INITIAL LICENSED OPERATOR EXAMINATION JOB PERFORMANCE MEASURE STATION: HOPE CREEK SYSTEM: Conduct of Operations TASK: Conduct Weekly Power Distribution Lineup TASK NUMBER: 2630010201 JPM NUMBER: NRC-ADM-001 ALTERNATE PATH: X K/A NUMBER: 2.1.31 IMPORTANCE FACTOR: 4.2 3.9 APPLICABILITY: RO SRO RO X SRO EVALUATION SETTING/METHOD: Simulator/Perform
REFERENCES:
HC.OP-ST.ZZ-0001, Revision 26 TOOLS AND EQUIPMENT: None VALIDATED JPM COMPLETION TIME: 15 Minutes TIME PERIOD IDENTIFIED FOR TIME CRITICAL STEPS: N/A JPM SOURCE: Modified Bank APPROVAL:
Author Facility Representative Chief Examiner CAUTION: No plant equipment shall be operated during the performance of a JPM without the following:
- 1. Permission from the OS or Unit CRS;
- 2. Direct oversight by a qualified individual (determined by the individual granting permission based on plant conditions).
- 3. Verification of the as left condition by a qualified individual.
ACTUAL JPM COMPLETION TIME: Minutes ACTUAL TIME CRITICAL COMPLETION: N/A JPM PERFORMED BY: GRADE: SAT UNSAT REASON, IF UNSATISFACTORY:
EVALUATORS SIGNATURE: DATE:
Page 1 of 15
INITIAL LICENSED OPERATOR EXAMINATION JOB PERFORMANCE MEASURE NAME:
DATE:
SYSTEM: Conduct of Operations TASK: Conduct Weekly Power Distribution Lineup TASK NUMBER: 2630010201 INITIAL CONDITIONS:
- 1. Emergency Diesel Generator AG400 has a mechanical problem and is declared inoperable.
- 2. HC.OP-ST.ZZ-0001, Power Distribution Lineup-Weekly, is in progress.
- 3. This procedure is being performed to satisfy Technical Specification Surveillance requirement 4.8.1.1.1.a.
INITIATING CUE:
Perform HC.O-ST.ZZ-0001, POWER DISTRIBUTION LINEUP - WEEKLY to satisfy Technical Specification 4.8.1.1.1.a only.
Successful Completion Criteria:
- 1. All critical steps completed.
- 2. All sequential steps completed in order.
- 3. All time-critical steps completed within allotted time.
- 4. JPM completed within validated time. Completion time may exceed the validated time if satisfactory progress is being made.
Page 2 of 15
INITIAL LICENSED OPERATOR EXAMINATION NAME:
JOB PERFORMANCE MEASURE DATE:
SYSTEM: Conduct of Operations TASK: Conduct Weekly Power Distribution Lineup STEP COMMENTS
- STEP
(*Denotes a Critical Step) EVAL (Required for
- NO. STANDARD
(#Denotes a Sequential Step) S/U UNSAT evaluation)
Examiner Cue: Provide the operator with a copy of the partially completed procedure HC.OP-ST.ZZ-0001(Q).
Operator reviews precautions and Operator reviews precautions and limitations. limitations.
Examiner Cue: If excessive time is taken to review precautions and limitations, inform operator that all are satisfied.
Examiner Note: Initialling the following steps is not critical.
Operator determines beginning step Operator determines correct beginning of the procedure. step of procedure to be 5.1.
5.0 Power Distribution Lineup N/A N/A N/A 5.1 LOG test start time in the Control Operator requests that the start time be Room log(s). logged in the Control Room log.
Examiner Cue: The test start time has been logged in the Control Room log.
Operator initials the step.
Page 3 of 15
INITIAL LICENSED OPERATOR EXAMINATION NAME:
JOB PERFORMANCE MEASURE DATE:
SYSTEM: Conduct of Operations TASK: Conduct Weekly Power Distribution Lineup STEP COMMENTS
- STEP
(*Denotes a Critical Step) EVAL (Required for
- NO. STANDARD
(#Denotes a Sequential Step) S/U UNSAT evaluation) 5.2 ENSURE that all prerequisites have Operator ensures that the prerequisites been satisfied IAW Section 2.0 of this are satisfied:
procedure.
Observes that permission to complete the test has been given by the OS/CRS Operator completes Att. 1, Section 3 Ensures no other testing or maintenance is in progress that will adversely affect the performance of this test Examiner Cue: If asked, No other testing or maintenance is in progress that will adversely affect the performance of this test.
Operator initials the step.
5.3 ENSURE Attachment 1, Section 1.0 Operator observes that Attachment 1, of the OS/CRS Data and Signature Section 1.0 of the OS/CRS Data and Sheet has been completed and Signature Sheet has been completed Regular Surveillance or Retest is and Regular Surveillance is indicated.
indicated.
Operator initials the step.
Page 4 of 15
INITIAL LICENSED OPERATOR EXAMINATION NAME:
JOB PERFORMANCE MEASURE DATE:
SYSTEM: Conduct of Operations TASK: Conduct Weekly Power Distribution Lineup STEP COMMENTS
- STEP
(*Denotes a Critical Step) EVAL (Required for
- NO. STANDARD
(#Denotes a Sequential Step) S/U UNSAT evaluation) 5.4 IF performing this procedure to satisfy Operator determines that these sections T/S Surveillance 4.8.1.1.1.a ONLY, only are to be completed and initials PERFORM the following sections: step.
[T/S 4.8.1.1.1.a]
4.16KV SWITCHGEAR 10A401 4.16KV SWITCHGEAR 10A402 4.16KV SWITCHGEAR 10A403 4.16KV SWITCHGEAR 10A404 OFFSITE TO ONSITE DISTRIBUTION 5.5 RECORD M&TE identification Operator determines that this step is not numbers and calibration due dates for required and marks step as N/A.
test equipment utilized for this test on Attachment 3 THEN ASSIGN a Production Resource Tool (PRT) to activity 0220 of Order 80014483 for the M&TE utilized AND RECORD in the long text of the PRT the surveillance and date performed.
[80024844]
Page 5 of 15
INITIAL LICENSED OPERATOR EXAMINATION NAME:
JOB PERFORMANCE MEASURE DATE:
SYSTEM: Conduct of Operations TASK: Conduct Weekly Power Distribution Lineup STEP COMMENTS
- STEP
(*Denotes a Critical Step) EVAL (Required for
- NO. STANDARD
(#Denotes a Sequential Step) S/U UNSAT evaluation)
Operator observes the breaker positions, (and bus Voltage for the START TIME:
4.16KV busses) of those breakers listed in Attachment 2 for:
- 5.6 PERFORM Power Distribution Lineup 4.16KV SWITCHGEAR 10A401
- by completing Attachment 2.
4.16KV SWITCHGEAR 10A402 4.16KV SWITCHGEAR 10A403 4.16KV SWITCHGEAR 10A404 OFFSITE TO ONSITE DISTRIBUTION The operator notes that the voltages of 10A401 and 10A403 are UNSAT, and initials as the performer.
Examiner Note: See attached for expected Operator response.
Page 6 of 15
INITIAL LICENSED OPERATOR EXAMINATION NAME:
JOB PERFORMANCE MEASURE DATE:
SYSTEM: Conduct of Operations TASK: Conduct Weekly Power Distribution Lineup STEP COMMENTS
- STEP
(*Denotes a Critical Step) EVAL (Required for
- NO. STANDARD
(#Denotes a Sequential Step) S/U UNSAT evaluation)
- 5.7 IF any indication not specified in Operator determines that Voltages on Attachment 2 was used to satisfy this 10A401 and 10A403 were low and that surveillance THEN DOCUMENT AND the indications not specified in JUSTIFY its use in Section 2.1.5 of Attachment 2 were used to satisfy this Attachment 1. surveillance and documents the reason in Section 2.1.5 of Attachment 1.
Examiner Note: See attached. The description in 2.1.5 need not exactly match that provided, but must state a correct decision making process.
Operator initials the step.
5.8 LOG test end time in Control Room Examiner Cue: Log entry completed.
log(s). Operator initials the step.
5.9 SUBMIT this procedure to the Examiner Cue: Provide Terminating OS/CRS for review AND completion Cue.
of Attachment 1.
STOP TIME:
Terminating Cue: Repeat back message from the operator on the status of the JPM, and then state "This JPM is complete" Page 7 of 15
JOB PERFORMANCE MEASURE INITIAL CONDITIONS:
- 1. Emergency Diesel Generator AG400 has a mechanical problem and is declared inoperable.
- 2. HC.OP-ST.ZZ-0001, Power Distribution Lineup-Weekly, is in progress.
- 3. This procedure is being performed to satisfy Technical Specification Surveillance requirement 4.8.1.1.1.a.
INITIATING CUE:
Perform HC.O-ST.ZZ-0001, POWER DISTRIBUTION LINEUP - WEEKLY to satisfy Technical Specification 4.8.1.1.1.a only.
Page 8 of 15
JOB PERFORMANCE MEASURE SIMULATOR INSTRUCTIONS Reset Simulator to any IC-1 Setup Electrical Distribution System as noted on page 28 of Attachment 2.
Complete Section 1 for Regular Surveillance and 4.8.1.1.1.a ONLY.
Tag the A DG out of service Ensure voltage on 10A401 and 10A403 is reading ~4153 volts (CRIDS points A7061 and A7066)
Page 9 of 15
JOB PERFORMANCE MEASURE SIMULATOR INSTRUCTIONS ATTACHMENT 2 Page 6 of 34 INPLANT DATA SHEET POWER DISTRIBUTION LINEUP - WEEKLY 1.0 Power Distribution Lineup (Continued)
EQUIPMENT NOMENCLATURE REQUIRED ACTUAL SAT/ PERF UNSAT CHANNEL A 4.16KV SWGR 10A401 40101 ALTERNATE FEEDER BKR OPEN OPEN SAT Initials TO 10A401 40103 10A401 FEED TO 10B450 CLOSED CLOSED SAT Initials
- 40107 EDG AG400 OUTPUT BKR OPEN OPEN SAT Initials TO 10A401 40108 NORMAL FEEDER BKR CLOSED CLOSED SAT Initials TO BUS 10A401 40110 10A401 FEED TO 10B410 CLOSED CLOSED SAT Initials
- IF IN A NORMAL 2 BUS ALIGNMENT [(2) 4.16 KV CLASS 1E BUSES AND (1) 4.16 KV NON-1E BUS ON EACH STATION SERVICE TRANSFORMER (SST) (1AX501, 1BX501)] WITH TAP CHANGER IN AUTO, RECORD THE FOLLOWING READING (USE CRIDS AS PRIMARY INDICATION (FLUKE SECONDARY))
(NOTES 2,3,4,&6) 4.16 KV Bus CIRCLE ONE: CRIDS (A7061) 4173 - 4370 4153 UNSAT Initials
- 10A401 Voltage Fluke (Model 45) 119.09 - 125.0 IF IN AN ABNORMAL BUS ALIGNMENT [(3) 4.16 KV CLASS 1E BUSES AND (1) 4.16 KV NON-1E BUS ON (1)
SST; OR, (4) 4.16 KV CLASS 1E BUSES AND (2) 4.16 KV NON-1E BUS ON (1) SST) (NOTES 2, 3, 4, & 6) 4.16 KV Bus CIRCLE ONE: CRIDS (A7061) 4236 - 4370
- 10A401 Voltage Fluke (Model 45) 120.89 - 125.0
- The asterisk indicates Acceptance Criteria - in order to satisfy the requirements of the acceptance criteria, the SAT/UNSAT block must be marked SAT.
(2) Voltage outside MIN/MAX may be indicative of a malfunctioning Transformer Load Tap Changer when in automatic. COMPARE Bus Voltage with Station Service Transformer Sec. Voltage. IF Bus Voltage is outside the MIN/MAX take Manual control of Load Tap Changer and ADJUST until voltage is within range. Voltage > MAX with Load Tap Changer on 1 position is normal during certain conditions (i.e., HI grid voltage and/or no loads on bus.) (NOTE: If in a normal 2 bus alignment with tap changer in manual and voltage remains within established limits, tap changer should be returned to AUTO. (Refer to the appropriate CRIDS point for the Station Service Transformer Sec. Voltage). [70038637]
(3) Instructions on the use of a Fluke (Model 45) to obtain Bus Voltage Values can be found in HC.OP-SO.MC-0001(Z), 13.8 KV Switchyard Operation, Attachment 6 - Fluke (Model 45) Hookup and Voltage Readings at PT Secondary.
(4) IF Bus Voltage cannot be adjusted > MIN, DECLARE the respective offsite circuit of the A.C. electrical power source INOP AND ENTER T/S 3.8.1.1.a Action Statement.
IF Bus Voltage cannot be adjusted < MAX, GENERATE notification to Hope Creek Electrical / I&C, System Engineering documenting each voltage operating limit violation (start & stop times), so that 4.16 KV System Engineer can track and analyze voltage levels, IAW Notification 20184742. [70038770]
(6) 4.16 KV Buses supplied from a common Station Service Transformer (1AX501, 1BX501) have the same voltage and associated CRIDS points should read the same discounting instrument loop inaccuracies. If in normal 2 bus (or less) alignment, any of the following CRIDS points are considered equivalent and may be substituted for any other if one or more is a failed indicator: (For 1AX501: A3209, A3484, A7061, A7066) (For 1BX501: A3210, A3487, A7076, A7071)
Page 6 of 38 Rev.26
JOB PERFORMANCE MEASURE SIMULATOR INSTRUCTIONS ATTACHMENT 2 Page 9 of 34 INPLANT DATA SHEET POWER DISTRIBUTION LINEUP - WEEKLY 1.0 Power Distribution Lineup (Continued)
SAT/
EQUIPMENT NOMENCLATURE REQUIRED ACTUAL PERF UNSAT CHANNEL C 4.16KV SWGR 10A403 40301 ALTERNATE FEEDER BKR OPEN OPEN SAT Init TO 10A403 40303 10A403 FEED TO 10B470 CLOSED CLOSED SAT Init
- 40307 EDG CG400 OUTPUT BKR OPEN OPEN SAT Init TO 10A403 40308 NORMAL FEEDER BKR TO CLOSED CLOSED SAT Init 10A403 40310 10A403 FEED TO 10B430 CLOSED CLOSED SAT Init
- IF IN A NORMAL 2 BUS ALIGNMENT [(2) 4.16 KV CLASS 1E BUSES AND (1) 4.16 KV NON-1E BUS ON EACH STATION SERVICE TRANSFORMER (SST) (1AX501, 1BX501)] WITH TAP CHANGER IN AUTO, RECORD THE FOLLOWING READING (USE CRIDS AS PRIMARY INDICATION (FLUKE SECONDARY))
(NOTES 2,3,4,&6) 4.16 KV Bus CIRCLE ONE: CRIDS (A7066) 4173 - 4370 4153 UNSAT Init
- 10A403 Voltage Fluke (Model 45) 119.09 - 125.0 IF IN AN ABNORMAL BUS ALIGNMENT [(3) 4.16 KV CLASS 1E BUSES AND (1) 4.16 KV NON-1E BUS ON (1)
SST; OR, (4) 4.16 KV CLASS 1E BUSES AND (2) 4.16 KV NON-1E BUS ON (1) SST) (NOTES 2, 3, 4, & 6) 4.16 KV Bus CIRCLE ONE: CRIDS (A7066) 4236 - 4370
- 10A403 Voltage Fluke (Model 45) 120.89 - 125.0
- The asterisk indicates Acceptance Criteria - in order to satisfy the requirements of the acceptance criteria, the SAT/UNSAT block must be marked SAT.
(2) Voltage outside MIN/MAX may be indicative of a malfunctioning Transformer Load Tap Changer when in automatic. COMPARE Bus Voltage with Station Service Transformer Sec. Voltage. IF Bus Voltage is outside the MIN/MAX take Manual control of Load Tap Changer and ADJUST until voltage is within range. Voltage > MAX with Load Tap Changer on 1 position is normal during certain conditions (i.e., HI grid voltage and/or no loads on bus.) (NOTE: If in a normal 2 bus alignment with tap changer in manual and voltage remains within established limits, tap changer should be returned to AUTO. (Refer to the appropriate CRIDS point for the Station Service Transformer Sec. Voltage). [70038637]
(3) Instructions on the use of a Fluke (Model 45) to obtain Bus Voltage Values can be found in HC.OP-SO.MC-0001(Z), 13.8 KV Switchyard Operation, Attachment 6 - Fluke (Model 45) Hookup and Voltage Readings at PT Secondary.
