MONTHYEARML24207A0862024-07-24024 July 2024 Relief Request Acceptance Review Results - McGuire Units 1 and 2 Alternatives Component Cooling Pumps, RHR Pumps ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds ML23230A0652023-08-31031 August 2023 William B. McGuire Nuclear Station, Units 1 and 2 - Relief Request Use of Later Edition of ASME Code ML23159A2712023-06-20020 June 2023 William B. McGuire Nuclear Station, Unit 1 - Relief Request Impractical Reactor System Welds ML23151A3482023-05-30030 May 2023 Duke Fleet - Request for Additional Information Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI RA-22-0257, Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1)2023-02-17017 February 2023 Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) ML22096A0032022-11-18018 November 2022 McGuire Nuclear Station and Shearon Harris Nuclear Power Plant Authorization of RA-19-0352 Regarding Use of Alternative for RPV Head Closure Stud Examinations ML22266A0782022-09-26026 September 2022 William B. Mcguire Nuclear Station, Unit 2 Pressurizer Power Operated Relief Valve Relief Request ML22242A1602022-08-30030 August 2022 Hardship Relief Request Pilot-Operated Relief Valve Acceptance Review Results ML21306A1592021-11-16016 November 2021 Request to Use Provisions of Later Edition and Addenda of the ASME Code, Section XI (EPID; L-2021-LLR-0048) ML21029A3352021-02-16016 February 2021 Request to Use a Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML20230A2052020-08-21021 August 2020 Relief Request RA-20-0031, Delay to Update the Code of Record for Inservice Inspection ML19217A3242019-08-14014 August 2019 Relief Request MC-SRV-NC-03, Alternate Testing for Pressurizer Power Operated Relief Valve Block Valve 2NC-35B RA-19-0026, Response to Request for Additional Information (RAI) Regarding Proposed Alternative to the Depth Sizing Qualification Requirement of Appendix Viii, Supplements 2 and 10 (18-GO-001)2019-02-11011 February 2019 Response to Request for Additional Information (RAI) Regarding Proposed Alternative to the Depth Sizing Qualification Requirement of Appendix Viii, Supplements 2 and 10 (18-GO-001) RA-18-0180, Supplement to Relief Request for an Alternative to the Depth Sizing Qualification Requirement of Appendix Viii, Supplements 22018-11-12012 November 2018 Supplement to Relief Request for an Alternative to the Depth Sizing Qualification Requirement of Appendix Viii, Supplements 2 ML17331A0862017-12-26026 December 2017 Alternative to Inservice Inspection Regarding Reactor Pressure Vessel Threads ML17034A3622017-02-22022 February 2017 Mcguire Nuclear Station, Unit 1 - Request 16-MN-002, Alternative to Defect Removal Prior to Performing Repair Activities on Nuclear Service Water System Piping Relief ML16358A6962017-01-17017 January 2017 Proposed Relief Request MC-SRV-NC-02, Alternate Testing for Pressurizer Power Operated Relief Valve (Porv) Block Valve 2NC-31B ML16266A0262016-10-18018 October 2016 Proposed Relief Request Serial No. 16-MN-003 for Alternate Repair of Nuclear Service Water Piping ML16294A2542016-10-13013 October 2016 Response to Request for Additional Information Regarding Relief Request 16-MN-002, Alternative to Defect Removal Prior to Performing Repair Activities on Nuclear Service Water System Piping ML16225A6542016-08-11011 August 2016 Email - McGuire Unit No. 1: Acceptance REVIEW- Relief Request 16-MN-003 Alternative to Defect Removal Prior to Performing Temporary Repair Activities on Three-Inch-Diameter Nuclear Service Water System Piping. MNS-16-062, Relief Request 16-MN-003 Alternative to Defect Removal Prior to Performing Temporary Repair Activities on Three-Inch-Diameter Nuclear Service Water System Piping2016-08-10010 August 2016 Relief Request 16-MN-003 Alternative to Defect Removal Prior to Performing Temporary Repair Activities on Three-Inch-Diameter Nuclear Service Water System Piping ML16210A0382016-07-28028 July 2016 Draft Relief Request Serial No. 16-MN-003 MNS-16-053, Relief Request 16-MN-002, Alternative to Defect Removal Prior to Performing Repair Activities on Nuclear Service Water System Piping2016-06-23023 June 2016 Relief Request 16-MN-002, Alternative to Defect Removal Prior to Performing Repair Activities on Nuclear Service Water System Piping ML16152A6012016-06-0808 June 2016 Withdrawal of Relief Request ML15232A5432015-08-27027 August 2015 Proposed Relief Request 15-MN-001 ML14188C3482014-07-14014 July 2014 Proposed