Arizona Public Service Company August 30, 2004 Gregg R. Overbeck, Senior Vice President, Nuclear Arizona Public Service Company P.O. Box 52034 Phoenix, AZ 85072-2034
SUBJECT:
MIDCYCLE PERFORMANCE REVIEW AND INSPECTION PLAN - PALO VERDE NUCLEAR GENERATING STATION
Dear Mr. Overbeck:
On August 4, 2004, the NRC staff completed its midcycle plant performance assessment of Palo Verde Nuclear Generating Station. The midcycle review for Palo Verde Nuclear Generating Station involved the participation of all technical divisions in evaluating performance for the first half of the calendar year 2004 assessment cycle. The process included a review of performance indicators (PIs) for the most recent quarter and inspection results over the previous 12 months. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility so that you will have an opportunity to prepare for these inspections and to inform us of any planned inspections that may conflict with your plant activities.
This performance review and inspection plan does not include physical protection information.
A separate letter designated and marked as Exempt from Public Disclosure in Accordance with 10 CFR 2.390 will include the physical protection review and resultant inspection plan.
Plant performance for the most recent quarter was within the Licensee Response Column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). However, the significance of two findings is still under review as part of the Significance Determination Process. These findings are: the failure to promptly identify that retaining ring slots on the Unit 2 steam generator nozzle dams were not adequately sized to allow the use of the standard lock pins; and an incorrect design configuration, combined with high vibrations, that resulted in a reactor coolant system pressure boundary leak. Additionally, one finding involving the failure to notify the shift manager and department leader for fuel operations of the events associated with damage to a fuel assembly was the subject of a predecisional enforcement conference held on August 20, 2004. The final characterization of this issue is still under review.
In our annual assessment letter dated March 3, 2004, we discussed aspects of the safety conscious work environment at Palo Verde. Our subsequent reviews found that, in general,
Arizona Public Service Company employees are aware of, and are familiar with, your Employee Concerns Program, Differing Professional Opinions Process, and the Management Issues Tracking and Resolution program.
We understand that you are conducting training of all site employees in the Integrated Issue Resolution Process and that this training should be completed by the end of September 2004.
We will continue to focus our baseline inspection activities on your actions for addressing your assessments within these areas.
The enclosed inspection plan details the inspections, except those related to physical protection, scheduled through March 31, 2006. The inspection plan includes inspections for the followup to the NRC Augmented Inspection Team that was dispatched in response to the loss of offsite power event, which occurred on June 14, 2004. This followup inspection is scheduled to begin in September 2004. The plan also includes inspections associated with the replacement of the Unit 1 steam generators. In addition to the baseline inspections, NRC will also be conducting inspections related to Temporary Instructions (TI) 2515/150, Revision 1, "Reactor Pressure Vessel Head and Vessel Head Penetration Nozzles;" TI 2515/152, Reactor Pressure Vessel Lower Head Penetration Nozzles (NRC Bulletin 2003-02); and TI 2515/153, Reactor Containment Sump Blockage. Additionally, the plan contains an inspection using TI 2515/159, Review of Generic Letter 89-13, Service Water System Problems Affecting Safety-Related Equipment. This TI is in response to the Davis-Besse Reactor Vessel Head Degradation Lessons-Learned Task Force and is being performed at a sampling of nuclear power plants across the country. The inspection plan is provided to minimize the resource impact on your staff and to allow for scheduling conflicts and personnel availability to be resolved in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last 12 months of the inspection plan are tentative and may be revised at the end-of-cycle review meeting.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at 817/860-8173 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