(4) IF Bus Voltage cannot be adjusted > MIN, DECLARE the respective offsite circuit of the A.C. electrical power source INOP AND ENTER T/S 3.8.1.1.a Action Statement.
IF Bus Voltage cannot be adjusted < MAX, GENERATE notification to Hope Creek Electrical / I&C, System Engineering documenting each voltage operating limit violation (start & stop times), so that 4.16 KV System Engineer can track and analyze voltage levels, IAW Notification 20184742. [70038770]
(6) 4.16 KV Buses supplied from a common Station Service Transformer (1AX501, 1BX501) have the same voltage and associated CRIDS points should read the same discounting instrument loop inaccuracies. If in normal 2 bus (or less) alignment, any of the following CRIDS points are considered equivalent and may be substituted for any other if one or more is a failed indicator: (For 1AX501: A3209, A3484, A7061, A7066) (For 1BX501: A3210, A3487, A7076, A7071)
Page 6 of 38 Rev.26
JOB PERFORMANCE MEASURE SIMULATOR INSTRUCTIONS ATTACHMENT 2 Page 12 of 34 INPLANT DATA SHEET POWER DISTRIBUTION LINEUP - WEEKLY 1.0 Power Distribution Lineup (Continued)
EQUIPMENT NOMENCLATURE REQUIRED ACTUAL SAT/ PERF UNSAT CHANNEL B 4.16KV SWGR 10A402 40201 NORMAL FEEDER BKR TO CLOSED CLOSED SAT Init 10A402 40203 10A402 FEED TO 10B460 CLOSED CLOSED SAT Init
- 40207 EDG BG400 OUTPUT BKR TO OPEN OPEN SAT Init 10A402 40208 ALTERNATE FEEDER BKR TO OPEN OPEN SAT Init 10A402 40210 10A402 FEED TO 10B420 CLOSED CLOSED SAT Init
- IF IN A NORMAL 2 BUS ALIGNMENT [(2) 4.16 KV CLASS 1E BUSES AND (1) 4.16 KV NON-1E BUS ON EACH STATION SERVICE TRANSFORMER (SST) (1AX501, 1BX501)] WITH TAP CHANGER IN AUTO, RECORD THE FOLLOWING READING (USE CRIDS AS PRIMARY INDICATION (FLUKE SECONDARY))
(NOTES 2,3,4,&6) 4.16 KV Bus CIRCLE ONE: CRIDS (A7076) 4173 - 4370 4184 SAT Init
- 10A402 Voltage Fluke (Model 45) 119.09 - 125.0 IF IN AN ABNORMAL BUS ALIGNMENT [(3) 4.16 KV CLASS 1E BUSES AND (1) 4.16 KV NON-1E BUS ON (1)
SST; OR, (4) 4.16 KV CLASS 1E BUSES AND (2) 4.16 KV NON-1E BUS ON (1) SST) (NOTES 2, 3, 4, & 6) 4.16 KV Bus CIRCLE ONE: CRIDS (A7076) 4236 - 4370
- 10A402 Voltage Fluke (Model 45) 120.89 - 125.0
- The asterisk indicates Acceptance Criteria - in order to satisfy the requirements of the acceptance criteria, the SAT/UNSAT block must be marked SAT.
(2) Voltage outside MIN/MAX may be indicative of a malfunctioning Transformer Load Tap Changer when in automatic. COMPARE Bus Voltage with Station Service Transformer Sec. Voltage. IF Bus Voltage is outside the MIN/MAX take Manual control of Load Tap Changer and ADJUST until voltage is within range. Voltage > MAX with Load Tap Changer on 1 position is normal during certain conditions (i.e., HI grid voltage and/or no loads on bus.) (NOTE: If in a normal 2 bus alignment with tap changer in manual and voltage remains within established limits, tap changer should be returned to AUTO. (Refer to the appropriate CRIDS point for the Station Service Transformer Sec. Voltage). [70038637]
(3) Instructions on the use of a Fluke (Model 45) to obtain Bus Voltage Values can be found in HC.OP-SO.MC-0001(Z), 13.8 KV Switchyard Operation, Attachment 6 - Fluke (Model 45) Hookup and Voltage Readings at PT Secondary.
(4) IF Bus Voltage cannot be adjusted > MIN, DECLARE the respective offsite circuit of the A.C. electrical power source INOP AND ENTER T/S 3.8.1.1.a Action Statement.
IF Bus Voltage cannot be adjusted < MAX, GENERATE notification to Hope Creek Electrical / I&C, System Engineering documenting each voltage operating limit violation (start & stop times), so that 4.16 KV System Engineer can track and analyze voltage levels, IAW Notification 20184742. [70038770]
(6) 4.16 KV Buses supplied from a common Station Service Transformer (1AX501, 1BX501) have the same voltage and associated CRIDS points should read the same discounting instrument loop inaccuracies. If in normal 2 bus (or less) alignment, any of the following CRIDS points are considered equivalent and may be substituted for any other if one or more is a failed indicator: (For 1AX501: A3209, A3484, A7061, A7066) (For 1BX501: A3210, A3487, A7076, A7071)
Page 6 of 38 Rev.26
JOB PERFORMANCE MEASURE SIMULATOR INSTRUCTIONS ATTACHMENT 2 Page 15 of 34 INPLANT DATA SHEET POWER DISTRIBUTION LINEUP - WEEKLY 1.0 Power Distribution Lineup (Continued)
SAT/
EQUIPMENT NOMENCLATURE REQUIRED ACTUAL PERF UNSAT CHANNEL D 4.16KV SWGR 10A404 40401 NORMAL FEEDER BKR CLOSED CLOSED SAT Init TO 10A404 40403 10A404 FEED TO 10B480 CLOSED CLOSED SAT Init
- 40407 EDG DG400 OUTPUT BKR OPEN OPEN SAT Init TO 10A404 40408 ALTERNATE FEEDER BKR OPEN OPEN SAT Init TO 10A404 40410 10A404 FEED TO 10B440 CLOSED CLOSED SAT Init
- IF IN A NORMAL 2 BUS ALIGNMENT [(2) 4.16 KV CLASS 1E BUSES AND (1) 4.16 KV NON-1E BUS ON EACH STATION SERVICE TRANSFORMER (SST) (1AX501, 1BX501)] WITH TAP CHANGER IN AUTO, RECORD THE FOLLOWING READING (USE CRIDS AS PRIMARY INDICATION (FLUKE SECONDARY))
(NOTES 2,3,4,&6) 4.16 KV Bus CIRCLE ONE: CRIDS (A7071) 4173 - 4370 4184 SAT Init
- 10A404 Voltage Fluke (Model 45) 119.09 - 125.0 IF IN AN ABNORMAL BUS ALIGNMENT [(3) 4.16 KV CLASS 1E BUSES AND (1) 4.16 KV NON-1E BUS ON (1)
SST; OR, (4) 4.16 KV CLASS 1E BUSES AND (2) 4.16 KV NON-1E BUS ON (1) SST) (NOTES 2, 3, 4, & 6) 4.16 KV Bus CIRCLE ONE: CRIDS (A7071) 4236 - 4370
- 10A404 Voltage Fluke (Model 45) 120.89 - 125.0
- The asterisk indicates Acceptance Criteria - in order to satisfy the requirements of the acceptance criteria, the SAT/UNSAT block must be marked SAT.
(2) Voltage outside MIN/MAX may be indicative of a malfunctioning Transformer Load Tap Changer when in automatic. COMPARE Bus Voltage with Station Service Transformer Sec. Voltage. IF Bus Voltage is outside the MIN/MAX take Manual control of Load Tap Changer and ADJUST until voltage is within range. Voltage > MAX with Load Tap Changer on 1 position is normal during certain conditions (i.e., HI grid voltage and/or no loads on bus.) (NOTE: If in a normal 2 bus alignment with tap changer in manual and voltage remains within established limits, tap changer should be returned to AUTO. (Refer to the appropriate CRIDS point for the Station Service Transformer Sec. Voltage). [70038637]
(3) Instructions on the use of a Fluke (Model 45) to obtain Bus Voltage Values can be found in HC.OP-SO.MC-0001(Z), 13.8 KV Switchyard Operation, Attachment 6 - Fluke (Model 45) Hookup and Voltage Readings at PT Secondary.
(4) IF Bus Voltage cannot be adjusted > MIN, DECLARE the respective offsite circuit of the A.C. electrical power source INOP AND ENTER T/S 3.8.1.1.a Action Statement.
IF Bus Voltage cannot be adjusted < MAX, GENERATE notification to Hope Creek Electrical / I&C, System Engineering documenting each voltage operating limit violation (start & stop times), so that 4.16 KV System Engineer can track and analyze voltage levels, IAW Notification 20184742. [70038770]
(6) 4.16 KV Buses supplied from a common Station Service Transformer (1AX501, 1BX501) have the same voltage and associated CRIDS points should read the same discounting instrument loop inaccuracies. If in normal 2 bus (or less) alignment, any of the following CRIDS points are considered equivalent and may be substituted for any other if one or more is a failed indicator: (For 1AX501: A3209, A3484, A7061, A7066) (For 1BX501: A3210, A3487, A7076, A7071)
Page 6 of 38 Rev.26
JOB PERFORMANCE MEASURE SIMULATOR INSTRUCTIONS ATTACHMENT 2 Page 25 of 34 INPLANT DATA SHEET POWER DISTRIBUTION LINEUP - WEEKLY 1.0 Power Distribution Lineup (Continued)
SAT/ PERF EQUIPMENT NOMENCLATURE REQUIRED ACTUAL UNSAT OFFSITE TO ONSITE DISTRIBUTION +
BS4-5 13KV BUS SECTION 4-5 BKR CLOSED OPEN UNSAT Init
- BS6-7 13KV BUS SECTION 6-7 BKR CLOSED CLOSED SAT Init
- 2T60 STA XFMR T2 CIRCUIT SWITCHER CLOSED OPEN UNSAT Init
- BS3-4 500KV BUS SECTION 3-4 BKR CLOSED CLOSED SAT Init
- BS6-5 500KV BUS SECTION 6-5 BKR CLOSED CLOSED SAT Init
- BS7-8 13KV BUS SECTION 7-8 BKR OPEN OPEN SAT Init
- BS2-3 13KV BUS SECTION 2-3 BKR OPEN OPEN SAT Init
- BS1-2 13KV BUS SECTION 1-2 BKR CLOSED CLOSED SAT Init
- BS9-0 13KV BUS SECTION 9-10 BKR CLOSED CLOSED SAT Init
- BS1-3 500KV BUS SECTION 1-3 BKR CLOSED CLOSED SAT Init
- BS5-1 500KV BUS SECTION 5-1 BKR CLOSED CLOSED SAT Init
- BS2-6 500KV BUS SECTION 2-6 BKR CLOSED CLOSED SAT Init
- BS2-4 500KV BUS SECTION 2-4 BKR CLOSED CLOSED SAT Init *
+ NOTE: The above alignment represents the normal lineup of the 500Kv/13.8Kv Switchyards. Deviations may exist while still maintaining two independent offsite power source separation. IF actual alignment deviates from the above, CONSULT Electrical Drawing E-0001-0 to determine if proper separation exists, and IAW the following criteria: 500Kv Bus Sections 1 & 2 energized by two offsite sources (Red Lion 5015, New Freedom 5023, or Salem X-Tie 5037). Two feeds (10X and 20X) into a split 13.8Kv Yard, with each feed supplying power to an energized separate Station Service Transformer (AX501 and BX501). An independent offsite feed is considered available to the safety related distribution system IF all four of the 1E infeed breakers are OPERABLE. IF less than 4 breakers are OPERABLE, CONSIDER the offsite feed inoperable and comply with ACTION 3.8.1.1 as appropriate.
Page 6 of 38 Rev.26
JOB PERFORMANCE MEASURE SIMULATOR INSTRUCTIONS ATTACHMENT 1 Page 2 of 3 OS/CRS DATA AND SIGNATURE SHEET POWER DISTRIBUTION LINEUP - WEEKLY 2.0 POST TEST INFORMATION 2.1 The data acquired during the performance of this test has been reviewed for completeness and compliance with Technical Specification 4.8.3.1, 4.8.3.2, or 4.8.1.1.1.a and the test is considered:
2.1.1 SATISFACTORY (All acceptance criteria is marked SAT)
/
OS/CRS DATE-TIME 2.1.2 UNSATISFACTORY AND IF necessary the T.S. ACTION statement has been implemented.
/
OS/CRS DATE-TIME 2.1.4 Order No.
2.1.5 Remarks Lineup determined to be satisfactory even though not in the normal Lineup as described on page 28. Using the NOTE, determined that 500KV Bus Sections 1 & 2 energized by two offsite sources, Section 1 by And Section 2 by . 10X and 20X are split into the 13.8KV Yard, with each feed supplying power to an energized separate.
Station Service Transformers AX501 and BX501.
2 Voltages LOW for 10A401 and 10A403 Page 6 of 38 Rev.26
INITIAL LICENSED OPERATOR EXAMINATION JOB PERFORMANCE MEASURE STATION: HOPE CREEK SYSTEM: Equipment Control TASK: Conduct Reactor Recirculation Single Loop Operation TASK NUMBER: 2020140401 JPM NUMBER: NRC-ADM-002 ALTERNATE PATH: K/A NUMBER: 2.2.12 IMPORTANCE FACTOR: 3.0 3.4 APPLICABILITY: RO SRO RO X SRO X EVALUATION SETTING/METHOD: Simulator/Perform
REFERENCES:
HC.OP-ST.BB-0007, Rev. 10 TOOLS AND EQUIPMENT:
VALIDATED JPM COMPLETION TIME: 12 Minutes TIME PERIOD IDENTIFIED FOR TIME CRITICAL STEPS: N/A JPM SOURCE: Bank APPROVAL:
Author Facility Representative Chief Examiner CAUTION: No plant equipment shall be operated during the performance of a JPM without the following:
- 1. Permission from the OS or Unit CRS;
- 2. Direct oversight by a qualified individual (determined by the individual granting permission based on plant conditions).
- 3. Verification of the as left condition by a qualified individual.
ACTUAL JPM COMPLETION TIME: Minutes ACTUAL TIME CRITICAL N/A JPM PERFORMED BY: GRADE: SAT UNSAT REASON, IF UNSATISFACTORY:
EVALUATORS SIGNATURE: DATE:
Page 1 of 50
INITIAL LICENSED OPERATOR EXAMINATION JOB PERFORMANCE MEASURE NAME:
DATE:
SYSTEM: Equipment Control TASK: Conduct Reactor Recirculation Single Loop Operation TASK NUMBER: 2020140401 INITIAL CONDITIONS:
- 1. Recirculation Pump A has been removed from service.
- 2. Preparations for Single Loop Operations are in progress in accordance with HC.OP-IO.ZZ-0006.
- 3. Section 5.1, Jet Pump Operability Verification, of HC.OP-ST.BB-0007, Recirculation Jet Pump Operability-Single Loop-Daily, has been completed.
INITIATING CUE:
Perform Section 5.2, APRM % Flow to Total Core Flow Comparison, of HC.OP-ST.BB-0007, Recirculation Jet Pump Operability-Single Loop-Daily.
Successful Completion Criteria:
- 1. All critical steps completed.
- 2. All sequential steps completed in order.
- 3. All time-critical steps completed within allotted time.
- 4. JPM completed within validated time. Completion time may exceed the validated time if satisfactory progress is being made.
Page 2 of 50
INITIAL LICENSED OPERATOR EXAMINATION NAME:
JOB PERFORMANCE MEASURE DATE:
SYSTEM: Equipment Control TASK: Conduct Reactor Recirculation Single Loop Operation STEP COMMENTS
- STEP
(*Denotes a Critical Step) EVAL (Required for UNSAT
- NO. STANDARD
(#Denotes a Sequential Step) S/U evaluation)
Operator obtains/locates procedure Provide the operator with the partially HC.OP-ST.BB-0007. completed HC.OP-ST.BB-0007.
Operator reviews Precautions and Operator reviews Precautions and Limitations. Limitations and initials each Precaution and Limitation in the space provided in the procedure.
Examiner Cue: If excessive time is taken reviewing Precautions and Limitations, inform operator that all are satisfied.
Examiner Note: It is not critical to initial the procedure steps.
Operator determines beginning step of the Operator determines correct beginning step procedure. to be 5.2.1.