Relief Request 13-MN-002 ML14013A2422014-01-17017 January 2014 Proposed Relief Request Nos. MC-SRP-KC-01 and MC-SRP-ND-01 (TAC Nos. MF1164, MF1165, MF1166 and MF1167 ML13294A6092013-11-0808 November 2013 Proposed Relief Request 12-MN-004 (TAC Nos. MF0508, MF0514, and MF0515) ML13010A5542013-01-14014 January 2013 Proposed Relief Request 12-MN-002 ML12355A1492012-11-29029 November 2012 Relief Request Serial # 12-MN-004 Limited Weld Examinations ML12264A3382012-09-24024 September 2012 Correction Letter for Approval Letter and Safety Evaluation for Relief Request 11-MN-002 Regarding the Extension of the Inservice Inspection Interval for Reactor Vessel Category B-A and B-D Welds ML12123A1122012-05-0909 May 2012 Request for Relief 12-MN-001, Relief Request for a Alternative Depth Sizing Criteria ML11160A1442011-06-23023 June 2011 Relief 10-MN-002, Extension of Volumetric Inspection of Steam Generator Primary Manway Studs for One Operating Cycle Beyond the Third 10-Year Inservice Inspection Interval End Date ML1015804222010-06-14014 June 2010 Relief 09-MN-005 for Alternative Leakage Testing for Various American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code (Code) Class 1 Piping and Components During the Third 10-Year Inservice ML1006200182010-03-0404 March 2010 Relief 09-MN-007 for Reactor Vessel Core Flood Nozzle Weld Examinations During the Third 10-Year Inservice Inspection ML0911400662009-05-13013 May 2009 Request for Relief 08-MN-003 for Reactor Vessel Hot Leg Nozzle to Safe End and Safe-End to Pipe Welds Examinations, TAC MD9614 ML0921706582009-05-0404 May 2009 Submittal of Relief Request Serial No. 09-MN-002 ML0814904712008-05-16016 May 2008 Relief Request 08-MN-001 ML0715604162007-06-0808 June 2007 Withdrawal of Relief Requests Associated with Pump Vibration (MD3253 Through MD3290) ML0712102492007-04-19019 April 2007 Relief Request 07-GO-0001. Proposed Alternative Approach Supports Application of Full Structural Weld Overlays on Various Pressurizer Nozzle-to-Safe End Welds ML0626202612006-09-11011 September 2006 Relief Request 06-GO-001 Request for Additional Information ML0615303872006-08-16016 August 2006 Request for Relief 05-MN-01, for Third 10-Year Interval Inservice Inspection Program Plan ML0634903992006-07-27027 July 2006 Relief Request 06-GO-001 ML0524502572005-09-0606 September 2005 Relief Requests for Third 10-Year Pump & Valve Inservice Testing Program ML0514601792005-05-23023 May 2005 Request for Relief, ISI Request for 04-MN-02, 04-MN-03 and 04-MN-04 ML0506105662005-03-18018 March 2005 Review of RR-03-05, Pressurizer Support Skirt Welds ML0506704672005-02-24024 February 2005 Inservice Testing Program Relief Request MC-SRP-NS-01, Request for Additional Information (RAI) ML0434400722004-12-0202 December 2004 Supplement to Relief Request No. 01-003 2024-07-24
[Table view] Category:Letter
MONTHYEARIR 05000369/20240032024-11-0404 November 2024 Integrated Inspection Report 05000369/2024003 and 05000370/2024003 ML24303A4212024-10-30030 October 2024 Mcguire Nuclear Station, Units 1 & 2, Notification of an NRC Fire Protection Team Inspection FPTI NRC 05000369/2025010, 05000370/2025010 and Request for Information RFI IR 05000369/20244022024-10-0808 October 2024 Security Baseline Inspection Report 05000369/2024402 05000370/2024402 IR 05000369/20240052024-08-26026 August 2024 Updated Inspection Plan for McGuire Nuclear Station, Units 1 and 2, (Report 05000369-2024005 and 05000370-2024005) IR 05000369/20244042024-08-0101 August 2024 Cover Letter Security Baseline Inspection Report 05000369/2024404 and 05000370/2024404 IR 05000369/20253012024-07-29029 July 2024 Notification of Licensed Operator Initial Examination 05000369/2025301 and 05000370/2025301 IR 05000369/20244032024-07-25025 July 2024 – Cyber Security Inspection Report 05000369/2024403 and 05000370/2024403 Rev IR 05000369/20240022024-07-24024 July 2024 Integrated Inspection Report 05000369/2024002 and 05000370/2024002 ML24183A0972024-07-12012 July 2024 ISFSI; Catawba 1, 2 & ISFSI; McGuire 1, 2 & ISFSI; Oconee 1, 2, 3 & ISFSI; Shearon Harris 1; H. B. Robinson 2 & ISFSI; and Radioactive Package Shipping Under 10 CFR 71 (71-266 & 71-345) – Review of QA Program Changes EPID L-2024-LLQ-0002 IR 05000369/20244012024-07-0303 July 2024 – Security Baseline Inspection Report 05000369/2024401 and 05000370/2024401 ML24176A2802024-06-26026 June 2024 Notification of Target Set Inspection and Request for Information (NRC Inspection Report 05000369-2024404 and 05000370-2024404) IR 05000369/20240112024-06-0404 June 2024 Biennial Problem Identification and Resolution Inspection Report 05000369/2024011 and 05000370/2024011 ML24149A1772024-05-28028 May 2024 NRC Response to Duke Energy 2025 FOF Schedule Change Request (Catawba and McGuire) IR 05000369/20240012024-05-0808 May 2024 Integrated Inspection Report 05000369-2024001 and 05000370-2024001 and 07200038-2024001 ML24110A0382024-04-30030 April 2024 – Correction to Issuance of Amendment Nos. 330 and 309, Regarding Implementation of Technical Specifications Task Force (TSTF) Traveler TSTF 505, Revision 2, Provide Risk-Informed Extended Completion Times - Ritstf ML24100A8742024-04-10010 April 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000369/2024403; and 05000370/2024403 ML24052A3062024-04-0808 April 2024 Issuance of Amendment Nos. 331 & 310, Regarding Adoption of Title 10 of Code of Federal Regulations Section 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Plants ML24031A5402024-03-26026 March 2024 Issuance of Amendment Nos. 330 and 309 Regarding Implementation of TSTF 505,Rev. 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4B ML24085A2402024-03-21021 March 2024 Requalification Program Inspection - McGuire Nuclear Station IR 05000369/20230062024-02-28028 February 2024 Annual Assessment Letter for McGuire Nuclear Station, Units 1 and 2 - NRC Inspection Report 05000369/2023006 and 05000370/2023006 ML24024A2182024-02-0505 February 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting) IR 05000369/20230042024-01-31031 January 2024 Integrated Inspection Report 05000369/2023004 and 05000370/2023004 ML24019A1392024-01-25025 January 2024 TSTF 505 and 50.69 Audit Summary ML24019A2002024-01-24024 January 2024 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000369/20234022023-12-14014 December 2023 – Material Control and Accounting Program Inspection Report 05000369/2023402 and 05000370/2023402 05000369/LER-1923-001, Automatic Actuation of the 1A Motor Driven Auxiliary Feedwater Pump Due to Human Error2023-12-13013 December 2023 Automatic Actuation of the 1A Motor Driven Auxiliary Feedwater Pump Due to Human Error ML23317A2272023-11-17017 November 2023 William B. McGuire Nuclear Station, Units 1 and 2 - Transmittal of Dam Inspection Report - Non-Proprietary ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000369/20230032023-10-24024 October 2023 Integrated Inspection Report 05000369/2023003 and 05000370/2023003; and Inspection Report 07200038/2023001 IR 05000369/20240102023-10-13013 October 2023 Notification of McGuire Nuclear Station Comprehensive Engineering Team Inspection – U.S. Nuclear Regulatory Commission Inspection Report 05000369, 370/2024010 IR 05000369/20230102023-10-13013 October 2023 Age Related Degradation Inspection Report 05000369/2023010 and 05000370/2023010 ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds IR 05000369/20233012023-09-20020 September 2023 William B. McGuire Nuclear Station - NRC Examination Report 05000369/2023301 and 05000370/2023301 ML23230A0652023-08-31031 August 2023 William B. McGuire Nuclear Station, Units 1 and 2 - Relief Request Use of Later Edition of ASME Code ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000369/20230052023-08-25025 August 2023 Updated Inspection Plan for McGuire Nuclear Station Units 1 and 2 (Report 05000369/2023005 and 05000370/2023005) IR 05000369/20234012023-08-0404 August 2023 – Security Baseline Inspection Report 05000369/2023401 and 05000370/2023401 (OUO-SRI) Cover IR 05000369/20230022023-07-28028 July 2023 Integrated Inspection Report 05000369/2023002 and 05000370/2023002 IR 05000369/20234202023-07-24024 July 2023 – Security Baseline Inspection Report 050003692023420 and 050003702023420 ML23206A0092023-07-24024 July 2023 William B. McGuire Nuclear Station – Operator Licensing Written Examination Approval 05000369/2023301 and 05000370/2023301 ML23207A0762023-07-14014 July 2023 EN 56557 - Update to Part 21 Report Re Potential Defect with Trane External Auto/Stop Emergency Stop Relay Card Pn: XI2650728-06 ML23159A2712023-06-20020 June 2023 William B. McGuire Nuclear Station, Unit 1 - Relief Request Impractical Reactor System Welds ML23237A2672023-06-13013 June 2023 June 13, 2002 - Meeting Announcement - McGuire and Catawba Nuclear Stations 50-369, 50-370 and 50-413, 50-414 ML23159A0052023-06-0505 June 2023 56557-EN 56557 - Paragon - Redlined ML23124A0862023-05-0303 May 2023 Cycle 29, Revision 1, Core Operating Limits Report (COLR) ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI IR 05000369/20230012023-05-0101 May 2023 Integrated Inspection Report 05000369/2023001 and 05000370/2023001 ML23115A2122023-05-0101 May 2023 Review of the Spring 2022 Steam Generator Tube Inspection Report ML23094A1832023-04-18018 April 2023 Audit Plan TSTF-505, Rev. 2, RITSTF Initiative 4B & 10 CFR 50.69, Risk-Informed Categorization & Treatment of Structures, Systems & Components for Nuclear Power Reactors (EPIDs L-2023-LLA-0021 & L-2023-LLA-0022) ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility 2024-08-26
[Table view] |
Text
Duke GARYR. PETERSON OPowere Vice President McGuire Nuclear Station A Duke Energy Company Duke Power MG01VP /12700 Hagers Ferry Road Huntersville, NC 28078-9340 704 875 5333 704 875 4809 fax grpeters @duke-energy. corn December 2, 2004 U. S. Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20555-0001
Subject:
Duke Energy Corporation (Duke)
McGuire Nuclear Station Units 1 and 2 Docket Nos. 50-369, 50-370 Supplement to Relief Request No.01-003
Reference:
(1) Letter addressed to NRC from Mr. H.B. Barron, dated June 4, 2002, (2) NRC Safety Evaluation Report from Mr. John Nakoski of the NRC, dated August 29, 2002(TAC Nos. MB5281 and MB5282)
In Reference 1, Duke requested relief for portions of ASME Code Class 1 piping and components connected to the Reactor Coolant System (RCS) that are isolated from direct RCS pressure (2235 psig) during normal operation. They are isolated from the reactor coolant loop by their location, either upstream of a check valve, between 2 check valves, or between 2 closed valves that must remain closed during the units startup and operation.
The purpose of this supplement to RFR 01-003 is to 1) amend the hold time pressure given for the Unit 1 alternate testing of "Portion 1" piping from 491 psig to a pressure range from >325 psig, ramping up to 491 psig; 2) amend the minimum pressure value for the actual hold times and test pressures achieved for the Unit 1 tests from 327 psig to 325 psig; and 3) confirm the corresponding Unit 2 portions of isolated class 1 piping were pressure tested (both during hold times and VT-2 examinations) to the acceptable range of >300 psig.
In Section V, "Alternate Testing" of the relief request, Duke proposed as an alternative, to test the various "Portions" of isolated piping to reduced pressure values that range from 300 psig to >800 psig (for both VT-2 examinations and hold times), which provides an acceptable level of assurance of the quality, safety and structural www.duke-energy.comr
U.S. Nuclear Regulatory Commission December 2, 2004 Page 2 integrity of the tested piping. The actual hold times and test pressures achieved for the Unit 1 tests were reported in the RR as >327 psig, and therefore met the alternate testing acceptance criteria. Duke supplied the actual test pressures and hold times attained in the Unit 1 tests for informational purposes only. The NRC approved the use of the lower pressures on the isolated portions of Class 1 piping in Reference 2.
However, it was later discovered (during planning and preparation for testing the "Portion 1" piping for Unit 2) that the actual alternate pressure maintained during the four hour hold time of the "Portion 1" piping for Unit 1 was ramping upward from a minimum of >325 psig at the start of the four hour hold time to 491 psig at the end of the hold time and beginning of VT-2 examination. The test data for the remaining "Portions 2 through 7" of RR 01-003 was examined and found to be consistent with the information provided in the relief request.
The ramping/changing conditions during the hold time and inspection of the "Portions 1 through 7" piping on Unit 2 were confirmed to remain above the 300 psig minimum pressure acceptance criteria throughout the four hour hold time and VT-2 examination during EOC15. Unit 2 pressure testing deviations from the information for Unit 1 testing provided in Reference 1 are as follows 1) "Portion 1" piping was ramped from 325 psig to 424 psig; 2) "Portion 3" piping was maintained at >307 psig; and
- 3) "Portion 5" piping was held at >307 psig.
Please direct questions regarding this matter to Norman T Simms of Regulatory Compliance at (704) 875-4685.
Sincerely, G. R. Peterson
I' U.S. Nuclear Regulatory Commission December 2, 2004 Page 3 cc: