Text
SOuTHERN CALIFORNIA EDISON~
AnIEDISON INTERNA71ION4 U Company A. Edward Scherer Manager of Nuclear Rcgulator) Affairs July 18, 2005 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555
Subject:
Docket Nos. 50-361 and 50-362 Additional Information Supporting Amendment Application Nos. 224 and 208 Containment Leakage Rate Testing Program San Onofre Nuclear Generating Station Units 2 and 3
References:
See Enclosure 2
Dear Sir or Madam:
This letter provides Attachments A through F, that were inadvertently omitted from our June 30, 2004, letter (Reference 1). By this letter, as supplemented by our May 27, 2005, letter (Reference 2) SCE requested a technical specification change to allow the deferral of the next ILRT Type A Test from the fourteenth refueling outage (scheduled for January 2006 for Unit 2 and October 2006 for Unit 3) to not later than March 30, 2010 for Unit 2 and September 9, 2010 for Unit 3 Additionally, by a separate submittal dated June 29, 2004, (Reference 3), SCE proposed a change to the technical specifications that, although it was unrelated to the integrated leak rate change, affected the same technical specification page (page 5.0-20a). In anticipation of the possibility that the technical specification change requested by the June 29, 2004 letter (Reference 3) may be approved prior to the integrated leak rate test change, this letter also includes the appropriately revised technical specification changes. Attachments G and H provide a clean copy of technical specification page 5.0-20a with both changes incorporated.
P.O. Box 128 San Clemente, CA 92672 949-368-7501 Fax 949-368-7575 I
Document Control Desk July 18, 2005 If you have any questions or require additional information, please contact Mr. Jack Rainsberry at (949) 368-7420.
Sincerely,
Enclosures:
- 1) PCN 554 Licensee Evaluation Attachments A through H
- 2) References cc:
B. S. Malleft, Regional Administrator, NRC Region IV C. C. Osterholtz, NRC Senior Resident Inspector, San Onofre Units 2 and 3 B. M. Pham, NRC Project Manager, San Onofre Units 2 and 3 S. Y. Hsu, Department of Health Services, Radiologic Health Branch
Enclosure I Amendment Applications 224 and 208, PCN 554 Licensee Evaluation Attachments A Through H
PCN 554 Attachment A (Existing Pages)
SONGS Unit 2
Procedures, Programs, and Manuals 5.5 5.5 Procedures, Programs, and Manuals (continued) 5.5.2.14 Configuration Risk Management Program (CRMP)
(Continued)
- d. Provisions for assessing the need for additional actions after the discovery of additional equipment out of service conditions while in the LCO Condition.
- e. Provisions for considering other applicable risk significant contributors such as Level 2 issues, and external events, qualitatively or quantitatively.
5.5.2.15 Containment Leakage Rate Testing Program A program shall be established to implement the leakage rate testing of the containment as required by 10 CFR 50.54(o) and 10 CFR 50, Appendix J, Option B, as modified by approved exemptions. This program shall be in accordance with the guidelines contained in Regulatory Guide 1.163, "Performance-Based Containment Leak-Test Program," dated September 1995.
The calculated peak containment internal pressure related to the design basis loss-of-coolant accident, Pas is 45.9 psig (Pa will conservatively be assumed to be equal to the calculated peak containment internal pressure for the design basis Main Steam Line Break (56.5 psig) for the purpose of containment testing in accordance with this Technical Specification).
The maximum allowable containment leakage rate, La, at Pas shall be 0.10% of containment air weight per day.
Leakage rate acceptance criteria are:
- a. The Containment overall leakage rate acceptance criterion is s 1.0 La.
During the first unit startup following testing in accordance with this program, the leakage rate acceptance criteria are
- 0.60 La for the Type B and Type C tests and s 0.75 La for the Type A tests;
- b. Air lock testing acceptance criteria are:
- 1)
Overall air lock leakage rate is
- 0.05 La when tested at 2 Pan
- 2)
For each door, the leakage rate is
- 0.01 La when pressurized to 2 9.0 psig.
(continued)
SAN ONOFRE--UNIT 2 5.0-20a Amendment No. 182 1
PCN 554 Attachment B (Existing Pages)
SONGS Unit 3
Procedures, Programs, and Manuals 5.5 5.5 Procedures, Programs, and Manuals (continued) 5.5.2.14 Configuration Risk Management Program (CRMP)
(Continued)
- d. Provisions for assessing the need for additional actions after the discovery of additional equipment out of service conditions while in the LCO Condition.
- e. Provisions for considering other applicable risk significant contributors such as Level 2 issues, and external events, qualitatively or quantitatively.