5.2.1 IF this is the first subsection of the Operator determines that this is not the first procedure to be performed THEN LOG subsection of the procedure to be test start time in the Control Room log(s). performed.
The operator then initials the appropriate procedure step.
Page 3 of 50
INITIAL LICENSED OPERATOR EXAMINATION NAME:
JOB PERFORMANCE MEASURE DATE:
SYSTEM: Equipment Control TASK: Conduct Reactor Recirculation Single Loop Operation STEP COMMENTS
- STEP
(*Denotes a Critical Step) EVAL (Required for UNSAT
- NO. STANDARD
(#Denotes a Sequential Step) S/U evaluation) 5.2.2 ENSURE that all prerequisites have been Operator reviews Prerequisites and initials satisfied IAW Section 2.2 of this each Prerequisite in the space provided in procedure. the procedure.
Examiner Cue: If excessive time is taken reviewing Prerequisites, inform operator that all are satisfied.
The operator then initials the appropriate procedure step.
5.2.3 ENSURE Attachment 1, Section 1.0 of Operator ensures Attachment 1, Section 1.0 the OS/CRS Data and Signature Sheet has of the OS/CRS Data and Signature Sheet been completed AND Regular has been completed and Regular Surveillance OR Retest is indicated. Surveillance or Retest is indicated.
The operator then initials the appropriate procedure step.
- 5.2.4 START TIME: Operator places the Meter Function Switch
channel, PLACE the Meter Function Switch to FLOW. The operator then initials the appropriate procedure step.
- 5.2.5 RECORD the value indicated for each Operator records the value indicated for
The operator then initials the appropriate procedure step.
Page 4 of 50
INITIAL LICENSED OPERATOR EXAMINATION NAME:
JOB PERFORMANCE MEASURE DATE:
SYSTEM: Equipment Control TASK: Conduct Reactor Recirculation Single Loop Operation STEP COMMENTS
- STEP
(*Denotes a Critical Step) EVAL (Required for UNSAT
- NO. STANDARD
(#Denotes a Sequential Step) S/U evaluation) 5.2.6 RETURN the Meter Function Switch at Operator returns the Meter Function Switch each APRM to the AVERAGE position. at each APRM to the AVERAGE position.
The operator then initials the appropriate procedure step.
- 5.2.7 Using the value of the highest APRM % Operator determines the established Total Flow obtained in Step 5.2.5, Core Flow from Attachment 10 using the DETERMINE the established Total Core highest APRM % Flow obtained in step Flow from Attachment 10. 5.2.5.
The operator then initials the appropriate procedure step.
5.2.8 ENTER the value obtained in Step 5.2.7 Operator enters the value obtained in step on Attachment 2. 5.2.7 on Attachment 2.
The operator then initials the appropriate procedure step.
5.2.9 ENTER the Total Core Flow obtained in Operator enters the Total Core Flow Step 5.1.4.F on Attachment 2. obtained in step 5.1.4.F on Attachment 2.
The operator then initials the appropriate procedure step.
Page 5 of 50
INITIAL LICENSED OPERATOR EXAMINATION NAME:
JOB PERFORMANCE MEASURE DATE:
SYSTEM: Equipment Control TASK: Conduct Reactor Recirculation Single Loop Operation STEP COMMENTS
- STEP
(*Denotes a Critical Step) EVAL (Required for UNSAT
- NO. STANDARD
(#Denotes a Sequential Step) S/U evaluation)
- 5.2.10 COMPARE the Total Core Flow from Operator compares the Total Core Flow
- Step 5.2.9 to the Established Total Core from step 5.2.9 to the Established Total Flow recorded in Step 5.2.8 (the Total Core Flow recorded in step 5.2.8 and Core Flow must be greater than or equal determines that the Total Core Flow is to the Established Total Core Flow). greater than the Established Total Core Flow.
Examiner Note: Entering SAT in 5.2.11 shows satisfactory completion.
The operator then initials the appropriate procedure step.
5.2.11 ENTER SAT OR UNSAT on Operator enters a SAT on Attachment 2.
Attachment 2. [T/S Table 4.3.1.1-1 Item 2.b Footnote (g)] The operator then initials the appropriate procedure step.
5.2.12 IF this is the final subsection of the Operator requests that the test end time in procedure THEN LOG test end time in the Control Room Narrative Log.
the Control Room log(s).
STOP TIME:
Terminating Cue: Repeat back message from the operator on the status of the JPM, and then state "This JPM is complete".
Page 6 of 50
JOB PERFORMANCE MEASURE INITIAL CONDITIONS:
- 1. Recirculation Pump A has been removed from service.
- 2. Preparations for Single Loop Operations are in progress in accordance with HC.OP-IO.ZZ-0006.
- 3. Section 5.1, Jet Pump Operability Verification, of HC.OP-ST.BB-0007, Recirculation Jet Pump Operability-Single Loop-Daily, has been completed.
INITIATING CUE:
Perform Section 5.2, APRM % Flow to Total Core Flow Comparison, of HC.OP-ST.BB-0007, Recirculation Jet Pump Operability-Single Loop-Daily.
Page 7 of 50
JOB PERFORMANCE MEASURE SIMULATOR INSTRUCTIONS Reset Simulator to IC-05.
Remove the A Recirculation Pump from service.
Insert a Group of control rods.
Raise Recirculation Pump B speed to 60%
Complete Section 5.1 of HC.OP-ST.BB-0007. Ensure data/plant conditions support successful completion of Section 5.2. Need to determine the Total Core Flow in step 5.1.4.F so that Total Core Flow is greater than or equal to the Established Total Core Flow.
Page 8 of 50
PSEG Internal Use Only TRAINING ONLY Page 9 of 1 PSEG NUCLEAR L.L.C.
HOPE CREEK GENERATING STATION HC.OP-ST.BB-0007(Q) - Rev. 8 RECIRCULATION JET PUMP OPERABILITY-SINGLE LOOP - DAILY USE CATEGORY: I REVISION
SUMMARY
Biennial Review performed Yes No N/A 9
- 1. IAW Generic procedure change identified under CR 990219121, (Closed To File), Limitation 3.2.1 was removed from this procedure. The direction contained in the Limitation regarding sequential performance of steps is adequately contained within higher tier administrative procedures including NC.NA-AP.ZZ-0001(Q) and NC.NA-WG.ZZ-0001(Q).
- 2. Based on request made by Reactor Engineering under Order 80018863, Note 5.1.4.F and steps 5.1.4.F.4 & 5 were revised to change the referenced flow value from 23,000 gpm to 23 kgpm.
The qualifying statements used in those steps were also revised to qualify the ACTION against flow exclusively, and not a combination of flow and Recirc Pump speed.
- 3. Based on writers review, the symbol % was added into title of section 5.2, and where used throughout procedure. Also added page numbering to attachments 8, 9, and 10. (no rev bars used)
- 4. Based on request made under Revision Request 96-0589 (TSSIP Comments), T/S references were added to body of procedure against steps which had an acceptance criteria against their signoff.
- 5. Based on request made under Order 80024441 the following changes were made:
- Revised steps 5.1.1 and 5.2.1 to state, IF this is the first subsection of the procedure to be performed, THEN LOG test start time in the Control Room log(s).
- Revised steps 5.1.10 and 5.2.12 to state, IF this is the final subsection of the procedure to be performed, THEN LOG test end time in the Control Room log(s).
- Revise steps 5.1.11 and 5.2.13 to state, IF this is the final subsection of the procedure to be performed, THEN SUBMIT this procedure to the OS/CRS for review and completion of Attachment 1.
- 6. Based on request made under DCP 80010289 ((Power Up Rate) (CD P514) Precaution 3.1.2 and Note # of Attachment 2 (Page 1 of 2) were modified to address the new MWTH value associated with < 38% Thermal Limit. (1268.8 versus 1251.3)
This entire revision can be considered editorial in nature.
IMPLEMENTATION REQUIREMENTS Effective date Implementation of DCP 80010289 APPROVED:
Manager Hope Creek Operations Date
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY RECIRCULATION JET PUMP OPERABILITY-SINGLE LOOP - DAILY TABLE OF CONTENTS SECTION TITLE PAGE 1.0 PURPOSE ................................................................................................................. 2 2.0 PREREQUISITES .................................................................................................... 2 3.0 PRECAUTIONS AND LIMITATIONS................................................................... 4 4.0 EQUIPMENT REQUIRED ...................................................................................... 4 5.0 PROCEDURE ........................................................................................................... 5 5.1 Jet Pump Operability Verification............................................................ 5 5.2 APRM % Flow to Total Core Flow Comparison ..................................... 9 6.0 RECORDS ................................................................................................................ 10
7.0 REFERENCES
.......................................................................................................... 10 ATTACHMENTS OS/CRS Data and Signature Sheet........................................................... 11 Control Room Data Sheet ........................................................................ 14 Inplant Data Sheet .................................................................................... 16 Pump Speed/Flow Curve Recirculation Loop "A"................................... 17 Pump Speed/Flow Curve Recirculation Loop "B"................................... 18 Recirc Pump "A" Flow vs Total Core Flow............................................. 19 Recirc Pump "B" Flow vs Total Core Flow ............................................. 20 Established % dp Graph - "A" Recirc Pump Operating........................... 21 Established % dp Graph - "B" Recirc Pump Operating ........................... 31 0 Established Total Core Flow vs APRM % Flow...................................... 41 Hope Creek Page 1 of 41 Rev. 10
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY RECIRCULATION JET PUMP OPERABILITY - SINGLE LOOP - DAILY 1.0 PURPOSE The purpose of this test is to determine the operability of the Reactor Recirculation Jet Pumps IAW the requirements specified in Technical Specifications Section 4.4.1.2.b, and, perform a comparison of established core flow at the existing recirculation loop flow (APRM % flow) to total core flow IAW the requirements specified in Technical Specifications Table 4.3.1.1-1 item 2.b footnote (g).
2.0 PREREQUISITES 2.1 Jet Pump Operability Verification 2.1.1 Permission to perform this test has been obtained from the OS/CRS as indicated by the completion of Attachment 1, Section 1.0.
RC 2.1.2 All personnel performing any steps in this procedure should complete RC Attachment 1, Section 3.0, prior to performing any part of this procedure. ______
2.1.3 The NCO has been informed that the following test is to be performed RC and the following alarms, indications and functions will be observed. ______
A. Alarms None B. Indications None C. Functions None 2.1.4 Plant is in Condition 1 or 2. RC 2.1.5 No other testing OR maintenance is in progress that will adversely affect the performance of this test. RC 2.1.6 Recirculation Pump A OR B is operating in Local Manual Mode IAW HC.OP-SO.BB-0002(Q),
Reactor Recirculation System Operation. [T/S 3.4.1.1.a.1]
RC Hope Creek Page 2 of 41 Rev. 10
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY 2.1.7 THERMAL POWER is < 70% of RATED THERMAL POWER.
[T/S 3.4.1.1.a.1]
RC 2.1.8 The speed of the operating Recirculation Pump should be limited to <90% of rated pump speed. [T/S 3.4.1.1.a.1] RC (90% of rated pump speed is 79% indicated.) ______
2.1.9 IF this is the first time the unit has entered single loop operation this operating cycle, WITH the current loop in operation, new single loop baseline data for the operating loop must be recorded IAW HC.OP-FT.BB-0001(Q), Jet Pump Data Acquisition.
Reactor Engineering must be notified to start analyzing data collected, AND a revision to this surveillance must be initiated.
RC 2.2 APRM % Flow to Total Core Flow Comparison 2.2.1 Permission to perform this test has been obtained from the OS/CRS as indicated by the completion of Attachment 1, Section 1.0.
RC 2.2.2 All personnel performing any steps in this procedure should complete RC Attachment 1, Section 3.0, prior to performing any part of this procedure. ______
2.2.3 The NCO has been informed that the following test is to be performed RC and the following alarms, indications and functions will be observed. ______
A. Alarms None B. Indications None C. Functions None 2.2.4 Plant is in Condition 1 or 2.
RC 2.3.5 No other testing OR maintenance is in progress that will adversely affect the performance of this test.
RC Hope Creek Page 3 of 41 Rev. 10
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY 3.0 PRECAUTIONS AND LIMITATIONS 3.1 Precautions 3.1.1 IF at any time during the performance of this test, a step can not be completed OR is observed to be unsatisfactory; IMMEDIATELY NOTIFY the NCO and OS/CRS. [CD-927E]
RC 3.1.2 Within NO MORE THAN 15 minutes prior to either THERMAL POWER increase or Recirculation Loop flow increase, verify the following differential temperature requirements are met if THERMAL POWER is
< 38% (1268.8 MWTH) of RATED THERMAL POWER or the Recirculation Loop flow in the operating loop is < 50% (22.6 KGPM) of rated loop flow by performing Attachment 3v of HC.OP-DL.ZZ-0026(Q), Surveillance Log. The temperature requirements in Steps 3.1.2.B and 3.1.2.C do not apply when the loop not in operation is isolated from the reactor pressure vessel:
RC A. < 145°F between Reactor Vessel steam space coolant AND bottom head drain line coolant.
RC B. < 50°F between the Reactor coolant within the loop not in operation RC AND the coolant in the reactor vessel. ______
C. < 50°F between the Reactor coolant within the loop not in operation RC AND the operating loop. ______
3.2 Limitations 3.2.1 The Surveillance requirements of Technical Specifications Section 4.4.1.2.b AND Technical Specifications Table 4.3.1.1-1 item 2.b footnote (g), can be satisfied using curves generated from data collected during previous operating cycles (i.e., use current rev.), while new baseline data is being analyzed AND processed into a new revision to this surveillance.
RC 3.2.2 IF satisfactory results can not be obtained using the curves generated from data collected during previous operating cycles, but can be obtained using the curves generated from data collected for the current operating cycle using HC.OP-FT.BB-0001(Q), Jet Pump Data Acquisition (following data analysis),
THEN an On-The-Spot change to this procedure should be processed to incorporate the new single loop baseline data for the operating loop .
RC 4.0 EQUIPMENT REQUIRED None Hope Creek Page 4 of 41 Rev. 10
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY 5.0 PROCEDURE NOTE 5.0 Individual Jet Pump dp's are obtained on Panel 10C619, Aux Bldg Control Area El. 102'.
5.1 Jet Pump Operability Verification 5.1.1 IF this is the first subsection of the procedure to be performed THEN LOG test start time in the Control Room log(s).
RC 5.1.2 ENSURE that all prerequisites have been satisfied IAW Section 2.1 of this procedure.
RC 5.1.3 ENSURE Attachment 1, Section 1.0 of the OS/CRS Data and Signature Sheet has been completed and Regular Surveillance RC or Retest is indicated. ______
5.1.4 RECORD the following information in the appropriate spaces on Attachment 2:
RC A. ENTER Recirculation Pump "A" speed RC IF operating, otherwise N/A. ______
B. ENTER Recirculation Pump "B" speed IF operating, otherwise N/A.
RC C. ENTER Recirculation Pump "A" flow IF operating, otherwise N/A.
RC D. ENTER Recirculation Pump "B" flow IF operating, otherwise N/A.
RC E. IF Recirculation Pump "A" is operating, ENTER SAT IF Recirculation Pump "A" flow is within + 10% of the established curve (at given speed) on Attachment 4, (otherwise, UNSAT). [T/S 4.4.1.2.b.1] RC IF Recirculation Pump "B" is operating, ENTER SAT IF Recirculation Pump "B" flow is within + 10% of the established curve (at given speed) on Attachment 5, (otherwise, UNSAT). [T/S 4.4.1.2.b.1]
RC Continued next page Hope Creek Page 5 of 41 Rev. 10
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY 5.1.4 (continued)
NOTE 5.1.4.F A. If the operating loop drive flow is > 23 kgpm ( 48% Recirc Pump speed) then the flow in the idle loop is negative (reverse) flow.
B. If the operating loop drive flow is < 23 kgpm ( 48% Recirc Pump speed) then the flow in the idle loop is positive (forward) flow.
F. CALCULATE Total Core Flow as follows:
RC
- 1. ENTER whether Jet Pump Loop Total Flow A AND B is from GETARS OR Flow Indicators. RC
- 2. ENTER Jet Pump Loop Total Flow A.
RC
- 3. ENTER Jet Pump Loop Total Flow B.