Troy W. Pruett, Chief Project Branch D Division of Reactor Projects
Arizona Public Service Company Docket: 50-528 50-529 50-530 License: NPF-41 NPF-51 NPF-74
Enclosure:
Palo Verde Inspection/Activity Plan cc:
Steve Olea Arizona Corporation Commission 1200 W. Washington Street Phoenix, AZ 85007 Douglas K. Porter, Senior Counsel Southern California Edison Company Law Department, Generation Resources P.O. Box 800 Rosemead, CA 91770 Chairman Maricopa County Board of Supervisors 301 W. Jefferson, 10th Floor Phoenix, AZ 85003 Aubrey V. Godwin, Director Arizona Radiation Regulatory Agency 4814 South 40 Street Phoenix, AZ 85040 M. Dwayne Carnes, Director Regulatory Affairs/Nuclear Assurance Palo Verde Nuclear Generating Station Mail Station 7636 P.O. Box 52034 Phoenix, AZ 85072-2034 Hector R. Puente Vice President, Power Generation El Paso Electric Company 310 E. Palm Lane, Suite 310 Phoenix, AZ 85004
Arizona Public Service Company Jeffrey T. Weikert Assistant General Counsel El Paso Electric Company Mail Location 167 123 W. Mills El Paso, TX 79901 John W. Schumann Los Angeles Department of Water & Power Southern California Public Power Authority P.O. Box 51111, Room 1255-C Los Angeles, CA 90051-0100 John Taylor Public Service Company of New Mexico 2401 Aztec NE, MS Z110 Albuquerque, NM 87107-4224 Cheryl Adams Southern California Edison Company 5000 Pacific Coast Hwy. Bldg. DIN San Clemente, CA 92672 Robert Henry Salt River Project 6504 East Thomas Road Scottsdale, AZ 85251 Brian Almon Public Utility Commission William B. Travis Building P.O. Box 13326 1701 North Congress Avenue Austin, TX 78701-3326 Institute of Nuclear Power Operations (INPO)
Records Center 700 Galleria Parkway SE, Suite 100 Atlanta, GA 30339
Arizona Public Service Company Electronic distribution by RIV:
Regional Administrator (BSM1)
DRP Director (ATH)
DRS Director (DDC)
Senior Resident Inspector (GXW2)
Branch Chief, DRP/D (TWP)
Senior Project Engineer, DRP/D (CJP)
Staff Chief, DRP/TSS (PHH)
RITS Coordinator (KEG)
RidsNrrDipmLipb V. Dricks, PAO (VLD)
W. Maier, RSLO (WAM)
C. Gordon (CJG)
DRS Branch Chiefs (LJS, MPS1, ATG, JAC)
L. Reyes, EDO (LAR1)
S. Richards, Chief, NRR/DIPM/IIPB (SAR)
R. Frahm, PPR Program Manager, NRR/DIPM/IIPB (RKF)
C. Carpenter, Deputy Dir. for Inspection and Programs (CAC)
B. Sheron, Associate Dir. for Project Licensing and Technical Analysis (BWS)
T. Bergman, Chief, ROPMS, OEDO (TAB)
H. Berkow, Director, LPD4, NRR/DLPM (HNB)
R. Gramm, Chief, PDIV-1A, NRR/DLPM (RAG)
T. Alexion, NRR Project Manager (TWA)
ADAMS: Yes G No Initials: _TWP_____
Publicly Available G Non-Publicly Available G Sensitive
Non-Sensitive S:\\DRP\\DRPDIR\\Midcycle2004\\PV.wpd RIV:SPE:DRP/D C:DRP/D concur D:DRS D:DRP C:DRP/D Sign CJPaulk TWPruett DDChamberlain ATHowell TWPruett
/RA/
/RA/
VLOrdaz
/RA/
/RA/
8/12/04 8/12/04 8/25/04 8/28/04 8/30/04 OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax
Palo Verde Inspection / Activity Plan 08/01/2004 - 03/31/2006 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 08/27/2004 07:51:30 Report 22 3
PEB-07B
- HX & HEAT SINK PERFORMANCE TESTING Baseline Inspections 08/16/2004 08/20/2004 Heat Sink Performance IP 7111107B 1, 2, 3 3
TI-SW
- TI-2515/159 - REVIEW OF GL 89-13 Safety Issues 08/16/2004 08/20/2004 Review of Generic Letter 89-13: Service Water System Problems Affecting Safety-Related Eq IP 2515/159 1, 2, 3 2
SPECIAL
- ECCS VOINDING SPECIAL INSPECTION Event Response Insp 08/23/2004 08/27/2004 Special Inspection IP 93812 1, 2, 3 3
OB-RQ
- OB-REQUALIFICATION Baseline Inspections 08/30/2004 09/03/2004 Licensed Operator Requalification Program IP 7111111B 1, 2, 3 5
AIT-FOL
- AIT (LOOP) FOLLOWUP INSP Event Response Insp 09/07/2004 09/24/2004 Augmented Inspection Team IP 93800 1, 2, 3 2
EB-08P
- ISI U3 - VESS VOL (TI 150/152) AS REQ Baseline Inspections 10/04/2004 10/08/2004 Inservice Inspection Activities - PWR IP 7111108P 3
Baseline Inspections 10/18/2004 10/22/2004 Inservice Inspection Activities - PWR IP 7111108P 3
1 TI 152
- TI 152 RPV LOWER HEAD PENETRATION NOZZLE Safety Issues 10/01/2004 12/31/2004 Reactor Pressure Vessel Lower Head Penetration Nozzles (NRC Bulletin 2003-02)
1 TI 153
- TI 153 REACTOR CONTAINMENT SUMP BLOCKAGE Safety Issues 10/01/2004 12/31/2004 Reactor Containment Sump Blockage (NRC Bulletin 2003-01)
