Letter Sequence Draft RAI |
---|
|
|
MONTHYEARML0415604642004-05-27027 May 2004 Proposed Technical Specification Changes Implementation of Alternate Source Term Project stage: Other ML0423304632004-08-20020 August 2004 Facsimile Transmission, Draft RAI to Be Discussed in an Upcoming Conference Call Project stage: Draft RAI ML0426602502004-09-22022 September 2004 Facsimile Transmission, Draft Request for Additional Information (RAI) to Be Discussed in an Upcoming Conference Call Project stage: Draft RAI ML0435100392004-12-29029 December 2004 Request for Additional Information Regarding Use of Alternate Source Term Project stage: RAI ML0500402642005-02-0909 February 2005 RAI, Use of Alternate Source Term Project stage: RAI ML0515400932005-04-25025 April 2005 Summary of Meeting with Dominion Nuclear Connecticut, Inc.,Surry & North Anna, Units 1 & 2, & Millstone, Units 2 & 3, Discuss Current Licensing Issues with Dominion. Enclosure 3 - Top Ten Millstone Licensing Tasks Project stage: Meeting ML0530704822005-11-18018 November 2005 RAI Regarding Use of Alternate Source Term Project stage: RAI ML0619901352006-09-15015 September 2006 Issuance of Amendment Alternate Source Term Project stage: Approval 2004-09-22
[Table View] |
|
---|
Category:Memoranda
MONTHYEARML24222A6992024-08-16016 August 2024 August 6, 2024, Summary of Regarding Potential License Amendment Request Change to Surveillance Requirements for Moderator Temperature Coefficient for Millstone, Unit No. 3, North Anna, Unit Nos. 1 and 2, and Summer, Unit No. 1 - ML22130A1702022-05-20020 May 2022 Summary of April 21, 2022, Public Meeting to Discuss Potential Emergency Preparedness License Amendment Request ML22028A3502022-01-21021 January 2022 Green Mountain Power, 2021 Annual Summary of Special Nuclear Committee ML21027A0232021-01-28028 January 2021 Summary of January 26, 2021 Closed Meeting with Dominion Energy Regarding Performance of Force on Force Exercises in a Pandemic Environment ML19165A1192019-06-14014 June 2019 Memoranda to File Environmental Assessment and Finding of No Significant Impact for the Virginia Electric and Power Company, Dominion Energy Kewaunee, Inc., and Dominion Nuclear Connecticut, Inc.'S Decommissioning Funding Plans Submitted ML17271A0532017-09-29029 September 2017 2017 Summary of Annual Decommissioning Funding Status Reports for Reactors in Decommissioning ML16088A2042016-03-28028 March 2016 Memo T Bowers from s Ruffin, Technical Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations W/ Encl 2 (Template) ML16088A2052016-03-28028 March 2016 Enclosure 1 - (72.30 DFP Reviews to Be Completed 2015) - Memo T Bowers from s Ruffin, Technial Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations ML15075A1922015-03-26026 March 2015 Reactor Coolant System Alloy 600 Inspection Program for License Renewal Commitment No. 14. (Tac No. MF3433) ML13031A1832013-02-0505 February 2013 Closed Meeting Announcement Millstone Drop-In ML13032A0572013-01-30030 January 2013 2012 Annual Summary of the Green Mountain Power Special Nuclear Committee ML12178A6132012-06-27027 June 2012 Notice of Forthcoming Pre-Application Meeting with Dominion Nuclear Connecticut, Inc. to Discuss a Proposed Millstone Power Station, Unit 2, License Amendment Request Concerning Spent Fuel Pool Criticality Re-Analysis ML13196A2202012-06-0606 June 2012 Memo from B. Balsam, NRR and D. Logan, NRR to J. Susco, NRR on Summary of Section 7 Consultation Activities Related to the National Marine Fisheries Service'S Final Rule to List the Atlantic Sturgeon ML11271A1782011-10-0303 October 2011 Review of Topical Report, Revision 11 for Kewaunee Power Station and ISFSI, Millstone Power Station, Units 1, 2, & 3 and ISFSI, North Anna Power Station, Units 1 & 2 and ISFSI, Surry Power Station, Units 1 & 2 and ISFSI (Tac ME6649, ME6650, ML11250A1712011-09-14014 September 2011 Notice of