ML052840069

From kanterella
Jump to navigation Jump to search
IR 05000250-05-010, IR 05000251-05-010 on 08/01/2005 - 10/07/2005; Turkey Point, Units 3 and 4; Significance Determination of Unresolved Items and Closure of Two Unresolved Items from Triennial Fire Protection Inspection
ML052840069
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 10/07/2005
From: Mccree V
Division of Reactor Safety II
To: Stall J
Florida Power & Light Co
References
EA-05-195 IR-05-010
Download: ML052840069 (17)


See also: IR 05000250/2005010

Text

ATTACHMENTS 2 AND 3 CONTAIN PROPRIETARY INFORMATION

October 7, 2005

EA-05-195

Florida Power and Light Company

ATTN: Mr. J. A. Stall, Senior Vice President

Nuclear and Chief Nuclear Officer

P. O. Box 14000

Juno Beach, FL 33408-0420

SUBJECT:

TURKEY POINT NUCLEAR PLANT - NRC TRIENNIAL FIRE PROTECTION

INSPECTION (FOLLOW UP) REPORTS 05000250/2005010 AND

05000251/2005010; PRELIMINARY WHITE FINDING AND EXERCISE OF

ENFORCEMENT DISCRETION

Dear Mr. Stall:

On October 7, 2005, the U.S. Nuclear Regulatory Commission (NRC) completed a follow up

inspection associated with triennial fire protection unresolved items (URIs) for your Turkey Point

Nuclear Plant, Units 3 and 4. In summary, certain fire protection items were determined to

result in a preliminary White finding as discussed below. The enclosed inspection report

documents the inspection findings, which were discussed on October 7, 2005, with

Mr. S. Greenlee and other members of your staff.

This inspection was an in-office examination of five unresolved items (URIs) which were

identified in NRC Inspection Report 05000250, 251/2004007 (ADAMS Accession Number

ML040890083) forwarded to you on March 26, 2004. The five URIs were: URI

05000251/2004007-001, Failure to Prevent Spurious Operation of Valve MOV-4-626 For a

Severe Fire in 4B 4160 V Switchgear Room; URI 05000250, 251/2004007-002, Local Manual

Operator Actions to Protect RCP Seal Package Cooling Not Timely; URI 05000251/

2004007-003, Local Manual Operator Actions Not Evaluated for Loss of Security Card Key

Access for a Severe Fire; URI 05000250,251/2004007-006, Local Manual Operator Actions to

Protect RCP Thermal Barrier Cooling Valves MOV-3-716A and MOV-4-716A For Control Room

Evacuation Not Timely; and URI 05000250, 251/2004007-007, Local Manual Operator Actions

For Control Room Evacuation Not Evaluated for Availability of Security Support. These issues

were unresolved pending a safety significance determination.

DOCUMENT TRANSMITTED HEREWITH CONTAINS SENSITIVE UNCLASSIFIED INFORMATION

WHEN SEPARATED FROM ATTACHMENTS 2 AND 3, THIS DOCUMENT IS DECONTROLLED

FPL

2

Based on the results of this inspection, the inspectors identified that the Turkey Point fire

response procedures were not effective in ensuring a safe shutdown of Units 3 and 4 for severe

fires in certain fire zones (FZs) (URIs05000251/2004007-001, 05000250,251/2004007-002,

and 05000250,251/2004007-006). Specifically, the control circuit of motor operated valve

(MOV) MOV-4-626, Reactor Coolant Pump (RCP) Thermal Barrier Component Cooling Water

(CCW) Return Isolation Valve, was not protected nor would spurious operation be prevented

during a fire in FZ 67, and could result in an RCP seal loss of coolant accident (LOCA); local

manual operator actions to verify correct alignment of thermal barrier cooling valves MOV-3-

716B, RCP Thermal Barrier CCW Supply Isolation Valve, and MOV-3-626 in FZ 63 (and

MOV-4-716B in FZ 67) would not be completed in a timely manner, and could result in an RCP

seal LOCA; and local manual operator actions to verify correct alignment of valves MOV-3-

716A and MOV-4-716A would not be completed in a timely manner for a fire in FA MM (FZs

106, 106R, or 97) and could result in an RCP seal LOCA. These inspection findings were

collectively assessed using the applicable significance determination process (SDP) Appendix F