RC
- 4. IF the operating loop drive flow is > 23 kgpm
( 48% Recirc Pump speed)
PERFORM the following:
RC
- a. IF Recirculation Pump A is operating, MULTIPLY the value obtained in Step 3 by 0.85, THEN SUBTRACT the resultant value from the value obtained in Step 2 AND ENTER calculated Total Core Flow. RC PROCEED to Step 5.1.4.G. ______
- b. IF Recirculation Pump B is operating, MULTIPLY the value obtained in Step 2 by 0.85, THEN SUBTRACT the resultant value from the value obtained in Step 3 AND ENTER calculated Total Core Flow.
PROCEED to Step 5.1.4.G.
RC Continued next page Hope Creek Page 6 of 41 Rev. 10
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY 5.1.4.F (continued)
- 5. IF the operating loop drive flow is < 23 kgpm
( 48% Recirc Pump speed) RC ADD the values obtained in Steps 2 and 3. ______
- 6. ENTER the total obtained in Step 5 as calculated Total Core Flow.
RC G. ENTER SAT IF calculated Total Core Flow is within + 10% of the established curve (at given operating Recirc Pump flow) on Attachment 6, Recirculation Pump Flow "A" vs Total Core Flow Curve, OR on Attachment 7, Recirculation Pump Flow "B" vs Total Core Flow RC Curve, (otherwise, UNSAT). [T/S 4.4.1.2.b.2] ______
NOTE 5.1.5 A. The constant motion of the individual jet pump d/p indicators makes data acquisition difficult. The recommended method is to take a high and a low reading and use their average. Noise is the most positive indication that the jet pump is operating.
B. Jet Pump d/p indication accuracy and readability are marginal during periods of low Core flow. Attempt to maximize Recirc Pump speeds before performing the following steps.
C. Jet pump data is only required for jet pumps 1 - 10 when "B" Recirc. Loop is in operation, and jet pumps 11 - 20 WHEN "A" Recirc. Loop is in operation.
5.1.5 COMPLETE Attachment 3 for individual Jet Pumps in the operating Recirc. Loop ONLY.
RC 5.1.6 DETERMINE on Attachment 3 whether the % dp is within + 20% of the established curve for the appropriate operating Recirc Pump (at a given speed) on Attachment 8 or 9.
RC 5.1.7 RECORD SAT RC OR UNSAT on Attachment 3. ______
5.1.8 On Attachment 2 ENTER SAT IF all individual Jet Pumps are recorded as SAT RC on Attachment 3 (otherwise, UNSAT). [T/S 4.4.1.2.b.3] ______
Hope Creek Page 7 of 41 Rev. 10
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY 5.1.9 ENTER THERMAL POWER from Core Performance Calculation (POLCA Report)
OR OD3 on Attachment 2. RC 5.1.10 IF this is the final subsection of the procedure THEN LOG test end time in the Control Room log(s).
RC 5.1.11 IF this is the final subsection of the procedure to be performed THEN SUBMIT this procedure to the OS/CRS for review RC AND completion of Attachment 1. ______
Hope Creek Page 8 of 41 Rev. 10
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY 5.2 APRM % Flow to Total Core Flow Comparison 5.2.1 IF this is the first subsection of the procedure to be performed THEN LOG test start time in the Control Room log(s). ______
5.2.2 ENSURE that all prerequisites have been satisfied IAW Section 2.2 of this procedure. ______
5.2.3 ENSURE Attachment 1, Section 1.0 of the OS/CRS Data and Signature Sheet has been completed AND Regular Surveillance OR Retest is indicated. ______
5.2.4 At APRM panel 10C608, at each APRM channel, PLACE the Meter Function Switch to FLOW. ______
5.2.5 RECORD the value indicated for each APRMs flow on Attachment 2. ______
5.2.6 RETURN the Meter Function Switch at each APRM to the AVERAGE position. ______
5.2.7 Using the value of the highest APRM % Flow obtained in Step 5.2.5, DETERMINE the established Total Core Flow from Attachment 10. ______
5.2.8 ENTER the value obtained in Step 5.2.7 on Attachment 2. ______
5.2.9 ENTER the Total Core Flow obtained in Step 5.1.4.F on Attachment 2. ______
5.2.10 COMPARE the Total Core Flow from Step 5.2.9 to the Established Total Core Flow recorded in Step 5.2.8 (the Total Core Flow must be greater than or equal to the Established Total Core Flow). ______
5.2.11 ENTER SAT OR UNSAT on Attachment 2.
[T/S Table 4.3.1.1-1 Item 2.b Footnote (g)] ______
5.2.12 IF this is the final subsection of the procedure THEN LOG test end time in the Control Room log(s). ______
5.2.13 IF this is the final subsection of the procedure to be performed THEN SUBMIT this procedure to the OS/CRS for review AND completion of Attachment 1. ______
Hope Creek Page 9 of 41 Rev. 10
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY 6.0 RECORDS 6.1 RETAIN the following IAW NC.NA-AP.ZZ-0003(Q); Document Management Program:
- Attachment 1 - OS/CRS Data and Signature Sheet
- Attachment 2 - Control Room Data Sheet
- Attachment 3 - Inplant Data Sheet
7.0 REFERENCES
7.1 GEK 90333 and 90334 7.2 GE SIL No. 330 7.3 GE SIL No. 517 7.4 HCGS FSAR TABLE 5.4.1 (for loop flow rated)
Hope Creek Page 10 of 41 Rev. 10
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY ATTACHMENT 1 OS/CRS DATA AND SIGNATURE SHEET RECIRCULATION JET PUMP OPERABILITY-SINGLE LOOP - DAILY (Page 1 of 3) 1.0 PRETEST INFORMATION 1.1 Reason for the Test 1.1.1 Regular Surveillance JS INITIALS 1.1.2 Retest/Other INITIALS 1.1.3 IF not performing the complete test, THEN LIST subsection to be performed, as well as marking N/A on the applicable subsection on the Attachment(s) that will not be performed, OR, that do not require an independent verification IAW NC.NA-AP.ZZ-0005(Q); Station Operating Practices.
SUBSECTION(S) 1.2 Plant Conditions 1.2.1 Operational Condition 1 1.2.2 Reactor Power Level 58%
1.2.3 GMWe 1.3 Permission to Perform the Test 1.3.1 Permission granted to perform this test.
John Smith / Today/0700 OS/CRS DATE-TIME 1.3.2 Work Order No. 456145678941 Hope Creek Page 11 of 41 Rev. 10
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY ATTACHMENT 1 OS/CRS DATA AND SIGNATURE SHEET RECIRCULATION JET PUMP OPERABILITY-SINGLE LOOP - DAILY (Page 2 of 3) 2.0 POST TEST INFORMATION 2.1 The data acquired during the performance of this test has been reviewed for completeness and compliance with Technical Specification 4.4.1.2.b and Table 4.3.1.1-1 item 2.b footnote (g) and the test is considered:
2.1.1 SATISFACTORY (All acceptance criteria is marked SAT)
/
OS/CRS DATE-TIME 2.1.2 UNSATISFACTORY AND IF necessary the T/S ACTION statement has been implemented.
/
OS/CRS DATE-TIME 2.1.3 Order No. __________________________________________________
2.1.4 Remarks__________________________________________________________
Hope Creek Page 12 of 41 Rev. 10
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY ATTACHMENT 1 OS/CRS DATA AND SIGNATURE SHEET RECIRCULATION JET PUMP OPERABILITY-SINGLE LOOP - DAILY (Page 3 of 3) 3.0 PROCEDURE PERFORMER(S) AND VERIFIER(S) 3.1 I have read and understand the steps of this procedure that I am responsible to perform.
(All Departments)
PRINT NAME SIGNATURE INITIALS DATE/TIME Russel Crowe / Russel Crowe / RC / Today/0800
/ / /
/ / /
/ / /
/ / /
/ / /
/ / /
/ / /
/ / /
/ / /
/ / /
/ / /
/ / /
/ / /
/ / /
Hope Creek Page 13 of 41 Rev. 10
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY ATTACHMENT 2 CONTROL ROOM DATA SHEET RECIRCULATION JET PUMP OPERABILITY-SINGLE LOOP - DAILY (Page 1 of 2) 2.1 Jet Pump Operability Verification STEP NOMENCLATURE VALUE 5.1.4.A RECIRCULATION PUMP "A" SPEED 1-BB-SIC-R621A 5.1.4.B RECIRCULATION PUMP "B" SPEED 1-BB-SIC-R621B 5.1.4.C RECIRCULATION PUMP "A" FLOW 1-BB-FI-R617-B31 #
KGPM 5.1.4.D RECIRCULATION PUMP "B" FLOW 1-BB-FI-R613-B31 #
KGPM 5.1.4.E "A" PUMP SPEED/FLOW DEVIATION CHECK *
"B" PUMP SPEED/FLOW DEVIATION CHECK
- 5.1.4.F.1 JET PUMP LOOP TOTAL FLOW "A" and "B" (GETARS or FLOW INDICATORS) 5.1.4.F.2 JET PUMP LOOP TOTAL FLOW "A" (FI-R611A-B21 or GETARS PID CHNL 040/STR# 065) MLB/HR 5.1.4.F.3 JET PUMP LOOP TOTAL FLOW "B" (FI-R611B-B21 or GETARS PID CHNL 041/STR# 066) MLB/HR 5.1.4.F.4.a (b) OR TOTAL (CALCULATED) CORE FLOW 5.1.4.F.6 MLB/HR **
5.1.4.G RECIRC PUMP FLOW vs TOTAL CORE FLOW CHECK
- 5.1.8 JET PUMP DIFFERENTIAL PRESSURE CHECK
- 5.1.9 CORE THERMAL POWER P1 or OD3 #
MWTH
- Acceptance Criterion - At least two of three blocks must be marked SAT (REFER to Tech Spec 4.4.1.2.b).
- IF > 35 MLB/HR AND < 45 MLB/HR, SEE precaution 3.1.3.
- IF THERMAL POWER is < 38% (1268.8 MWTH) of RATED THERMAL POWER OR Recirculation Loop flow in the operating loop is < 22.6 KGPM, SEE Precaution 3.1.2.
Hope Creek Page 14 of 41 Rev. 10
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY ATTACHMENT 2 CONTROL ROOM DATA SHEET RECIRCULATION JET PUMP OPERABILITY-SINGLE LOOP - DAILY (Page 2 of 2) 2.2 APRM % Flow to Total Core Flow Comparison STEP NOMENCLATURE VALUE APRM F % FLOW APRM D % FLOW 5.2.5 APRM B % FLOW APRM A % FLOW APRM C % FLOW APRM E % FLOW 5.2.8 ESTABLISHED TOTAL CORE FLOW FOR HIGHEST APRM %
FLOW (Attachment 10) 5.2.9 TOTAL (CALCULATED) CORE FLOW STEP NOMENCLATURE SAT/UNSAT PERF 5.2.11 TOTAL CORE FLOW (5.2.9) IS GREATER THAN OR EQUAL TO ESTABLISHED TOTAL CORE FLOW (5.2.8) *
- Acceptance Criterion - the SAT/UNSAT block must be marked SAT.
Hope Creek Page 15 of 41 Rev. 10
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY ATTACHMENT 3 INPLANT DATA SHEET RECIRCULATION JET PUMP OPERABILITY-SINGLE LOOP - DAILY (Page 1 of 1) 2.2 Jet Pump Operability Verification (LOCATED ON PANEL 10C619) 5.1.7 COLUMN A JET PUMP INDIVIDUAL JET COLUMN A WITHIN + 20% OF PUMP % dp ESTABLISHED % dp on ATTACHMENT 8 or 9 ENTER SAT OR UNSAT JP-1 JP-2 JP-3 JP-4 JP-5 JP-6 JP-7 JP-8 JP-9 JP-10 JP-11 JP-12 JP-13 JP-14 JP-15 JP-16 JP-17 JP-18 JP-19 JP-20 Hope Creek Page 16 of 41 Rev. 10
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY ATTACHMENT 4 PUMP SPEED/FLOW CURVE RECIRCULATION LOOP "A" (Page 1 of 1)
RECIRCULATION PUMP "A" FLOW (KGPM) 50 50 45 45 40 40 35 35 30 30 25 25 20 20 15 15 10 10 5 5 0 0 25 30 35 40 45 50 55 60 65 70 75 80 RECIRC PUMP "A" SPEED (%)
Cycle 5, SLO A (1-BB-SIC-R621A)
Hope Creek Page 17 of 41 Rev. 10
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY ATTACHMENT 5 PUMP SPEED/FLOW CURVE RECIRCULATION LOOP "B" (Page 1 of 1)
RECIRCULATION PUMP "B" FLOW (KGPM) 50 50 45 45 40 40 35 35 30 30 25 25 20 20 15 15 10 10 5 5 0 0 20 25 30 35 40 45 50 55 60 65 70 75 80 RECIRCULATION PUMP "B" SPEED (%)
Cycle 5, SLO B (1-BB-SIC-R621B)
Hope Creek Page 18 of 41 Rev. 10
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY ATTACHMENT 6 RECIRC PUMP "A" FLOW vs TOTAL CORE FLOW CURVE (Page 1 of 1)
TOTAL CORE FLOW (MLB/HR) 56 56 54 54 52 52 50 50 48 48 46 46 44 44 42 42 40 40 38 38 36 36 34 34 32 32 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 RECIRCULATION PUMP "A" FLOW (KGPM)
(1-BB-FI-R617-B31) ycle 5, SLO A, PP/CORE FLOW Hope Creek Page 19 of 41 Rev. 10
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY ATTACHMENT 7 RECIRC PUMP "B" FLOW vs TOTAL CORE FLOW CURVE (Page 1 of 1)
TOTAL CORE FLOW (MLB/HR) 56 56 54 54 52 52 50 50 48 48 46 46 44 44 42 42 40 40 38 38 36 36 34 34 32 32 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 RECIRCULATION PUMP "B" FLOW (KGPM)
(1-BB-FI-R613-B31)
Cycle 5, SLO B, PP/CORE FLOW Hope Creek Page 20 of 41 Rev. 10
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY ATTACHMENT 8 ESTABLISHED % dP GRAPH - "A" RECIRC PUMP OPERATING (Page 1 of 10)
JET PUMP 11 JET PUMP DIFFERENTIAL PRESS (%dp) 75 75 70 70 65 65 60 60 55 55 50 50 45 45 40 40 35 35 30 30 25 25 20 20 15 15 10 10 5 5 0 0 25 30 35 40 45 50 55 60 65 70 75 80 RECIRC PUMP "A" SPEED (%)
(1-BB-SIC-R621A)
Cycle 5, SLO A, JP11 Hope Creek Page 21 of 41 Rev. 10
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY ATTACHMENT 8 ESTABLISHED % dP GRAPH - "A" RECIRC PUMP OPERATING (Page 2 of 10)
JET PUMP 12 JET PUMP DIFFERENTIAL PRESS (%dp) 75 75 70 70 65 65 60 60 55 55 50 50 45 45 40 40 35 35 30 30 25 25 20 20 15 15 10 10 5 5 0 0 25 30 35 40 45 50 55 60 65 70 75 80 RECIRC PUMP "A" SPEED (%)
(1-BB-SIC-R621A)
Cycle 5, SLO A, JP12 Hope Creek Page 22 of 41 Rev. 10
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY ATTACHMENT 8 ESTABLISHED % dP GRAPH - "A" RECIRC PUMP OPERATING (Page 3 of 10)
JET PUMP 13 JET PUMP DIFFERENTIAL PRESS (%dp) 75 75 70 70 65 65 60 60 55 55 50 50 45 45 40 40 35 35 30 30 25 25 20 20 15 15 10 10 5 5 0 0 25 30 35 40 45 50 55 60 65 70 75 80 RECIRC PUMP "A" SPEED (%)
(1-BB-SIC-R621A)
