Ltr,Bulletin 2003-01, Potential Impact of Debris Blockage on Emergency Sump Recirculation at Pressurized-Water Reactors.
ML041110660
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 04/20/2004
From: Mozafari B
NRC/NRR/DLPM/LPD2
To: Young D
Florida Power & Light Co
mozafari B, NRR/DLPM, 415-2020
References
BL-03-001, TAC MB9569
Download: ML041110660 (4)


Text

April 20, 2004 Mr. Dale E. Young, Vice President Crystal River Nuclear Plant (NA1B)

ATTN: Supervisor, Licensing &

Regulatory Programs 15760 West Power Line Street Crystal River, FL 34428-6708

SUBJECT:

CRYSTAL RIVER UNIT 3 - RESPONSE TO NRC BULLETIN 2003-01, POTENTIAL IMPACT OF DEBRIS BLOCKAGE ON EMERGENCY SUMP RECIRCULATION AT PRESSURIZED-WATER REACTORS (TAC NO.

MB9569)

Dear Mr. Young:

This letter acknowledges receipt of your response dated August 8, 2003, to Nuclear Regulatory Commission (NRC)Bulletin 2003-01, Potential Impact of Debris Blockage on Emergency Sump Recirculation at Pressurized-Water Reactors, dated June 9, 2003. The NRC issued Bulletin 2003-01 to all pressurized-water reactor (PWR) licensees requesting that they provide a response, within 60 days of the date of Bulletin 2003-01, that contains either the information requested in the following Option 1 or Option 2 stated in Bulletin 2003-01:

Option 1: State that the emergency core cooling system (ECCS) and containment spray system (CSS) recirculation functions have been analyzed with respect to the potentially adverse post-accident debris blockage effects identified in this bulletin, taking into account the recent research findings described in the Discussion section, and are in compliance with all existing applicable regulatory requirements.

Option 2: Describe any interim compensatory measures that have been implemented or that will be implemented to reduce the risk which may be associated with potentially degraded or nonconforming ECCS and CSS recirculation functions until an evaluation to determine compliance is complete. If any of the interim compensatory measures listed in the Discussion section will not be implemented, provide a justification. Additionally, for any planned interim measures that will not be in place prior to your response to this bulletin, submit an implementation schedule and provide the basis for concluding that their implementation is not practical until a later date.

You provided an Option 2 response. You stated in your response that you will implement, or have implemented, several interim compensatory measures and provided schedules for their implementation. We have considered your Option 2 response for compensatory measures that have been or will be implemented to reduce the interim risk associated with potentially degraded or nonconforming ECCS and CSS recirculation functions until an evaluation to determine compliance is complete. Based on your response, we consider your actions to be

D. Young complete. Please retain any records of your actions in response to Bulletin 2003-01, as the NRC staff may conduct subsequent inspection activities regarding this issue.

Should you have any questions, please contact me at 301-415-1419 or the lead PM for this issue, John G. Lamb, at 301-415-1446.

Sincerely,

/RA/

Brenda L. Mozafari, Senior Project Manager, Section 2 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-302

ML041110660 NRR-106 OFFICE PDII-2/PM PDII-2/LA SC/SPLB* PDII-2/SC NAME BMozafari EDunnington SWeerakkody WBurton DATE 3/26/04 3/24/04 3/29/04 4/19/04 Mr. Dale E. Young Crystal River Nuclear Plant, Unit 3 Florida Power Corporation cc:

Mr. R. Alexander Glenn Chairman Associate General Counsel (MAC-BT15A) Board of County Commissioners Florida Power Corporation Citrus County P.O. Box 14042 110 North Apopka Avenue St. Petersburg, Florida 33733-4042 Inverness, Florida 34450-4245 Mr. Jon A. Franke Mr. Michael J. Annacone Plant General Manager Engineering Manager Crystal River Nuclear Plant (NA2C) Crystal River Nuclear Plant (NA2C) 15760 W. Power Line Street 15760 W. Power Line Street Crystal River, Florida 34428-6708 Crystal River, Florida 34428-6708 Mr. Jim Mallay Mr. Daniel L. Roderick Framatome ANP Director Site Operations 1911 North Ft. Myer Drive, Suite 705 Crystal River Nuclear Plant (NA2C)

Rosslyn, Virginia 22209 15760 W. Power Line Street Crystal River, Florida 34428-6708 Mr. William A. Passetti, Chief Department of Health Senior Resident Inspector Bureau of Radiation Control Crystal River Unit 3 2020 Capital Circle, SE, Bin #C21 U.S. Nuclear Regulatory Commission Tallahassee, Florida 32399-1741 6745 N. Tallahassee Road Crystal River, Florida 34428 Attorney General Department of Legal Affairs Mr. Richard L. Warden The Capitol Manager Nuclear Assessment Tallahassee, Florida 32304 Crystal River Nuclear Plant (NA2C) 15760 W. Power Line Street Mr. Craig Fugate, Director Crystal River, Florida 34428-6708 Division of Emergency Preparedness Department of Community Affairs Steven R. Carr 2740 Centerview Drive Associate General Counsel - Legal Dept.

Tallahassee, Florida 32399-2100 Progress Energy Service Company, LLC Post Office Box 1551 Raleigh, North Carolina 27602-1551