Information Notice 2005-29, Steam Generator Tube and Support Configuration
ML052280011 | |
Person / Time | |
---|---|
Issue date: | 10/27/2005 |
From: | Hiland P NRC/NRR/DIPM/IROB |
To: | |
Yoder M, NRR/DE/EMCB, 415-4017 | |
References | |
IN-05-029 | |
Download: ML052280011 (6) | |
UNITED STATES
NUCLEAR REGULATORY COMMISSION
OFFICE OF NUCLEAR REACTOR REGULATION
WASHINGTON, D.C. 20555 October 27, 2005 NRC INFORMATION NOTICE 2005-29: STEAM GENERATOR TUBE AND SUPPORT
CONFIGURATION
ADDRESSEES
All holders of operating licenses or construction permits for pressurized water reactors (PWRs)
except those who have permanently ceased operations and have certified that fuel has been
permanently removed from the reactor vessel.
PURPOSE
The U.S. Nuclear Regulatory Commission (NRC) is issuing this information notice to describe
recent experience in which the configuration of steam generator tube supports or expansions
was different than expected. It is expected that recipients will review the information for
applicability to their facilities and consider actions, as appropriate, to avoid similar problems.
However, suggestions contained in this information notice are not NRC requirements; therefore, no specific action or written response is required.
DESCRIPTION OF CIRCUMSTANCES
The following describes the as-found condition of the steam generators at Byron Unit 1, Davis- Besse, and Waterford Unit 3 during inspections performed during 2005.
Byron Unit 1
Byron Unit 1 replaced the four recirculating steam generators in 1997 with steam generators
designed and fabricated by Babcock and Wilcox International. Each steam generator has
6,633 thermally treated Alloy 690 U-tubes. The U-tubes are supported by stainless steel lattice
grid structures along the straight portion of the tube and by a collector bar and fan bars in the
U-bend region. All fan bars are connected to the collector bar.
During the 2005 steam generator tube inspections, an evaluation of the bobbin coil eddy current
data revealed that the collector bar did not completely engage all of the row 1 tubes in steam
generator B as expected. Investigations discovered that the collector bar engaged, or partially
engaged, only 10 of the 67 row 1 tubes on the hot-leg side of the steam generator, rather than
engaging all 67 of the row 1 tubes. The collector bar was verified to engage all row 1 tubes on
the cold-leg side of the steam generator. Additionally, the collector bar was verified to be
engaged in all row 1 hot-leg and cold-leg tubes in the other three steam generators.
The nonengaged collector bar of the row 1 hot-leg tubes was identified by eddy current data
analysis software that was programmed to compare the existing support structure location with
the design locations of the support structures (landmarks). Following identification of this
condition, a review of past inspection data revealed that this condition existed before the
replacement steam generators were placed into service. The licensee concluded that the
condition was not the result of inservice degradation. Since the as-found condition of the steam
generator was different than the condition analyzed during the design of the steam generator, an analysis was performed to show that the tubes remain adequately supported despite the
mispositioning of the collector bar. Concerned that the "disengaged" tubes would vibrate and
become worn at the lattice support or at the other collector bar location on the cold leg side, the
licensee reviewed eddy current inspections at those locations and found no wear to date. The
licensee concluded that flow-induced vibration is not increased due to the lack of contact with
the collector bar.
Davis-Besse
Davis-Besse has two once-through steam generators designed and fabricated by Babcock and
Wilcox International. Each steam generator contains approximately 15,500 Alloy 600 mill- annealed tubes. The tubes are partial-depth-expanded into both the upper and the lower
tubesheet.
Based on recent operating experience at other similarly designed plants, a significant number of
rotating probe inspections were performed at the tube end in the lower tubesheet (cold-leg) for
the first time during the 2005 outage at Davis-Besse. While performing these inspections, most
tubes (all but approximately 100 tubes) were identified as having two roll-expanded regions in
the lower tubesheet. The presence of two rolls (rather than one) in the lower tubesheet region
was not known by personnel responsible for determining potential forms of degradation that
could affect the tubes. A review of fabrication records indicated the second roll was installed
during the original manufacture of the steam generators since there was inadequate control of
the original roll in the lower tubesheet and many of the original rolls were too short. The tubes
were rerolled prior to annealing the steam generator. The second rolls are referred to as shop
rerolls to distinguish them from reroll repairs performed subsequent to commercial operation.
Approximately 30 tubes were plugged during the 2005 outage as a result of crack like
indications detected at the shop rerolls in the lower tubesheet. None of the crack like
indications were safety significant.
Waterford Unit 3
Waterford Unit 3 has two recirculating steam generators designed and fabricated by
Combustion Engineering. The mill-annealed Alloy 600 steam generator tubes are supported in
the straight portion of the tube by a number of carbon steel lattice grid (i.e., eggcrate) tube
supports and in the U-bend region by diagonal bars (also called batwings) and vertical straps.
Several of the lattice grid tube supports are referred to as partial eggcrate supports since they
only support some of the tubes. The tubes in rows 1 through 18 are U-bends and the tubes in
rows 19 through 147 are square bends (i.e., there are two 90-degree bends for tubes in rows
19 through 147). Routine eddy current testing of the steam generator tubes in 2005 identified that two diagonal
batwing supports in steam generator 2 had moved. The two batwings were displaced from their
nominal locations on the cold-leg side of tubes in columns 82, 83, and 84. These batwings
were at their nominal locations during the previous inspection. Wear scars were observed for
tubes in these columns during the 2005 inspections. These wear scars occurred in the free
span of the tube at the nominal axial location of the batwing and thus were apparently formed
before the displacement of the batwings. These wear indications were not observed during the
previous inspection. The depth of these wear indications ranged from 7- to 30-percent of the
tube wall thickness.