Cycle 5, SLO A, JP13 Hope Creek Page 23 of 41 Rev. 10
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY ATTACHMENT 8 ESTABLISHED % dP GRAPH - "A" RECIRC PUMP OPERATING (Page 4 of 10)
JET PUMP 14 JET PUMP DIFFERENTIAL PRESS (%dp) 75 75 70 70 65 65 60 60 55 55 50 50 45 45 40 40 35 35 30 30 25 25 20 20 15 15 10 10 5 5 0 0 25 30 35 40 45 50 55 60 65 70 75 80 RECIRC PUMP "A" SPEED (%)
(1-BB-SIC-R621A)
Cycle 5, SLO A, JP14 Hope Creek Page 24 of 41 Rev. 10
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY ATTACHMENT 8 ESTABLISHED % dP GRAPH - "A" RECIRC PUMP OPERATING (Page 5 of 10)
JET PUMP 15 JET PUMP DIFFERENTIAL PRESS (%dp) 75 75 70 70 65 65 60 60 55 55 50 50 45 45 40 40 35 35 30 30 25 25 20 20 15 15 10 10 5 5 0 0 25 30 35 40 45 50 55 60 65 70 75 80 RECIRC PUMP "A" SPEED (%)
(1-BB-SIC-R621A)
Cycle 5, SLO A, JP15 Hope Creek Page 25 of 41 Rev. 10
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY ATTACHMENT 8 ESTABLISHED % dP GRAPH - "A" RECIRC PUMP OPERATING (Page 6 of 10)
JET PUMP 16 JET PUMP DIFFERENTIAL PRESS (%dp) 75 75 70 70 65 65 60 60 55 55 50 50 45 45 40 40 35 35 30 30 25 25 20 20 15 15 10 10 5 5 0 0 25 30 35 40 45 50 55 60 65 70 75 80 RECIRC PUMP "A" SPEED (%)
(1-BB-SIC-R621A)
Cycle 5, SLO A, JP16 Hope Creek Page 26 of 41 Rev. 10
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY ATTACHMENT 8 ESTABLISHED % dP GRAPH - "A" RECIRC PUMP OPERATING (Page 7 of 10)
JET PUMP 17 JET PUMP DIFFERENTIAL PRESS (%dp) 75 75 70 70 65 65 60 60 55 55 50 50 45 45 40 40 35 35 30 30 25 25 20 20 15 15 10 10 5 5 0 0 25 30 35 40 45 50 55 60 65 70 75 80 RECIRC PUMP "A" SPEED (%)
(1-BB-SIC-R621A)
Cycle 5, SLO A, JP17 Hope Creek Page 27 of 41 Rev. 10
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY ATTACHMENT 8 ESTABLISHED % dP GRAPH - "A" RECIRC PUMP OPERATING (Page 8 of 10)
JET PUMP 18 JET PUMP DIFFERENTIAL PRESS (%dp) 75 75 70 70 65 65 60 60 55 55 50 50 45 45 40 40 35 35 30 30 25 25 20 20 15 15 10 10 5 5 0 0 25 30 35 40 45 50 55 60 65 70 75 80 RECIRC PUMP "A" SPEED (%)
(1-BB-SIC-R621A)
Cycle 5, SLO A, JP18 Hope Creek Page 28 of 41 Rev. 10
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY ATTACHMENT 8 ESTABLISHED % dP GRAPH - "A" RECIRC PUMP OPERATING (Page 9 of 10)
JET PUMP 19 JET PUMP DIFFERENTIAL PRESS (%dp) 75 75 70 70 65 65 60 60 55 55 50 50 45 45 40 40 35 35 30 30 25 25 20 20 15 15 10 10 5 5 0 0 25 30 35 40 45 50 55 60 65 70 75 80 RECIRC PUMP "A" SPEED (%)
(1-BB-SIC-R621A)
Cycle 5, SLO A, JP19 Hope Creek Page 29 of 41 Rev. 10
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY ATTACHMENT 8 ESTABLISHED % dP GRAPH - "A" RECIRC PUMP OPERATING (Page 10 of 10)
JET PUMP 20 JET PUMP DIFFERENTIAL PRESS (%dp) 75 75 70 70 65 65 60 60 55 55 50 50 45 45 40 40 35 35 30 30 25 25 20 20 15 15 10 10 5 5 0 0 25 30 35 40 45 50 55 60 65 70 75 80 RECIRC PUMP "A" SPEED (%)
(1-BB-SIC-R621A)
Cycle 5, SLO A, JP20 Hope Creek Page 30 of 41 Rev. 10
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY ATTACHMENT 9 ESTABLISHED % dP GRAPH - "B" RECIRC PUMP OPERATING (Page 1 of 10)
JET PUMP 01 JET PUMP DIFFERENTIAL PRESS (%dp) 75 75 70 70 65 65 60 60 55 55 50 50 45 45 40 40 35 35 30 30 25 25 20 20 15 15 10 10 5 5 0 0 20 25 30 35 40 45 50 55 60 65 70 75 80 RECIRC PUMP "B" SPEED (%)
(1-BB-SIC-R621B)
Cycle 5, SLO B, JP1 Hope Creek Page 31 of 41 Rev. 10
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY ATTACHMENT 9 ESTABLISHED % dP GRAPH - "B" RECIRC PUMP OPERATING (Page 2 of 10)
JET PUMP 02 JET PUMP DIFFERENTIAL PRESS (%dp) 75 75 70 70 65 65 60 60 55 55 50 50 45 45 40 40 35 35 30 30 25 25 20 20 15 15 10 10 5 5 0 0 20 25 30 35 40 45 50 55 60 65 70 75 80 RECIRC PUMP "B" SPEED (%)
(1-BB-SIC-R621B)
Cycle 5, SLO B, JP2 Hope Creek Page 32 of 41 Rev. 10
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY ATTACHMENT 9 ESTABLISHED % dP GRAPH - "B" RECIRC PUMP OPERATING (Page 3 of 10)
JET PUMP 03 JET PUMP DIFFERENTIAL PRESS (%dp) 75 75 70 70 65 65 60 60 55 55 50 50 45 45 40 40 35 35 30 30 25 25 20 20 15 15 10 10 5 5 0 0 20 25 30 35 40 45 50 55 60 65 70 75 80 RECIRC PUMP "B" SPEED (%)
(1-BB-SIC-R621B)
Cycle 5, SLO B, JP3 Hope Creek Page 33 of 41 Rev. 10
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY ATTACHMENT 9 ESTABLISHED % dP GRAPH - "B" RECIRC PUMP OPERATING (Page 4 of 10)
JET PUMP 04 JET PUMP DIFFERENTIAL PRESS (%dp) 75 75 70 70 65 65 60 60 55 55 50 50 45 45 40 40 35 35 30 30 25 25 20 20 15 15 10 10 5 5 0 0 20 25 30 35 40 45 50 55 60 65 70 75 80 RECIRC PUMP "B" SPEED (%)
(1-BB-SIC-R621B)
Cycle 5, SLO B, JP4 Hope Creek Page 34 of 41 Rev. 10
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY ATTACHMENT 9 ESTABLISHED % dP GRAPH - "B" RECIRC PUMP OPERATING (Page 5 of 10)
JET PUMP 05 JET PUMP DIFFERENTIAL PRESS (%dp) 75 75 70 70 65 65 60 60 55 55 50 50 45 45 40 40 35 35 30 30 25 25 20 20 15 15 10 10 5 5 0 0 20 25 30 35 40 45 50 55 60 65 70 75 80 RECIRC PUMP "B" SPEED (%)
(1-BB-SIC-R621B)
Cycle 5, SLO B, JP 5 Hope Creek Page 35 of 41 Rev. 10
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY ATTACHMENT 9 ESTABLISHED % dP GRAPH - "B" RECIRC PUMP OPERATING (Page 6 of 10)
JET PUMP 06 JET PUMP DIFFERENTIAL PRESS (%dp) 75 75 70 70 65 65 60 60 55 55 50 50 45 45 40 40 35 35 30 30 25 25 20 20 15 15 10 10 5 5 0 0 20 25 30 35 40 45 50 55 60 65 70 75 80 RECIRC PUMP "B" SPEED (%)
(1-BB-SIC-R621B)
Cycle 5, SLO B, JP6 Hope Creek Page 36 of 41 Rev. 10
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY ATTACHMENT 9 ESTABLISHED % dP GRAPH - "B" RECIRC PUMP OPERATING (Page 7 of 10)
JET PUMP 07 JET PUMP DIFFERENTIAL PRESS (%dp) 75 75 70 70 65 65 60 60 55 55 50 50 45 45 40 40 35 35 30 30 25 25 20 20 15 15 10 10 5 5 0 0 20 25 30 35 40 45 50 55 60 65 70 75 80 RECIRC PUMP "B" SPEED (%)
(1-BB-SIC-R621B)
Cycle 5, SLO B, JP7 Hope Creek Page 37 of 41 Rev. 10
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY ATTACHMENT 9 ESTABLISHED % dP GRAPH - "B" RECIRC PUMP OPERATING (Page 8 of 10)
JET PUMP 08 JET PUMP DIFFERENTIAL PRESS (%dp) 75 75 70 70 65 65 60 60 55 55 50 50 45 45 40 40 35 35 30 30 25 25 20 20 15 15 10 10 5 5 0 0 20 25 30 35 40 45 50 55 60 65 70 75 80 RECIRC PUMP "B" SPEED (%)
(1-BB-SIC-R621B)
Cycle 5, SLO B, JP8 Hope Creek Page 38 of 41 Rev. 10
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY ATTACHMENT 9 ESTABLISHED % dP GRAPH - "B" RECIRC PUMP OPERATING (Page 9 of 10)
JET PUMP 09 JET PUMP DIFFERENTIAL PRESS (%dp) 80 80 75 75 70 70 65 65 60 60 55 55 50 50 45 45 40 40 35 35 30 30 25 25 20 20 15 15 10 10 5 5 20 25 30 35 40 45 50 55 60 65 70 75 80 RECIRC PUMP "B" SPEED (%)
(1-BB-SIC-R621B)
Cycle 5, SLO B, JP9 Hope Creek Page 39 of 41 Rev. 10
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY ATTACHMENT 9 ESTABLISHED % dP GRAPH - "B" RECIRC PUMP OPERATING (Page 10 of 10)
JET PUMP 10 JET PUMP DIFFERENTIAL PRESS (%dp) 75 75 70 70 65 65 60 60 55 55 50 50 45 45 40 40 35 35 30 30 25 25 20 20 15 15 10 10 5 5 0 0 20 25 30 35 40 45 50 55 60 65 70 75 80 RECIRC PUMP "B" SPEED (%)
(1-BB-SIC-R621B)
Cycle 5, SLO B, JP10 Hope Creek Page 40 of 41 Rev. 10
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY ATTACHMENT 10 ESTABLISHED TOTAL CORE FLOW vs APRM % FLOW (Page 1 of 1)
TOTAL CORE FLOW (MLB/HR) 50 50 48 48 46 46 RECIRC PUMP 'B' OPERATING 44 44 42 42 RECIRC PUMP 'A' OPERATING 40 40 38 38 36 36 34 34 32 32 30 30 4 8 12 16 20 24 28 32 36 40 44 48 52 APRM % FLOW (10C608)
CYCLE 5, SLO, APRM % FLOW Hope Creek Page 41 of 41 Rev. 10
INITIAL LICENSED OPERATOR EXAMINATION JOB PERFORMANCE MEASURE STATION: HOPE CREEK SYSTEM: Conduct of Operations TASK: Complete an On The Spot Change (OTSC)
TASK NUMBER: 2010200101 JPM NUMBER: NRC-ADM-003 ALTERNATE PATH: K/A NUMBER: 2.1.20 IMPORTANCE FACTOR: 4.3 4.2 APPLICABILITY: RO SRO RO SRO X EVALUATION SETTING/METHOD: Classroom/Perform
REFERENCES:
NC.DM-AP.ZZ-0002 Rev. 2 TOOLS AND EQUIPMENT:
VALIDATED JPM COMPLETION TIME: 12 Minutes TIME PERIOD IDENTIFIED FOR TIME CRITICAL STEPS: N/A JPM SOURCE: New APPROVAL:
Author Facility Representative Chief Examiner CAUTION: No plant equipment shall be operated during the performance of a JPM without the following:
- 1. Permission from the OS or Unit CRS;
- 2. Direct oversight by a qualified individual (determined by the individual granting permission based on plant conditions).
- 3. Verification of the as left condition by a qualified individual.
ACTUAL JPM COMPLETION TIME: Minutes ACTUAL TIME CRITICAL N/A JPM PERFORMED BY: GRADE: SAT UNSAT REASON, IF UNSATISFACTORY:
EVALUATORS SIGNATURE: DATE:
Page 1 of 20
INITIAL LICENSED OPERATOR EXAMINATION JOB PERFORMANCE MEASURE NAME:
DATE:
SYSTEM: Conduct of Operations TASK: Complete an On The Spot Change (OTSC)
TASK NUMBER: 2010200101 INITIAL CONDITIONS:
- 1. The plant is in OPCON 3 preparing to place Shutdown Cooling in service
- 2. It has been determined that HV-F048A(B) RHR HX SHELL SIDE BYP MOV should be opened after ~2 minutes have elapsed vs. the current 5 minutes. To prevent a thermal shock on the RHR piping.
- 3. You have been directed by the CRS to complete a OTSC to change step 5.2.8 of HC.OP-SO.BC-0002, Decay Heat Removal from ~5 minutes to ~2 minutes.
INITIATING CUE:
Initiate an OTSC IAW NC.DM-AP.ZZ-0002, Procedure On the Spot Change (OTSC) Process to change the time until HV-F048A(B) is opened in step 5.2.8 from ~5 minutes to ~ 2 minutes.
Successful Completion Criteria:
- 1. All critical steps completed.
- 2. All sequential steps completed in order.
- 3. All time-critical steps completed within allotted time.
- 4. JPM completed within validated time. Completion time may exceed the validated time if satisfactory progress is being made.
Page 2 of 20
INITIAL LICENSED OPERATOR EXAMINATION NAME:
JOB PERFORMANCE MEASURE DATE:
SYSTEM: Conduct of Operations TASK: Complete an On The Spot Change (OTSC)
STEP COMMENTS
- STEP
(*Denotes a Critical Step) EVAL (Required for UNSAT
- NO. STANDARD
(#Denotes a Sequential Step) S/U evaluation)
Operator obtains/locates procedure NC.DM-AP.ZZ-0002.
Examiner Cue: When the Operator has demonstrated that he can knows which procedure is need, provide him a copy of NC.DM-AP.ZZ-0002. Also provide the Operator with a copy of HC.OP-SO.BC-0002.
Operator determines he needs to perform Section 5.1
- 5.1.1 Verify that the copy of the procedure Operator verifies the copy he has been is the latest active revision in given is the latest revision of the procedure.
A. DCRMS.
Examiner Cue: Operator will need access to a computer terminal to verify latest active revision in DCRMS B. Obtain copies of all active OTSCs. Operator determines there are NO active OTSCs on this procedure.
C. Discuss the proposed OTSC with the Operator discusses the proposed OTSC Job Supervisor or Superintendent or with Evaluator.
Department Manager. If there is a Operator determines that there is NO change of intent involved (refer to change in Intent per Attachment 1.
Attachment 1 for criteria), DO NOT use an OTSC to resolve the Examiner Cue: Act as the Operators condition. Supervisor and get the Operator to determine if there is a Change in Intent of the procedure.
Page 3 of 20
INITIAL LICENSED OPERATOR EXAMINATION NAME:
JOB PERFORMANCE MEASURE DATE:
SYSTEM: Conduct of Operations TASK: Complete an On The Spot Change (OTSC)
STEP COMMENTS
- STEP
(*Denotes a Critical Step) EVAL (Required for UNSAT
- NO. STANDARD
(#Denotes a Sequential Step) S/U evaluation)
- D. Obtain a copy of Form-1, On-The- Operator obtains a copy of Form-1 OTSC Spot-Change Form: change form
- Assign an OTSC#. Use the
- OTSC# - Rev 17A current revision number of the
- Page 21 is affected page.
procedure followed by the next Description of change is: Change available sequential letter (e.g., step 5.2.8 to read as follows:
Rev. 6A, 6B).
WHEN ~2 minutes have elapsed
- Complete the Description Of THEN OPEN BC-HV-F048A(B)
Change, Reason for Change and RHR HX SHELL SIDE BYP Pages Changed sections. List all MOV affected pages individually. or words to this effect.
[CD-607E]
- Reason for change - Prevent
- Attach information that is used as overcooling the RHR piping or the technical basis for the change. words to that effect.
- Evaluate the impact of the
- Pages affected - Page 21 proposed change on any existing OTSCs.
- Attach the information provided to him from engineering.
- Ensure that the change is not a change of intent.
