MONTHYEARML0402907492004-01-14014 January 2004 Response to NRC RAIs Pertaining to the Review of the License Applications - Scoping and Screening Methodology and Results Project stage: Response to RAI ML0413305512004-05-10010 May 2004 03/25-26/2004 Summary of Telephone Conferences with Indiana Michigan Power Company (I&M Representatives Regarding Draft Request for Additional Information on DC Cook Nuclear Plant, Units 1 & 2, LRA Project stage: Draft RAI ML0415304722004-06-0101 June 2004 Summary of Telephone Conference Between U.S. Nuclear Regulatory Commission (NRC) and Indiana Michigan Power Company (I&M) Representatives Concerning Draft Requests for Additional Information on Donald C. Cook, Nuclear Plants Project stage: Draft RAI ML0418104272004-06-29029 June 2004 Summary of Telephone Conference Held on May 12, 2004, Between the U.S. Nuclear Regulatory Commission (NRC) and Indiana Michigan Power Company Representatives Concerning Draft Requests for Additional Information on DC Cook, Units 1 & 2, LRA Project stage: Draft RAI ML0421102752004-07-27027 July 2004 & 05/21/2004 Summary of Telephone Conference Calls with Indiana Michigan Power Co Regarding Responses to Request for Additional Information on D. C. Cook Units 1 & 2, LRA Project stage: RAI ML0424704102004-08-11011 August 2004 Units I and 2, License - Renewal Application - Response to Requests for Additional Information on Aging Management Programs, (TAC Nos. Mc 1202 and Mc 1203) Project stage: Response to RAI ML0423703752004-08-23023 August 2004 Summary of Telephone Conference Held on July 29, 2004 Between the U.S. Nuclear Regulatory Commission (NRC) and Indiana Michigan Power Company (I&M) Representatives Concerning Requests for Additional Information on Donald C. Cook Nuclear Pla Project stage: RAI ML0424406712004-08-31031 August 2004 Summary of Telephone Conference Held on August 10, 2004 Between the U.S. Nuclear Regulatory Commission (NRC) and Indiana Michigan Power Company (I&M) Representatives Concerning Requests for Additional Information on Donald C. Cook Nuclear P Project stage: RAI ML0523404472005-08-30030 August 2005 Renewed Facility Operating License No. DPR-58, Donald C. Cook Nuclear Plant, Unit No. 1 - Docket No. 50-315 Project stage: Other ML0523404112005-08-30030 August 2005 Mano K. Nazar Ltr Re. Donald C. Cook Nuclear Plant, Units 1 and 2 - Issuance of Renewed Facility Operating Licenses Nos. DPR-58 and DPR-74 Project stage: Approval ML0523404812005-08-30030 August 2005 Renewed Facility Operating License No. DPR-74, Donald C. Cook Nuclear Plant, Unit No. 2 - Docket No. 50-316 Project stage: Other 2004-07-27
[Table View] |
Similar Documents at Cook |
---|
Category:Meeting Summary
MONTHYEARML24305A1002024-11-0101 November 2024 Summary of Meeting with Indiana Michigan Power Company to Discuss Potential Changes to the Emergency Plan for Donald C. Cook Nuclear Plant, Units 1 and 2 ML24183A2292024-07-0101 July 2024 Summary of Public Outreach to Discuss the NRC 2023 End-Of-Cycle Plant Performance Assessment of Donald C. Cook Nuclear Plant, Units 1 and 2 ML24103A1872024-04-16016 April 2024 Summary of Meeting with Indiana Michigan Power Co., Regarding Surveillance Capsule Program for DC Cook Nuclear Plant, Unit 2 ML24031A5872024-02-0202 February 2024 Summary of Meeting with Indiana Michigan Power Company Regarding Neutron Flux Instrumentation for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML23215A1662023-08-17017 August 2023 Summary of July 31, 2023, Meeting with Indiana Michigan Power Company Regarding Operating Power Sources for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML23199A2402023-07-19019 July 2023 Summary of the July 13, 2023, Public Outreach to Discuss the NRC 2022 End-of-Cycle Plant Performance Assessment of Donald C. Cook Nuclear Plant, Units 1 and 2 ML22355A6022023-01-0303 January 2023 Summary of December 14, 2022, with Indiana Michigan Power Company to Discuss