NUREG-1021. Draft Revision 9 ES-301 Administrative Topics Outline Form ES-301-1 Facility: CCNPP Date of Examination: 03/01/2004 Examination Level (circle one): RO / SRO Operating Test Number:

Administrative Topic Describe activity to be performed (see Note)

A.1 .a 2.1.19 3.0 Ability to use plant computer to obtain and evaluate parametric Conduct of information on plant system or component status Operations Enter feed flow correction factors into the plant computer per OI-50A. verifvina NI calibration.

< 1 A . l .b 2.1.25 2.8 Conduct of Ability to obtain and interpret station reference materials such as graphs, monographs, and tables which contain performance Operations data Verifv shutdown marain in mode 3 with one stuck CEA A. 2 2.2.13 3.6 Knowledge of tagging and clearance procedures Equipment Control Verify tagout boundaries per NO-1-112 A. 3 Radiation Control A.4 2.4.43 2.8 Knowledge of emergency communications and techniques Emergency Plan Recall Emergency Response Organization per ERPIP-105 NOTE: All items (5 total) are required for SROs. RO applicants require only 4 items unless they are retaking only the administrative topics, when 5 are required.

ES-301 Control Room/ln-Plant Svstems Outline Form ES-301-2 Facility: CCNPP Date of Examination: 03/01/2004 Exam Level (circle one): RO / SRO(I) / SRO(U) Operating Test No.:

Control Room Systems (8 for RO; 7 for SRO-I; 2 or 3 for SRO-U)

Type Safety System/JPM Title Code* Function NJ

a. CVCS/Shift Charging Pumps per OI-2A (Discharge relief lifts on 2 started pump) 004A2.22 3.2/3.1 3
b. ECCS/Test LPSl check valves per STP-0-65-1

, 006A4.02 4.013.8

&primary

c. RHRAnitiate SDC (An RCS leak develops when suction MOVs

~ _ _ _

are oDened) 005A1.05 3.3/3.3

d. Emergency Diesel Generatorsnransfer4 KV bus from an EDG to Offsite Power 064A4.06 3.9/3.9 DJA,S Control Rod Drive System/Realign a CEA (CEA drops when e-) moved) 003AA1.02 3.613.4 M,AJS
f. Verify Containment Spray Actuation 026A4.01 4.W4.3 NS
g. Process RMS/Test Containment Atmosphere Rad. Mon. per STP-0-33-1 073A4.03 3.1/3.2 NJS a
h. Secure a Circulating Water Pump per OI-14A 075A2.02 2.5/2.7

In-Plant Systems (3 for RO; 3 for SRO-I; 3 or 2 for SRO-U)

1. Manually Override SW valves 068AA1.21 3.9/4.1 7 secondary
j. ESFAS/de-energize ESFAS cabinet per 01-34 013K2.01 3.6/3.8
k. Liquid RadWaste/Perform flush of Rad. Monitor per Ol-17C.

(Discharge valve shuts during- flush) 068A3.02 3.W3.6 T I NUREG-1021,Draft Revision 9

ES-301 Control Roomlln-Plant Svstems Outline F o ES-301-2

~

Facility: CCNPP Date of Examination: 03/01/2004 Exam Level (circle one): RO / SRO(I) / SRO(U) Operating Test No.:

Control Room Systems (8 for RO; 7 for SRO-I; 2 or 3 for SRO-U)

Type Safety SystemlJPM Title Code* Function

a. CVCS1Shift Charging Pumps per OI-2A (Discharge relief lifts on 2 started pump) 004A2.22 3.213.1 3
b. ECCS/Test LPSl check valves per STP-0-65-1 006A4.02 4.013.8 4-primary
c. RHR1lnitiate SDC (An RCS leak develops when suction MOVs are opened) 005A1.05 3.313.3
d. Emergency Diesel Generatorsrrransfer 4KV loads from an EDG to Offsite Power 064A4.06 3.913.9
e. Control Rod Drive System1Realign a CEA (CEA drops when moved) 003AA1.02 3.6/3.4
f. Verify Containment Spray Actuation 026A4.01
g. Process RMS/Test Containment Atmosphere Rad. Mon. per STP-0-33-1 073A4.03 3.1/3.2 h.
1. Manually Ovemde SW valves D 4 068AA1.21 secondary D 2
j. ESFAS/de-energize ESFAS cabinet per 01-34 013K2.01 3.6i3.8 NlRA 9
k. Liquid RadWaste/Perforrn flush of Rad. Monitor per 01-17C.

(Discharge valve shuts during flush) 068A3.02 3.W3.6

NUREG-1021, Draft Revision 9 ES-301 Control Roodln-Plant Systems Outline Form ES-301-2 acility: CCNPP Date of Examination: 03/01/2004

,xam Level (circle one): RO / SRO(I) / SRO(U) Operating Test No.:

Control Room Systems (8 for RO; 7 for SRO-I; 2 or 3 for SRO-U)

Safety SystemlJPM Title Function

. CVCS/Shift Charging Pumps per 01-2A (Discharge relief lifts on 2 started pump) 004A2.22 3.213.1 6

b. Emergency Diesel GeneratorslTransfer 4 'KV bus from an EDG to Offsite Power 064A4.06 3.913.9 ~

4-primary RHFUlnitiate SDC (An RCS leak develops when suction MOVs are opened) 005A1.05 3.3/3.3 1.

2.

B.

h.

H In-Plant Systems (3 for RO; 3 for SRO-I; 3 or 2 for SRO-U)

D 4

1. Manually Override SW valves secondary 068AAl.I2 4.414.4 N,RlA 9
j. Liquid RadWastelPerform flush of Rad. Monitor per 01-17C.

(Discharge valve shuts during flush) 068A3.02 3.613.6

  • Type Codes; (D)irect from bank, (M)odified from bank, (N)ew, (A)ltemate path, (C)ontrol room, (S)imulator, (L)ow-Power, (R)CA

. .