- Should not be any other OTSCs so there should be NO effect on other OTSCs
- Operator verifies again that this NOT a change of Intent Page 4 of 20
INITIAL LICENSED OPERATOR EXAMINATION NAME:
JOB PERFORMANCE MEASURE DATE:
SYSTEM: Conduct of Operations TASK: Complete an On The Spot Change (OTSC)
STEP COMMENTS
- STEP
(*Denotes a Critical Step) EVAL (Required for UNSAT
- NO. STANDARD
(#Denotes a Sequential Step) S/U evaluation)
- E. Mark-up the affected procedure Operator marks up affected procedure page(s) with the required changes as pages showing changes he will make.
follows:
Operator identifies changes by placing
- Obtain a clean copy of all affected vertical Revision bars and the OTSC pages. Change Number in the Right margin.
- Address text changes only (no changes to drawings, except for text on drawing pages - there should be no new drawings.)
- Do not change pre-existing page numbers, etc.
- Identify changes by placing vertical revision bars and the OTSC change number in the right margin.
- Ensure previously approved OTSCs for the current revision are not adversely affected.
Page 5 of 20
INITIAL LICENSED OPERATOR EXAMINATION NAME:
JOB PERFORMANCE MEASURE DATE:
SYSTEM: Conduct of Operations TASK: Complete an On The Spot Change (OTSC)
STEP COMMENTS
- STEP
(*Denotes a Critical Step) EVAL (Required for UNSAT
- NO. STANDARD
(#Denotes a Sequential Step) S/U evaluation)
- F. Sign and date the OTSC Form-1 and Operator signs and dates the OTSC Form-1 attach the OTSC Form-1 (with any technical basis documentation) to the marked-up copy of the procedure, including affected OTSCs (hereafter referred to as the OTSC package).
Terminating Cue: When Operator has signed and dated the OTSC Form-1, and then state "This JPM is complete".
Page 6 of 20
PSEG Internal Use Only HC.OP-ST.BB-0007(Q)
TRAINING ONLY INITIAL CONDITIONS:
- 1. The plant is in OPCON 3 preparing to place Shutdown Cooling in service
- 2. It has been determined that HV-F048A(B) RHR HX SHELL SIDE BYP MOV should be opened after ~2 minutes have elapsed vs. the current 5 minutes. To prevent a thermal shock on the RHR piping.
- 3. You have been directed by the CRS to complete a OTSC to change step 5.2.8 of HC.OP-SO.BC-0002, Decay Heat Removal from ~5 minutes to ~2 minutes.
INITIATING CUE:
Initiate an OTSC IAW NC.DM-AP.ZZ-0002, Procedure On the Spot Change (OTSC) Process to change the time until HV-F048A(B) is opened in step 5.2.8 from ~5 minutes to ~ 2 minutes.
Page 7 of 20
INITIAL LICENSED OPERATOR EXAMINATION JOB PERFORMANCE MEASURE:
STATION: Hope Creek SYSTEM: Emergency Plan TASK: Utilize The ECG To Determine The Emergency Classification And/Or Reportability Of An Event And/Or Plant Condition TASK NUMBER: 2000500302 JPM NUMBER: NRC-ADM-004 ALTERNATE PATH: K/A NUMBER: 2.4.38 IMPORTANCE FACTOR: 2.2 4.0 APPLICABILITY: RO SRO RO SRO X EVALUATION SETTING/METHOD: Simulator/Perform
REFERENCES:
Hope Creek Event Classification Guide, Rev. 45 HC.OP-AB.RPV-0009, Rev 1 TOOLS, EQUIPMENT AND PROCEDURES:
VALIDATED JPM COMPLETION TIME: Minutes TIME PERIOD IDENTIFIED FOR TIME CRITICAL STEPS: 15 minutes JPM SOURCE: New APPROVAL:
Author Facility Representative Chief Examiner CAUTION: No plant equipment shall be operated during the performance of a JPM without the following:
- 2. Direct oversight by a qualified individual (determined by the individual granting permission based on plant conditions).
- 3. Verification of the as left condition by a qualified individual.
ACTUAL JPM COMPLETION TIME: Minutes ACTUAL TIME CRITICAL COMPLETION: Minutes JPM PERFORMED BY: GRADE: SAT UNSAT REASON, IF UNSATISFACTORY:
EVALUATORS SIGNATURE: DATE:
Nuclear Common Page 1 of 5 Rev. 1
INITIAL LICENSED OPERATOR EXAMINATION JOB PERFORMANCE MEASURE:
NAME:
DATE:
SYSTEM: Emergency Plan TASK: Utilize The ECG To Determine The Emergency Classification And/Or Reportability Of An Event And/Or Plant Condition TASK NUMBER: 2000500302 INITIAL CONDITIONS:
- 1. Plant is in the condition at the end of Simulator Scenario #1. With conditions as follows:
- a. RCIC Isolation valves are failed open.
- b. RCIC steam piping has broken in the RCIC pump room causing both HPCI and RCIC Room Temperatures to exceed 250°F
- c. Reactor has been Emergency Depressurized using EO-0202 INITIATING CUE:
Based on the current condition of the Plant, classify this event and complete Step I. A. of ECG , 2, 3, OR 4 as appropriate. This is a Time Critical Task.
Successful Completion Criteria:
- 1. All critical steps completed.
- 2. All sequential steps completed in order.
- 3. All time-critical steps completed within allotted time.
- 4. JPM completed within validated time. Completion time may exceed the validated time if satisfactory progress is being made.
Nuclear Common Page 2 of 5 Rev. 1
NC.TQ-WB.ZZ-0310(Z)
INITIAL LICENSED OPERATOR EXAMINATION NAME:
JOB PERFORMANCE MEASURE DATE:
SYSTEM: Emergency Plan TASK: Utilize The ECG To Determine The Emergency Classification And/Or Reportability Of An Event And/Or Plant Condition STEP COMMENTS
- STEP
(*Denotes a Critical Step) EVAL (Required for UNSAT
- NO. STANDARD
(#Denotes a Sequential Step) S/U evaluation)
Operator obtains Hope Creek Event Operator obtains the correct procedure.
Classification Guide.
START TIME: Start time should be logged after the operator has reviewed the initial conditions and repeated the task back.
ECG Classification: To use this ECG Operator assesses the initial conditions, Section volume, follow this sequence: and determines that Sections 3.2 RCS i.IV.C 1. ASSESS the event and/or plant Barrier and 3.3 Containment Barrier are appropriate.
conditions and DETERMINE which ECG section(s) is most appropriate.
ECG 2. REFER to Section EAL/RAL Operator reviews the EALs and Section Flowchart diagram(s), and identify determines that the Initiating Conditions i.IV.C the Initiating Conditions that are for EALs 3.2.3.B and 3.3.4 are related related to the event/condition that to the event that has occurred.
has occurred or is ongoing.
- ECG 3. RCS Barrier (3.2.3 B) is Operator adds 3 points for a failed RCS Section determined to be failed - 3 points barrier and 2 points for a failed i.IV.C and Containment Barrier (3.3.4) is Containment barrier and determines determined to be failed - 2 points that 5 points is enough to warrant a declaration of a SAE.
Nuclear Common Page 3 of 5 Rev. 1
NC.TQ-WB.ZZ-0310(Z)
INITIAL LICENSED OPERATOR EXAMINATION NAME:
JOB PERFORMANCE MEASURE DATE:
SYSTEM: Emergency Plan TASK: Utilize The ECG To Determine The Emergency Classification And/Or Reportability Of An Event And/Or Plant Condition STEP COMMENTS
- STEP
(*Denotes a Critical Step) EVAL (Required for UNSAT
- NO. STANDARD
(#Denotes a Sequential Step) S/U evaluation)
ECG 4. IDENTIFY and IMPLEMENT the Operator identifies and implements Section referenced Attachment under ECG Attachment 3.
i.IV.C Action Required.
Att. 3 (EC) LOG SHEET 3.2.3 B and 3.3.4, time and date in the A. DECLARE AN SITE AREA appropriate spots in Attachment 3, and initials the step as the EC.
EMERGENCY AT HOPE CREEK Examiner Note: It is not critical to initial the procedure steps.
EAL # _______,
Declared at _____ hrs on _____
time date Examiner Note: Copy the declaration STOP TIME:
time that the operator entered on Att. 2; the difference between the START time and the Declared time is the critical time (15 min.)
Terminating Cue: Repeat back message from the operator on the status of the JPM, and then state "This JPM is complete.
Nuclear Common Page 4 of 5 Rev. 1
ATTACHMENT 4 JOB PERFORMANCE MEASURE JPM/SIMULATOR SETUP INSTRUCTIONS (OPTIONAL)
INITIAL CONDITIONS:
- 1. Plant is in the condition at the end of Simulator Scenario #1. With conditions as follows:
- a. RCIC Isolation valves are failed open.
- b. RCIC steam piping has broken in the RCIC pump room causing both HPCI and RCIC Room Temperatures to exceed 250°F
- c. Reactor has been Emergency Depressurized using EO-0202 INITIATING CUE:
Based on this information, classify this event and complete Step I. A. of ECG Attachment 1, 2, 3, OR 4 as appropriate. This is a Time Critical Task.
Nuclear Common Page 5 of 5 Rev. 1
INITIAL LICENSED OPERATOR EXAMINATION JOB PERFORMANCE MEASURE STATION: HOPE CREEK SYSTEM: Emergency/ECG/E-Plan/Fire & Medical TASK: Complete a Major Equipment and Electrical Status (MEES) Form TASK NUMBER:
JPM NUMBER: NRC-ADM-005 ALTERNATE PATH: K/A NUMBER: 2.4.39 IMPORTANCE FACTOR: 3.3 APPLICABILITY: RO SRO RO X SRO EVALUATION SETTING/METHOD: Simulator/Perform
REFERENCES:
Hope Creek Event Classification Guide, Attachment 8, Revision 11 TOOLS AND EQUIPMENT: None VALIDATED JPM COMPLETION TIME: (10) Minutes TIME PERIOD IDENTIFIED FOR TIME CRITICAL STEPS: N/A JPM SOURCE: Modified Bank APPROVAL:
Author Facility Representative Chief Examiner CAUTION: No plant equipment shall be operated during the performance of a JPM without the following:
- 1. Permission from the OS or Unit CRS;
- 2. Direct oversight by a qualified individual (determined by the individual granting permission based on plant conditions).
- 3. Verification of the as left condition by a qualified individual.
ACTUAL JPM COMPLETION TIME: Minutes ACTUAL TIME CRITICAL COMPLETION: N/A JPM PERFORMED GRADE: SAT UNSAT REASON, IF UNSATISFACTORY:
EVALUATORS SIGNATURE: DATE:
Page 1 of 7
INITIAL LICENSED OPERATOR EXAMINATION JOB PERFORMANCE MEASURE NAME:
DATE:
SYSTEM: Emergency/ECG/E-Plan/Fire & Medical TASK: Complete a Major Equipment and Electrical Status (MEES) Form TASK NUMBER:
INITIAL CONDITIONS:
- 1. You are the On-Shift Plant Operator designated as Communicator 2.
INITIATING CUE:
Complete a Major Equipment and Electrical Status (MEES) Form in accordance with ECG Attachment 8.
Successful Completion Criteria:
- 1. All critical steps completed.
- 2. All sequential steps completed in order.
- 3. All time-critical steps completed within allotted time.
- 4. JPM completed within validated time. Completion time may exceed the validated time if satisfactory progress is being made.
Page 2 of 7
INITIAL LICENSED OPERATOR EXAMINATION NAME:
JOB PERFORMANCE MEASURE DATE:
SYSTEM: Emergency/ECG/E-Plan/Fire & Medical TASK: Complete a Major Equipment and Electrical Status (MEES) Form STEP COMMENTS
- STEP
(*Denotes a Critical Step) EVAL (Required for UNSAT
- NO. STANDARD
(#Denotes a Sequential Step) S/U evaluation)
Operator obtains and locates Operator obtains the correct procedure.
Attachment 8 of the Hope Creek Examiner Note: It is acceptable to ECG.
provide the operator the Attachment.
Operator determines beginning step Operator determines correct beginning of the procedure. step of procedure to be B.1.
Examiner Cue: Inform the Operator START TIME: that this is the Initial MEES form to be completed.
B.1. WHEN in an ALERT or higher emergency OR AFTER significant Operator enters the date, time, and changes in plant status; THEN completes the Major Equipment and COMPLETE the Major Equipment Electrical Status (MEES) Form, while and Electrical Status (MEES) Form. walking-down the control room boards.
Examiner Cue: WHEN the operator asks for the status of 1BC663, B Hydrogen Recombiner, STATE that it is not in service but is available.
Page 3 of 7
INITIAL LICENSED OPERATOR EXAMINATION NAME:
JOB PERFORMANCE MEASURE DATE:
SYSTEM: Emergency/ECG/E-Plan/Fire & Medical TASK: Complete a Major Equipment and Electrical Status (MEES) Form STEP COMMENTS
- STEP
(*Denotes a Critical Step) EVAL (Required for UNSAT
- NO. STANDARD
(#Denotes a Sequential Step) S/U evaluation)
Operator initials the Major Equipment STOP TIME: and Electrical Status (MEES) Form.
(NOT Critical)
Examiner Note: See attached for the completed Form.
Examiner Note: PCIG compressors may be marked as OUT OF SERVICE(N) or as IN SERVICE(Y).
CRITICAL NOTATIONS ARE:
- Correct status of:
o RHR Pumps o Offsite power o Core Spray pumps o EDGs o HPCI and RCIC Terminating Cue: Repeat back message from the operator on the status of the JPM, and then state "This JPM is complete" Page 4 of 7
JOB PERFORMANCE MEASURE INITIAL CONDITIONS:
- 1. You are the On-Shift Plant Operator designated as Communicator 2.
INITIATING CUE:
Complete a Major Equipment and Electrical Status (MEES) Form in accordance with ECG Attachment 8.
Page 5 of 7
JOB PERFORMANCE MEASURE SIMULATOR INSTRUCTIONS Reset Simulator to an 100% IC. (Keep simulator in freeze.)
Insert RR31A2 at 100%.
Insert EG12 with a 120 second time delay.
Place the simulator in RUN.
Take all scram actions.
Restore 1E Breakers.
Restore PCIG.
Allow plant conditions to stabilize.
Acknowledge all alarms and flashing indications.
Place the simulator in freeze.
Page 6 of 7
EXAMINERS COPY FOR TRAINING ONLY TODAY NOW N Y N Y N Y N Y N Y N Y N Y N N Y N Y N Y N N Y N Y Y Y Y Y Y Y Y Y N Y Y Y N N
N N N N N N N N N N Y N N N Y N Y N Y N Y Y Y N Y Y N Y Y N Y Y N Y N Y Y N Y N
N Y Y
Y INITIALS Page 7 of 7
INITIAL LICENSED OPERATOR EXAMINATION JOB PERFORMANCE MEASURE STATION: HOPE CREEK SYSTEM: Radiation Control TASK: Review a Containment Purge form TASK NUMBER: 2290050101 JPM NUMBER: NRC-ADM-006 ALTERNATE PATH: K/A NUMBER: 223001A4.03 IMPORTANCE FACTOR: 3.4 APPLICABILITY: RO SRO RO SRO X EVALUATION SETTING/METHOD: Simulator/Perform
REFERENCES:
HC.OP-AP.ZZ-0104, Revision 8 TOOLS AND EQUIPMENT: Calculator VALIDATED JPM COMPLETION TIME: (10) Minutes TIME PERIOD IDENTIFIED FOR TIME CRITICAL STEPS: N/A JPM SOURCE: Bank APPROVAL:
Author Facility Representative Chief Examiner CAUTION: No plant equipment shall be operated during the performance of a JPM without the following:
- 1. Permission from the OS or Unit CRS;
- 2. Direct oversight by a qualified individual (determined by the individual granting permission based on plant conditions).
- 3. Verification of the as left condition by a qualified individual.
ACTUAL JPM COMPLETION TIME: Minutes ACTUAL TIME CRITICAL COMPLETION: N/A JPM PERFORMED GRADE: SAT UNSAT REASON, IF UNSATISFACTORY:
EVALUATORS SIGNATURE: DATE:
Page 1 of 7
INITIAL LICENSED OPERATOR EXAMINATION JOB PERFORMANCE MEASURE NAME:
DATE:
SYSTEM: Radiation Control TASK: Review a Containment Purge form TASK NUMBER: 2290050101 INITIAL CONDITIONS:
- 1. A plant shutdown is in progress for a Refueling outage.
- 2. The Reactor is shutdown.
- 3. At 0200 today Purging of the Primary Containment commenced..
- 4. At 0846 today Operational Condition 4 was entered.
