ML041890341

From kanterella
Jump to navigation Jump to search
Draft Section a Operating
ML041890341
Person / Time
Site: Oyster Creek
Issue date: 04/19/2004
From: Hackenberg J
AmerGen Energy Co
To: Conte R
NRC/RGN-I/DRS/OSB
Conte R
References
-RFPFR, 50-219/04-301 50-219/04-301
Download: ML041890341 (32)


Text

ES-301 Administrative Topics Outline Form ES-301-1 Facility:

Oyster Creek NRC Examination Level (circle one): RO / SRO Operating Test Number:

2004NRC Describe activity to be performed Date of Examination: Week of April 19, 2004 Administrative Topic (see Note)

Conduct of Operations

[RO & SRO]

Conduct of Operations Equipment Control 11 Emergency Plan

[for SRO only]

RO/SRO - Calculate DW bulk temperature (JPM, new, SP-26, 1

tified Leakage (JPM, new

)

SRO - Approve Unidentified Leakrate Calculation (JPM, new, RO/SRO - Surveillance Test prerequisites for Core Spray -

(Alternate Path) ( backup booster pump, JPM, new, 200.OG)new=200.OJ RO - Determine stay time based on current exposure, administrative limit and survey map of work area (JPM, new=21OO.OM)

SRO - Approve Radioactive Discharge Permit - (Alternate Path)

( change faulted information, JPM, 200.06, new)

SRO only - Make an Emergency Plan Classification and complete notification form (JPM) Perform after SRO completes scenario, written for each scenarios classification

[backup - Fire/Natural Hazard based (

NOTE: All items (5 items) are required for SROs. RO applicants require only 4 items unless they are retaking only the administrative topics, when 5 are required.

AmerGem An Exelon/British Energy Company JOB PERFORMANCE MEASURE 200.OK

Title:

Calculate Bulk Drywell Temperature Task: Calculate Bulk Drywell Temperature I 2230101504 Validation Time: min I Faulted: NO I Time Critical: NO I NO I

I I

Name Social Security Number I

I DIRECTIONS TO TRAINEE:

Before you start, I will state the task conditions and initiating cues and fully answer any questions. To complete this task successfully, you must perform or simulate each critical element correctly and demonstrate proper procedural adherence.

NOTE: Directions are only required once in a given JPM session.

Date:

JPM 200.OK Rev. 0 2EFERENCE SECTION:

b TASK CONDITIONS :

The PCS is out of service All Control Room indications of Drywell Temperature are unavailable.

GENERAL TOOLS AND EQUIPMENT:

Data sheet of Recorder points from IA55 & TR-1 OOA GENERAL

REFERENCES:

Support Procedure 26, Determining Bulk Drywell Temperature, Rev. 16.

TASK STANDARD:

Attachment SP-26-1 & section 3.3 complete with calculated temperature of 148.8 degrees.

CRITICAL ELEMENTS: (*)

b 5,617 2 of 6

JPM 200.OK Rev. 0

, L PERFORMANCE SECTION:

TASK CONDITIONS:

1 The PCS is out of service All Control Room indications of Drywell Temperature are unavailable.

INITIATING CUES:

You are directed to calculate Bulk Drywell Temperature in accordance with Support Procedure 26.

START TIME PERFORMANCE CHECKLIST

1. Obtain controlled copy of 11 SP-26 11 2. Verifies that all prerequisites have been met.
3.

Determines that computer point DWTEMP is not avai lab1 e.

4. Calls RB NLO to obtain recorder data from IA55 and TR-100 on 51 RB.

CUE:

Give Operator the datz

  • 6. Transfers calculated data from Attachment SP-26-1 to Step 3.3.2.
  • 7. Calculates Bulk Drywell Temperature to be 148.8 degrees per step 3.3.2.

STANDARD INITIAL SATNNSAT Obtains controlled copy of SP-26.

Reviews prerequisites and determines that they have been met.