The batwing assembly is formed by two opposing diagonal bars connected by a short horizontal
bar. A visual inspection of the lower portion of the batwings confirmed that two batwings had
failed at the intersection of the horizontal bar and a slotted bar, which runs perpendicularly to
the horizontal bar and is keyed to the horizontal bar. The slotted bar holds the lower portion of
the batwing in place. The licensee concluded that the failure mechanism was fatigue, based on
the location of the failure, the length of the batwing (one of the longest in the steam generator),
and the flow in this region of the tube bundle. The loads on the batwing in this region are not
high enough to cause an overload-type failure.
As a result of these findings, several corrective actions were taken, including plugging and
stabilizing many tubes, performing analyses, and evaluating the integrity of the batwing-to- wrapper bar welds. The analyses were done to confirm that tube integrity will not be
compromised for the period of time between tube inspections if additional batwings fail. The
evaluations were done to ensure that the failed batwings would not become free to move
throughout the steam generator, (i.e., become loose parts). The batwing-to-wrapper bar welds
connect all of the batwings and are located on the outside of the tube bundle to permit access
for visual inspection.
BACKGROUND
High-cycle fatigue due to inadequate tube support (antivibration bar location anomalies) was
the cause of a tube rupture in 1987 (Bulletin 88-02, Rapidly Propagating Fatigue Cracks on
Steam Generator Tubes).
Steam generator internals can be important in ensuring that the tubes are capable of
performing their intended safety function (Generic Letter 97-06, Degradation of Steam
Generator Internals).
DISCUSSION
The positioning of the tube supports (e.g., antivibration bars, batwings, vertical straps, collector
bars, fan bars, lattice grids, support plates) is important in ensuring the tubes are adequately
supported. Inadequate tube support can result in increased tube vibration and increased tube
wear and fatigue. At Byron Unit 1, the nonengaged collector bar in the U-bend region of many row 1 tubes was
discovered through a review of inspection data. The data indicated that the support was not in
the correct position. This condition was identified by applying a computerized data-screening
algorithm to the inspection data. In the case of Waterford 3, the failed batwing support was
discovered by investigating several indications of wear that were apparently occurring at a
location not associated with a support structure. In both cases, the actual tube support
conditions were evaluated to identify any tube integrity concerns (e.g., flow-induced vibration).
Prompt identification of supports that are not in their proper position (as a result of fabrication or
from service-induced conditions) is important to ensure that appropriate actions are taken in a
timely manner before tube integrity is compromised.
At Davis-Besse, the presence of a second roll expansion in the lower tubesheet was not known
by responsible plant personnel. Roll expansions are locations of high stress and are more
susceptible to degradation. As a result, it is important to know all locations of high stress to
ensure that appropriate inspection techniques are used at those locations to detect possible
degradation.
At Waterford Unit 3, additional evaluations and inspections were performed to ensure that the
actual configuration of the failed batwings was stable. Since one end of each failed batwing
was free to move, the welds securing the other ends were evaluated to ensure the failed
batwings would not become free during operation and potentially impact other tubes.
Evaluating the as-found condition to ensure that continued degradation will not result in the
generation of loose parts is also important for ensuring tube integrity.
In summary, it is important to compare the as-found condition of the steam generator to the
steam generator design. This includes confirming that the as-found location of the steam
generator tube supports is consistent with the original design. Significant differences between
the as-found and as-designed location of the tube supports can result in increased tube
vibration and increased tube wear and fatigue. Promptly identifying significant differences
between the as-found and as-designed configuration may prevent a loss of tube integrity.
Similarly, monitoring the current condition and location of the tube supports is important to
ensure that any service-induced degradation or movement of the supports is promptly detected
and evaluated. In addition, it is important to know the actual configuration of the steam
generator tubes to ensure that all high-stress locations are identified in the degradation
assessment and inspected with techniques capable of detecting the forms of degradation that
may occur at those locations.
CONTACT
Please direct any questions about this matter to the technical contact(s) or the Lead Project
Manager listed below, or to the appropriate Office of Nuclear Reactor Regulation (NRR) project
manager.
/RA/
Patrick L. Hiland, Chief
Reactor Operations Branch
Division of Inspection Program Management
Office of Nuclear Reactor Regulation
Technical Contact:
Matthew Yoder, NRR
301-415-4017 E-mail: mgy@nrc.gov
Note: NRC generic communications may be found on the NRC public Website, http://www.nrc.gov, under Electronic Reading Room/Document Collections.
ML052280011 OFFICE EMEB:DE Tech Editor EMCB:DE BC:EMCB:DE
NAME VHodge PKleene MGYoder WHBateman
DATE 10/13/2005 8/18/2005 10/13/2005 10/18/2005 OFFICE ADPT:DLPM ADPT:DLPM ADPT:DLPM TL:OES:IROB:DIPM
NAME GDick WAMacon KKalyanam IJung
DATE 10/21/2005 10/21/2005 10/20/2005 10/25/2005 OFFICE SC:OES:IROB:DIPM C:IROB:DIPM
NAME MJRoss-Lee PLHiland
DATE 10/27/2005 10/27/2005