Notification of Crystal River Ssdpc Inspection Report 05000302-05-006
ML050540383
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 02/23/2005
From: Ogle C
Division of Reactor Safety II
To: Young D
Florida Power Corp
References
IR-05-006
Download: ML050540383 (6)


See also: IR 05000302/2005006

Text

February 23, 2005

Mr. Dale E. Young, Vice President

Crystal River Nuclear Plant (NA1B)

ATTN: Supervisor, Licensing &

Regulatory Programs

15760 West Power Line Street

Crystal River, FL 34428-6708

SUBJECT: NOTIFICATION OF CRYSTAL RIVER NUCLEAR PLANT - SAFETY SYSTEM

DESIGN AND PERFORMANCE CAPABILITY INSPECTION - NRC

INSPECTION REPORT 05000302/20050006

Dear Mr. Young:

The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC)

Region II staff will conduct a safety system design and performance capability inspection at

your Crystal River Nuclear Plant during the weeks of April 25 - 29, 2005 and May 9 -13, 2005.

A team of five inspectors will perform this inspection. The inspection team will be led by

Mr. Larry Mellen, a Senior Reactor Inspector from the NRC Region II Office. This inspection

will be conducted in accordance with baseline inspection program Attachment 71111.21, Safety

System Design and Performance Capability.

The inspection will evaluate the capability of installed plant equipment to detect and respond to

a loss of coolant accident. Procedures which direct the mitigating actions for this event will also

be evaluated.

During a telephone conversation on February 23, 2005, Mr. Mellen of my staff, and

Mr. Dennis Herrin, Lead Engineer, Licensing and Regulatory Programs, of your staff, confirmed

arrangements for an information gathering site visit and the two-week onsite inspection. The

schedule is as follows:

  • Information gathering visit: Week of March 28, 2005
  • Onsite inspection weeks: April 25 - 29, 2005 and May 9 -13, 2005

The purpose of the information gathering visit is to obtain information and documentation

outlined in the Enclosure needed to support the inspection. Mr. Walter Rogers, a Region II

Senior Reactor Analyst, may accompany Mr. Mellen during the information gathering visit to

review probabilistic risk assessment data and identify risk significant components which will be

examined during the inspection. Please contact Mr. Mellen prior to preparing copies of the

materials listed in the Enclosure. The inspectors will try to minimize your administrative burden

by specifically identifying only those documents required for inspection preparation.

During the information gathering visit, Mr. Mellen will also discuss the following inspection

support administrative details: office space; specific documents requested to be made

available to the team in their office space; arrangements for site access; and the availability of

FPC 2

knowledgeable plant engineering and licensing personnel to serve as points of contact during

the inspection.

Thank you for your cooperation in this matter. If you have any questions regarding the

information requested or the inspection, please contact Mr. Mellen at (404) 562-4531 or me at

(404) 562-4605.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its

enclosure will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records (PARS) component of NRCs document system

(ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-

rm/adams.html (the Public Electronic Reading Room).

Sincerely,

\\RA\\

Charles R. Ogle, Chief

Engineering Branch 1

Division of Reactor Safety

Docket Nos.: 50-302

License Nos.: DPR-72

Enclosure: Information Request for the Safety System Design and

Performance Capability Inspection

cc w/encl:

Daniel L. Roderick

Director Site Operations

Crystal River Nuclear Plant (NA2C)

Electronic Mail Distribution

Jon A. Franke

Plant General Manager

Crystal River Nuclear Plant (NA2C)

Electronic Mail Distribution

Richard L. Warden

Manager Nuclear Assessment

Crystal River Nuclear Plant (NA2C)

Electronic Mail Distribution

cc w/encl contd: - (See page 3)

FPC 3

cc w/encl contd:

Michael J. Annacone

Engineering Manager

Crystal River Nuclear Plant (NA2C)

Electronic Mail Distribution

R. Alexander Glenn

Associate General Counsel (MAC - BT15A)

Florida Power Corporation

Electronic Mail Distribution

Steven R. Carr

Associate General Counsel - Legal Dept.