Determines that computer point DWTEMP is not available.

Calls RB NLO to obtain recorder data from IA55 and TR-100 on 51 RB.

sheet.

i I

Completes Attachment SP-26-1 Transfers calculated data from Attachment SP-26-1 to Step 3.3.2.

Calculates Bulk Drywell Temperature to be 148.8 degrees per step 3.3.2.

u COMPLETION TIME 3 of 6

JPM 200.OK Rev. 0 SIMULATOR SETUP NONE required.

Malfunctions:

Over rides :

Remotes:

Jomputer Aided Exercises:

b 4 of 6

u Recorder Point PT PT. 35 (IA55)

PT. 36 (IA55)

PT. 37 (IA55)

PT. 38 (IA55)

PT. 39 (IA55)

PT. 1 (TR-1OOA)

PT. 2 (TR-1OOA)

PT. 3 (TR-1OOA)

PT. 4 (TR-IOOA)

PT. 5 (TR-1OOA)

PT. 6 (TR-1OOA)

PT. 7 (TR-1OOA)

PT. 8 (TR-IOOA)

PT. 9 (TR-1OOA)

PT. 10 (TR-1OOA)

PT. 11 (TR-1OOA)

P i. 12 (TR-1OOA)

PT. 13 (TR-1 OOA)

JPM 200.OK Rev. 0 DATA SHEET TE1 OOA 138 TE1 OOB 144 TE1 OOC 142 TE1 OOD 151 TE1 OOE 151 TE103A 152 TElO3B 144 TE103C 149 TE103D 153 TE103E 152 TE104A 152 TE104B 155 TE104C 160 TE104D 168 TE104E 163 TE105A 161 TE105B 164 TE105C 164 5 of 6

TASK CONDITIONS:

The PCS is out of service All Control Room indications of Drywell Temperature are unavailable.

INITIATING CUES:

You are directed to calculate Bulk Drywell Temperature in accordance with Support Procedure 26.

6 of 6

ES-301 Control Room Svstems and Facilitv Walk-Throuah Test Outline Form ES-301-2 System / JPM Title

a. RO/SRO - Standby Liquid Control (SLC) / Initiate SLC (Alternate Path, change faulted component) [PRA related]
b. RO/SRO - Feed and CondensateKS - Terminate and Prevent injection Facility:

Ovster Creek NRC Date of Examination: Week of April 19, 2004 Exam Level (circle one): RO / SRO(1) / SRO(U)

Operating Test No.:

2004NRC (I

Type Code*

Safety Function 1

21 1.01 M, S, A 200.00Q N, s 2

)I Control Room Systems (8 for RO, 7 for SRO-I, 2 or 3 for SRO-U)

c. RO/SRO - ADS / Close a stuck open EMRV (Alternate Path - fail first step) 21 8.01 D, S, A
d. RO/SRO - Recirculation system / Respond to a tripped recirc pump with 5 operating (Alternate Path - Discharge Valve will not close) Last NRC 3

202.1 0 4

D, s, A

e. ROISRO - Primary Containment / Bypass Isolation Interlock for Torus Vent valves and prepare to vent the Torus 223.01 D, s 5
g. RO/SRO - Control Room Ventilation / Purge Control Room using Control Room HVAC System
f. RO/SRO - AC Electrical /Transfer Bus 1A from Auxiliary Transformer to Start-up Transformer

//

288.02 9

D, s 6

h. RO only - Recirculation system / Conduct Recirc Pump Trip Logic functional test 202.1 1 7

D, s It I

I

c. TBCCW/Line-up TBCCW during SBO 274.01 8

D, R, L Abnormal

a.

Fire Water system / Line-up Fire Water to the Core Spray 286.04 2

System [PRA related] need alternate water makeup to IC or CS 1 M,R, L 1

Emergency

b. CRDAnitiate the Remote Shutdown Panel on Control Room Evacuation I i?::

I Emergency 4

  • Type Codes: (D)irect from bank, (M)odified from bank, (N)ew, (A)lternate path, (C)ontrol room, ll (S)imulator, (L)ow-Power, (R)CA

AmerGen,,

An Exelon/British Energy Company JOB PERFORMANCE MEASURE 200.0F

Title:

Calculate Tech Spec Log Sheet Unidentified Leak Rate Task: Operate Sumps and Drains System Calculate DW Unidentified Leakrate 291 01 01 402 291 01 04304 KA# 223001 A1.10 RATING :

RO-3.4 SRO-3. 6 Validation Time: 15 min I Faulted: NO I

Time Critical: NO I

I Name Social Security Number DIRECTIONS TO TRAINEE:

Before you start, I will state the task conditions and initiating cues and fully answer any questions. To complete this task successfully, you must perform or simulate each critical element correctly and demonstrate proper procedural adherence. Peer checking will not be provided during the performance of required tasks.

NOTE: Directions are only required once in a given JPM session.

Comments 1 Of4

JPM 200.0F REFERENCE SECTION:

Rev. 0 TASK CONDITIONS:

Plant is at 100% power Both DWEDT pumps are operable At 0000 the 1-8 sump integrator reading was 105200 At 0400 the 1-8 sump integrator reading was 105344 Torus water level yesterday was 147.8 Torus water level today is 147.8 The STA reports that Torus unexpected leakage is 0.02 GENERAL TOOLS AND EQUIPMENT:

Procedure 681.4.004, Tech Spec Log Sheet, Rev. 0 GENERAL

REFERENCES:

Procedure 31 2.9, Primary Containment Control, Rev. 29 TASK STANDARD:

L Determine Unidentified Leakage CRITICAL ELEMENTS: (*)

293,435, $

INITIATING CUES:

You have been directed to determine Unidentified Leakage on the Tech Spec Log Sheet (Attachment 106-4) IAW Procedure 31 2.9, Primary Containment Control.

2 of 4

JPM 200.0F Rev. 0 PERFORMANCE SECTION:

1 TASK CONDITIONS:

Plant is at 100% power Both DWEDT pumps are operable At 0000 the 1-8 sump integrator reading was 105200 At 0400 the 1-8 sump integrator reading was 105344 Torus water level yesterday was 147.8 Torus water level today is 147.8 The STA reports that Torus unexpected leakage is 0.02

1.

Obtains controlled copy of procedure.

INITIATING CUES:

You have been directed to determine Unidentified Leakage on the Tech Spec Log Sheet IAW Procedure 31 2.9, Primary Containment Control.

Procedure 312.9 obtained START TIME 2s Records integrator readings on log sheet PERFORMANCE CHECKLIST Records integrator readings for 0000 and 0400 on TS log sheet STANDARD 3

Calculates the difference between the two readings 4!

Divides to get leakage

& Enters leakage on log rate sheet I

INITIAL SAT/U NS AT Subtracts 105200 from 105344 to get 144 gallons Divides 144 by 240 minutes to get 0.6 gpm leakage for 1-8 sump Enters 0.6 in 1-8 column

6.

Enters Identified Leakage Adjust IAW + note enters 0 for leakage adjustment

7.

Enters Torus unexpected leakage IAW STA report, enters 0.02 in Torus unexpected leakage column

8.

Calculates Total Unidentified leakage Adds 0.6 to 0 to 0.02 and gets 0.62 and enters this number in the Total column COMPLETION TIME 3 of 4

TASK CONDITIONS:

Plant is at 100% power Both DWEDT pumps are operable At 0000 the 1-8 sump integrator reading was 105200 At 0400 the 1-8 sump integrator reading was 105344 Torus water level yesterday was 147.8 Torus water level today is 147.8 The STA reports that Torus unexpected leakage is 0.02 11 INITIATING CUES:

You have been directed to determine Unidentified Leakage on the Tech Spec Log Sheet IAW Procedure 31 2.9, Primary Containment Control.

4 of 4

Title Technical Specification Log Sheet TECHNICAL SPECIFICATION LOG SHEET ATTACHMENT 1 Revision No.

0 SHIFT

?A-7P Comments:

Elev. 119' EDG Fuel Pool Fuel Oil Tank Temp Lvl.

Limit 4 25" F

Limit

>14K Gal.

Calculated in accordance with Procedure 31 2.11 Conducted in accordance with 681.4.005. NA when generator is off line.

Maximum 3OF difference between various Torus temperature indications.

If both DWEDT pumps are inoperable, use 3.0gpm for identified leakage and subtractfrom the 1-8 value (Procedure 312.9). If DWEDT purnp(s) are operable, enter zero (0).

+

FI -1

i, OYSTER CREEK GENERATING STATION PROCEDURE an~xclwvantfbti Energycmpany

  • 1 Number 681.4.004 Title Technical Specification Log Sheet SHIFT 7A-IP I Revisiong No.

Li uid Poison Tk.

T o w P 4160V UV Service Water Rad Monitor (7A-7P)

GALS Limit ILO9

,9OOF C

D RNO8C RN31 RNO8C RN31B Alarms Lvl. v (e

Lights Lit DaiL ThursdayCkSource B

2 1172 CPM CPM CPM CPM Clear GALS (Local)

(IOF)

, Init.

Init.

TECHNICAL SPECIFICATION LOG SHEET ATTACHMENT 1 (continued)

SDV Vent and Drain Valves

^...-

I I Valves Open (init)

I Source Check (Monday)-

(I)

(1) 7A-7P It) 7A-7P Ill 7A-7Pll)

If Bulk Temp Exceeds 1500F Commence using Proc. OPS-3024.09.

shutdown Head Flange Area Temps:

if2 are greater than 31sOF ev-drywell cooling if 2 are greater than 329F commence a plant shutdown IAW Roc. 203.1.

AmerGem An ExelonIBritish Enerav ComDanv JOB PERFORMANCE MEASURE 200.0J

Title:

Determine Core Spray Surveillance Requirements Task: Ensure Compliance to Station Procedures for all plant conditions 341 030241 1 KA# G2.2.12 RAT1 NG :

RO-3.0 SRO-3.4 Validation Time 15 minutes I Time Critical I

NO I

Name Social Security Number I

I DIRECTIONS TO TRAINEE:

Before you start, I will state the task conditions and initiating cues and fully answer any questions. To complete this task successfully, you must perform or simulate each critical element correctly and demonstrate proper procedural adherence. Peer checking will not be provided during the performance of required tasks.

NOTE: Directions are only required once in a given JPM session.

Comments Sigi na t u res Evaluator's Date Operator's Date

JPM 200.05 REFERENCE SECTION:

TASK CONDITIONS:

Plant is at 100% power MAPLHR is 89.23%

EDG #1 & EDG #2 have passed their most recent surveillance The breaker for NZ03C is racked out GENERAL TOOLS AND EQUIPMENT:

none GENERAL

REFERENCES:

Surveillance Procedure 61 0.4.002, Core Spray Pump Operability Test, Rev. 43 Technical Specification 3.4 TASK STANDARD:

Determine Core Spray Surveillance requirements IAW 61 0.4.002 b

CRITICAL ELEMENTS: (*)

294 INITIATING CUES:

You have been directed to determine if the Prerequisites have been met for Core Spray system 2 to be tested IAW 61 0.4.002 Core Spray Pump Operability Test.

JPM 200.05 PERFORMANCE SECTION:

START TIME u

PERFORMANCE CHECKLIST

1.

Obtains controlled copy of procedure.

2.

Determines Core Spray system is not in reduced availability

3.

Determines EDG status

  • 4.

Determines Core Spray system 1 is inop

5.