Potential Changes to the Emergency Plan for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML22318A1992022-11-21021 November 2022 Summary of November 7, 2022, Meeting with Indiana Michigan Power Company Regarding Neutron Flux Instrumentation for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML22154A5342022-06-0909 June 2022 Summary of the June 1, 2022, Public Outreach to Discuss the NRC 2021 End-Of-Cycle Plant Performance Assessment of Donald C. Cook Nuclear Plant ML22011A2732022-01-13013 January 2022 Summary of Meeting with Indiana Michigan Power Company to Discuss Planned Final Response to Generic Letter 2004-02 for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML21349B3092022-01-0303 January 2022 Summary of Meeting with Indiana Michigan Power Company to Discuss Potential Changes to the Quality Assurance Program for Donald C. Cook Nuclear Plant, Units 1 and 2 ML21202A1072021-07-23023 July 2021 Summary of July 20, 2021, with Indiana Michigan Power Company to Discuss Potential Changes to the Emergency Plan for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML21196A5182021-07-15015 July 2021 July 8, 2021, Summary of Public Webinar to Discuss the NRC 2020 End-Of-Cycle Plant Performance Assessment of the Donald C. Cook Nuclear Plant ML21082A0052021-03-24024 March 2021 Summary of March 19, 2021, with Indiana Michigan Power Company Regarding Containment Water Level Channels for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML20349A0152020-12-17017 December 2020 Summary of November 30, 2020, Teleconference with Indiana Michigan Power Company Regarding a Planned License Amendment Request to Extend the Containment Integrated Leak Rate Testing Interval for Donald C. Cook Nuclear Plant, Unit No. 2 ML20282A2712020-10-14014 October 2020 Summary of October 2, 2020, Teleconference with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit No. 1 ML20248H4752020-09-10010 September 2020 Summary of August 6, 2020, Teleconference with Indian Michigan Power Company Related to Steam Generator Eddy Current Testing License Amendment Request ML20209A6032020-07-27027 July 2020 Summary of the July 21, 2020, Public Webinar to Discuss the NRC 2019 End-of-Cycle Plant Performance Assessment of the Donald C. Cook Nuclear Plant, Units 1 and 2 ML20133K1282020-05-21021 May 2020 Summary of May 4, 2020, Teleconference with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML20121A0692020-05-0404 May 2020 Summary of Teleconference with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML20041C9492020-02-13013 February 2020 Summary of February 6, 2020, Teleconference with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML19350A0552019-12-30030 December 2019 Summary of 12/12/2019 Meeting with Indiana Michigan Power Company, License Amendment Request for D.C. Cook Nuclear Plant, Units 1 and 2 to Delete Surveillance Requirement Related to Diesel Generator Load Test Resistor Banks ML19212A5652019-07-30030 July 2019 Summary of Public Open House to Discuss NRC Activities and the 2018 End-Of-Cycle Performance Assessment of Donald C. Cook Nuclear Generating Plant, Units 1 and 2 ML19141A0622019-06-0606 June 2019 Summary of November 19, 2018, Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML19099A3262019-04-16016 April 2019 Summary of Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML19067A0482019-03-12012 March 2019 Summary of Public Teleconference with Indiana Michigan Power Co. (I&M) Review of LAR for Approval of Leak-Before-Break Methodology for Reactor Coolant System Small Diameter Piping (EPID-2019-LLA-0054) ML18334A0402018-12-13013 December 2018 Summary of Meeting with Indian Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit No. 1 ML18109A0692018-04-26026 April 2018 Summary of April 10, 2018, Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML18052B0542018-02-26026 February 2018 Summary of February 15, 2018, Meeting with Indian Michigan Power