Forthcoming Meeting with Petitioner Requesting Action Under 10 CFR 2.206 Regarding Immediate Suspension of the Operating Licenses of General Electric (GE) Mark 1 Boiling Water Reactors (Bwrs) ML1116804602011-06-30030 June 2011 Review of Commitment Change Report for 2009 ML1103106822011-02-0101 February 2011 Revised Notice of Forthcoming Public Meeting with Dominion Nuclear Connecticut, Inc., to Discuss Millstone Power Station Licensing Activities ML1100701752011-01-11011 January 2011 Request for Technical Assistance on Request for Exemption Form Certain Requirements of 10 CFR 73.55 for Millstone Power Station, Unit 1 ML1035103202010-12-20020 December 2010 30-Day Report of Emergency Core Cooling System Model Change ML1033305502010-12-15015 December 2010 Potential Notice of Enforcement Discretion for the Turbine Driven Auxiliary Feedwater Pump ML1031202422010-11-0808 November 2010 Notice of Teleconference with Dominion Nuclear Connecticut, Inc. to Discuss Millstone Power Station, Unit No. 3 Generic Letter 2004-02 Supplemental Response ML1030100732010-10-28028 October 2010 Meeting Notice Milestone Power Station Revised 10 CFR 73.55 ML1019502842010-07-14014 July 2010 Notice of Forthcoming Public Teleconference with Dominion Nuclear Connecticut, Inc. to Discuss Millstone Power Station, Unit No. 3 Generic Letter 2004-02 Supplemental Response ML1008204222010-03-26026 March 2010 Notice of Conference Call with Dominion Nuclear Connecticut, Inc. to Discuss Millstone Power Station, Unit Nos 2 and 3 Generic Letter 2004-02 Supplemental Responses ML1003314992010-03-0101 March 2010 Notice of Conference Call with Dominion Nuclear Connecticut, Inc., to Discuss Millstone Power Station, Unit Nos. 2 and 3 Generic Letter 2004-02 Supplemental Responses ML0931406252009-11-17017 November 2009 Summary of Teleconference Verbal Authorization for Relief Request RR-89-67 ML0913401332009-05-15015 May 2009 Notice of Forthcoming Meeting with Dominion Nuclear Connecticut, Inc. to Discuss the Submittal of a License Amendment Request Regarding the Removal of Charging Pumps from the Technical Specifications for Millstone Power Station, Unit No. 2 ML0906205722009-03-0303 March 2009 Meeting Minutes of the Power Uprates Subcommittee, July 8, 2008 ML0811500912008-04-23023 April 2008 Proposed Stretch Power Uprate to Millstone Power Station, Unit 3 ML0807400842008-03-14014 March 2008 Draft Regulatory Guide for Comment ML0734708412007-12-11011 December 2007 Drop-In Visit from Dominion (Millstone) ML0730304052007-10-31031 October 2007 E. Marinos Memo Technical Assistance Request-Dominion Resources, Inc.'S December 6, 2006, Request for Exemption from 10 CFR 74.13(a) Requirements Regarding Material Status Report Submittal Time Frame ML0715100542007-05-31031 May 2007 Closeout of TAC Numbers for Licensing Activities That Do Not Require Staff Review ML0710201942007-04-24024 April 2007 Draft Open Items from Staff Audit of Corrective Actions to Address Generic Letter 2004-02 ML0707902492007-03-20020 March 2007 Facsimile Transmission, Draft Request for Additional Information Regarding Steam Generator Tube Integrity ML0634902692007-01-11011 January 2007 Memo: K. Mcconnell to M. Lesar - Notice of Environmental Assessment and Finding of No Significant Impact Related to Partial Exemption from 10 CFR Part 50, Recordkeeping Requirements - Millstone Power Station, Unit 1 ML0633901162006-12-19019 December 2006 Fax - Draft Request for Additional Information Regarding Post-Maintenance/Modification Surveillance Requirements ML0630701472006-12-12012 December 2006 Facsimile Transmission, Draft Request for Additional Information ML0631101502006-11-13013 November 2006 Request for Additional Information Regarding Human Factors - Millstone, Unit 2, Alternate Source Term License Amendment Request ML0626800242006-10-0202 October 2006 Transfer of Project Management Responsibilities