Progress Energy Service Company, LLC

Electronic Mail Distribution

Attorney General

Department of Legal Affairs

The Capitol

Tallahassee, FL 32304

William A. Passetti

Bureau of Radiation Control

Department of Health

Electronic Mail Distribution

Craig Fugate, Director

Division of Emergency Preparedness

Department of Community Affairs

Electronic Mail Distribution

Chairman

Board of County Commissioners

Citrus County

110 N. Apopka Avenue

Inverness, FL 36250

Jim Mallay

Framatome Technologies

Electronic Mail Distribution

_________________________

OFFICE RII:DRS

SIGNATURE LSM

NAME LMellen

DATE 2/23/2005 2/ /2005 2/ /2005 2/ /2005 2/ /2005 2/ /2005 2/ /2005

E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO

INFORMATION REQUEST FOR THE CRYSTAL RIVER 3 SAFETY SYSTEM DESIGN

AND PERFORMANCE CAPABILITY INSPECTION

LOSS OF COOLANT ACCIDENT (Small Break, Large Break, Inter-System)

(Please provide the information electronically in searchable .pdf files on CDROM. The

CDROM should be indexed and hyperlinked to facilitate ease of use. Information in

lists should contain enough information to be easily understood by someone who has a

knowledge of pressurized water reactor technology.)

1. Design basis documents for the engineered safety features (ESF) and emergency core

cooling systems (ECCS) used to mitigate the loss of coolant accident (LOCA) event.

Design basis documents for the high, medium, and low voltage electrical systems that

power the ESF and ECCS components/systems.

2. All procedures used to implement the mitigation strategy for the LOCA event. Include

alarm response procedures as well as normal, abnormal, and emergency operating

procedures (EOPs) as appropriate. Also include the EOP users guide and EOP setpoint

document as well as calculations used to support the setpoints in EOPs for the LOCA

event.

3. Piping and instrumentation drawings (P&IDs) for the ECCS and other systems used to

mitigate the LOCA event. Two (2) paper copies are preferred for these.

4. List of surveillance procedures used to ensure the operability of equipment required by

your Technical Specifications that is used during the mitigation of the LOCA event.

5. List of engineering calculations (electrical, mechanical/nuclear, instrumentation and

controls) applicable to the ECCS components and other related systems used for a

LOCA event.

6. List of temporary modifications and operator work-arounds involving any components

required for mitigation of a LOCA event for the past 3 years

7. System descriptions and operator training modules for the LOCA event, the ECCS, and

other systems used to mitigate the event. Include a brief overview of the LOCA event

mitigation strategy, including operator actions and equipment used.

8. List of operating experience program evaluations of industry, vendor, or NRC generic

issues related to a LOCA event.

9. A list of major modifications completed in the past five years to the ECCS and other

systems used to mitigate a LOCA event.

Enclosure

2

10. Calibration and functional test procedures for instruments used to monitor Reactor

Coolant System (RCS) pressure, pressurizer level, RCS hot and cold leg temperatures,

RCS subcooling, high pressure coolant injection flow, low pressure coolant injection

flow, borated water storage tank level, auxillary feedwater flow, condensate storage

tank level, and containment sump level.

11. Quality Assurance audits and/or self assessments performed on the ECCS and other

systems used to mitigate a LOCA in the past 24 months.

12. Plant Technical Specifications, Bases, and Technical Requirements Manual.

13. A current copy of the Updated Final Safety Analysis Report.

14. Procedures that provide implementation guidance for the following programs: Corrective

Action Program, Maintenance Rule Program, Design Control Program, and Operating

Experience Program.

15. Probabilistic risk assessment (PRA) event tree for the LOCA event. A list of PRA

identified system dependencies and success criteria for the ECCS and other systems

used to mitigate a LOCA. Provide LOCA cutsets and risk achievement worths for those

basic events (assuming only a LOCA initiating event).

16. System health reports and/or other performance monitoring information for the ECCS

and other systems used to mitigate a LOCA event.

17. A list of condition reports and non-routine work requests initiated since 1999 affecting

the ECCS and other systems used to detect and mitigate a LOCA event.

18. Maintenance Rule performance criteria for systems used to detect and mitigate a LOCA

event. A list of maintenance rule failures of equipment used to detect or mitigate a

LOCA event.

19. Key one line diagrams for the alternating current and the 125-volt direct current systems

that provide power for the pumps, valves, and instrumentation and control circuits

associated with the ECCS and other systems used to mitigate the LOCA. Also, include

the one line diagrams for the Class 1E medium and low voltage switchgear and the 480

volt motor control centers. (Paper copies are preferred for these)

20. Provide a list of valves used to mitigate a LOCA that are required to change position or

are manually manipulated during implementation of the LOCA mitigation strategy.

Provide equipment failure rates over the past 10 years for these components.