Phase 1 and 2 Worksheets and preliminarily determined to be White (i.e., an issue with low to

moderate safety significance, which may require additional NRC inspections) because they

could affect fire protection defense in depth. Our SDP Phase 1 and 2 evaluations of these

findings are provided in Attachment 3. The findings associated with URIs 05000251/2004007-

001 and 05000250,251/2004007-002 were determined to be an apparent violation of 10 CFR Part 50, Appendix R, Section III.G.2 requirements and the finding associated with URI

05000250,251/2004007-006 was determined to be an apparent violation of 10 CFR Part 50,

Appendix R,Section III.G.3 requirements.

In this case, your staff was aware of the fire induced circuit failure vulnerabilities in early 2001

and implemented local manual operator actions to compensate for these vulnerabilities which,

upon inspection, the NRC determined to be non-feasible. As such, the NRC concluded that

enforcement discretion was not warranted because corrective actions in response to the

vulnerabilities were not prompt, comprehensive or effective. This apparent violation is being

considered for escalated enforcement action in accordance with the Enforcement Policy,

because it is associated with a White finding. The current Enforcement Policy is included on

the NRCs Web site at http://www.nrc.gov/reading-rm/adams.html.

These findings presented an immediate safety concern. In response to the findings, the

licensee implemented immediate corrective and compensatory actions. These actions

effectively reduced the risk to very low (Green).

Before we make a final decision on this matter, we are providing you an opportunity to (1)

present to the NRC your perspectives on the facts and assumptions, used by the NRC to arrive

at the finding and its significance, at a Regulatory Conference or (2) submit your position on the

finding to the NRC in writing. If you request a Regulatory Conference, it should be held within

30 days of the receipt of this letter and we encourage you to submit supporting documentation

at least one week prior to the conference in an effort to make the conference more efficient and

effective. If a Regulatory Conference is held, it will be open for public observation. If you

decide to submit only a written response, such response should be sent to the NRC within 30

days of the receipt of this letter.

Please contact Mr. D. Charles Payne at (404) 562-4669 within seven days of the date of this

letter to notify the NRC of your intentions regarding the regulatory conference for the

preliminary White finding.

FPL

3

If we have not heard from you within 10 days, we will continue with our significance

determination and associated enforcement processes on this finding, and you will be advised by

separate correspondence of the results of our deliberations on this matter.

Since the NRC has not made a final determination in this matter, no Notice of Violation is being

issued for the inspection finding at this time. In addition, please be advised that the number

and characterization of the apparent violation described in the referenced inspection report may

change as a result of further NRC review. For administrative purposes, this letter is issued as a

separate NRC Inspection Report No. 05000250,251/2005010 and the above apparent violation

is identified as AV 0500250,251/2005010-01, Unprotected Post-Fire Safe Shutdown Cables and

Related Non-feasible Local Manual Operator Actions. Accordingly, URIs 05000251/2004007-

001, 05000250,251/2004007-002, and 05000250,251/2004007-006 are closed.

In addition, this report documents closure of URIs05000251/2004007-003 and 05000250,

251/2004007-007 in Attachment 2. For URI 05000251/2004007-003, a violation of 10 CFR 50,

Appendix R, requirements was identified involving circuit analysis issues for which the NRC is

exercising enforcement discretion and reactor oversight process discretion (i.e. not subjecting

the violation to the SDP). The basis for the enforcement discretion is NRC Enforcement

Manual Section 8.1.7.1 (c), Fire Induced Circuit Failures. One of the conditions for applying

discretion is that the circuit vulnerabilities be corrected within a reasonable time frame. NRC

Inspection Manual Chapter 0305, Operating Reactor Assessment Program, Section 06.06.2,

Violations in Specified Areas of Interest Qualifying for Enforcement Discretion, states that

violations related to certain circuit issues which are eligible for enforcement discretion shall also

be eligible for reactor oversight process discretion. The conditions for applying discretion were

met because you did not dispute the violation, entered it into your corrective action program and

completed timely corrective action. No findings were identified associated with URI 05000250,

251/2004007-007. Accordingly, URIs05000251/2004007-003 and 05000250,251/ 2004007-