ML0625100662006-09-29029 September 2006 Facsimile Transmission, Draft Request for Additional Information Regarding Extension of Integrated Leakage Rate Test Interval ML0619500042006-07-14014 July 2006 Facsimile Transmission, Draft Request for Additional Information Regarding Post Maintenance/Modification Surveillance Requirements ML0619500092006-07-14014 July 2006 Facsimile Transmission, Draft Request for Additional Information Regarding Relaxation Request IR-2-46, Reactor Pressure Vessel Head Inspections ML0617805592006-07-10010 July 2006 Revised Closeout Letter for Bulletin 2003-01, Potential Impact of Debris Blockage on Emergency Sump Recirculation at Pressurized-Water Reactors. ML0617701952006-06-26026 June 2006 Closeout of Tac Number for Licensing Activities Incorrectly Identified for Staff Review ML0606702532006-03-24024 March 2006 Facsimile Transmission, Draft Request for Additional Information to Be Discussed in an Upcoming Conference Call ML0608601632006-03-21021 March 2006 Handouts to Applicants (Folder 3) ML0604005082006-03-0202 March 2006 Facsimile Transmission, Draft Request for Additional Information to Be Discussed in an Upcoming Conference Call ML0602700882006-01-31031 January 2006 Facsimile Transmission Draft Request for Additional Information to Be Discussed in an Upcoming Conference Call (Tac No. MC8327) ML0602502612006-01-26026 January 2006 Facsimile Transmission, Draft Request for Additional Information to Be Discussed in an Upcoming Conference Call 2024-08-16
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24213A2602024-07-31031 July 2024 Request for Additional Information LAR to Support Implementation of Framatome Gaia Fuel IR 05000336/20244032024-07-22022 July 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000336/2024403 and 05000423/2024403 ML24113A2502024-04-22022 April 2024 Request for Additional Information (e-mail 4/22/2024) License Renewal Commitment for Aging Management Program of Alloy 600 Components ML24065A3112024-03-0505 March 2024 Request for Additional Information (Redacted) (03/05/2025 E-mail from R. Guzman to S. Sinha) Framatome Gaia Fuel LOCA LAR ML23318A0952023-11-14014 November 2023 Request for Additional Information (E-mail Dated 11/14/2023) LAR to Revise TSs Related to Framatome Gaia Fuel ML23199A2832023-07-18018 July 2023 Request for Additional Information (E-mail Dated 7/18/2023) LAR to Revise the Pressure-Temperature Limits ML23171B0522023-06-20020 June 2023 NRR E-mail Capture - RAI for Review of Appendix F to DOM-NAF-2-P (Redacted) ML23089A1882023-03-29029 March 2023 Request for Additional Information (E-mail Dated 3/29/2023) Spring 2022 Steam Generator Tube Inspection Report ML23073A1802023-03-14014 March 2023 Notification of Commercial Grade Dedication Inspection (05000336/2023010 and 05000423/2023010) and Request for Information ML22251A1292022-09-0909 September 2022 Request for Additional Information Related to Response to Generic Letter 2004-04 ML22242A0452022-08-23023 August 2022 NRR E-mail Capture - Dominion GL 04-02 Response Draft RAIs (L-2017-LRC-0000) ML21225A5022021-08-13013 August 2021 Request for Additional Information for North Anna Power Station, Units 1 and 2, Surry Power Station, Units 1 and 2, and Millstone Power Station, Units 2 and 3, Appendix E of Fleet Report Com-Naf-2 (EPID:L02021-LLT-0000) Public Version ML21195A2442021-07-13013 July 2021 NRR E-mail Capture - Draft RAI Appendix E to Topical Report DOM-NAF-2 Qualification of the Framatome BWU-I CHF Correlation in the Dominion Energy VIPRE-D Computer Code ML21182A2902021-07-0101 July 2021 7/1/2021 E-mail - Request for Additional Information Alternative Frequency to Supplemental Valve Position Verification Testing Requirements ML21112A3082021-04-22022 April 2021 Request for Additional Information (E-mail Dated 4/22/2021) License Amendment Request for Measurement Uncertainty Recapture Power Uprate ML21105A1152021-04-15015 April 2021 Request for Additional Information (e-mail Dated 4/15/2021) Proposed LAR for Addition of Analytical Methodology to the Core Operating Limits Report for a LBLOCA ML21078A0332021-03-18018 March 2021 NRR E-mail Capture - Millstone Power Station, Unit 2 - Request for Additional Information - Proposed LAR to Revise TSs for Steam Generator Inspection Frequency ML21076A4622021-03-17017 March 2021 NRR E-mail Capture - Draft RAI for Versatile Internals and Component Program for Reactors Vipre Code Review (L-2021-LLT-0000) ML21077A1652021-02-26026 February 2021 (02/26/2021 E-mail) Draft Request for Additional Information LAR to Revise Technical Specifications for Steam Generator Inspection Frequency ML21034A5762021-02-0303 February 2021 Request for Additional Information (e-mail Dated 1/3/2021) Alternative Request RR-05-06 Inservice Inspection Interval Extension for Steam Generator Weld Inspections ML20246G5612020-09-0202 September 2020 Request for Additional Information (E-mail Dated 9/2/2020) License Amendment Request for a One-Time Deferral of the Steam Generator Inspections ML20244A2902020-08-31031 August 2020 Request for Additional Information (E-mail Dated 8/31/2020) License Amendment Request to Revise Battery Surveillance Requirements ML20231A7172020-08-18018 August 2020 Request for Additional Information (e-mail Dated 8/18/2020) License Amendment Request to Revise TS Table 3.3-11 Accident Monitoring Instrumentation ML20184A0052020-07-0202 July 2020 Request for Additional Information (E-mail Dated 7/2/2020) Relief Request IR-3-33 for Limited Coverage Examiniations ML20075A0322020-03-15015 March 2020 Request for Additional Information (E-mail Dated 3/15/2020) Alternative Request IR-4-03 for Use of an Alternative Non-Code Methodology to Demonstrate Structural Integrity ML20050F9212020-02-19019 February 2020 Request for Additional Information (E-mail Dated 2/19/2020) Proposed LAR to Revise TS 3.8.1.1, AC Sources Operating ML20023D0372020-01-23023 January 2020 Request for Additional Information (E-mail Dated 1/23/2020) Proposed LAR to Revise TS 3.8.1.1, AC Sources Operating ML19361A0382019-12-23023 December 2019 12/23/19 E-mail from R.Guzman to S. Sinha - Draft Request for Additional Information Planned Audit of LAR to Revise TS 3.8.1.1 ML19277B9082019-10-0707 October 2019 Supplemental Information Needed for Acceptance of Requested Licensing Action Extension of Technical Specification 3.8.1.1, A.C. Sources - Operating, Allowed Outage Time ML19248D7552019-09-0505 September 2019 Request for Additional Information Via E-mail from R.Guzman to S. Sinha Proposed License Amendment Request to Adopt 10 CFR 50.69 ML19169A0962019-06-17017 June 2019 NRR E-mail Capture - Request for Additional Information Emergency Action Level Scheme Change for Millstone Power Station - Units 1, 2, and 3, North Anna Power Station - Units 1 and 2, and Surry Power Station - Units 1 and 2 ML19162A0052019-06-10010 June 2019 NRR E-mail Capture - Draft RAIs for Dominion EAL Scheme Change ML19042A1822019-02-11011 February 2019 Request for Additional Information LAR for TS Changes to Spent Fuel Storage and New Fuel Storage, 02/11/2019 E-mail from R. Guzman to S. Sinha ML18291B3262018-10-18018 October 2018 Request for Additional Information LAR Regarding Proposed Technical Specification Changes for Spent Fuel Pool Storage and New Fuel Storage, E-mail from R.Guzman to S.Sinha ML18277A1762018-10-0404 October 2018 Request for Additional Information LAR to Revise TS Action Statement for Loss of Control Building Inlet Ventilation Rad Monitor Instrumentation Channels (e-mail from R.Guzman to M.Whitlock, EPID: L-2018-LLA-0099) ML18213A1152018-08-0101 August 2018 Request for Additional Information Alternative Request P-06 'C' Charging Pump (08/01/2018 E-mail from R. Guzman to M. Whitlock) ML18171A1532018-06-20020 June 2018 