- 5. At 1142 today the purge lineup was secured in accordance with HC.OP-SO.GS-0001, Containment Atmosphere Control System Operation.
INITIATING CUE:
Review todays Containment Prepurge Cleanup, Inerting, Or Pressure Control Valve Permit and Log in accordance with HC.OP-AP.ZZ-0104.
Successful Completion Criteria:
- 1. All critical steps completed.
- 2. All sequential steps completed in order.
- 3. All time-critical steps completed within allotted time.
- 4. JPM completed within validated time. Completion time may exceed the validated time if satisfactory progress is being made.
Page 2 of 7
INITIAL LICENSED OPERATOR EXAMINATION NAME:
JOB PERFORMANCE MEASURE DATE:
SYSTEM: Radiation Control TASK: Review a Containment Purge form STEP COMMENTS
- STEP
(*Denotes a Critical Step) EVAL (Required for UNSAT
- NO. STANDARD
(#Denotes a Sequential Step) S/U evaluation)
Examiner Cue: Provide the operator with HC.OP-AP.ZZ-0104 and the supporting paperwork (Attached).
Operator reviews requirements. Operator reviews requirements.
Operator determines beginning step Operator determines correct beginning of the procedure. step to be 5.2.6.
Operator verifies the calculations.
START TIME: Operator notices that the incorrect STOP TIME was used in Section C.
Examiner Note: The operator may
- 5.2.6 The CRS/SM should verify the calculations, sign in the appropriate request that the NCO make the space for verification and close out corrections. If so, provide Cue.
and enter the time and date. Examiner Cue: Make the corrections that you have noted.
(Time should be 0846, and Total Hours STOP TIME:
should be 7.0.)
Operator makes correction to the STOP TIME, TOTAL TIME, and the Total number of hours valves/line open this permit. Then presents it back to the NCO for completion of the procedure.
Terminating Cue: Repeat back message from the operator on the status of the JPM, and then state "This JPM is complete" Page 3 of 7
JOB PERFORMANCE MEASURE INITIAL CONDITIONS:
- 1. A plant shutdown is in progress for a Refueling outage.
- 2. The Reactor is shutdown.
- 3. At 0200 today Purging of the Primary Containment commenced.
- 4. At 0848 today Operational Condition 4 was entered.
- 5. At 1142 today the purge lineup was secured in accordance with HC.OP-SO.GS-0001, Containment Atmosphere Control System Operation.
INITIATING CUE:
Review todays Containment Prepurge Cleanup, Inerting, Or Pressure Control Valve Permit and Log in accordance with HC.OP-AP.ZZ-0104.
Page 4 of 7
HC.OP-AP.ZZ-0104(Q)
FORM 2 CONTAINMENT PREPURGE CLEANUP, INERTING, OR PRESSURE CONTROL VALVE PERMIT SECTION A Date: Today NOTE: This permit is valid only until 2400 of this date Gaseous Effluent Permit #: 050050001 SECTION B HOURS VALVES/LINES OPEN PREVIOUS YEAR (Note 1)
Calculate Total Hours Open (1) Max. allowed for 365 days (Admin Limit) 452 hrs During Previous Year (NOTE 1)
DATE NUMBER OF HOURS (2) Total previous year (NOTE 1) (-) 36.0 3/3/05 5.5 Hours available this date (line 1 minus line 2) (=) 416 6/25/05 3.5 8/30/05 24.0 Hours authorized this date (24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> or the 24 8/31/05 3.0 hours available this date whichever is less)
NCO performing calculation Date/Time John Smith Today/0100 SM/CRS verification and authorization Date/Time Andrew Jones Today/0130 SECTION C VALVE/LINE OPEN TIME (Note 2)
START TIME STOP TIME TOTAL HOURS Time at which valve/line was open or Time at which valve/line was closed or Total number of hours Condition 1, 2, or 3 was entered with valve/line Condition 4 or 5 was entered with valve/line valve/line opened this cycle open opened (NOTE 3) 0200 1142 0848 10.0 7.0 Total number of hours valves/line open this permit: 10.0 7.0 NCO performing calculations Date/Time Today/Time Johnny Unitas SM/CRS Closing permit Date/Time NOTE 1: The previous year includes the period from 2400 on todays date back to 0001 on the same date one year earlier.
NOTE 2: Completed Form 2 should be filed in the AP-104 binder in the Control Room.
NOTE 3: When computing the total hours (round up to the nearest 0.5 hr or to the nearest 1.0 hr).
Hope Creek Page 9 of 9 Rev. 8
HC.OP-AP.ZZ-0104(Q)
FORM 2 CONTAINMENT PREPURGE CLEANUP, INERTING, OR PRESSURE CONTROL VALVE PERMIT SECTION A Date: Today NOTE: This permit is valid only until 2400 of this date Gaseous Effluent Permit #: 050050001 SECTION B HOURS VALVES/LINES OPEN PREVIOUS YEAR (Note 1)
Calculate Total Hours Open (1) Max. allowed for 365 days (Admin Limit) 452 hrs During Previous Year (NOTE 1)
DATE NUMBER OF HOURS (2) Total previous year (NOTE 1) (-) 36.0 3/3/05 5.5 Hours available this date (line 1 minus line 2) (=) 416 6/25/05 3.5 8/30/05 24.0 Hours authorized this date (24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> or the 24 8/31/05 3.0 hours available this date whichever is less)
NCO performing calculation Date/Time John Smith Today/0100 SM/CRS verification and authorization Date/Time Andrew Jones Today/0130 SECTION C VALVE/LINE OPEN TIME (Note 2)
START TIME STOP TIME TOTAL HOURS Time at which valve/line was open or Time at which valve/line was closed or Total number of hours Condition 1, 2, or 3 was entered with valve/line Condition 4 or 5 was entered with valve/line valve/line opened this cycle open opened (NOTE 3) 0200 1142 10.0 Total number of hours valves/line open this permit: 10.0 NCO performing calculations Date/Time Today/Time Johnny Unitas SM/CRS Closing permit Date/Time NOTE 1: The previous year includes the period from 2400 on todays date back to 0001 on the same date one year earlier.
NOTE 2: Completed Form 2 should be filed in the AP-104 binder in the Control Room.
NOTE 3: When computing the total hours (round up to the nearest 0.5 hr or to the nearest 1.0 hr).
Hope Creek Page 9 of 9 Rev. 8
HC.OP-AP.ZZ-0104(Q)
FORM 1 Page ___1__ of __1___
CONTAINMENT PREPURGE CLEANUP, INERTING, OR PRESSURE CONTROL VALVE PERMIT LOG DATE HOURS HOURS NAME OF OS/CRS NCO HOURS TOTAL NAME OF SM/CRS NCO PREV. AUTH. AUTHORIZING THIS INITIAL USED THIS HOURS CLOSING THIS PERMIT INITIAL YEAR THIS PERMIT PERMIT PREVIOUS (NOTE 1) PERMIT YEAR (NOTE 1) 2/4/04 45 20.5 P. Manning KLW 5.5 50.5 T. Brady JW 3/3/05 0 20.5 T. Brady JW 5.5 5.5 T. Brady JW 6/25/05 5.5 24.0 P. Manning KLW 3.5 9.0 P. Manning KLW 8/30/05 9.0 24.0 D. McNabb SD 24.0 33.0 D. McNabb SD 8/31/05 33.0 18.5 E. Manning SD 3.0 36.0 E. Manning SD Today 36.0 24.0 A. Jones JS NOTE 1: The previous year includes the period from 2400 on todays date back to 0001 on the same date one year earlier.
Hope Creek Page 8 of 9 Rev. 8
INITIAL LICENSED OPERATOR EXAMINATION JOB PERFORMANCE MEASURE STATION: HOPE CREEK SYSTEM: Conduct of Operations TASK: Perform An Accident Monitoring Instrumentation Channel Check TASK NUMBER: 0201070201 JPM NUMBER: NRC-ADM-007 ALTERNATE PATH: X K/A NUMBER: 2.1.7 IMPORTANCE FACTOR: 3.7 4.4 APPLICABILITY: RO SRO RO X SRO EVALUATION SETTING/METHOD: Simulator/Perform
REFERENCES:
HC.OP-ST.SH-0001 (Q), Rev. 23 TOOLS AND EQUIPMENT: None VALIDATED JPM COMPLETION TIME: (8) Minutes TIME PERIOD IDENTIFIED FOR TIME CRITICAL STEPS: N/A JPM SOURCE: Bank APPROVAL:
Author Facility Representative Chief Examiner CAUTION: No plant equipment shall be operated during the performance of a JPM without the following:
- 1. Permission from the OS or Unit CRS;
- 2. Direct oversight by a qualified individual (determined by the individual granting permission based on plant conditions).
- 3. Verification of the as left condition by a qualified individual.
ACTUAL JPM COMPLETION TIME: Minutes ACTUAL TIME CRITICAL COMPLETION: N/A JPM PERFORMED BY: GRADE: SAT UNSAT REASON, IF UNSATISFACTORY:
EVALUATORS SIGNATURE: DATE:
Page 1 of 9
INITIAL LICENSED OPERATOR EXAMINATION JOB PERFORMANCE MEASURE NAME:
DATE:
SYSTEM: Conduct of Operations TASK: Perform An Accident Monitoring Instrumentation Channel Check TASK NUMBER: 2160010201 INITIAL CONDITIONS:
- 1. HC.OP-ST.SH-0001(Q), Accident Monitoring Instrumentation Channel Check - Monthly is required.
- 2. No other testing or maintenance is in progress that will adversely affect the performance of this test.
INITIATING CUE:
Perform Steps 5.1 through 5.6 of HC.OP-ST.SH-0001(Q). Another operator will complete the rest of the Surveillance.
Successful Completion Criteria:
- 1. All critical steps completed.
- 2. All sequential steps completed in order.
- 3. All time-critical steps completed within allotted time.
- 4. JPM completed within validated time. Completion time may exceed the validated time if satisfactory progress is being made.
Page 2 of 9
INITIAL LICENSED OPERATOR EXAMINATION NAME:
JOB PERFORMANCE MEASURE DATE:
SYSTEM: Conduct of Operations TASK: Perform An Accident Monitoring Instrumentation Channel Check STEP COMMENTS
- STEP
(*Denotes a Critical Step) EVAL (Required for UNSAT
- NO. STANDARD
(#Denotes a Sequential Step) S/U evaluation)
Examiner Cue: Provide the operator with a copy of the partially completed procedure HC.OP-ST.SH-0001(Q).
Operator reviews precautions and Operator reviews precautions and limitations. limitations.
Examiner Cue: If excessive time is taken to review precautions and limitations, inform operator that all are satisfied.
Examiner Note: Initialing the following steps is not critical.
5.1 LOG test start time in the Control Operator requests that the start time be Room log(s). logged in the Control Room log.
Examiner Cue: The test start time has been logged in the Control Room log.
Operator initials the step.
5.2 ENSURE that all prerequisites have Operator ensures that the prerequisites been satisfied IAW Section 2.0. are satisfied:
Operator completes Attachment 1 Section 3.0 before performing any part of this procedure.
Operator initials the step.
Page 3 of 9
INITIAL LICENSED OPERATOR EXAMINATION NAME:
JOB PERFORMANCE MEASURE DATE:
SYSTEM: Conduct of Operations TASK: Perform An Accident Monitoring Instrumentation Channel Check STEP COMMENTS
- STEP
(*Denotes a Critical Step) EVAL (Required for UNSAT
- NO. STANDARD
(#Denotes a Sequential Step) S/U evaluation) 5.3 ENSURE Attachment 1, Section 1 of Operator observes that Attachment 1, the OS/CRS Data and Signature Section 1.0 of the OS/CRS Data and Sheet has been completed AND Signature Sheet has been completed Regular Surveillance OR Retest is and Regular Surveillance is indicated.
indicated.
Operator initials the step.
START TIME:
5.4 PERFORM a Channel Check of the following Reactor Vessel Pressure instruments, RECORD AND N/A N/A N/A COMPARE the indicated pressure readings on Attachment 2: [T/S 4.3.7.5-1, item 1]
- 5.4.1 REACTOR PRESSURE Indicator PI- Operator records the value of PI-3684A 3684A (Red) (Red) on Attachment 2. [995 psig]
- 5.4.2 REACTOR PRESSURE Recorder Operator records the value of PR-PR-3684B (Red pen) 3684B (Red pen) on Attachment 2. [992 psig]
- 5.4.3 VERIFY Reactor Pressure Operator compares the values recorded instrumentation Channel Check for PI-3684A (Red) and PR-3684B (Red complete, ENTER SAT or UNSAT pen) and verifies they are within 75 AND INITIAL the appropriate space psig. Then enters SAT and initials the on Attachment 2. appropriate space on Attachment 2.
Page 4 of 9
INITIAL LICENSED OPERATOR EXAMINATION NAME:
JOB PERFORMANCE MEASURE DATE:
SYSTEM: Conduct of Operations TASK: Perform An Accident Monitoring Instrumentation Channel Check STEP COMMENTS
- STEP
(*Denotes a Critical Step) EVAL (Required for UNSAT
- NO. STANDARD
(#Denotes a Sequential Step) S/U evaluation) 5.5 PERFORM a Channel Check of the following Reactor Vessel Water Level instruments, RECORD AND N/A N/A N/A COMPARE the indicated level readings on Attachment 2: [T/S 4.3.7.5-1, item 2]
- 5.5.1 REACTOR FUEL ZONE Water Level Operator records the value of LR-R615 Recorder LR-R615 (10C650 A (10C650 A Subsection F) on Subsection F) Attachment 2. [-111 inches]
- 5.5.2 REACTOR FUEL ZONE Water Level Operator records the value of LI-R610 Indicator LI-R610 (10C650 A (10C650 A Subsection G) on Subsection G) Attachment 2. [-111 inches]
- 5.5.3 REACTOR CHANNEL A Water Level Operator records the value of LR-Recorder LR-R623A (Red pen) R623A (Red pen) on Attachment 2. [32 inches]
- 5.5.4 REACTOR CHANNEL B Water Level Operator records the value of LR-Recorder LR-R623B (Red pen) R623B (Red pen) on Attachment 2. [26 inches]
- 5.5.5 REACTOR WATER Level Recorder Operator records the value of LR-LR-3622A (Blue pen) 3622A (Blue pen) on Attachment 2. [26 inches]
- 5.5.6 REACTOR WATER Level Recorder Operator records the value of LR-LR-3622B (Blue pen) 3622B (Blue pen) on Attachment 2. [28 inches]
Page 5 of 9
INITIAL LICENSED OPERATOR EXAMINATION NAME:
JOB PERFORMANCE MEASURE DATE:
SYSTEM: Conduct of Operations TASK: Perform An Accident Monitoring Instrumentation Channel Check STEP COMMENTS
- STEP
(*Denotes a Critical Step) EVAL (Required for UNSAT
- NO. STANDARD
(#Denotes a Sequential Step) S/U evaluation)
- 5.5.7 VERIFY Reactor Water Level Operator compares the values recorded instrumentation Channel Check for:
complete, ENTER SAT or UNSAT
- LR-R615 (10C650 A Subsection F),
AND INITIAL the appropriate space on Attachment 2.
- LI-R610 (10C650 A Subsection G)
- LR-R623A (Red pen)
- LR-R623B (Red pen)
And verifies they are within 10 inches, AND,
- LR-3622A (Blue pen)
- LR-3622B (Blue pen),
Are within 20 inches, Then enters SAT and initials the appropriate space on Attachment 2.
Operator: refers to NOTE 1, determines that LR-R623B and LR-R623A exceeds half the required value, and notifying System Engineering is required.
5.6 PERFORM a Channel Check of the following Suppression Pool Water Level instruments, RECORD AND N/A N/A N/A COMPARE the indicated level readings on Attachment 2: [T/S 4.3.7.5-1, item 3]
- 5.6.1 SUPPRESSION POOL Water Level Operator records the value of LR-4805-Recorder LR-4805-1 (10C650B 1 (10C650B Subsection B) on Subsection B) Attachment 2. [76.3 inches]
Page 6 of 9
INITIAL LICENSED OPERATOR EXAMINATION NAME:
JOB PERFORMANCE MEASURE DATE:
SYSTEM: Conduct of Operations TASK: Perform An Accident Monitoring Instrumentation Channel Check STEP COMMENTS
- STEP
(*Denotes a Critical Step) EVAL (Required for UNSAT
- NO. STANDARD
(#Denotes a Sequential Step) S/U evaluation)
- 5.6.2 SUPPRESSION POOL Water Level Operator records the value of LI-4801 Indicator LI-4801 on Attachment 2. [76.5 inches]
- 5.6.3 VERIFY Suppression Pool Water Operator compares the values recorded Level instrumentation channel check for LR-4805-1 and LI-4801 and verifies complete, ENTER SAT or UNSAT they are within 9 inches. Then enters AND INITIAL the appropriate space SAT and initials the appropriate space on Attachment 2. [CD-488E] on Attachment 2.
