Request for Additional Information Security Plan Sections 1-9
ML041940456
Person / Time
Site: Nine Mile Point  Constellation icon.png
Issue date: 06/24/2004
From: Brian Benney
NRC/NRR/DLPM/LPD2
To: Spina J
Nine Mile Point
Benney B, NRR/DLPM, 415-3764
References
TAC MC2941, TAC MC2942
Download: ML041940456 (3)


Text

SAFEGUARDS INFORMATION SAFEGUARDS INFORMATION WARNING: Violation of Section 147 of the Atomic Energy Act, Safeguards Information is subject to Civil and Criminal Penalties June 24, 2004 Mr. James A. Spina Vice President Nine Mile Point Nuclear Station, LLC P. O. Box 63 Lycoming, NY 13093

SUBJECT:

NINE MILE POINT NUCLEAR STATION, UNITS 1 AND 2 - REQUEST FOR ADDITIONAL INFORMATION RE: SECURITY PLAN SECTIONS 1-9 (TAC NOS. MC2941 AND MC2942 )

Dear Mr. Spina:

In response to the April 29, 2003, Orders revising the design basis threat, you submitted revised physical security plans, safeguards contingency plans, and guard training and qualification plans, including an implementation schedule, for Nine Mile Point Nuclear Station, Units 1 and 2.

The Nuclear Regulatory Commission staff is reviewing your submission and has determined that a request for additional information (RAI) is necessary in order to complete its evaluation based on its review of Sections 1 through 9 of your physical security plan. Please respond to the enclosed RAI within 10 days from the date of this letter. If circumstances result in the need to revise the target response date, please contact me at (301) 415-3498.

Sincerely,

/RA/

Brian Benney, Project Manager Security Plan Review Team Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-220 and 50-410

Enclosure:

As stated cc w/o encl: See next page NOTICE: The enclosed information contains Safeguards Information. Upon separation from the enclosure, this letter is DECONTROLLED.

June 24, 2004 Mr. James A. Spina Vice President Nine Mile Point Nuclear Station, LLC P. O. Box 63 Lycoming, NY 13093

SUBJECT:

NINE MILE POINT NUCLEAR STATION, UNITS 1 AND 2 - REQUEST FOR ADDITIONAL INFORMATION RE: SECURITY PLAN SECTIONS 1-9 (TAC NOS. MC2941 AND MC2942 )

Dear Mr. Spina:

In response to the April 29, 2003, Orders revising the design basis threat, you submitted revised physical security plans, safeguards contingency plans, and guard training and qualification plans, including an implementation schedule, for Nine Mile Point Nuclear Station, Units 1 and 2.

The Nuclear Regulatory Commission staff is reviewing your submission and has determined that a request for additional information (RAI) is necessary in order to complete its evaluation based on its review of Sections 1 through 9 of your physical security plan. Please respond to the enclosed RAI within 10 days from the date of this letter. If circumstances result in the need to revise the target response date, please contact me at (301) 415-3498.

Sincerely,

/RA/

Brian Benney, Project Manager Security Plan Review Team Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-220 and 50-410

Enclosure:

As stated cc w/o encl: See next page DISTRIBUTION:

PUBLIC SPRT R/F OGC ACRS ADAMS Accession Number: ML041940456 OFFICE SPRT/NRR/PM SPRT/NSIR SPRT/NRR/SC NAME BBenney JPeralta JNakoski DATE 6/24/04 6/24/04 6/24/04 OFFICIAL RECORD COPY