Verifies MAPLHGR

  • 6. Determines Surveillance 610.4.002 can NOT be performed STANDARD

~

~

~~

Procedure 61 0.4.002 obtained IAW TS 3.4.A, Core Spray is NOT in reduced availability because the reactor is not in the REFUEL mode with reactor water <212 degrees F or in the cold shutdown mode Determines both EDGs are operable because they have passed their surveillance tests and have no inoperable components Determines Core Spray system 1 must have no inoperable components and system 1 Backup Booster pump (NZ03C) breaker is racked out, making it INOP

~

From task conditions, verifies MAPLHGR is less than 90%. MAPLHGR is 89.23%

IAW 610.4.002, the 3.1 PREREQUISITES can NOT be met and the surveillance should not be performed INITIAL SATNNSAT COMPLETION TIME

TASK CONDITIONS:

Plant is at 100% power MAPLHR is 89.23%

EDG #1 & EDG #2 have passed their most recent surveillance The breaker for NZ03C is racked out IN lTl AT1 NG CUES:

You have been directed to determine if the Prerequisites have been met for Core Spray system 2 to be tested IAW 61 0.4.002, Core Spray Pump Operability Test.

i AmerGen,.

An Exelon/British Energy Company JOB PERFORMANCE MEASURE 200.OM

Title:

Calculate Radiation Area Stay Time I

KA# 2.3.4 I

RATING:

RO - 2.5 SRO - 3.1 Validation Time 10 minutes Time Critical NO DIRECTIONS TO TRAINEE:

Before you start, I will state the task conditions and initiating cues and fully answer any questions. To complete this task successfully, you must perform or simulate each critical element correctly and demonstrate proper procedural adherence.

NOTE: Directions are only required once in a given JPM session.

11 Comments 1 Of4

JPM 200.OM Rev. 0 SEFERENCE SECTION:

TASK CON D I TI0 NS :

The plant is at 100% power.

You are assigned a task to be performed in the Shutdown Cooling Room Your current quarterly accumulated exposure is 30 mr.

The RWP exposure limit is 100 mr The current RWP survey map indicates a dose rate of 50 mr/hr in the area you are to work.

GENERAL TOOLS AND EQUIPMENT:

GENERAL

REFERENCES:

NONE TASK STANDARD:

u Calculates a stay time of 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> and 24 minutes CRITICAL ELEMENTS: (*)

2 of 4

JPM 200.OM (1 1. Reviews task conditions

  • 2. Subtracts accumulated Lll exposure from RWP limit.

Rev. 0 Reviews task conditions Subtracts 30 mr from 100 mr and gets 70 mr remaining to limit.

I PERFORMANCE SECTION:

u

  • 3. Divides dose remaining to limit dose rate by.

TASK CON D I TI 0 N S :

The plant is at 100% power.

You are assigned a task to be performed in the Shutdown Cooling Room Your current quarterly accumulated exposure is 30 mr.

The RWP exposure limit is 100 mr The current RWP survey map indicates a dose rate of 50 mr/hr in the area you are to work.

Divides 70 mr by 50 mr/hr and gets 1.4 hrs Determines that stay time in 1 hr & 24 INITIATING CUES:

Calculate the allowable stay to perform your task without exceeding limits.

START TIME PERFORMANCE CHECKLIST I

STANDARD It I minutes.

I COMPLETION TIME 3 of 4

TASK CONDITIONS:

The plant is at 100% power.

You are assigned a task to be performed in the Shutdown Cooling Room Your current quarterly accumulated exposure is 30 mr.

The RWP exposure limit is 100 mr The current RWP survey map indicates a dose rate of 50 mr/hr in the area you are to work.

INITIATING CUES:

Calculate the allowable stay to perform your task without exceeding limits.