007 are closed.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter,

portions of the enclosure, and your response (if any) will be available electronically for public

inspection in the NRC Public Document Room or from the Publicly Available Records (PARS)

component of NRCs document system (ADAMS). However, the NRC is continuing to review

the appropriate classification of Attachments 2 and 3 under our records management program,

considering changes in our practices following the events of September 11, 2001. Using our

interim guidance, Attachments 2 and 3 have been marked as Proprietary Information or

Sensitive Information in accordance with Section 2.390(d) of Title 10 of the Code of Federal

Regulations and will not be placed in the PDR. Please control the document accordingly (i.e.,

treat the document as if you had determined that it contained trade secrets and commercial or

financial information that you considered privileged or confidential).

FPL

4

We will inform you if the classification of these documents changes as a result of our ongoing

assessments. ADAMS is accessible from the NRC web site at http://www.nrc.gov/reading-

rm/adams.html (the Public Electronic Reading Room).

If you have any questions regarding this letter, please contact me at 404-562-4600.

Sincerely,

/RA/

Victor M. McCree, Director

Division of Reactor Safety

Docket Nos. 50-250, 50-251

License Nos. DPR-31, DPR-41

Enclosure: Inspection Report 05000250/2005010 and 05000251/2005010

w/Attachment: 1. Supplemental Information

2. Closure of URIs05000251/2004007-003 and

05000250, 251/2004007-007

3. SDP Phase 1 and 2 worksheets

cc w/encl:

FPL

5

cc w/encl:

T. O. Jones

Site Vice President

Turkey Point Nuclear Plant

Florida Power and Light Company

Electronic Mail Distribution

Walter Parker

Licensing Manager

Turkey Point Nuclear Plant

Florida Power and Light Company

Electronic Mail Distribution

Michael O. Pearce

Plant General Manager

Turkey Point Nuclear Plant

Florida Power and Light Company

Electronic Mail Distribution

David Moore, Vice President

Nuclear Operations Support

Florida Power & Light Company

Electronic Mail Distribution

Rajiv S. Kundalkar

Vice President - Nuclear Engineering

Florida Power & Light Company

Electronic Mail Distribution

M. S. Ross, Managing Attorney

Florida Power & Light Company

Electronic Mail Distribution

Marjan Mashhadi, Senior Attorney

Florida Power & Light Company

Electronic Mail Distribution

Attorney General

Department of Legal Affairs

The Capitol

Tallahassee, FL 32304

William A. Passetti

Bureau of Radiation Control

Department of Health

Electronic Mail Distribution

County Manager

Metropolitan Dade County

Electronic Mail Distribution

Craig Fugate, Director

Division of Emergency Preparedness

Department of Community Affairs

Electronic Mail Distribution

Curtis Ivy

City Manager of Homestead

Electronic Mail Distribution

_________________________

OFFICE

DRP:RII

DRP:RII

DRP:RII

DRP:RII

DRP:RII

DRP:RII

DRP:RII

SIGNATURE

/RA/

/RA/

NAME

SNinh

JMunday

DATE

10/6/05

10/6/05

E-MAIL COPY?

YES

NO YES

NO YES

NO YES

NO YES

NO YES

NO YES

NO

OFFICE

DRS:RII

DRS:RII

DRS:RII

EICS

SIGNATURE

/RA/

/RA By CPayne for/

/RA/

/RA/

NAME

WRogers

RRodriguez

CPayne

CEvans

DATE

E-MAIL COPY?

YES

NO YES

NO YES

NO YES

NO YES

NO YES

NO YES

NO

Enclosure

U.S. NUCLEAR REGULATORY COMMISSION

REGION II

Docket Nos:

50-250, 50-251

License Nos:

DPR-31, DPR-41

Report Nos:

05000250/2005010 and 05000251/2005010

Licensee:

Florida Power & Light Company (FP&L)

Facility:

Turkey Point Nuclear Plant, Units 3 & 4

Location:

9760 S. W. 344th Street

Florida City, FL 33035

Dates:

August 1, 2005 - October 7, 2005

Inspectors:

R. Rodriguez, Reactor Inspector

W. Rogers, Senior Reactor Analyst

S. Ninh, Senior Project Engineer

Approved by:

D. Charles Payne, Chief

Engineering Branch 2

Division of Reactor Safety

SUMMARY OF FINDINGS

IR 05000250/2005-010, 05000251/2005-010; 08/01/2005 - 10/07/2005; Turkey Point Nuclear

Power Plant, Units 3 and 4; Significance Determination of Unresolved Items and Closure of

Two Unresolved Items from Triennial Fire Protection Inspection.