Company Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 (EPID L-2018-LRM-0008 ML18018B1382018-01-22022 January 2018 Summary of Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit No. 1 ML17265A4922017-10-0404 October 2017 Summary of Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 2 ML17235B1232017-08-23023 August 2017 Summary of the July 27, 2017, Open House to Discuss the 2016 End-of-Cycle Plant Performance Assessment of Donald C. Cook Nuclear Plant ML17082A0762017-03-27027 March 2017 Summary of March 20, 2017, Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML16308A1132016-11-16016 November 2016 Summary of October 27, 2016, Public Meeting with Indiana Michigan Power Company Regarding the Donald C. Cook Nuclear Plant, Units 1 and 2 ML16244A7062016-08-30030 August 2016 Summary of the August 22, 2016, Donald C. Cook Public Meeting ML16193A5912016-07-15015 July 2016 Summary of Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Units 1 and 2 ML15271A0462015-10-0505 October 2015 Summary of Public Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Units 1 and 2 ML15237A3362015-09-0202 September 2015 Summary of August 24, 2015, Telephone Call to Provide Verbal Authorization of Relief Request ISIR-4-06, Alternate Repair of Socket Weld ML15107A0982015-04-24024 April 2015 April 14, 2015, Summary of Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Units 1 and 2 ML14311A3182014-11-14014 November 2014 Summary of Conference Call with Donald C. Cook Nuclear Plant, Unit 1 Regarding the Fall 2014 Steam Generator Inspections ML14231A0752014-08-27027 August 2014 Summary of the August 8, 2014, Pre-Application Meeting with American Electric Power Company to Discuss a Future License Amendment Request for Alternative Source Term and TSTF-490 ML14209A9422014-07-30030 July 2014 July 9, 2014, Summary of Category 1, Public Meeting with Indiana Michigan Power Company to Discuss Seismic Hazard Reevaluations Associated with Implementation of Japan Lessons-Learned Near-Term Task Force Recommendation 2.1 ML14199A0802014-07-18018 July 2014 Summary of July 8, 2014 Donald C. Cook Public Annual Assessment Meeting ML14023A3872014-01-30030 January 2014 Summary of Joint Steering Committee Meeting to Discuss Activities Related to Lessons-Learned from the Fukushima Dai-Ichi Nuclear Power Plant Event ML13210A2272013-08-0202 August 2013 6/26/13, Summary of Pre-Application Meeting to Discuss Pending License Amendment Request to Modify the CNP Unit 1 Normal Operating Pressure and Temperature ML13189A2322013-07-15015 July 2013 Summary of Conference Telephone Call Regarding the 2013 Steam Generator Tube Inspections ML13154A4062013-06-0303 June 2013 5/30/2013 - Summary of the D.C. Cook Public Meeting ML12159A4022012-06-0707 June 2012 May 31, 2012 Summary of Public Meeting to Discuss the 2011 Annual Assessment Results for D.C. Cook ML1133307782011-11-29029 November 2011 Record of Discussion by Phone on 10/5/11 Regarding Steam Generator Inspection ML11129A2422011-06-0808 June 2011 Summary of Meeting with Indiana Michigan Power Company to Discuss Issues Related to a Future Submittal Using NFPA 805 2024-07-01
[Table view] |
Text
June 1, 2004 LICENSEE: Indiana Michigan Power Company FACILITY: Donald C. Cook Nuclear Plant, Units 1 and 2
SUBJECT:
SUMMARY
OF TELEPHONE CONFERENCE ON MAY 6, 2004, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION (NRC) AND INDIANA MICHIGAN POWER COMPANY (I&M) REPRESENTATIVES CONCERNING DRAFT REQUESTS FOR ADDITIONAL INFORMATION ON DONALD C. COOK NUCLEAR PLANT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NOS. MC1202 AND MC1203)
The U.S. Nuclear Regulatory Commission staff (the staff) and representatives of Indiana Michigan Power Company (the applicant) held a telephone conference call on May 6, 2004, to discuss a draft request for additional information (D-RAI) concerning the Donald C. Cook Nuclear Plant (CNP) license renewal application (LRA).
