Letter 02/09/2006, Acknowledgement of Letter Dated January 18, 2006 - Response to Notice of Violation & Yellow Finding
ML060400440
Person / Time
Site: Kewaunee Dominion icon.png
Issue date: 02/09/2006
From: Satorius M
Division Reactor Projects I
To: Christian D
Dominion Energy Kewaunee
References
EA-05-176, IR-05-018
Download: ML060400440 (4)


Text

February 9, 2006 EA-05-176 Mr. David A. Christian Senior Vice President and Chief Nuclear Officer Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711

SUBJECT:

ACKNOWLEDGEMENT LETTER FOR A YELLOW FINDING AND NOTICE OF VIOLATION (NRC INSPECTION REPORT 05000305/2005018);

KEWAUNEE POWER STATION

Dear Mr. Christian:

Thank you for your letter dated January 18, 2006, in response to the Notice of Violation for a finding issued on December 21, 2005. Your response stated that you concurred with the violation and significance determination process characterization of Yellow.

In your letter, you indicated that this violation does not reflect current performance at the plant.

You identified the causes of the violation included: lack of detail in design basis documentation regarding flooding, high energy line break, seismic, and tornado protection; weaknesses in design basis maintenance; lack of knowledge of design basis and fully effective processes for determining the significance of problems and resolution prioritization; lack of rigor in plant staff evaluation and resolution of problems; and, flaws in Kewaunees probabilistic risk assessment with respect to flooding risk. Your letter also provided information about corrective steps taken and the results achieved, including Kewaunees improvement initiatives (submitted to the NRC in a March 18, 2005, letter) and actions completed prior to restart of the plant. In a November 14, 2005, letter, you provided an update to the improvement initiatives and identified additional improvement initiatives to address underlying issues in the violation. Additionally, you stated that you plan to submit a license amendment request to clarify the flooding design basis for the plant in the first quarter of 2006.

Based on discussions between my staff and members of your staff, an Inspection Procedure (IP) 95002 supplemental inspection is scheduled to occur in May 2006.

D. Christian In accordance with 10 CFR 2.390 of the NRC's Rules of Practice, a copy of this letter and your response will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Mark A. Satorius, Director Division or Reactor Projects Docket No. 50-305 License No. DPR-43 cc: M. Gaffney, Site Vice President C. Funderburk, Director, Nuclear Licensing and Operations Support T. Breene, Manager, Nuclear Licensing L. Cuoco, Esq., Senior Counsel D. Zellner, Chairman, Town of Carlton J. Kitsembel, Public Service Commission of Wisconsin

D. Christian In accordance with 10 CFR 2.390 of the NRC's Rules of Practice, a copy of this letter and your response will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Mark A. Satorius, Director Division or Reactor Projects Docket No. 50-305 License No. DPR-43 cc: M. Gaffney, Site Vice President C. Funderburk, Director, Nuclear Licensing and Operations Support T. Breene, Manager, Nuclear Licensing L. Cuoco, Esq., Senior Counsel D. Zellner, Chairman, Town of Carlton J. Kitsembel, Public Service Commission of Wisconsin DOCUMENT NAME: E:\Filenet\ML060400440.wpd G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII RIII RIII NAME LHaeg:sls PLouden KOBrien MSatorius DATE 02/08/06 02/08/06 02/08/06 02/09/06 OFFICIAL RECORD COPY

D. Christian ADAMS Distribution:

ADAMS (PARS)

SECY OCA L. Reyes, EDO W. Kane, DEDR M. Johnson, OE C. Nolan, OE D. Starkey, OE N. Hilton, OE J. Caldwell, RIII G. Grant, RIII L. Chandler, OGC B. Jones, OGC J. Dyer, NRR S. Richards, Chief, IIPB, NRR M. Tschiltz, Chief, SPSB, NRR D. Merzke, NRR J. Stang, NRR D. Holody, Enforcement Coordinator, RI C. Evans, Enforcement Coordinator, RII K. OBrien, Enforcement Coordinator, RIII K. Fuller, Enforcement Coordinator, RIV R. Pascarelli, Enforcement Coordinator, NRR M. Cheok, RES E. Brenner, OPA H. Bell, OIG G. Caputo, OI J. Schlueter, OSTP C. Weil, RIII:EICS J. Strasma, RIII:PA R. Lickus, RIII J. Lynch, RIII OEWEB OEMAIL PJH2 RidsNrrDirsIrib SXB3 CAA1 DRPIII DRSIII