This in-office review was conducted by two regional inspectors and a senior reactor analyst.

One preliminary White finding with an apparent violation was identified. The significance of

most findings is indicated by their color (Green, White, Yellow, Red) using Inspection Manual

Chapter (IMC) 0609, Significance Determination Process (SDP). Findings for which the SDP

does not apply may be Green or be assigned a severity level after NRC management review.

The NRC's program for overseeing the safe operation of commercial nuclear power reactors is

described in NUREG-1649, Reactor Oversight Process, Revision 3, dated July 2000.

A.

NRC-Identified and Self-Revealing Findings

Cornerstone: Initiating Events and Mitigating Systems

Preliminary White. The inspectors identified an apparent violation (AV) of 10 CFR 50, Appendix R requirements for failure to: 1) protect the control circuit of

motor operated valve (MOV) MOV-4-626, Reactor Coolant Pump (RCP)

Thermal Barrier Component Cooling Water (CCW) Return Isolation Valve and

to prevent its spurious operation during a fire in fire zone (FZ) 67; 2) ensure that

local manual operator actions used to verify correct alignment of MOV-3-716A

and MOV-4-716A, RCP Thermal Barrier CCW Supply Isolation Valves, and

MOV-3-626, were completed in a timely manner for fires in either FZ 63 or FZ

67; and 3) to ensure local manual operator actions to verify correct alignment of

MOV-3-716A and MOV-4-716A were completed in a timely manner for a fire in

FZ 106. These conditions could result in an RCP seal loss of coolant accident

(LOCA).

This finding is greater than minor because it degraded the defense in depth for

fire protection and also because it is associated with the protection against

external factors attribute and degraded the reactor safety mitigating systems

cornerstone objective. The finding adversely affected the reliability and

capability of equipment required to achieve and maintain a safe shutdown

condition following a severe fire in Fire Zones 61, 63, 67, 70, 98 and 106.

(Section 4OA5)

B.

Licensee-Identified Violations.

None

REPORT DETAILS

4. OTHER ACTIVITIES

4OA5 Other

.1

(Closed) URI 05000251/2004007-001, Failure to Prevent Spurious Operation of Valve

MOV-4-626 For a Severe Fire in 4B 4160 V Switchgear Room

(Closed) URI 05000250,251/2004007-002, Local Manual Operator Actions to Protect

RCP Seal Package Cooling Not Timely

(Closed) URI 05000250,251/2004007-006, Local Manual Operator Actions to Protect

RCP Thermal Barrier Cooling Valves MOV-3-716A and MOV-4-716A For Control Room

Evacuation Not Timely

Introduction. An apparent violation (AV) of 10 CFR 50, Appendix R requirements was

identified for failure to: 1) protect the control circuit of motor operated valve (MOV)

MOV-4-626, Reactor Coolant Pump (RCP) Thermal Barrier Component Cooling Water

(CCW) Return Isolation Valve and to prevent its spurious operation during a fire in fire

zone (FZ) 67; 2) ensure that local manual operator actions used to verify correct

alignment of MOV-3-716A and MOV-4-716A, RCP Thermal Barrier CCW Supply

Isolation Valves and MOV-3-626 were completed in a timely manner for fires in either FZ

63 or FZ 67; and 3) ensure local manual operator actions to verify correct alignment of

valves MOV-3-716A and MOV-4-716A were completed in a timely manner for a fire in

FZ 106. These conditions could result in an RCP seal loss of coolant accident (LOCA).