1 ALARA1
- ALARA PLANNING AND CONTROLS Baseline Inspections 11/01/2004 11/05/2004 ALARA Planning and Controls IP 7112102 1, 2, 3 3
OB-INIT
- OB - INITIAL EXAMINATION Not Applicable 11/29/2004 12/03/2004 PALO VERDE UNIT 1 (12/04) INITIAL X02273 1
Not Applicable 11/29/2004 12/03/2004 PALO VERDE UNIT 2 (12/04) - INITIAL X02275 2
Not Applicable 11/29/2004 12/03/2004 PALO VERDE UNIT 3 (12/04) - INITIAL X02276 3
Not Applicable 12/13/2004 12/17/2004 PALO VERDE UNIT 1 (12/04) INITIAL X02273 1
Not Applicable 12/13/2004 12/17/2004 PALO VERDE UNIT 2 (12/04) - INITIAL X02275 2
Not Applicable 12/13/2004 12/17/2004 PALO VERDE UNIT 3 (12/04) - INITIAL X02276 3
1 ALARA2
- ALARA PLANNING AND CONTROLS Baseline Inspections 01/10/2005 01/14/2005 ALARA Planning and Controls IP 7112102 1, 2, 3 4
RP TEAM
- RP PUBLIC DOSE TEAM INSPECTION Baseline Inspections 01/31/2005 02/04/2005 Radiation Monitoring Instrumentation and Protective Equipment IP 7112103 1, 2, 3 Baseline Inspections 01/31/2005 02/04/2005 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems IP 7112201 1, 2, 3 Baseline Inspections 01/31/2005 02/04/2005 Radioactive Material Processing and Transportation IP 7112202 1, 2, 3 Baseline Inspections 01/31/2005 02/04/2005 Radiological Environmental Monitoring Program IP 7112203 1, 2, 3 3
OB-EP EX
- EMERGENCY PREPAREDNESS EXERCISE Baseline Inspections 02/28/2005 03/04/2005 Exercise Evaluation IP 7111401 1, 2, 3 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Palo Verde Inspection / Activity Plan 08/01/2004 - 03/31/2006 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 08/27/2004 07:51:30 Report 22 3
OB-EP EX
- EMERGENCY PREPAREDNESS EXERCISE Baseline Inspections 02/28/2005 03/04/2005 Emergency Action Level and Emergency Plan Changes IP 7111404 1, 2, 3 Baseline Inspections 02/28/2005 03/04/2005 Performance Indicator Verification IP 71151 1, 2, 3 1
EB02/17B
- PERMANENT PLANT MODS Baseline Inspections 03/07/2005 03/11/2005 Permanent Plant Modifications IP 7111117B 1, 2, 3 1
PEB-12B
- MAINTENANCE EFFECTIVENESS Baseline Inspections 03/07/2005 03/11/2005 Maintenance Effectiveness IP 7111112B 1, 2, 3 1
EB08P
- ISI U2 - VESSEL VOL (TI 150/152) AS REQ Baseline Inspections 03/28/2005 04/01/2005 Inservice Inspection Activities - PWR IP 7111108P 2
Baseline Inspections 04/11/2005 04/15/2005 Inservice Inspection Activities - PWR IP 7111108P 2
3 OB-INIT
- INITIAL EXAM Not Applicable 07/11/2005 07/15/2005 PALO VERDE UNIT1 (05/05) INITIAL EXAM X02282 1
Not Applicable 07/11/2005 07/15/2005 PALO VERDE UNIT 2 (11/05) - INITIAL EXAM X02283 2
Not Applicable 07/11/2005 07/15/2005 PALO VERDE UNIT 3 (11/05) - INITIAL EXAM X02284 3
Not Applicable 08/01/2005 08/05/2005 PALO VERDE UNIT1 (05/05) INITIAL EXAM X02282 1
Not Applicable 08/01/2005 08/05/2005 PALO VERDE UNIT 2 (11/05) - INITIAL EXAM X02283 2
Not Applicable 08/01/2005 08/05/2005 PALO VERDE UNIT 3 (11/05) - INITIAL EXAM X02284 3
1 ACRSA
- ACCESS CONTROL TO RAD SIGNIFICANT AREAS Baseline Inspections 10/03/2005 10/07/2005 Access Control to Radiologically Significant Areas IP 7112101 1, 2, 3 1
EB08P
- ISI U1 - VESS VOL (TI 150/152) AS REQ Baseline Inspections 10/10/2005 10/14/2005 Inservice Inspection Activities - PWR IP 7111108P 1
Baseline Inspections 10/24/2005 10/28/2005 Inservice Inspection Activities - PWR IP 7111108P 1
1 EP2
- EMERG PREPAREDNESS PROGRAM INSPECTION Baseline Inspections 01/23/2006 01/27/2006 Alert and Notification System Testing IP 7111402 1, 2, 3 Baseline Inspections 01/23/2006 01/27/2006 Emergency Response Organization Augmentation Testing IP 7111403 1, 2, 3 Baseline Inspections 01/23/2006 01/27/2006 Emergency Action Level and Emergency Plan Changes IP 7111404 1, 2, 3 Baseline Inspections 01/23/2006 01/27/2006 Correction of Emergency Preparedness Weaknesses and Deficiencies IP 7111405 1, 2, 3 Baseline Inspections 01/23/2006 01/27/2006 Performance Indicator Verification IP 71151 1, 2, 3 5
EB
- SSD&PCI/50.59 Baseline Inspections 03/06/2006 03/10/2006 Safety System Design and Performance Capability IP 7111121 1, 2, 3 Baseline Inspections 03/20/2006 03/24/2006 Evaluation of Changes, Tests, or Experiments IP 7111102 1, 2, 3 Baseline Inspections 03/20/2006 03/24/2006 Safety System Design and Performance Capability IP 7111121 1, 2, 3 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.