Request for Additional Information Via E-mail from R.Guzman to W.Craft Alternative Requests for Inservice Testing Program (E-mail from R.Guzman to W.Craft) (EPID: L-2018-LLR-0012-LLR-0022) ML18137A3132018-05-17017 May 2018 Request for Additional Information Via E-mail from R.Guzman to W.Craft Proposed License Amendment Request to Revise ILRT Type a and Type C Test Intervals ML17297A8472017-10-27027 October 2017 Request for Supplemental Information Regarding Generic Letter 2016-01, Monitoring of Neutron Absorbing Materials in Spent Fuel Pools (CAC No. MF9430; EPID L-2016-LRC-0001) ML17033B6142017-02-0202 February 2017 Request for Additional Information, 2017/02/02 E-mail from R.Guzman to W.Craft Proposed Alternative RR-04-24 and IR-3-30 for the Elimination of Reactor Pressure Vessel Threads in Flange Examination (CAC Nos. MF8468/MF8469) ML17005A3282017-01-0505 January 2017 MPS2 EOC-23 and MPS3 EOC-17 Steam Generator Tube Inspection Reports - Requests for Additional Information ML16260A0062016-09-16016 September 2016 2016/09/16 E-mail from R. Guzman to W. Craft Request for Additional Information - License Amendment Request Realistic Large Break Loss of Coolant Accident Analysis (MF7761) ML16267A0022016-09-12012 September 2016 2016/09/12 E-mail from R.Guzman to W.Craft Request for Additional Information - LAR to Revise ECCS TS and FSAR Ch. 14 to Remove Charging (MF7297) ML16133A3562016-05-12012 May 2016 E-mail from R. Guzman to C. Sly Request for Additional Information Supporting License Amendment Request to Remove Charging Credit ML16068A4142016-03-0808 March 2016 Request for Additional Information - Relief Request RR-04-19 Examination Cat R-A, Risk-Informed Piping Examinations (MF6569) ML16055A5302016-02-24024 February 2016 2016/02/24 E-mail from R.Guzman to W.Craft Request for Additional Information - LAR to Adopt Dominion Core Design and Safety Analysis Methods (MF6251) ML16047A1712016-02-16016 February 2016 2016/02/16 E-mail from R.Guzman to M. Whitlock Request for Additional Information - Small Break Loss of Coolant Accident Re-Analysis (MF6700) ML16043A5232016-02-12012 February 2016 Request for Additional Information 2016/02/12 E-mail from R. Guzman to M.Whitlock Relief Requests IR-3-22 and IR-3-23 (CAC Nos. MF6573 and MF6574) ML16013A4772016-01-13013 January 2016 NRR E-mail Capture - Millstone Power Station, Units 2 and 3 - Request for Additional Information License Amendment Request for Removal of Severe Line Outage Detection (Slod) from the Offsite Power System - (MF6430, MF6431) ML16011A5172016-01-11011 January 2016 NRR E-mail Capture - Millstone Power Station, Unit 3, Reactor Vessel Surveillance Capsule Withdrawal Schedule - Request for Additional Information 2024-07-31
[Table view] |
Text
August 20, 2004 MEMORANDUM TO: James W. Clifford, Chief, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation FROM: Victor Nerses, Sr. Project Manager /RA/
Project Directorate I, Section 2 Division of Licensing Project Management Office of Nuclear Reactor Regulation
SUBJECT:
MILLSTONE POWER STATION, UNIT NO. 3 FACSIMILE TRANSMISSION, DRAFT REQUEST FOR ADDITIONAL INFORMATION (RAI) TO BE DISCUSSED IN AN UPCOMING CONFERENCE CALL (TAC NO. MC3333)
The attached draft RAI was transmitted by facsimile on August 20, 2004, to Mr. Paul Willoughby, Dominion Nuclear Connecticut, Inc. (DNC). This draft RAI was transmitted to facilitate the technical review being conducted by the staff and to support a conference call with DNC in order to clarify certain items in the licensees submittal. The draft RAI is related to DNCs submittal dated May 27, 2004, regarding the implementation of a alternate source term methodology. Review of the RAI would allow DNC to determine and agree upon a schedule to respond to the RAI. This memorandum and the attachment do not convey a formal request for information or represent an NRC staff position.