Description. Pursuant the safe shutdown analysis report (SSAR), thermal barrier

cooling is the assured method for protecting the RCP seals during a severe fire in FZ 67

because charging pump seal injection flow may be terminated by operator action or lost

due to the fire. Valve MOV-4-626 is a motor operated valve in the thermal barrier CCW

header returning from all three Unit 4 RCPs. The valve can be controlled from either the

main control room (MCR) (FZ 106) or the alternate safe shutdown panel (ASP) [which is

located in the 4B 4160V switchgear room (FZ 67)]. Because the control cable for this

valve terminates at the ASP and the cable is unprotected, thermal insult to the control

circuit for the valve could cause it to spuriously close. Closure of the valve would stop

thermal barrier cooling return flow from all three Unit 4 RCPs. Guidance in 0-ONOP-

016.10, Pre-fire Plan Fire Zone 67, directs local manual operator actions to prevent, or

recover from, spurious closure of MOVs that could interrupt thermal barrier cooling. For

FZ 67, thermal barrier cooling valves MOV-4-716B and MOV-4-626 could be subject to

spurious operation but the inspectors found that MOV-4-626 was not included in the

procedure.

On September 9, 2003, the licensee identified an error in the safe shutdown analysis

(SSA) Essential Equipment List. They found that valve MOV-4-626 was not properly

classified as being required to assure safe shutdown (SSD). As a result, the fire

response procedure failed to include MOV-4-626 as part of the mitigation strategy

against spurious valve operation. The issue was entered into the licensees corrective

action program (CAP) as condition report (CR) 03-1330-1. The need to review and

2

update 0-ONOP-016.10 was entered into the CAP as CR 04-0292; but this deficiency

was not resolved prior to the inspection. During the inspection, the licensee resolved

this concern by issuing an on-the-spot-change to 0-ONOP-016.10 which specified

manual actions to de-energize and verify open MOV-4-626. The licensee documented

this action in its CAP as CR 04-0610.

Thermal barrier cooling is also the assured method for protecting the RCP seals during

a severe fire in FZ 63 because charging pump seal injection flow may be terminated by

operator action or lost due to the fire. In lieu of protecting the control circuits and cables

for the RCP thermal barrier cooling valves (MOV-3-716B and MOV-3-626 in FZ 63; and

MOV-4-716B in FZ 67), guidance in 0-ONOP-016.10 directed local manual operator

actions to prevent, or recover from, spurious closure of the MOVs. When evaluating the

feasibility of the manual actions using the guidance in NRC inspection procedure (IP)

71111.05T, Fire Protection [Triennial], the inspectors identified that procedure 0-ONOP-

016.10 allowed 20 minutes to complete the operator actions for verification of thermal

barrier cooling valve alignment. However, industry analyses [Westinghouse Direct Work

No. DW-94-011; Westinghouse WCAP-10541, Revision 2; and Westinghouse WCAP-

15603, Revision 1-A] have determined that seal package damage could occur within 13

minutes of loss of all seal package cooling. Thus, the operator guidance provided in

procedure 0-ONOP-016.10 does not provide timely action and could result in an RCP

seal LOCA. Loss of reactor coolant system (RCS) inventory due to an RCP seal LOCA

could be beyond the capacity of equipment dedicated to achieve and maintain post-fire

safe shutdown. The licensee entered the finding into its CAP as CR 04-0688 and

resolved this concern by revising procedure 0-ONOP-016.10.

Fire Area (FA) MM includes the MCR, the MCR roof, and the Unit 3 and 4 mechanical

equipment room. Per the SSAR, thermal barrier cooling is the assured method for

protecting the RCP seals during a severe fire in FA MM because charging pump seal

injection flow may be terminated by operator action or lost due to the fire. Guidance in

procedure 0-ONOP-105 directs local manual operator actions to prevent, or recover

from, spurious closure of MOVs that could interrupt thermal barrier cooling. The

inspectors identified that 0-ONOP-105, Attachment 7 (Unit 3) and Attachment 8 (Unit 4)

allowed 20 minutes to complete the operator actions for verifying that MOV-3-716A and

MOV-4-716A were open. However, industry analyses [Westinghouse Direct Work No.

DW-94-011; Westinghouse WCAP-10541, Revision 2; and Westinghouse WCAP-

15603, Revision 1-A] have determined that seal package damage could occur within 13

minutes of loss of all seal package cooling. Thus, the operator guidance provided in

procedure 0-ONOP-105 does not provide timely action and could result in an RCP seal

LOCA. Loss of RCS inventory due to an RCP seal LOCA could be beyond the capacity

of equipment dedicated to achieve and maintain post-fire safe shutdown. The licensee

entered the finding into its CAP as CR 04-0688 and resolved this concern by revising

procedure 0-ONOP-105.

Analysis. These findings degraded the defense in depth for fire protection and also they

are associated with the protection against external factors attribute and degraded the

reactor safety mitigating systems cornerstone objective. The findings adversely affected

the reliability and capability of equipment required to achieve and maintain a SSD

condition following a severe fire. The findings are applicable to post-fire SSD from the

MCR or the ASP during a fire in Unit 3 and Unit 4 control room, cable spreading room,

3

switchgear rooms, or motor control center rooms. In this case, your staff was aware of

the fire induced circuit failure vulnerabilities in early 2001, but implemented local manual

operator action that were determined to be non-feasible. As such, the NRC concluded

that enforcement discretion was not warranted because corrective actions in response

to the vulnerabilities were not prompt, comprehensive or effective. Therefore, Reactor

Oversight Process (ROP) discretion was not warranted as well. Accordingly, these

inspection findings were assessed using the applicable SDP. As discussed below,

these findings were preliminarily determined to be White (i.e., an issue with low to

moderate increased importance to safety, which may require additional NRC

inspections.)

Because the findings affect fire protection, they were assessed in accordance with the

NRC Reactor Oversight Processs SDP as described in NRC Inspection Manual Chapter 0609, Appendix F (MC 0609, App. F). In the Phase 1, the findings were associated with

post-fire safe shutdown, they were assigned a high degradation rating and they existed

for more than 30 days. As a result, a Phase 2 Risk Evaluation was required.

Summary of Phase 2 SDP Analysis

This evaluation was performed by Region II inspectors with the assistance of the

regional SRA. The Turkey Point Phase 2 SDP Analysis is included in this inspection

report as Attachment 3.

The fire protection Phase 2 analysis involves a quantitative assessment of core damage

frequency (CDF) increase given a finding. There are nine analysis steps and five

screening checks. The assessment includes quantification of a Fire Frequency, Fire

Damage State, Non-Suppression Probability and Conditional Core Damage Probability

(CCDP).

Preliminary risk significance of the inspection finding was determined to be of low to

moderate safety significance (White) for Unit 3 and Unit 4. The critical assumptions of

SDP Phase 2 are as follows:

FZ 106, MCR. A fire will need to progress for approximately 10 minutes before

procedure 0-ONOP-105 would have to be enacted. Ten minutes was selected

because this would provide adequate time to put out the fire with emergency

plan activation considerations. Therefore, the probability of non-suppression

(PNS) = 0.09.

FZ 98, cable spreading room (CSR). Operators will not enter into procedure

0-ONOP-105 until some evaluation of the fire is performed. The fires resulting in

0-ONOP-105 being implemented would be those still in progress after Halon

actuation fails to suppress the fire or to control it. Therefore, the probability of

non-suppression = 0.05 and the credit for manual suppression = 0.31 for 10

minutes after which 0-ONOP-105 will be used.

FZs 98 and 106. The ASP does not provide LOCA mitigation capability in the

event of MCR evacuation. Therefore, CCDP is assigned as 1.0.

4

FZs 61, 63, 67, and 70. The licensees full scope model quantification results for

these FZs determined CCDP = 1E-3. Upon review, the senior risk analyst (SRA)

concluded that this was a representative value of CCDP and will be used in place

of the Turkey Point SDP Phase 2 notebook results. Recovery credit of 1 point is

given for operator action to open hot leg injection valve. This CCDP of 1E-3 will

be used for FZs 61, 63, 67, and 70.

FZ 70, Unit 3 switchgear room. Same procedure omission existed. Will be

treated similar to FZ 67.

FZ 106R, MCR roof and FZ 97, HVAC equipment room. These FZs have no

credible ignition sources, and therefore, these FZs are not being evaluated.