4 of 4

AmerGen An Exelon/Bntish Energy Company JOB PERFORMANCE MEASURE 200.OB

Title:

Approve Radioactive Discharge Permits Task: Release water from 1-5 Sump 3410302012 KA# 290001 2.1.23 RATING :

RO-3.9 SRO-4.0 Validation Time I 2 minutes I Time Critical I

NO DIRECTIONS TO TRAINEE:

Before you start, I will state the task conditions and initiating cues and fully answer any questions. To complete this task successfully, you must perform or simulate each critical element correctly and demonstrate proper procedural adherence. Peer checking will not be provided during the performance of required tasks.

NOTE: Directions are only required once in a given JPM session.

Comments Signa tu res

JPM 200.OB REFERENCE SECTION:

i, TASK CONDITIONS:

Plant at 100%

Water is to be released overboard from 1-5 Sump Dilution flow is 460,000 gpm GENERAL TOOLS AND EQUIPMENT:

Calculator GENERAL

REFERENCES:

Procedure 101.9, Release of Water to the Environment from 1-5 Sump, Rev. I O, 01.92 (1-5 sump release to environs)

TASK STANDARD:

Deny approval of discharge permit - (based on incomplete calculations and/or missing approvals)

CRITICAL ELEMENTS: (*)

4 INITIATING CUES:

You are directed to review the provided discharge permit for approval IAW-

-3, Reieaze of Water to the E r

i l

JPM 200.OB PERFORMANCE CHECKLIST

1.

Obtains controlled copy of procedure PERFORMANCE SECTION:

u STANDARD INITIAL SATIUNSAT Obtains controlled copy of procedure 101.9 W

2.

Review the analysis results TASK CONDITIONS:

Plant at 100%

Water is to be released overboard from 1-5 Sump Dilution flow is 460,000 gpm Recognize analysis results are above the limit of I

.OE-6 uci/ml, which requires additional calculations that were NOT performed INITIATING CUES:

You are directed to review the provided discharge permit for approvalSAtPQ

> - / t r 0

ter to the Enviro

-5 s p

3.

Review required signatures/approvals are complete START TIME Recognize verification of calculation and Chemistry Manager signatures were NOT obtained

  • 4. Denies approval for release Release cannot be approved based on incomplete calculations and/or missing approvals COMPLETION TIME

TASK CONDITIONS:

Plant at 100%

Water is to be released overboard from 1-5 Sump Dilution flow is 460,000 gpm INITIATING CUES:

You are directed to review the provided discharge permit for approval #WV-P r o u r e 10J+9+kle ase of &

L AmerGen,.

An Exelon/British Energy Company JOB PERFORMANCE MEASURE 345.04N

Title:

Classify an Emergency or Abnormal Event Task: Classify an Emergency or Abnormal Event.

I2000502401 KA# 294001 GA1-16 RAT1 NG :

RO - N/A SRO - 4.7 Validation Time 9 minutes I Faulted: NO I Time Critical I

YES I

I I

Name Social Security Number DIRECTIONS TO TRAINEE:

Before you start, I will state the task conditions and initiating cues and fully answer any questions. To complete this task successfully, you must perform or simulate each critical element correctly and demonstrate proper procedural adherence.

NOTE: Directions are only required once in a given JPM session.

~~

Comments

JPM 345.04N Rev. 0 AEFERENCE SECTION:

TASK CONDITIONS:

The plant is operating at 100% power.

There is a strong NW wind blowing at 60 MPH There is a full moon causing abnormally low tides.

The Intake Operator reports that the intake level is -2.7ft. indicated on the staff gauge.

GENERAL TOOLS AND EQUIPMENT:

GENERAL

REFERENCES:

Procedure EPI P-OC-.OI, Rev. 14 TASK STANDARD:

Within 15 minutes of start time declares an ALERT based on EAL 0.2 and properly completes the Notification Form.

u CRITICAL ELEMENTS: (*)

2 of 5

L 11 PERFORMANCE CHECKLIST JPM 345.04N PERFORMANCE SECTION:

STANDARD INITIAL SATNNSAT Rev. 0 TASK CONDITIONS:

The plant is operating at 100% power.

