ML053250415
Jump to navigation
Jump to search
ML053250415 | |
Person / Time | |
---|---|
Site: | Palo Verde |
Issue date: | 11/15/2005 |
From: | NRC Region 4 |
To: | |
References | |
FOIA/PA-2004-0307 | |
Download: ML053250415 (2) | |
Text
- A-cr - T5$S w Wt Preliminary Issue List Palo Verde Nuclear Generating Station Augmented Inspection Team NOTE: This is NOT an all-inclusive list.
- A single phase to ground fault resulted in loss of offsite power and three unit trip
-11, F'X 5 l S
- Auxiliary Relay, Liberty Transmission Line Fault Detection/Protection System Failure
- inadequate design resulted in single failure vulnerability
- additional single failure design issues identified and corrected to extent practical
- licensee also did not appear to make resolution of this issue a startup issue until the concern was raised by the AIT
- Unit 1 Atmospheric Dump Valve 185 Failure
- control room operator distraction with minimal impact on event response
- apparent cause being determined
- Unit 1 Letdown Heat Exchanger Isolation Failure
- licensee performance deficiency associated with understanding implications of temporary modification installed in plant
- little impact on control room response to event
- some potential impact on fire response being reviewed by AIT
- Unit 1 and 3 General Electric Magne Blast Circuit Breaker Failures
- complicated event recovery efforts by delaying the return of offsite power to ESF buses
- licensee determined apparent cause as "breaker not cycled frequently enough"
- AIT challenged licensee on apparent cause, raised concern regarding current functionality of breakers
- resident staff following as potential operability issue
- Unit 2 Train "A' Emergency Diesel Generator Failure
- resulted in a loss of power to Train "A" ESF busses following loss of offsite power
- Unit 2, Train uE" Positive Displacement Charging Pump Trip
- operator error resulted in suction line isolation and protective trip of pump
- AIT identified that auxiliary operator was delayed approximately 10 minutes at the RCA access point even after the operator explained he was on a time critical mission
- when RCA access delay was discussed with licensee, AIT determined that the licensee was unaware of delay .
.-formatlon In thisMU reo d5 UasUeMU
- l accordance with the Freedom of Information aJIA,exemptiou it rJIA. i\ ) RDQ
- Unit 3 Bypass Valve/Control Cabinet Malfunctions
- good operator actions minimized impact on plant, was operator distraction
- potential design modification issue being reviewed by AIT as apparent cause
- Unit 3 Reactor Coolant Pump Lube Oil Lift Pump Breaker Thermal Overload Trip
- no impact on trip but some minor impacts on recovery
- potential design issue associated with set point of thermal overloads
- Unit 3 Low Pressure Safety Injection System In-leakage (Check Valve V217)
- little impact on event, operator distraction to take manual actions to prevent over pressurization
- apparent cause was Borg-Warner check valve leakage, potential maintenance issue
- Unit 3 Variable Over Power Trip - Reactor Coolant Pump Speed Increase to 67 Hz
- licensee investigating potential impacts on plant equipment
- AIT raised questions about hydraulic affects, if any
- apparent cause was test switch out of position
- maintenance personnel failed to use restoration procedure six days prior to event following testing
- some impact on emergency response organization which needed to use alternate TSC
- Procedure Issue Associated with Minimum Amperage for Reactor Coolant Pumps
- complicated recovery efforts by delaying RCP restoration
- appears minimum amperage basis involved NPSH limits
- high voltage in switchyard resulted in low amperage I.
I----i
- Emergency Response Organization Notification Issues
~1
- some delay in notification occurred but little impact
- apparent cause associated with procedure adequacy and communication failures
- Initial Notification of State and Local Official Issues
- Unit 1 and Unit 3 did meet their guidelines on timeliness of initial notification
- little overall impact because Unit 2 Alert Notification was timely
- apparent cause being reviewed
.i