The probability of no small break LOCA = 0.8

The probability of thermal shock small break LOCA = 0.2

Units 3 and 4 SDP Phase 2 results are summarized in the table as follows. Detailed

SDP Phase 1 and 2 worksheets are in Attachment 3:

Performance Deficiency:

Failure to implement

Westinghouse Technical

Bulletin Guidance on

RCP seal LOCA

Unit affected

Fire Zones Affected

SDP Phase 1 and 2

URI 2004007-01

4

61 and 67

Yes

URI 2004007-02

3 & 4

61, 63, 67, 70

Yes

URI 2004007-06

3 & 4

98 and 106

Yes

5

Unit 4 Fire Zones

SDP Phase 2

Results

Unit 3 Fire Zones

SDP Phase 2

Results

61 - Unit 4 MCC

1.52E-7

63 - Unit 3 MCC

1.34E-7

67 - Unit 4 Switchgear

Room

2.0E-8

70- Unit 3

Switchgear Room

2.0E-8

98 - Unit 4 CSR Portion

6.0E-7

98 - Unit 3 CSR

Portion

5.3E-7

106- Unit 4 MCR Portion

5.8E-6

106- Unit 3 MCR

Portion

4.0E-6

Total Delta CDF for Unit 4 6.57E-06.

Total Delta CDF for

Unit 3

4.68E-06

SDP/Enforcement Review Panel (SERP) Evaluation

The total change in CDF due to the performance deficiency was found to be 6.57E-06/yr

for Unit 4 and 4.68E-06/yr for Unit 3. The color associated with this magnitude of

change in CDF is White. Therefore, the SERP has preliminarily determined this issue to

be a preliminary White finding.

Enforcement. 10 CFR 50.48 (b)(1) requires, in part, that all nuclear power plants

licensed to operate prior to January 1, 1979, must satisfy the applicable requirements of

Appendix R,Section III.G. Section III.G.2 states, in part, that where cables or

equipment, including associated non-safety circuits that could prevent operation or

cause maloperation due to hot shorts, open circuits, or shorts to ground, of redundant

trains of systems necessary to achieve and maintain hot shutdown conditions are

located within the same fire area outside of primary containment, one of three means of

ensuring that one of the redundant trains is free of fire damage shall be provided.

Section III.G.3 states that alternative shutdown capability should be provided where the

protection of systems whose function is required for hot shutdown, does not satisfy the

requirements of III.G.2. Section III.L of Appendix R provides requirements to be met by

alternative shutdown methods. Section III.L.2.b states, in part, that The reactor coolant

makeup function shall be capable of maintaining the reactor coolant level...within the

level indication in the pressurizer in PWRs.

Contrary to the above, on February 13, 2004, the inspectors identified three examples

where 10 CFR 50, Appendix R requirements were not met:

a.

The licensee failed to protect control circuits and cables that could cause

maloperation of MOV-4-626, RCP Thermal Barrier Component Cooling Water

System Return Isolation Valve in FZ 67. This condition existed since at least

September 9, 2003, when it was first identified by the licensee.

6

b.

The licensee failed to protect control circuits and cables that could cause

maloperation of necessary RCP thermal barrier component cooling system

valves MOV-3-716B and MOV-3-626 in FZ 63; and MOV-4-716B valve in FZ 67.

This condition has existed since at least February 9, 2001, when the applicable

procedure page was last revised.

c.

The licensee failed to protect control circuits and cables that could cause

maloperation of necessary RCP thermal barrier component cooling system

valves in FZ 106; and did not meet the alternative shutdown capability

requirements. Specifically, the licensees procedure may not mitigate a spurious

closure of valves MOV-3-716A and MOV-4-716A in a timely manner, possibly

resulting in an RCP seal LOCA, and pressurizer level dropping below the

indicating range. This condition has existed since at least April 24, 2002, when

the applicable procedure pages were last revised.

These findings were an immediate safety concern and the licensee immediately initiated

corrective actions to mitigate or correct these issues before the inspection team left the

site. The licensee revised plant fire response procedures to include MOV-4-626 and the

13-minute requirement for the completion of local manual operator actions to verify the

RCP thermal barrier return valve and supply valves alignment in the affected fire zones.

In this case, your staff was aware of the fire induced circuit failure vulnerabilities in early

2001, but implemented local manual operator actions that were determined to be non-

feasible. As such, the NRC concluded that enforcement discretion was not warranted

because corrective actions in response to the vulnerabilities were not prompt,

comprehensive and effective. Therefore, these issues are collectively identified as

Apparent Violation (AV) 05000250,251/2005010-01, Unprotected Post-Fire Safe

Shutdown Cables and Related Non-feasible Local Manual Operator Actions.

