May 27, 2004 PETITIONER: Raymond Shadis Staff Technical Advisor New England Coalition FACILITY: Vermont Yankee Nuclear Power Plant

SUBJECT:

PETITION FOR VERMONT YANKEE (TAC NO. MC2745)

SUMMARY

OF MAY 5, 2004, CONFERENCE CALL WITH RAYMOND SHADIS OF THE NEW ENGLAND COALITION, REGARDING THE 10 CFR 2.206 On April 23, 2004, a Petition was submitted by the New England Coalition under the provisions of 10 CFR 2.206 regarding the Vermont Yankee Nuclear Power Plant (Vermont Yankee). On May 5, 2004, a teleconference was held between the Nuclear Regulatory Commision (NRC)

Petition Review Board (PRB) and representatives of the New England Coalition. This call with the petitioners was to afford them the opportunity to provide additional information or clarification regarding the issues raised in the Petition.

The Petition requested that until such time as the licensee has rendered an accurate and NRC-verified account of the location, disposition, and condition of all irradiated fuel, including fuel currently loaded in the reactor core, that the NRC order a halt to all fuel movement at Vermont Yankee. As the basis for this request, the petitioner (Raymond Shadis) stated that because Entergy Nuclear Operations, Inc. (Entergy) has lost control of the spent fuel inventory at Vermont Yankee, he had no confidence that Entergy did not put leaking fuel or suspected leaking fuel assemblies back into the reactor core during this refueling outage.

The PRB informed the petitioner that the request to stop all fuel movement at Vermont Yankee was moot as all fuel movement for this outage had been completed by the time of receipt of his request. During this call, he reaffirmed to the PRB the Petitions request to stop all fuel movement, but stated, he understood that at the present time that would limit the request to the spent fuel pool (SFP). He also stated that he wanted an Order issued to the licensee to do a verification of the inventory of all the special nuclear material in the SFP that is to be verified by the NRC. He also noted that he is not averse to moving fuel in the SFP if it is related to the inventory inspection.

Following the conference call, the PRB met in closed session to discuss the merits of the petitioners request. The PRB determined that the Petition satisfied the criteria for review under 10 CFR 2.206 because the Petition contained a request for enforcement-related actions, the bases for the enforcement-related actions were given, and no other NRC proceedings were available for which the petitioners concerns could be addressed. The PRB agreed to meet later to discuss if any immediate action was needed in response to the request. The PRB also decided to refer to the NRC Office of the Inspector General those allegations of NRC wrongdoing resulting from the May 5, 2004, teleconference with the petitioner. The goal is to

R. Shadis issue an acknowledgment letter, including a discussion of the request for immediate action, by May 28, 2004. is the transcript of this confernce call. A list of participants is provided as , including members of the public.

Please direct any inquiries to Alan Wang at 301-415-1445 or ABW@nrc.gov].

/RA/

Alan B. Wang, Project Manager, Section 2 Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation

Enclosures:

As stated cc w/encls: See next page

ML041410554 OFFICE PDIV-2/PM PDI-2/LA VY/SC NAME AWang CRaynor AHowe DATE 5/26/04 5/26/04 5/26/04 PETITION REVIEW CONFERENCE CALL PARTICIPANTS MAY 5, 2004 NRC L. Marsh *NRR/DLPM, Director E. Leeds PRB Chairperson C. Holden NRR/DLPM, Director, Project Directorate I A. Howe NRR/DLPM, Vermont Yankee Section Cheif A. Wang Petition Manager D. Skay Agency Coordinator, 2.206 Petitions R. Ennis NRR/DLPM, Vermont Yankee Project Manager H. Berkow NRR/DLPM, Director, Project Directorate IV J. Stang NRR/DLPM S. Lewis Office of General Counsel New England Coalition R. Shadis (via phone)

P. Blanche (via phone)

A. Gundersen (via phone)

P. Alexander (via phone)

Entergy C. Faison (via phone)

R. Deplukas (via phone)

R. Williams (via phone)

J. DeVincentis (via phone)

Members of Public S. Small, Rutland Herald (via phone)

L. Butler, Brattleboro Reformer (via phone)

J. Scott, Freelance TV and Press Reporter (via phone)

  • Office of Nuclear Reactor Regulation, Division of Licensing Project Management Enclosure 2

Vermont Yankee Nuclear Power Station cc:

Regional Administrator, Region I Ms. Carla A. White, RRPT, CHP U. S. Nuclear Regulatory Commission Radiological Health 475 Allendale Road Vermont Department of Health King of Prussia, PA 19406-1415 P.O. Box 70, Drawer #43 108 Cherry Street Mr. David R. Lewis Burlington, VT 05402-0070 Shaw, Pittman, Potts & Trowbridge 2300 N Street, N.W. Mr. James M. DeVincentis Washington, DC 20037-1128 Manager, Licensing Vermont Yankee Nuclear Power Station Ms. Christine S. Salembier, Commissioner P.O. Box 0500 Vermont Department of Public Service 185 Old Ferry Road 112 State Street Brattleboro, VT 05302-0500 Montpelier, VT 05620-2601 Resident Inspector Mr. Michael H. Dworkin, Chairman Vermont Yankee Nuclear Power Station Public Service Board U. S. Nuclear Regulatory Commission State of Vermont P.O. Box 176 112 State Street Vernon, VT 05354 Montpelier, VT 05620-2701 Director, Massachusetts Emergency Chairman, Board of Selectmen Management Agency Town of Vernon ATTN: James Muckerheide P.O. Box 116 400 Worcester Rd.

Vernon, VT 05354-0116 Framingham, MA 01702-5399 Operating Experience Coordinator Jonathan M. Block, Esq.

Vermont Yankee Nuclear Power Station Main Street 320 Governor Hunt Road P.O. Box 566 Vernon, VT 05354 Putney, VT 05346-0566 G. Dana Bisbee, Esq. Mr. John F. McCann Deputy Attorney General Director, Nuclear Safety Assurance 33 Capitol Street Entergy Nuclear Operations, Inc.

Concord, NH 03301-6937 440 Hamilton Avenue White Plains, NY 10601 Chief, Safety Unit Office of the Attorney General Mr. Gary J. Taylor One Ashburton Place, 19th Floor Chief Executive Officer Boston, MA 02108 Entergy Operations 1340 Echelon Parkway Ms. Deborah B. Katz Jackson, MS 39213 Box 83 Shelburne Falls, MA 01370

Vermont Yankee Nuclear Power Station cc:

Mr. John T. Herron Mr. Ronald Toole Sr. VP and Chief Operating Officer 1282 Valley of Lakes Entergy Nuclear Operations, Inc. Box R-10 440 Hamilton Avenue Hazelton, PA 18202 White Plains, NY 10601 Ms. Stacey M. Lousteau Mr. Danny L. Pace Treasury Department Vice President, Engineering Entergy Services, Inc.

Entergy Nuclear Operations, Inc. 639 Loyola Avenue 440 Hamilton Avenue New Orleans, LA 70113 White Plains, NY 10601 Mr. Raymond Shadis Mr. Brian OGrady New England Coalition Vice President, Operations Support Post Office Box 98 Entergy Nuclear Operations, Inc. Edgecomb, ME 04556 440 Hamilton Avenue White Plains, NY 10601 Mr. James P. Matteau Executive Director Mr. Michael J. Colomb Windham Regional Commission Director of Oversight 139 Main Street, Suite 505 Entergy Nuclear Operations, Inc. Brattleboro, VT 05301 440 Hamilton Avenue White Plains, NY 10601 Mr. William K. Sherman Vermont Department of Public Service Mr. John M. Fulton 112 State Street Assistant General Counsel Drawer 20 Entergy Nuclear Operations, Inc. Montpelier, VT 05620-2601 440 Hamilton Avenue White Plains, NY 10601 Mr. Michael Kansler President Mr. Jay K. Thayer Entergy Nuclear Operations, Inc.

Site Vice President 440 Hamilton Avenue Entergy Nuclear Operations, Inc. White Plains, NY 10601 Vermont Yankee Nuclear Power Station P.O. Box 0500 185 Old Ferry Road Brattleboro, VT 05302-0500 Mr. Kenneth L. Graesser 38832 N. Ashley Drive Lake Villa, IL 60046 Mr. James Sniezek 5486 Nithsdale Drive Salisbury, MD 21801