ML041340392
| ML041340392 | |
| Person / Time | |
|---|---|
| Site: | Cook |
| Issue date: | 05/12/2004 |
| From: | NRC/RGN-III |
| To: | |
| References | |
| Download: ML041340392 (22) | |
Text
D.C. Cook Performance Meeting D.C. Cook Performance Meeting Supplemental Inspection - Inspection Procedure 95002 Exit Meeting Supplemental Inspection - Inspection Procedure 95002 Exit Meeting Nuclear Regulatory Commission - Region III Nuclear Regulatory Commission - Region III Lisle, Illinois Lisle, Illinois May 12, 2004 May 12, 2004
NRC Representatives NRC Representatives
Patrick Hiland, Acting Deputy Division Director, DRP
- (630) 829-9601
Brian Kemker, Senior Resident Inspector
- (269) 465-5353
Ivy Netzel, Resident Inspector
- (269) 465-5353
Eric Duncan, Branch Chief
- (630) 829-9628
Steve Burton, Inspection Procedure 95002 Team Leader
- (763) 295-2066
Agenda
Review of Reactor Oversight Process
Discussion of D.C. Cook Performance
Inspection Procedure 95002 Inspection Results
Licensee Response and Remarks
NRC Closing Remarks
NRC Available to Address Public Questions
NRC Performance Goals
Maintain safety and protect the environment
Enhance public confidence
Improve effectiveness, efficiency, and realism of processes and decision making
Reduce unnecessary regulatory burden
Regulatory Framework REACTOR SAFETY PUBLIC HEALTH AND SAFETY AS A RESULT OF CIVILIAN NUCLEAR REACTOR OPERATION INITIATING EVENTS MITIGATING SYSTEMS BARRIER INTEGRITY EMERGENCY PREPAREDNESS PUBLIC RADIATION SAFETY OCCUPATIONAL RADIATION SAFETY PHYSICAL PROTECTION Cornerstones RADIATION SAFETY SAFEGUARDS NRCs Overall Safety Mission HUMAN PERFORMANCE SAFETY CONSCIOUS WORK ENVIRONMENT PROBLEM IDENTIFICATION AND RESOLUTION Cross-Cutting Areas Strategic Performance Areas
Reactor Oversight Process Safety Cornerstones Baseline Inspection Results Significance Threshold Action Matrix Significance Threshold Performance Indicator Results Regulatory Response Strategic Performance Areas Safety Cornerstones Baseline Inspection Results Significance Threshold Action Matrix Significance Threshold Performance Indicator Results Regulatory Response Strategic Performance Areas
Significance Threshold Performance Indicators Green:
Only Baseline Inspection White:
May increase NRC oversight Yellow:
Requires more NRC oversight Red:
Requires more NRC oversight Inspection Findings Green:
Very Low safety issue White:
Low to moderate safety issue Yellow:
Substantial safety issue Red:
High safety issue
Action Matrix Concept Licensee
Response
Regulatory
Response
Degraded Cornerstone Multiple/Rep.
Degraded Cornerstone Unacceptable Performance Increasing Safety Significance Increasing NRC Inspection Efforts Increasing NRC/Licensee Management Involvement Increasing Regulatory Actions
Purpose of Todays Meeting
Provide a public forum for the discussion of Provide a public forum for the discussion of D.C. Cook performance D.C. Cook performance
NRC to discuss D.C. Cook performance issues NRC to discuss D.C. Cook performance issues identified during the IP 95002 inspection identified during the IP 95002 inspection
D.C. Cook management will respond to the D.C. Cook management will respond to the information presented and inform the NRC of information presented and inform the NRC of new or existing programs to maintain or new or existing programs to maintain or improve their performance improve their performance
D.C. Cook Performance Summary
AEP has operated D.C. Cook in a manner that preserves public health and safety. All cornerstone objectives are being met.
Unit 1 is in the Regulatory Response column of the Action Matrix.
Unit 2 is in the Degraded Cornerstone column of the Action Matrix. Two Unit 2 White performance indicators at the end of the assessment period represented a moderate degradation in safety performance.
One substantive cross-cutting issue in the Problem Identification and Resolution area remains open.
NRC continues to conduct baseline inspections at D.C. Cook for the assessment period and performed a supplemental inspection to review the White performance indicators.
White Performance Indicators
Two Unit 2 White performance indicators in the Two Unit 2 White performance indicators in the Initiating Events cornerstone were identified during Initiating Events cornerstone were identified during the 2003 assessment period placing Unit 2 in the the 2003 assessment period placing Unit 2 in the Degraded Cornerstone column of the Action Matrix.
Degraded Cornerstone column of the Action Matrix.
A White performance indicator in the Unplanned A White performance indicator in the Unplanned Scrams Per 7000 Critical Hours area was identified in Scrams Per 7000 Critical Hours area was identified in 4Q03.
4Q03.
A White performance indicator in the Scrams With A White performance indicator in the Scrams With Loss of Normal Heat Removal area was first Loss of Normal Heat Removal area was first identified in 2Q03 and updated in 4Q03 to reflect identified in 2Q03 and updated in 4Q03 to reflect crossing the Green/White threshold in 3Q02.
crossing the Green/White threshold in 3Q02.