5.5.2.15 Containment Leakage Rate Testing Program A program shall be established to implement the leakage rate testing of the containment as required by 10 CFR 50.54(o) and 10 CFR 50, Appendix J, Option B, as modified by approved exemptions. This program shall be in accordance with the guidelines contained in Regulatory Guide 1.163, "Performance-Based Containment Leak-Test Program", dated September 1995.
The calculated peak containment internal pressure related to the design basis loss-of-coolant accident, Pa, is 45.9 psig (Pa will' conservatively be assumed to be equal to the calculated peak containment internal pressure for the design basis Main Steam Line Break (56.5 psig) for the purpose of containment testing in accordance with this Technical Specification).
The maximum allowable containment leakage rate, La, at Pa, shall be 0.10% of containment air weight per day.
Leakage rate acceptance criteria are:
- a. The Containment overall leakage rate acceptance criterion is 1.0 La.
During the first unit startup following testing in accordance with this program, the leakage rate acceptance criteria are
- 0.60 La for the Type B and Type C tests and
- 0.75 La for the Type A tests;
- b. Air lock testing acceptance criteria are:
- 1)
Overall air lock leakage rate is s 0.05 La when tested at 2 Pat
- 2)
For each door, the leakage rate is
- 0.01 La when pressurized to 2 9.0 psig.
(continued)
SAN ONOFRE--UNIT 3 5.0-20a Amendment No. 173
PCN 554 Attachment C (Proposed Pages)
(Redline and Strikeout)
SONGS Unit 2
Procedures, Programs, and Manuals 5.5 5.5 Procedures, Programs, and Manuals (continued) 5.5.2.14 Configuration Risk Management Program (CRMP)
(Continued)
- d. Provisions for assessing the need for additional actions after the discovery of additional equipment out of service conditions while in the LCO Condition.
- e. Provisions for considering other applicable risk significant contributors such as Level 2 issues, and external events, qualitatively or quantitatively.
5.5.2.15 Containment Leakage Rate Testing Program A program shall be established to implement the leakage rate testing of the containment as required by 10 CFR 50.54(o) and 10 CFR 50, Appendix J, Option B, as modified by approved exemptions.
This program shall be in accordance with the guidelines contained in Regulatory Guide 1.163, "Performance-Based Containment Leak-Test Program," dated September 1995 as modified by the following exception:
NEI 94 1995, Section 9.2.3: The first Type A Test performed after the March 31, 1995 Type A Test shall be performed'no later than March 30, 2010.
The calculated peak containment internal pressure related to the design basis loss-of-coolant accident, Pa, is 45.9 psig (Pa will conservatively be assumed to be equal to the calculated peak containment internal pressure for the design basis Main Steam Line Break (56.5 psig) for the purpose of containment testing in accordance with this Technical Specification).
The maximum allowable containment leakage rate, La, at Pa, shall be 0.10% of containment air weight per day.
Leakage rate acceptance criteria are:
- a. The Containment overall leakage rate acceptance criterion is
- 1.0 La.
During the first unit startup following testing in accordance with this program, the leakage rate acceptance criteria are
- 0.60 La for the Type B and Type C tests and
- 0.75 La for the Type A tests;
- b.
Air lock testing acceptance criteria are:
- 1)
Overall air lock leakage rate is
- 0.05 La when tested at 2 Pa
- 2)
For each door, the leakage rate is
- 0.01 La when pressurized to 2 9.0 psig.
(continued)
SAN ONOFRE--UNIT 2 5.0-20a Amendment No. M-Z
PCN 554 Attachment D (Proposed Pages)
(Redline and Strikeout)
SONGS Unit 3
Procedures, Programs, and Manuals 5.5 5.5 Procedures, Programs, and Manuals (continued) 5.5.2.14 Configuration Risk Management Program (CRMP)
(Continued)
- d. Provisions for assessing the need for additional actions after the discovery of additional equipment out of service conditions while in the LCO Condition.
- e. Provisions for considering other applicable risk significant contributors such as Level 2 issues, and external events, qualitatively or quantitatively.
5.5.2.15 Containment Leakage Rate Testing Program A program shall be established to implement the leakage rate testing of the containment as required by 10 CFR 50.54(o) and 10 CFR 50, Appendix J, Option B, as modified by approved exemptions. This program shall be in accordance with the guidelines contained in Regulatory Guide 1.163, "Performance-Based Containment Leak-Test Program", dated September 1995 as modified by the following exception:
Program" dae Setme 195..
NEI 94 1995, Section 9.2.3: The first Type A Test performed after the September'10, 1995 Type A-Test shall be performed no later than September 9, 2010.
The calculated peak containment internal pressure related to the design basis loss-of-coolant accident, Pas is 45.9 psig (Pa will conservatively be assumed to be equal to the calculated peak containment internal pressure for the design basis Main Steam Line Break (56.5 psig) for the purpose of containment testing in accordance with this Technical Specification).
