Z Indiana Michigan Power Company INDIANA 500 Circle Drive MICHIGAN Buchanan, MI 49107-1395 POWER SAFEGUARDS INFORMATION waeptcom April 28, 2004 AEP:NRC:2073-12 Docket Nos:
50-315 50-316 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001
SUBJECT:
Supplemental Response to the April 29. 2003. Orders to Donald C. Cook Nuclear Plant Unit 1 and Unit 2 The NRC issued an Order dated April 29, 2003, Requiring Compliance with Revised Design Basis Threat ("Order EA-03-086" or "Order") and other security related Orders (collectively "Orders") for the Donald C. Cook Nuclear Plant (CNP). This Supplemental Response of Indiana Michigan Power Company (I&M) to Order EA-03-086 supplements the previous response dated May 30, 2003, that I&M filed pursuant to 10 CFR § 50.4 and Section III, Conditions A.1, B.1 and B.2,.
Order EA-03-086 imposes license conditions on nuclear power plants licensed pursuant to the Atomic Energy Act of 1954 and Title 10 of the Code of Federal Regulations.Section III.A of the Order requires licensees to revise their physical security plans and safeguards contingency plans to provide protection against the revised design basis threat (DBT) set forth in Attachment 2 to the Order.Section III.A also requires licensees to revise the security force training and qualification plan to implement the revised DBT. These revised plans, along with an implementation schedule, were required to be submitted to the Commission for review and approval no later than April 29, 2004.
In accordance with the Order and 10 CFR § 50.4, I&M is submitting this Supplemental Response for the above-mentioned licensed facility. This submittal includes, as Attachment A, revisions to the CNP Physical Security Plan, the Contingency Plan, and the Training and Qualification Plan as required by Order EA-03-086. These plans contain the integrated commitments to comply with NOTE: THE ATTACHMENTS TO THIS LETTER CONTAIN "SAFEGUARDS INFORMATION" AND MUST BE PROTECTED ACCORDINGLY. UPON SEPARATION OF THE ATTACHMENTS, THIS LETTER IS "DECONTROLLED."
SAFEGUARDS INFORMATION 4 \\e
U.S. Nuclear Regulatory Commission AEP:NRC:2073-12 April 28, 2004 Page 2 Order EA-03-086 and the other security related Orders issued on February 25, 2002, January 7, 2003, and April 29, 2003. As a result, these plans supersede previous submittals of I&M in these areas, including those related to the February 25, 2002, January 7, 2003, and April 29, 2003, Orders. I&M will continue to implement the provisions of those previous submittals except to the extent that they are superseded by these plans. All changes that have been or will be made have been evaluated to ensure that they do not compromise plant safety.
I&M has developed these plans to be consistent with NEI-03-01 (Revision 1),
Nuclear Power Plant Access Authorization Program (April 2004); NEI-03-09 (Revision 2 (draft)), Security Officer Training Program (April 2004); and NEI-03-12 (Revision 2 (draft)), Template for the Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, [and Independent Spent Fuel Storage Installation Security Program] (April 2004). The schedule for completing those actions, which includes the identification of major transitional activities, is provided in Attachment B to this submittal. To facilitate the NRC's review, any provisions that are different from NEI-03-12 are identified and the justification provided in Attachment C, Deviations from NEI-03-12, to this submittal. Attachment D, Previous Exemptions to 10 CFR Part 73, is a listing of any exemptions to 10 CFR Part 73 previously granted to I&M and an explanation of their status under the plans hereby submitted. Attachment E, Justification for Alternatives, includes the justification for any of the alternatives provided in NEI-03-12 or in "NRC Guidance on Implementation of the April 2003 Revised Design Basis Threat" that I&M has adopted.
Because there are still a few open issues to be resolved with the NRC regarding certain provisions of NEI-03-12, I&M will supplement this response, if necessary, upon final resolution of those issues to conform with NEI-03-12 as finally approved by the NRC. However, with the filing of these plans, I&M will be implementing its revised protection strategy and completing plant modifications and security personnel training pursuant to these plans to ensure that implementation will be completed by October 29, 2004, as required by the Orders. Upon completion of the implementation of these plans, I&M will be in compliance with all applicable security requirements. For the purpose of complying with the requirements of 10 CFR Part 73 to conduct an annual audit, the date of the letter that will be submitted to the NRC pursuant to Order EA-03-086 certifying that implementation of the plans is complete will be the effective date for determining commencement of the annual audit requirement period.
Because of the requirement for these plans to be fully implemented by October 29, 2004; the need to integrate the requirement of the revised DBT Order with the Orders issued February 25, 2002, January 7, 2003, and April 29, 2003; and the
U.S. Nuclear Regulatory Commission AEP:NRC:2073-12 April 28, 2004 Page 3 Commission's determination that it would be appropriate to exercise enforcement discretion to accommodate any transitional issues which may arise as licensees, in good faith, take reasonable actions to implement the specific requirements of the Orders, I&M requests that enforcement discretion be exercised during the transition period until full implementation of the plans is accomplished and the physical plant modifications and security force training are complete. At that time, the revised plans will be fully implemented and the exercise of enforcement discretion will no longer be necessary.
Respectfully submitted, Site Vice President HLE/jen c w/o attachments:
J. L. Caldwell - NRC Region III K. D. Curry - AEP Ft. Wayne INPO Records Center J. T. King - MPSC J. G. Lamb - NRC Washington DC MDEQ - WHMDIHWRPS NRC Resident Inspector
U.S. Nuclear Regulatory Commission April 28, 2004 Page 4 AEP:NRC:2073-12 AFFIRMATION I, Joseph N. Jensen, being duly sworn, state that I am Site Vice President of Indiana Michigan Power Company (I&M), that I am authorized to sign and file this request with the Nuclear Regulatory Commission on behalf of I&M, and that the statements made and the matters set forth herein pertaining to I&M are true and correct to the best of my knowledge, information, and belief.
Indiana Michigan Power Company Site Vice President SWORN TO AND SUBSCRIBED BEFORE ME JULIE E. NEWMILLER Notary Public, Berrien County, Ml My Commission Expires Aug 22,2004 C-5?6v
.My Commission Expires I;, _
,: