency and power delivery requirements for each ENS plant.

If analysis results indicate the potential for ENS site-specific requirements are not being met, Entergy Transmission determines if these requirements can be met for the period of interest by making changes to transmission system configuration/operation. If Entergy Transmission determines that the requirements cannot be met or are not being met, then ENS plant notification is required. Per the requirements of ENS-DC-201, if such notification is made, ENS will initiate a condition report and evaluate operability. Thus, ENS plant operations will be made aware of worsening grid conditions that could result in the inability to meet the ENS site post-trip design basis accident load requirements from the offsite power source.

(g) Do you contact your TSO periodically for the duration of the grid-risk-sensitive maintenance activities?

ENS Response to Request 6(g):

Yes. GGNS Tech Spec 3.8.1 requires the offsite source to be assessed, in part by contacting the TSO, every 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> during EDG outages or times when onsite or offsite AC power requirements are not met. This assessment is performed per surveillance procedure that confirms reliability of onsite and offsite power systems. GGNS Licensed Operators perform this surveillance every 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> when the LCO Action Statement has been entered.

(h) If you have a formal agreement or protocol with your TSO, describe how NPP operators and maintenance personnel are trained and tested on this formal agreement or protocol.

ENS Response to Request 5(h):

GGNS operators and maintenance personnel receive training, as described in the answer to question 1(d), to ensure their understanding of the function and operation of the GGNS offsite electrical distribution system and components. This training includes the GGNS

'Switchyard and Transmission Interface Agreement" as well as the GGNS "Switchyard Work Control" Standard, MS-21.

Attachment to GNRO*-2006/00014 Page 17 of 23 (i) If your grid reliability evaluation, performed as part of the maintenance risk assessment required by 10 CFR 50.65(a) (4), does not consider or rely on some arrangement for communication with the TSO, explain why you believe you comply with 10 CFR 50.65(a)(4).

ENS Response to Request 5(i):

As previously discussed, risk sensitive maintenance activities are communicated with Entergy Transmission and changes in risk during the maintenance evolution are similarly communicated as required. Therefore, this question is not applicable to GGNS.

U) If risk is not assessed (when warranted) based on continuing communication with the TSC throughout the duration of grid-risk-sensitive maintenance activities, explain why you believe you have effectively implemented the relevant provisions of the endorsed industry guidance associated with the maintenance rule.

ENS Response to Request 5(j):

As previously discussed, risk sensitive maintenance activities are communicated with Entergy Transmission and changes in risk during the maintenance evolution are similarly communicated as required. Therefore, this question is not applicable to GGNS.

(k) Wt)h respect to questions 5(i) and 50), you may, as an alternative, describe what actions you intend to take to ensure that the increase in risk that may result from proposed grid-risk-sensitive activities is assessed before and during grid-risk-sensitive maintenance activities, respectively.

ENS Response to Request 5(k):

Since GGNS maintains communication with offsite Entergy Transmission for risk-sensitive maintenance, no alternative communications are considered necessary.

NRC Request 6. Use of risk assessment results, including the results of grid reliability evaluations, in managing maintenance risk, as required by 10 CFR 50.65(a)(4).

(a) Does the TSO coordinate transmission system maintenance activities that can have an impact on the NPP operation with the NPP operator?

ENS Response to Request 6(a):

Entergy Transmission maintenance is classified as either planned maintenance or emergent maintenance. Additionally, ENS has an added tool where planned Entergy Transmission system outages, that are relevant to ENS sites, are posted on an Entergy Intranet web page.

Planned maintenance activities with the potential to affect ENS operation are incorporated into the near-term advance (day-ahead) grid analysis specifically for ENS to use in determining the status of the Entergy Transmission grid, particularly near ENS plants.

Attachment to GNRO..2006/00014 Page 18 of 23 Emergent maintenance activities and planned maintenance activities with the potential to affect ENS operation are required to be coordinated with the affected ENS site per the formal agreements indicated in this response for each respective ENS site.

(b) Do you coordinate NPP maintenance activities that can have an impact on the transmission system with the TSO?

ENS Response to Request 6(b):

Scheduled and unscheduled ENS unit outages and ENS unit power reductions are communicated between ENS units, Entergy System Planning and Operation and Entergy Transmission for transmission security purposes. Also, see response to Request 5(a).

(c) Do you consider and implement, if warranted, the rescheduling of grid-risk-sensitive maintenance activities (activities that could (i) increase the likelihood of a plant trip, (ii) increase LOOP probability, or (iii) reduce LOOP or SBO coping capability) under existing, imminent, or worsening degraded grid reliability conditions?

ENS Response to Request 6(c):

Yes. Degraded grid reliability conditions would require a condition report to be initiated and an Dperability determination to be performed. Grid-risk-sensitive maintenance would be rescheduled to such a time that the grid has recovered and the EOOS risk was acceptalle to the plant.

GGNS Management Standard 21 designates the responsibilities of the Point of Contact (PC)C) who is responsible for coordination of grid maintenance and testing. The POC facilitates preparation and review of these impact statements with assistance from GGN';

Operations. These activities, once approved, are placed on the integrated plant schedules.

These processes assure that the work is thoroughly evaluated for its impact on the plant. In addition, by adding the activities to the integrated plant schedules, they are evaluated to assure there are no conflicts with other in-house activities, thus maintaining adequate defense-in-depth. GGNS Operations personnel are involved, via the impact statements and integrated schedule, to insure that grid activities are coordinated with in-house activities so that adequate electrical diversity is maintained at all times. The POC works closely with Operations and Entergy Transmission in communication and coordination of these activities.

Note: Per the GGNS Switchyard and Transmission Interface Agreement, GGNS has maintenance responsibility (including necessary repair or replacement) for the GGNS support transformers, main output transformers, and any other equipment to the point of the defined power transmission interface. Based on this agreement, GGNS currently has maintenance responsibility for the Service Transformers, as well as, the 34.5 kV Switchyard.

All Dther equipment located in the switchyard is maintained by Entergy Transmission.

Attachment to GNRO*2006/00014 Page 19 of 23 (d) If there is an overriding need to perform grid-risk-sensitive maintenance activities under existing or imminent conditions of degraded grid reliability, or continue grid-risk-sensitive maintenance when grid conditions worsen, do you implement appropriate risk management actions? If so, describe the actions that you would take. (These actions could include alternate equipment protection and compensatory measures to limit or minimize risk.)

ENS Response to Request 6(d):

Yes, when time allows an assessment of risk is preformed prior to switchyard related maintenance [MS-21]. As discussed in the response to Request 5(d), GGNS has clear guidance on ensuring the risk is minimized where grid sensitive maintenance could occur.

However, as discussed in the response to 5(b), emergent conditions may result in the need for action prior to conduct of the assessment, or could change the conditions of a previously performed assessment. Examples include plant configuration or mode changes, additional SS-s out of service due to failures, or significant changes in external conditions (weather, offsite power availability). Irrespective, GGNS applies the most appropriate risk and deterministic tools available to ensure plant and grid protection. If maintenance must be performed during grid-sensitive periods, the in-plant risk directive limits all other maintenance activities that would worsen the risk to the plant or the grid. If additional actions are needed, then compensatory measures will be taken to the extent practical. All grid-sensitive maintenance requires control room management approval prior to work being performed.

(e) Describe the actions associated with questions 6(a) through 6(d) above that would be taken, state whether each action is governed by documented procedures and identify the procedures, and explain why these actions are effective and will be consistently accomplished.

ENS Response to Request 6(e):

All actions described in the responses to Requests 6(a) through 6(d), are directed by either Entergy Transmission agreements and/or GGNS specific procedures. These agreements and procedures are not new to Entergy Transmission or GGNS and have been exercised on a routine basis. GGNS believes that the specific requirements of the procedures discussed are effective and repeatable to ensure grid-sensitive maintenance is reduced to a minimum.

(f) Describe how NPP operators and maintenance personnel are trained and tested to assure they can accomplish the actions described in your answers to question 6(e).

ENS Response to Request 6(f):

As discussed in the answer to question 5(h) above, training is provided on a GGNS specific management standard, which provides controls for switchyard activities. The procedure assigns responsibilities and establishes interfaces for coordination of scheduled and unscheduled maintenance. Risk factors and impacts of specific work activities are identified and evaluated in accordance with the guidance of this procedure and a decision making process is provided to determine if specific maintenance activities are to be allowed.

Attachment to GNRO -2006/00014 Page 20 of 23 (g) If there is no effective coordination between the NPP operator and the TSO regarding transmission system maintenance or NPP maintenance activities, please explain why you believe you comply with the provisions of 10 CFR 50.65(a)(4).

ENS Response to Request 6(g):

ENS believes that there is effective coordination between ENS operators and Entergy Transmission maintenance activities; therefore, this question is not applicable.

(h) If you do not consider and effectively implement appropriate risk management actions during the conditions described above, explain why you believe you effectively addressed the relevant provisions of the associated NRC-endorsed industry guidance.

ENS Response to Request 6(h):

ENS believes that there is effective coordination between ENS operators and Entergy Transmission maintenance activities; therefore, this question is not applicable.

(i) You may, as an alternative to questions 6(g) and 6(h) describe what actions you intend to take to ensure that the increase in risk that may result from grid-risk-sensitive maintenance activities is managed in accordance with 10 CFR 50.65(a)(4).

ENS Response to Request 6(i):

No alternate actions are considered necessary and therefore, this question is not applicable to GGNS.

Offsite power restoration procedures in accordance with 10 CFR 50.63 as developed in Section 2 of RG 1.155*

Pursuant to 10 CFR 50.63, the NRC requires that each NPP licensed to operate be able to withstand an SBO for a specified duration and recover from the SBO. NRC RG 1.155 gives licensees guidance on developing their approaches for complying with 10 CFR 50.63.

NRC Request 7. Procedures for identifying local power sources that could be made available to resupply your plant following a LOOP event.

Note: Section 2, Offsite Power," of RG 1.155 (ADAMS Accession No. MLOO3740034) states:

Procedures should include the actions necessary to restore offsite power and use nearby power sources when offsite power is unavailable. As a minimum, the following potential causes for loss of offsite power should be considered:

- Grid undervoltage and collapse

- Weather-induced power loss

- Preferred power distribution system faults that could result in the loss of normal power to essential switchgear buses

Attachment to GNRO*-2006/00014 Page 21 of 23 (a) Briefly describe any agreement made with the TSO to identify local power sources that could be made available to resupply power to your plant following a LOOP event.

ENS Response to Request 7(a):

Formal agreements previously described between ENS plants and Entergy Transmission dictate priority restoration of offsite power to these units. Entergy Transmission maintains restoration plans for the Entergy Transmission system:The plans include the use of system black-start capable generation, where available. Such restoration plans consider all available Entergy Transmission restoration options, including but not limited to use of other local-area generation for re-supply of ENS plants. Restoration of off site power to ENS facilities has the highest restoration priority. Grid operators train on this procedure annually per NERC training requirements. Entergy Transmission is not responsible for the use of any onsite generation sources under site control.

(b) Are your NPP operators trained and tested on identifying and using local power sources to resupply your plant following a LOOP event? If so, describe how.

ENS Response to Request 7(b):

ENS operators are responsible for the use of ENS onsite resources under ENS control, only.

Entergy Transmission is responsible for the use of Entergy system resources, including, but not limited to, use of local-area (offsite) generation to re-supply ENS plants following a LOOP event and such re-supply is designated as a priority activity within Entergy Transmission restoration plans, as previously described.

GGNS has an off-normal event procedure, "Loss of AC Power", which covers both LOOP and station blackout conditions. The GGNS Emergency Diesel Generator SOI procedure provides guidance for normal and abnormal EDG operation.

(c) If you have not established an agreement with your plant's TSO to identify local power sources that could be made available to resupplypower to yourplant following a LOOP event, explain why you believe you comply with the provisions of 10 CFR 50.63, or desc,-ibe what actions you intend to take to establish compliance.

ENS Response to Request 7(c):

ENS has agreements previously described between ENS plants and Entergy Transmission that dictate priority restoration of offsite power to ENS units. Entergy Transmission maintains restoration plans for the Entergy Transmission system. The plans include the use of system black-start capable generation, where available. Such restoration plans consider all available Entergy Transmission restoration options, including but not limited to use of other (offsite) local-area generation for re-supply of ENS plants. Therefore, this question is not applicable.

Attachment to GNRO-2006/0001 4 Page 22 of 23 Losses of offsite power caused by grid failures at a frequency of equal to or greater than once in 20 site.-years in accordance with Table 4 of Regulatory Guide 1.155 for complying with 10 CFR 50.63.

Pursuant to 10 CFR 50.63, the NRC requires that each NPP licensed to operate be able to withstand an SBO for a specified duration and recover from the SBO. NRC RG 1.155 gives licensees guidance on developing their approaches for complying with 10 CFR 50.63.

NRC Request 8. Maintaining SBO coping capabilities in accordance with 10 CFR 50.63.

(a) Has your NPP experienced a total LOOP caused by grid failure since the plant's coping duration was initially determined under 10 CFR 50.63?

ENS Response to Request 8(a):

GGNS has not experienced a total loss of offsite power or a grid failure that would have initiated a station blackout.

(b) If so, have you reevaluated the NPP using the guidance in Table 4 of RG 1.155 to determine if your NPP should be assigned to the P3 offsite power design characteristic group?

ENS Response to Request 8(b):

This question is not applicable to GGNS.

(c) If so, what were the results of this reevaluation, and did the initially determined coping duration for the NPP need to be adjusted?

ENS Response to Request 8(c):

This question is not applicable to GGNS.

(d) If your NPP has experienced a total LOOP caused by grid failure since the plant's coping duration was initially determined under 10 CFR 50.63 and has not been reevaluated using the guidance in Table 4 of RG 1.155, explain why you believe you comply with the provisions of 10 CFR 50.63 as stated above, or describe what actions you intend to take to ensure that the NPP maintains its SBO coping capabilities in accordance with 10 CFR 50.63.

ENS Response to Request 8(d):

This question is not applicable to GGNS.

Attachment to GNRO-2006/00014 Page 23 of 23 Actions to ensure compliance NRC Request 9. If you determine that any action is warranted to bring your NPP into compliance with NRC regulatory requirements, including TSs, GDC 17, 10 CFR 50.65(a) (4),

10 CFR 50.63, 10 CFR 55.59 or 10 CFR 50.120, describe the schedule for implementing it.

ENS Response to Request 9 Entergy believes that GGNS is in compliance with NRC regulatory requirements and no further actions are necessary.