A There is a strong NW wind blowing at There is a full moon causing abnormally low tides.

The Intake Operator reports that the intake level is -2.7ft. indicated on the staff gauge.

IN IT1 AT1 NG CUES:

State the minimum classification for these conditions and complete the Emergency Report Form for Shift Manager approval.

START TIME

1.

Obtain controlled copy of procedure Obtains controlled copy of procedure EPIP-oc-.01

  • 2.

Determined Emergency Classification and associated EAL.

  • 3 Completes Emerqency Classification block.
4.

Completes Event Descrbtion block Declares ALERT - EAL HA3.5 Intake level is less than -2.5 ft.

Time Critical Portion of JPM complete Time Complete (51 5 minutes)

Fill in the block with:

An ALERT was declared at current time on current date. The EAL is 0-2 Fill in the block with:

Description similar to; Intake level is c-2.5 ft

  • 5.

Completes Radioactive Release Status block.

  • 6.

Completes Meteoroloaical Condition block Fill in the block with:

Check the line that states that There is no abnormal radiological release in progress Fill in the block with:

From the Weather screen record; Wind direction is from I degrees and wind speed is miles per hour (use 380 elevation 3 of 5

JPM 345.04N Rev. 0 I(

STANDARD INITIAL SAT/UNSAT PERFORMANCE CHECKLIST

7.

Completes On-Site Fill in the block with:

Protective Action block Checks the three lines for ALERT condition.

8.

Present to Shift Manager Presents filled-in Notification form to evaluator for SM approval.

COMPLETION TIME 4 of 5

TASK CONDITIONS:

The plant is operating at 100% power.

There is a strong NW wind blowing at 60 MPH There is a full moon causing abnormally low tides.

The Intake Operator reports that the intake level is -2.7ft.,,Idicated on the staff gauge.

INITIATING CUES:

State the minimum classification for these conditions and complete the Emergency Report Form for Shift Manager approval.

5 of 5

OYSTER CREEK EMERGENCY PRlEpAREDNESS IMPLEMENTING PROCEDURE

AmerGen, An ExelonlBnbsh Energy Company Title CLASSIFICATION OF EMERGENCY CONDITIONS L

Categories 0 & P "Natural and Man-made Hazards" Number EPIP-OC-.O1 Revision No.

14 Clas si f ica t ion EAL ' s Basis Alert Natural Phenomenon

1. Earthquake affecting plant operations.

-or-

2. Intake canal water level 5 -2.5 feet, as measured by the staff gauge.

-or-

-or-

3. Intake water level at the intake structure lower deck.
4. Sustained hurricane force winds of greater than 95 mph, as indicated on wind speed recorder.

-or-

5. Any tornado striking the facility.

Man-made Hazards

1. Aircraft crash OR other missile impact within the protected area OR onto any permanent plant structure.
2. Known explosion damage to any permanent plant structure.
3. Release of TOXIC or FLAMMABLE GAS into the plant which

-or-

-or-affects the safe operation of the plant as determined by the Shift Manager/Ehergency Director.

-or-

4. Turbine failure resulting in casing penetration.

An Operational Basis Earthmake (0.11G) may cause damage to some portions of the site but should not affect the ability of safety functions to operate. Method of detection is validated by a reliable source (e.g. Lamont-Doherty Geological Observatory: (914)359-2900). The OBE is as determined from 10CFRlOtD. The EAL's addressing intake water level both high and low are escalations of a worsening condition cited in the U.E. class. The level's address the Nureg concern for approaching design conditions where the heat sink's effectiveness may be reduced and subsequently lost. EAL #5 is based on the assumption that a tornado striking (touching down)) the facility (within the protected area boundary) may have potentially damaged plant structures containing function or systems required for safe shutdown of the plant. If such damage is confirmed, the event may be escalated to a Site Area Emergency.

(EPIPOl/S4

)

E2-29