The conference call was useful in clarifying the intent of the staffs question. On the basis of the discussions, the applicant was able to better understand the staff's D-RAI. No staff decisions were made during the meeting. provides a listing of the telephone conference participants. Enclosure 2 contains the D-RAI discussed with the applicant, including a brief description on the status of the item.
The applicant has had an opportunity to review and comment on this summary.
/RA/
Jonathan Rowley, Project Manager License Renewal Section A License Renewal and Environmental Impacts Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Docket Nos.: 50-315 and 50-316
Enclosures:
As stated cc w/enclosures: See next page
June 1, 2004 LICENSEE: Indiana Michigan Power Company FACILITY: Donald C. Cook Nuclear Plant, Units 1 and 2
SUBJECT:
SUMMARY
OF TELEPHONE CONFERENCE ON MAY 6, 2004, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION (NRC) AND INDIANA MICHIGAN POWER COMPANY (I&M) REPRESENTATIVES CONCERNING DRAFT REQUESTS FOR ADDITIONAL INFORMATION ON DONALD C. COOK NUCLEAR PLANT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NOS. MC1202 AND MC1203)
The U.S. Nuclear Regulatory Commission staff (the staff) and representatives of Indiana Michigan Power Company (the applicant) held a telephone conference call on May 6, 2004, to discuss a draft request for additional information (D-RAI) concerning the Donald C. Cook Nuclear Plant (CNP) license renewal application (LRA).
The conference call was useful in clarifying the intent of the staffs question. On the basis of the discussions, the applicant was able to better understand the staff's D-RAI. No staff decisions were made during the meeting. provides a listing of the telephone conference participants. Enclosure 2 contains the D-RAI discussed with the applicant, including a brief description on the status of the item.
The applicant has had an opportunity to review and comment on this summary.
/RA/
Jonathan Rowley, Project Manager License Renewal Section A License Renewal and Environmental Impacts Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Docket Nos.: 50-315 and 50-316
Enclosures:
As stated cc w/enclosures: See next page DISTRIBUTION:
See next page Document Name:C:\ORPCheckout\FileNET\ML041530472.wpd Accession No: ML041530472 OFFICE PM:RLEP LA:RLEP SC:RLEP NAME JRowley MJenkins SLee DATE 06/1/04 06/1/04 06/1/04 OFFICIAL RECORD COPY
DISTRIBUTION: Dated: June 1, 2004 Accession No: ML041530472 HARD COPY RLEP RF J. Rowley (PM)
E-MAIL:
RidsNrrDrip RidsNrrDe G. Bagchi K. Manoly W. Bateman J. Calvo R. Jenkins P. Shemanski J. Fair RidsNrrDssa RidsNrrDipm D. Thatcher R. Pettis C. Li M. Itzkowitz (RidsOgcMailCenter)
R. Weisman M. Mayfield A. Murphy S. Smith (srs3)
S. Duraiswamy Y. L. (Renee) Li RLEP Staff R. Gramm A. Howell J. Stang J. Strasma, RIII M. Kotzalas OPA NRR/ADPT secretary (RidsNrrAdpt)
LIST OF PARTICIPANTS FOR TELEPHONE CONFERENCE CONCERNING DRAFT REQUESTS FOR ADDITIONAL INFORMATION MAY 6, 2004 Participants Affiliation Jonathan Rowley U.S. Nuclear Regulatory Commission (NRC)
John Fair NRC Neil Haggerty Indiana Michigan Power Company (I&M)
Bob Kalinowski I&M Richard Gumbir I&M Mark Rinckel Framatome*
- I&M contractor Enclosure 1