Accordingly, URIs05000251/2004007-001, 05000250,251/2004007-002, and

05000250,251/2004007-006 are closed.

.2

Unapproved Local Manual Operator Actions for Post-Fire Safe Shutdown

In response to the inspection findings, the licensee took immediate compensatory

actions (some of which included procedural revisions to perform local manual operator

actions in a different manner) to reduce the risk associated with the inspectors findings.

Although these changes appear to reduce the risk to the Green threshold, the current

status of the facility still includes manual operator actions which do not meet the

requirements of Appendix R,Section III.G.2, and for which the licensee failed to obtain

NRC approval. In this case, the licensee put in place various unapproved local manual

operator actions as compensatory measures to meet the requirements of Appendix R,

Section III.G.2

7

Because the compensatory measures did not include one of the three means of

ensuring that one of the redundant trains is free of fire damage (as required by

Appendix R,Section III.G.2), and because no prior approval from the Commission had

been obtained, this issue is being reviewed by NRC and is tracked as URI

05000250,251/2005010-02, Unapproved Local Manual Operator Actions for Post-Fire

Safe Shutdown.

.3

(Closed) URI 05000251/2004007-003. Local Manual Actions Not Evaluated for Loss of

Security Card Key Access for a Severe Fire in 4B 4160V Switchgear Room.

(Closed) URI 05000250.51/2004007-007. Local Manual Action For Control Room

Evacuation Not Evaluated For Availability of Security Support

Discussions of URIs pertains to sensitive information. Consequently, the details for

closing these two URIs is contained in Attachment 2.

4OA6 Meeting, Including Exit

On October 7, 2005, the inspection results of this report were discussed with

Mr. S. Greenlee and other members of his staff who acknowledged the findings. No

proprietary information was provided or examined during the inspection.

Attachment 1

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee personnel:

W. Parker, Licensing Manager

M. Pearce, Plant General Manager

S. Greenlee, Acting Plant General Manager

NRC personnel:

C. Payne, Chief, Engineering Branch 2, Region II

S. Stewart, Senior Resident Inspector, Turkey Point

LIST OF ITEMS OPENED, CLOSED AND DISCUSSED

Opened

05000250,251/2005010-01

AV

Unprotected Post-Fire Safe Shutdown

Cables and Related Non-feasible Local

Manual Operator Actions (Section 4OA5.1)

05000250,251/2005010-02

URI

Unapproved Local Manual Operator Actions

for Post-Fire Safe Shutdown (Section

4OA5.2)

Closed

05000251/2004007-001

URI

Failure to Prevent Spurious Operation of

Valve MOV-4-626 For a Severe Fire in 4B

4160 V Switchgear Room. (4OA5.1)

05000250,251/2004007-002

URI

Local Manual Operator Actions to Protect

RCP Seal Package Cooling Not Timely.

(4OA5.1)05000251/2004007-003

URI

Local Manual Operator Actions Not

Evaluated for Loss of Security Card Key

Access for a Severe Fire. (Attachment 2)

05000250,251/2004007-006

URI

Local Manual Operator Actions to Protect

RCP Thermal Barrier Cooling Valves

MOV-3-716A and MOV-4-716A For Control

Room Evacuation Not Timely. (Section

4OA5.1)

05000250, 251/2004007-007

URI

Local Manual Operator Actions For Control

Room Evacuation Not Evaluated for

2

End Attachment 1

Availability of Security Support.

(Attachment 2)

LIST OF DOCUMENTS REVIEWED

Applicable Codes and Standards

NFPA 72E, Standard on Automatic Fire Detectors, 1987 Edition

CRs Reviewed

CR 04-0683, Inconsistency Identified in Manual Actions Prescribed in the Safe Shutdown

Analysis and the Operations Safe Shutdown Manual Actions for Fire Zone 63 in

0-ONOP-16.10

CR 04-0686, Ceiling Level Fire Detectors in the 4B Switchgear Room (Fire Zone 67) Do

Not Meet the Spacing Guidelines per NRC MC 0609F, Attachment 2 and Is Not

Consistent With UFSAR Section 3.5.1.