D.C. Cook Performance Indicators REACTOR SAFETY PUBLIC HEALTH AND SAFETY AS A RESULT OF CIVILIAN NUCLEAR REACTOR OPERATION INITIATING EVENTS MITIGATING SYSTEMS BARRIER INTEGRITY EMERGENCY PREPAREDNESS PUBLIC RADIATION SAFETY OCCUPATIONAL RADIATION SAFETY PHYSICAL PROTECTION Cornerstones RADIATION SAFETY SAFEGUARDS NRCs Overall Safety Mission Strategic Performance Areas Unplanned Scrams Scrams With Loss of Normal Heat Removal Drill/Exercise Performance High Pressure Injection System Unavailability Heat Removal System Unavailability Safety System Functional Failures Unplanned Power Changes Emergency AC Power System Unavailability Personnel Screening Program Residual Heat Removal System Unavailability Reactor Coolant System Activity ERO Drill Participation Reactor Coolant System Leakage Alert and Notification System RETS/ODCM Radiological Effluent Occupational Exposure Control Effectiveness FFD/Personnel Reliability Program Protected Area Equipment Performance Indicators
D.C. Cook Supplemental Inspection Activities
A Supplemental Inspection to review the Scrams A Supplemental Inspection to review the Scrams With Loss of Normal Heat Removal White With Loss of Normal Heat Removal White performance indicator was conducted in accordance performance indicator was conducted in accordance with IP 95001, Inspection For One or Two White with IP 95001, Inspection For One or Two White Inputs in a Strategic Performance Area, and was Inputs in a Strategic Performance Area, and was completed on November 21, 2003.
completed on November 21, 2003.
A Supplemental Inspection to review the White A Supplemental Inspection to review the White finding in the Public Radiation cornerstone of the finding in the Public Radiation cornerstone of the Radiation Safety Strategic Performance Area in Radiation Safety Strategic Performance Area in accordance with IP 95001 is in progress and accordance with IP 95001 is in progress and scheduled to be completed next week.
scheduled to be completed next week.
D.C. Cook Supplemental Inspection Activities
A Supplemental Inspection to collectively review the A Supplemental Inspection to collectively review the Scrams With Loss of Normal Heat Removal and Scrams With Loss of Normal Heat Removal and Unplanned Scrams Per 7000 Critical Hours White Unplanned Scrams Per 7000 Critical Hours White performance indicators was conducted from April 19 performance indicators was conducted from April 19 to April 30, 2004 to April 30, 2004
Inspection conducted in accordance with IP 95002, Inspection conducted in accordance with IP 95002, Inspection For One Degraded Cornerstone Or Any Inspection For One Degraded Cornerstone Or Any Three White Inputs On A Strategic Performance Three White Inputs On A Strategic Performance Area Area
D.C. Cook Inspection Procedure 95002 Inspection Objectives
To provide assurance that the root causes and To provide assurance that the root causes and contributing causes are understood for the individual contributing causes are understood for the individual and collective performance issues.
and collective performance issues.
To independently assess the extent of condition and To independently assess the extent of condition and the extent of cause for the individual and collective the extent of cause for the individual and collective performance issues.
performance issues.
To provide assurance that licensee corrective actions To provide assurance that licensee corrective actions for the performance issues are sufficient to address for the performance issues are sufficient to address the root causes and contributing causes, and to the root causes and contributing causes, and to prevent recurrence.
prevent recurrence.
D.C. Cook Inspection Procedure 95002 Inspection Results
The issues were inspector-identified and self-revealing The issues were inspector-identified and self-revealing
The issues were evaluated from a risk perspective The issues were evaluated from a risk perspective
Prior trends were not evaluated with respect to the collective Prior trends were not evaluated with respect to the collective nature of the scrams nature of the scrams
Prior opportunities for identifying the causal factors for the Prior opportunities for identifying the causal factors for the scrams were not recognized scrams were not recognized
A systematic method was used for evaluating the causal A systematic method was used for evaluating the causal factors factors
The evaluation was completed at a level of detail The evaluation was completed at a level of detail commensurate with the safety significance of the issue commensurate with the safety significance of the issue
D.C. Cook Inspection Procedure 95002 Inspection Results
Corrective actions to address the contributing causes were Corrective actions to address the contributing causes were appropriate appropriate
Integration of corrective action items with the recovery plan Integration of corrective action items with the recovery plan was inconsistent was inconsistent
Traditional schedules for completion & measures for success Traditional schedules for completion & measures for success had not been established had not been established
Key performance indicators and managerial controls were Key performance indicators and managerial controls were established that could be effective in managing the corrective established that could be effective in managing the corrective actions actions
The inspectors extent of condition and extent of cause review The inspectors extent of condition and extent of cause review identified no significant deficiencies identified no significant deficiencies
D.C. Cook Inspection Procedure 95002 Inspection Results Summary Summary
Proper integration of the recovery plan and the corrective Proper integration of the recovery plan and the corrective action program is paramount to ensure success with correcting action program is paramount to ensure success with correcting the identified causal factors the identified causal factors
Of the causal factors identified, a common denominator was Of the causal factors identified, a common denominator was an ineffective corrective action program an ineffective corrective action program
Plant events not collectively evaluated to identify corrective Plant events not collectively evaluated to identify corrective actions to improve plant performance actions to improve plant performance
Licensee Response and Remarks Joseph Jensen Site Vice-President Indiana Michigan Power Company
Contacting the NRC
Report an emergency
(301) 816-5100 (call collect)
Report a safety concern:
(800) 695-7403
Allegation@nrc.gov
General information or questions
www.nrc.gov
Select What We Do for Public Affairs
Reference Sources
Reactor Oversight Process
http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html
Public Electronic Reading Room
http://www.nrc.gov/reading-rm.html
Public Document Room
1-800-397-4209 (Toll Free)
Public Comment Opportunity