Docket No. 50-423
Enclosure:
Draft Request for Additional Information
August 20, 2004 MEMORANDUM TO: James W. Clifford, Chief, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation FROM: Victor Nerses, Sr. Project Manager /RA/
Project Directorate I, Section 2 Division of Licensing Project Management Office of Nuclear Reactor Regulation
SUBJECT:
MILLSTONE POWER STATION, UNIT NO. 3 FACSIMILE TRANSMISSION, DRAFT REQUEST FOR ADDITIONAL INFORMATION (RAI) TO BE DISCUSSED IN AN UPCOMING CONFERENCE CALL (TAC NO. MC3333)
The attached draft RAI was transmitted by facsimile on August 20, 2004, to Mr. Paul Willoughby, Dominion Nuclear Connecticut, Inc. (DNC). This draft RAI was transmitted to facilitate the technical review being conducted by the staff and to support a conference call with DNC in order to clarify certain items in the licensees submittal. The draft RAI is related to DNCs submittal dated May 27, 2004, regarding the implementation of a alternate source term methodology. Review of the RAI would allow DNC to determine and agree upon a schedule to respond to the RAI. This memorandum and the attachment do not convey a formal request for information or represent an NRC staff position.
Docket No. 50-423
Enclosure:
Draft Request for Additional Information DISTRIBUTION:
PDI-2 Rdg PUBLIC LBrown GMakar VNerses Accession No.: ML042330463 *RAI request OFFICE PDI-2/PM EMCB/SC* SPSB/SC NAME VNerses LLund RDennig DATE 8/20/04 8/19/04 8/20/04 OFFICIAL RECORD COPY
DRAFT REQUEST FOR ADDITIONAL INFORMATION MILLSTONE POWER STATION, UNIT NO. 3 (TAC NO. MC3333)
In a letter dated May 27, 2004 (ML041560464), Dominion Nuclear Connecticut, Inc. (the licensee) submitted a proposed license amendment based on application of an Alternative Radiological Source Term (AST) methodology for Millstone Power Station Unit 3. The staff isreviewing the submittal and has determined that the following additional information to complete the review
- 1. In the license amendment proposal, the licensee states that the containment sump pH will be at least 7 (Table 3.1-4). Please discuss the assumptions and calculations used to determine that the sump pH will remain above 7 for 30 days following the LOCA. Please provide this information in sufficient detail for the staff to perform independent calculations to evaluate the licensees conclusion. If the calculations were performed manually, describe the methodology and provide sample calculations. If a computer code was used, describe the code and provide the input values and how they were determined. Provide the results of the pH calculations at different time intervals and explain how the time intervals were selected.
- 2. Did the meteorological measurement program meet the recommendations of Regulatory Guide (RG) 1.23, Onsite Meteorological Programs, during the period from 1997 through 2001?
- 3. With regard to guidance in RG 1.194, Atmospheric Relative Concentrations for Control Room Radiological Habitability Assessments at Nuclear Power Plants, and use of the ARCON96 computer code, the source-to-receptor distance is the shortest horizontal distance between the release point and intake. ARCON96 uses this distance and the elevations of the source and receptor to calculate the slant path.
For releases within building complexes, the shortest horizontal distance between the release point and the intake could be through intervening buildings. In these cases, it is acceptable to take the length of the shortest path (e.g., taut string length) around or over the intervening building as the source-to-receptor distance. However, staff notes that if the source and receptor are at different heights with respect to each other, calculating a taut string length may already factor in the vertical component of the distance. In this case, the same value should be input into ARCON96 for both the release and intake heights to avoid estimating erroneous additional slant path distance. Do the taut string lengths discussed in Calculation No. DBAX/Qs-04053R3 factor in the differences in elevations between the sources and receptor?
ATTACHMENT
- 4. Page 7 of Calculation No. DBAX/Qs-04053R3 states that the Turbine Building Vent stack flow rate must be maintained to at least 7.08 m3/s in the winter. Is this the minimum flow rate during all times of the year and is it reasonable to expect that it can be maintained during the course of an accident (e.g., as addressed by technical specifications) even if a single failure or loss of offsite power occurs?
- 5. Do X/Q estimates for all of the release/receptor pairs address the most limiting cases, including those potentially associated with single failure and loss of offsite power?
- 6. In a column title for breathing rates in Table 1.3-5 of Attachment 1 to your letter, does it mistakenly include X/Q with the units of breathing rate?