DRAFT REQUEST FOR ADDITIONAL INFORMATION (D-RAI) DISCUSSED FOR DONALD C. COOK (CNP), UNITS 1 AND 2, LICENSE RENEWAL DURING MAY 6, 2004 TELEPHONE CONFERENCE Donald C. Cook LRA Section 4.3, METAL FATIGUE D-RAI 4.3.3-1 Section 4.3.3 of the LRA discusses I&Ms evaluation of the impact of the reactor water environment on the fatigue life of components. The discussion references the fatigue sensitive component locations for an early vintage Westinghouse plant identified in NUREG/CR-6260, Application of NUREG/CR-5999 Interim Fatigue Curves to Selected Nuclear Power Plant Components. The LRA indicates that the design usage factors provided in Table 5-98 of NUREG/CR-6260 were used for the evaluation of the charging nozzle, safety injection nozzle and RHR tee. The design usage factors were based on an evaluation of the Turkey Point facility, including a plant specific evaluation of the RHR piping and detailed finite element analyses of the charging and safety injection nozzles. Discuss the applicability of these analyses to the D. C. Cook facility. The discussion should include a comparison of piping sizes and thicknesses, including the design of the thermal sleeves between D. C. Cook and Turkey Point. The discussion should also include a comparison of the number and type of design transients cycles between D. C. Cook and Turkey Point.
Status: I&M was requested to consider the safety evaluations for Surry and North Anna to aid in the response to this D-RAI. I&M indicated that the question was clear.
Enclosure 2
Donald C. Cook Nuclear Plant, Units 1 and 2 cc:
Regional Administrator, Region III Michigan Department of Environmental U.S. Nuclear Regulatory Commission Quality 801 Warrenville Road Waste and Hazardous Materials Div.
Lisle, IL 60532-4351 Hazardous Waste & Radiological Protection Section Attorney General Nuclear Facilities Unit Department of Attorney General Constitution Hall, Lower-Level North 525 West Ottawa Street 525 West Allegan Street Lansing, MI 48913 P.O. Box 30241 Lansing, MI 48909-7741 Township Supervisor Lake Township Hall Michael J. Finissi, Plant Manager P.O. Box 818 Indiana Michigan Power Company Bridgman, MI 49106 Nuclear Generation Group One Cook Place U.S. Nuclear Regulatory Commission Bridgman, MI 49106 Resident Inspectors Office 7700 Red Arrow Highway Mr. Joseph N. Jensen, Site Vice President Stevensville, MI 49127 Indiana Michigan Power Company Nuclear Generation Group David W. Jenkins, Esquire One Cook Place Indiana Michigan Power Company Bridgman, MI 49106 One Cook Place Bridgman, MI 49106 Mr. Fred Emerson Nuclear Energy Institute Mayor, City of Bridgman 1776 I Street, N.W., Suite 400 P.O. Box 366 Washington, DC 20006-3708 Bridgman, MI 49106 Richard J.Grumbir Special Assistant to the Governor Project Manager, License Renewal Room 1 - State Capitol Indiana Michigan Power Company Lansing, MI 48909 Nuclear Generation Group 500 Circle Drive Mr. John A. Zwolinski Buchanan, MI 49107 Director, Design Engineering and Regulatory Affairs Mr. Mano K. Nazar Indiana Michigan Power Company American Electric Power Nuclear Generation Group Senior Vice President and Chief Nuclear 500 Circle Drive Officer Buchanan, MI 49107 Indiana Michigan Power Company Nuclear Generation Group David A. Lochbaum 500 Circle Drive Nuclear Safety Engineer Buchanan, MI 49107 Union of Concern Scientists 1707 H Street NW, Suite 600 Washington, DC 20036