The maximum allowable containment leakage rate, L., at Pa, shall be 0.10% of containment air weight per day.
Leakage rate acceptance criteria are:
- a. The Containment overall leakage rate acceptance criterion is s 1.0 La.
During the first unit startup following testing in accordance with this program, the leakage rate acceptance criteria are
- 0.60 L. for the Type B and Type C tests and
- 0.75 La for the Type A tests;
- b. Air lock testing acceptance criteria are:
- 1)
Overall air lock leakage rate is
- 0.05 La when tested at 2 Pan
- 2)
For each door, the leakage rate is
- 0.01 La when pressurized to 2 9.0 psig.
(continued)
SAN ONOFRE--UNIT 3 5.0-20a Amendment No. 174
PCN 554 Attachment E (Proposed Pages)
SONGS Unit 2
Procedures, Programs, and Manuals 5.5 5.5 Procedures, Programs, and Manuals (continued) 5.5.2.14 Configuration Risk Management Program (CRMP)
(Continued)
- d. Provisions for assessing the need for additional actions after the discovery of additional equipment out of service conditions while in the LCO Condition.
- e. Provisions for considering other applicable risk significant contributors such as Level 2 issues, and external events, qualitatively or quantitatively.
5.5.2.15 Containment Leakage Rate Testing Program A program shall be established to implement the leakage rate testing of the containment as required by 10 CFR 50.54(o) and 10 CFR 50, Appendix J, Option B, as modified by approved exemptions. This program shall be in accordance with the guidelines contained in Regulatory Guide 1.163, "Performance-Based Containment Leak-Test Program," dated September 1995 as modified by the following exception:
NEI 94 1995, Section 9.2.3: The first Type A Test performed after the March 31, 1995 Type A Test shall be performed no later than March 30, 2010.
The calculated peak containment internal pressure related to the design basis loss-of-coolant accident, Pa, is 45.9 psig (Pa will conservatively be assumed to be equal to the calculated peak containment internal pressure for the design basis Main Steam Line Break (56.5 psig) for the purpose of containment testing in accordance with this Technical Specification).
The maximum allowable containment leakage rate, La, at Pa, shall be 0.10% of containment air weight per day.
Leakage rate acceptance criteria are:
- a. The Containment overall leakage rate acceptance criterion is s 1.0 La.
During the first unit startup following testing in accordance with this program, the leakage rate acceptance criteria are
- 0.60 La for the Type B and Type C tests and s 0.75 La for the Type A tests;
- b. Air lock testing acceptance criteria are:
- 1)
Overall air lock leakage rate is s 0.05 La when tested at 2 Pal
- 2)
For each door, the leakage rate is
- 0.01 La when pressurized to 2 9.0 psig.
(continued)
SAN ONOFRE--UNIT 2 5.0-20a Amendment No.
PCN 554 Attachment F (Proposed Pages)
SONGS Unit 3
Procedures, Programs, and Manuals 5.5 5.5 Procedures, Programs, and Manuals (continued) 5.5.2.14 Configuration Risk Management Program (CRMP)
(Continued)
- d. Provisions for assessing the need for additional actions after the discovery of additional equipment out of service conditions while in the LCO Condition.
- e. Provisions for considering other applicable risk significant contributors such as Level 2 issues, and external events, qualitatively or quantitatively.
5.5.2.15 Containment Leakage Rate Testing Program A program shall be established to implement the leakage rate testing of the containment as required by 10 CFR 50.54(o) and 10 CFR 50, Appendix J, Option B, as modified by approved exemptions.
This program shall be in accordance with the guidelines contained in Regulatory Guide 1.163, "Performance-Based Containment Leak-Test Program", dated September 1995 as modified by the following exception:
NEI 94 1995, Section 9.2.3: The first Type A Test performed after the September 10, 1995 Type A Test shall be performed no later than September 9, 2010.
The calculated peak containment internal pressure related to the design basis loss-of-coolant accident, Pa, is 45.9 psig (Pa will conservatively be assumed to be equal to the calculated peak containment internal pressure for the design basis Main Steam Line Break (56.5 psig) for the purpose of containment testing in accordance with this Technical Specification).
The maximum allowable containment leakage rate, L., at Pa, shall be 0.10% of containment air weight per day.
Leakage rate acceptance criteria are:
- a. The Containment overall leakage rate acceptance criterion is
- 1.0 La.
During the first unit startup following testing in accordance with this program, the leakage rate acceptance criteria are
- 0.60 La for the Type B and Type C tests and s 0.75 La for the Type A tests;
- b. Air lock testing acceptance criteria are:
- 1)
Overall air lock leakage rate is
- 0.05 La when tested at 2 Pal
- 2)
For each door, the leakage rate is
- 0.01 La when pressurized to 2 9.0 psig.