STOP TIME:
Terminating Cue: Repeat back message from the operator on the status of the JPM, and then state "This JPM is complete" Page 7 of 9
JOB PERFORMANCE MEASURE INITIAL CONDITIONS:
- 1. HC.OP-ST.SH-0001(Q), Accident Monitoring Instrumentation Channel Check -
Monthly is required.
- 2. No other testing or maintenance is in progress that will adversely affect the performance of this test.
INITIATING CUE:
Perform Steps 5.1 through 5.6 of HC.OP-ST.SH-0001(Q). Another operator will complete the rest of the Surveillance.
Page 8 of 9
JOB PERFORMANCE MEASURE SIMULATOR INSTRUCTIONS Reset to an 100% IC Complete Section 1 of HC.OP-ST.SH-0001(Q) to support the surveillance Insert the following Instructor Overrides (IOs):
I/O OVERRIDE
SUMMARY
Initial Description Delay Ramp Remote/Event Init Val Final
_____ 1. 8AR22 R AO REAC LEVEL LR-R623A-B21 32
_____ 2. 8AR26 R AO REAC LEVEL LR-R623B-B21 26
_____ 3.
VERIFY:
LR-R623A-B21 indicates 32 LR-R623B-B21 indicates 26.
Check other indications and compare to JPM. Adjust as necessary.
Page 9 of 9
INITIAL LICENSED OPERATOR EXAMINATION JOB PERFORMANCE MEASURE STATION: HOPE CREEK SYSTEM: Equipment Control TASK: Review and Approve a Clearance for Installation TASK NUMBER: 2290050101 JPM NUMBER: NRC-ADM-008 ALTERNATE PATH: K/A NUMBER: 2.2.13 IMPORTANCE FACTOR: 3.8 APPLICABILITY: RO SRO RO SRO X EVALUATION SETTING/METHOD: Classroom/Perform
REFERENCES:
SH.OP-AP.ZZ-0015, Rev 18, Safety Tagging Operations TOOLS AND EQUIPMENT: None VALIDATED JPM COMPLETION TIME: (10) Minutes TIME PERIOD IDENTIFIED FOR TIME CRITICAL STEPS: N/A JPM SOURCE: New APPROVAL:
Author Facility Representative Chief Examiner CAUTION: No plant equipment shall be operated during the performance of a JPM without the following:
- 1. Permission from the OS or Unit CRS;
- 2. Direct oversight by a qualified individual (determined by the individual granting permission based on plant conditions).
- 3. Verification of the as left condition by a qualified individual.
ACTUAL JPM COMPLETION TIME: Minutes ACTUAL TIME CRITICAL COMPLETION: N/A JPM PERFORMED GRADE: SAT UNSAT REASON, IF UNSATISFACTORY:
EVALUATORS SIGNATURE: DATE:
Page 1 of 10
INITIAL LICENSED OPERATOR EXAMINATION JOB PERFORMANCE MEASURE NAME:
DATE:
SYSTEM: Equipment Control TASK: Review and Approve a Clearance for Installation TASK NUMBER: 2290050101 INITIAL CONDITIONS:
- 1. GJ-V004, Chilled Water Circulating Pump (AP-400) Discharge Isolation valve is leaking by its seat.
- 2. Maintenance advised removal and replacement of the valve.
- 3. The Initiator has Evaluated the need for the tagging, Determined the Blocking Points and Tag Types, and Created the Tagging Package.
- 4. Both Field Verification and Pre-staging has been performed.
- 5. Discipline Review has been performed. ALL Walkdown and Discipline Review comments have been resolved.
- 6. You have been designated as the Approving Supervisor by the Operations Manager and been directed to perform the WCD Review and Pre-Approval.
- 7. All documents and drawings have been verified to be the most recent plant configuration.
- 8. Note - SAP just became unavailable - Use the attached Form 5 for order operations permitted to the WCD.
INITIATING CUE:
- 1. Given the Attached Tagging Package, Perform WCD Review and Pre-Approval IAW SH.OP-AP.ZZ-0015, Safety Tagging Operations Successful Completion Criteria:
- 1. All critical steps completed.
- 2. All sequential steps completed in order.
- 3. All time-critical steps completed within allotted time.
- 4. JPM completed within validated time. Completion time may exceed the validated time if satisfactory progress is being made.
Page 2 of 10
INITIAL LICENSED OPERATOR EXAMINATION NAME:
JOB PERFORMANCE MEASURE DATE:
SYSTEM: Equipment Control TASK: Review and Approve a Clearance for Installation STEP COMMENTS
- STEP
(*Denotes a Critical Step) EVAL (Required for UNSAT
- NO. STANDARD
(#Denotes a Sequential Step) S/U evaluation)
Examiner Cue: Provide the operator with SH.OP-AP.ZZ-0015 and the supporting paperwork (Attached).
Operator reviews requirements. Operator reviews requirements.
Operator determines he is to perform section 5.2.3 of SH.OP-AP.ZZ-0015.
START TIME:
5.2.3 Operator refers to SH.OP-AP.ZZ-0015 and determines the appropriate start point is Section 5.2.3
- 1. Operator notes that Approving Operator determines that he has been Supervisor shall be designated by the designated by the Operations Manager Operations Manager to approve as the Approving Supervisor WCDs.
EXAMINER CUE: This information was provided to the Operator in the Initial Conditions.
- 2.
- The Initiator and Approving Operator determines that he and the Supervisor shall be different Initiator are different individuals individuals.
[CD-538E]
Page 3 of 10
INITIAL LICENSED OPERATOR EXAMINATION NAME:
JOB PERFORMANCE MEASURE DATE:
SYSTEM: Equipment Control TASK: Review and Approve a Clearance for Installation STEP COMMENTS
- STEP
(*Denotes a Critical Step) EVAL (Required for UNSAT
- NO. STANDARD
(#Denotes a Sequential Step) S/U evaluation)
- 3. Perform the following: Operator reviews Form 5 and
- Review order operations determines that valve V004 is being permitted to the WCD to worked.
determine equipment to be worked and work scope
((Note), use Form 5 if SAP is Examiner Cue: Inform Operator that unavailable).
SAP is unavailable and provide Operator with a completed Form 5
- IF any order operations Operator determines that NO order permitted to the WCD are on operations permitted to the WCD are on tagging hold (HT), THEN have tagging hold (HT) these order operation(s) de-permitted from the WCD OR have the tagging hold resolved Examiner Cue: If the operator is prior to Pre-Approval. unsure order operations are, prompt
- Document this in the WCD him/her that there are NO order long text. operations on tagging hold.
- Ensure any Notifications Operator Ensures notifications for field referenced for field work under work un the WCD have been converted the WCD are converted to to orders per NC.WM-AP.ZZ-0001 orders per NC.WM-AP.ZZ-EXAMINER CUE: Notification has 0001 (Q).
been converted to Order
- Review documents and Operator reviews documents and drawings provided in the drawing provided in the tagging tagging package. package Page 4 of 10
INITIAL LICENSED OPERATOR EXAMINATION NAME:
JOB PERFORMANCE MEASURE DATE:
SYSTEM: Equipment Control TASK: Review and Approve a Clearance for Installation STEP COMMENTS
- STEP
(*Denotes a Critical Step) EVAL (Required for UNSAT
- NO. STANDARD
(#Denotes a Sequential Step) S/U evaluation)
- Ensure documents and Operator determines that the drawings represent the most documents and drawings represent the recent plant configuration most recent plant configuration.
EXAMINER CUE: Documents and drawings are the most recent plant configuration
- Review sequence of blocking Operator reviews sequence of blocking points against guidance in points against guidance in Attachment Attachment 4. 4 and determines that sequence appears to be proper.
Examiner Cue: Operator may determine that no vents are drains are open, inform Operator to note the problem and continue.
- Review applicable Limiting Operator reviews applicable LCO and Conditions for Operation (LCO) ensures potential Tech Spec Action and ensure that potential Technical Specification Action Statements are identified.
Statements are identified. Operator should determine that Tech Spec 3.7.2 needs an LCO generated for disabling 1 CREF train.
Page 5 of 10
INITIAL LICENSED OPERATOR EXAMINATION NAME:
JOB PERFORMANCE MEASURE DATE:
SYSTEM: Equipment Control TASK: Review and Approve a Clearance for Installation STEP COMMENTS
- STEP
(*Denotes a Critical Step) EVAL (Required for UNSAT
- NO. STANDARD
(#Denotes a Sequential Step) S/U evaluation)
- For ESO requests, ensure N/A - not an ESO request.
blocking points have been properly transferred to the WCD, that the WCD is set as Individual, and that the ESO title is activated.
Page 6 of 10
INITIAL LICENSED OPERATOR EXAMINATION NAME:
JOB PERFORMANCE MEASURE DATE:
SYSTEM: Equipment Control TASK: Review and Approve a Clearance for Installation STEP COMMENTS
- STEP
(*Denotes a Critical Step) EVAL (Required for UNSAT
- NO. STANDARD
(#Denotes a Sequential Step) S/U evaluation)
- IF any of the following Operator determines that NO Vent components will be used as and/or Drain valves are used as blocking points, OR will be worked on inside the tagging blocking points.
boundary, THEN Check the blocking points comply with the rules in Specifically, from Page 1 of Attachment Attachment 2: 2.
- Vents and Drains WHEN tagging mechanical systems for
- Grinnell-Saunders maintenance, THEN a minimum of one Diaphragm Valves drain, vent, relief device or other
- Repacking Valves on the component that could relieve energy Backseat shall be tagged with a RBT.
- Motor Operated Valves
- Air Operated Valves and Dampers Examiner Cue: Operator must
- Blank Flanges determine that at Least 1 vent and/or
- Freeze Seals drain valve must be opened.
- Electrical Disconnects, Operator may determine that more Grounds, Equipment than 1 Vent and Drain valves should w/YPTs, Breakers, be used. This is acceptable. If Cubicles, Handswitches, Operator wishes to return package Control Circuits to the initiator after locating the 1st
- Bailey Fuses mistake, inform operator to continue with review to determine if there are
- Bezels and Control any more errors.
Room/Remote Shutdown Panel Controls Page 7 of 10
INITIAL LICENSED OPERATOR EXAMINATION NAME:
JOB PERFORMANCE MEASURE DATE:
SYSTEM: Equipment Control TASK: Review and Approve a Clearance for Installation STEP COMMENTS
- STEP
(*Denotes a Critical Step) EVAL (Required for UNSAT
- NO. STANDARD
(#Denotes a Sequential Step) S/U evaluation)
- Check the WCD complies Operator reviews Attachment 3 and with Attachment 3 for rules ensures that the WCD complies with on tag types. Attachment 3.
Operator should determine that the WCD does NOT comply with Attachment 3, specifically that a Yellow Permissive tags should NOT be placed on H1GJ-HS-9652A1, AUX BLDG CNT CH WTR CPRSR AK400 C/S and H1GJ-HS-9651A, AUX BLDG CNT CH WTR PMP AP-400 C/SW Operator recommends replacing Yellow Permissive Tag with either a Red Blocking Tag (RBT) or an Information Tag (INF)
- Check applicability and Operator determines that the Special adequacy of Special Instructions does not address Tech Instructions to support the Spec 3.7.2 tagging evolution, refer to guidance in Attachment 4.
- Check Walkdown and Operator determines that ALL Discipline Review Walkdown and Discipline review comments have been comments have been resolved.
resolved.
Page 8 of 10
INITIAL LICENSED OPERATOR EXAMINATION NAME:
JOB PERFORMANCE MEASURE DATE:
SYSTEM: Equipment Control TASK: Review and Approve a Clearance for Installation STEP COMMENTS
- STEP
(*Denotes a Critical Step) EVAL (Required for UNSAT
- NO. STANDARD
(#Denotes a Sequential Step) S/U evaluation)
- Independently check that Operator determines that the clearance the WCD adequately adequately isolates the equipment to be isolates the equipment to worked if at least 1 vent and/or drain be worked.
valve were added to the clearance.
- Independently check that Operator determines that no other work the WCD does not will be affected by this clearance.
adversely affect other plant EXAMINER CUE: If asked, inform equipment not directly Operator that no other work will be involved in the work scope.
impacted by this clearance.
- 4
- IF changes are required, Operator determines that changes are THEN return the tagging required and RETURNS tagging package to the Initiator. package to the Initiator Terminating Cue: Once the Operator determines that changes are required and states that he will return the tagging package to the initiator, then state "This JPM is complete" Page 9 of 10
INITIAL CONDITIONS:
- 1. GJ-V004, Chilled Water Circulating Pump (AP-400) Discharge Isolation valve is leaking by its seat.
- 2. Maintenance advised removal and replacement of the valve.
- 3. The Initiator has Evaluated the need for the tagging, Determined the Blocking Points and Tag Types, and Created the Tagging Package.
- 4. Both Field Verification and Pre-staging has been performed.
- 5. Discipline Review has been performed. ALL Walkdown and Discipline Review comments have been resolved.
- 6. You have been designated as the Approving Supervisor by the Operations Manager and been directed to perform the WCD Review and Pre-Approval.
- 7. All documents and drawings have been verified to be the most recent plant configuration.
- 8. Note - SAP just became unavailable - Use the attached Form 5 for order operations permitted to the WCD.
INITIATING CUE:
Given the Attached Tagging Package, Perform WCD Review and Pre-Approval IAW SH.OP-AP.ZZ-0015, Safety Tagging Operations Page 10 of 10
SH.OP-AP.ZZ-0015(Q)
FORM 5 ORDER LOG PAGE __1_ OF _1_WORK CLEARANCE DOCUMENT NUMBER:
ESO NUMBER:
ORDER DESCRIPTION ORDER # ORDER DESCRIPTION ORDER #
Rework/replace valve GJ-V004 to stop 60101234 seat leakage
FOR TRAINING ONLY FOR TRAINING ONLY FOR TRAINING ONLY FOR TRAINING ONLY FOR TRAINING ONLY
FOR TRAINING ONLY
FOR
- 1) ORDER WORK PLAN OVERVIEW:
REWORK SEAT OF 1GJV-004 CHW A CIRC PMP AP400 DSCH VLV TRAINING ONLY
- 2) IMPACT TO PLANT EQUIPMENT OPERABILITY:
A CHILLED WATER CIRC. PUMP AP400 WILL BE TAGGED OUT OF SERVICE A WATER CHILLER AK400 WILL BE TAGGED OUT OF SERVICE LIST APPLICABLE TECH SPECS - NONE
- 3) POSSIBLE ACTUATIONS AND/OR ALARMS: NONE EXPECTED
- 4) RELEVANT OPERATING EXPERIENCE: NONE
- 5) RELATED REGULAR MAINT. TASKS FOR POSSIBLE ACCREDITATION:
NONE, THIS IS CM ORDER FOR LEAKING DISCHARGE VALVE INFO FROM N1 20157812 09/05/2003 12:35:39 RICHARD KEENAN (NURCK)
ACTUAL CONDITION: While performing work under order 30045129 on the AP400 CHILLED WATER CIRC PMP it was noted that valve H1GJ-1-GJ-V004 is leaking through the seat/disc. This leak is classified as a minor leak as evaluated with the Leak Detecting Equipment. This leakage in not into the room, but through the valve into the pump requiring complete drainage of the Aux.
Bldg. Control Area Chillers to perform work on the AP400 CHILLED WATER CIRC PMP. This valve should be reworked/replaced in the next available work window.
IMPACT ON PLANT / PERSONNEL SAFETY: None CONDITIONS CAUSE: Normal wear and tear.
ACTIONS TAKEN TO CORRECT THE CONDITION: Wrote this notification. Verified that there is a replacement valve in the Material Center.
RECOMMEND CORRECTION: Rework/replace valve in the next available work window.
RESPONSIBLE INDIVIDUAL: Rich C. Keenan USE TITLE/POSITION: Maintenance Supervisor FURTHER INVOLVEMENT FOLLOW UP OPERABILITY: No POST MAINTENANCE TEST HAS FAILED: No