(continued)
SAN ONOFRE--UNIT 3 5.0-20a Amendment No.
Attachment G (Proposed Pages)
SONGS Unit 2
Procedures, Programs, and Manuals 5.5 5.5 Procedures, Programs, and Manuals (continued) 5.5.2.15 Containment Leakage Rate Testing Program A program shall be established to implement the leakage rate testing of the containment as required by 10 CFR 50.54(o) and 10 CFR 50, Appendix J, Option B, as modified by approved exemptions. This program shall be in accordance with the guidelines contained in Regulatory Guide 1.163, "Performance-Based Containment Leak-Test Program," dated September 1995 as modified by the following exception:
NEI 94 1995, Section 9.2.3: The first Type A Test performed after the September 10, 1995 Type A Test shall be performed no later than September 9, 2010.
The calculated peak containment internal pressure related to the design basis loss-of-coolant accident, Pa, is 45.9 psig (Pa will conservatively be assumed to be equal to the calculated peak containment internal pressure for the design basis Main Steam Line Break (56.5 psig) for the purpose of containment testing in accordance with this Technical Specification).
The maximum allowable containment leakage rate, La, at Pa, shall be 0.10% of containment air weight per day.
Leakage rate acceptance criteria are:
- a. The Containment overall leakage rate acceptance criterion is
- 1.0 La.
During the first unit startup following testing in accordance with this program, the leakage rate acceptance criteria are
- 0.60 La for the Type B and Type C tests and
- 0.75 La for the Type A tests;
- b. Air lock testing acceptance criteria are:
- 1)
Overall air lock leakage rate is
- 0.05 La when tested at 2 Pat
- 2)
For each door, the leakage rate is < 0.01 La when pressurized to 2 9.0 psig.
(continued)
SAN ONOFRE--UNIT 2 5.0-20a Amendment No.
Attachment H (Proposed Pages)
SONGS Unit 3
Procedures, Programs, and Manuals 5.5 5.5 Procedures, Programs, and Manuals (continued) 5.5.2.15 Containment Leakage Rate Testing Program A program shall be established to implement the leakage rate testing of the containment as required by 10 CFR 50.54(o) and 10 CFR 50, Appendix J, Option B, as modified by approved exemptions.
This program shall be in accordance with the guidelines contained in Regulatory Guide 1.163, "Performance-Based Containment Leak-Test Program", dated September 1995 as modified by the following exception:
NEI 94 1995, Section 9.2.3: The first Type A Test performed after the September 10, 1995 Type A Test shall be performed no later than September 9, 2010.
The calculated peak containment internal pressure related to the design basis loss-of-coolant accident, Pa, is 45.9 psig (Pa will conservatively be assumed to be equal to the calculated peak containment internal pressure for the design basis Main Steam Line Break (56.5 psig) for the purpose of containment testing in accordance with this Technical Specification).
The maximum allowable containment leakage rate, La, at Pa, shall be 0.10% of containment air weight per day.
Leakage rate acceptance criteria are:
- a.
The Containment overall leakage rate acceptance criterion is
- 1.0 La.
During the first unit startup following testing in accordance with this program, the leakage rate acceptance criteria are
- 0.60 La for the Type B and Type C tests and
- 0.75 La for the Type A tests;
- b.
Air lock testing acceptance criteria are:
- 1)
Overall air lock leakage rate is
- 0.05 La when tested at 2 P,.
- 2)
For each door, the leakage rate is
- 0.01 La when pressurized to 2 9.0 psig.
(continued)
SAN ONOFRE--UNIT 3 5.0-20a Amendment No.
References:
References:
- 1)
Letter from D. E. Nunn (SCE) to the U.S. Nuclear Regulatory Commission dated June 30, 2004;
Subject:
"Docket Nos. 50-361 and 50-362, Amendment Application Nos.
224 and 208, Proposed Change Number (PCN) 554, Technical Specification (TS) 5.5.2.15, Containment Leakage Rate Testing Program, San Onofre Nuclear Generating Station, Units 2 and 3."
- 2)
Letter from B. Katz (SCE) to the U.S. Nuclear Regulatory Commission dated May 27, 2005;
Subject:
"Docket Nos. 50-361 and 50-362, Supplement One To Amendment Application Nos. 224 and 208, Proposed Change Number (PCN) 554, Technical Specification (TS) 5.5.2.15, Containment Leakage Rate Testing Program, San Onofre Nuclear Generating Station, Units 2 and 3."
- 3)
Letter from D. E. Nunn (SCE) to the U.S. Nuclear Regulatory Commission dated June 29, 2004;
Subject:
'Docket Nos. 50-361 and 50-362, Proposed Change Number (NPF-10/15) 533, License Amendment Request, Miscellaneous Technical Specification Changes, San Onofre Nuclear Generating Station Units 2 and 3.