November 2002 Retake Exam 50-400/2002-302 Draft JPMs
ML040560231
Person / Time
Site: Harris 
Issue date: 11/21/2002
From:
Carolina Power & Light Co
To: Ernstes M
NRC/RGN-II
References
50-400/02-302
Download: ML040560231 (34)


Text

Final Submittal (Blue Paper)

HARRIS EXAM 50-400/2002-302 OPERATING TEST)

NOVEMBER 21,2002 DRAFT JPMS

HARRIS NUCLEAR PLANT 2002 SWQ NRC RETEST JPMS

TABLE OF CONTENTS SlMULATOR JPMS

1. B.1.a - Emergency Boratian
2. B.1.b - Isolate Ruptured SG - MSIV Will NOT Close
3. B.1.c - Restoring the Control Room Area HVAC System to Normal After A Control Koom Isolation Signal IN PLANT JPMS
4. B.2.a - Energize A Dead Bus With A Diesel Locally
5. B.2.b - Emergency Makeup To Fuel Fools From Emergency Service Water System

JPM-B.l.a H A N S Retake REGION I1 INITIAL LICENSE EXAMINATION JOB PEWBMANCE MEASURE JPM -B. 1.a Emergency Booration CANDIDATE:

EXAMINER:

Page 1 of 7 Rev Date 10/28/02

JF'M-B. I.a HARRIS Retake REGION II INITIAL LICENSE EXAMINATION JOB PERFORMANCE IvEASURE TASK:

Perform AOP-002, Emergency Boration ALTERNATE PATH:

Emergency Boration using RWST path via LCV-115B and/or LCV-l15D, to the CSIP suction FACILITY JFM NUMBER CR-037 KA:

004A2.14 IMPORTANCE:

SRO 3.9 RO 3.8 KA STATEMENT:

Ability to (a) predict the impacts ofthe following malfunctions or operations on the CVCS; and (b) based on those predictions, use procedures to correct, control, or mitigate the consequences of those malfunctions or operations: Emergency boration At least 90 gpm Boration flow as indicated on F%-l22A.1 is being delivered from the running Charginglsafety Injection Pump to the Reactor coolant System TASK STANDARD:

SIMULATOR X INPLANT P R E F E W D EVALUATION LOCATION:

P E W O M X

SIMULATE PREFERRED EVALUATION METHOD:

REFERENCES:

AOP-002, Emergency Boration VALIDATION TIME:

10 MINUTES TIME CRITICAL:

No CANDIDATE:

START TIME:

FINISH TIME:

PERFORMANCE TIME:

MINUTES PERFORMANCE RATING:

SAT UNSAT COMMENTS:

EXAMINER:

Signature Date Page 2 of7 Rev Date 10/28/02

JPM-B.1.a H A M S Retake TOOLS / EQUIPMENr / PROCEDURE§ NEEDED:

e o

Initialize to a 100% power IC-19 (OK to a saved IC with the following setup)

Fail two rods to insert on a Keactor Trip.

o MFP GW16A rod D-4 severity 220 steps (control bank C) o MFP CRF16B rod H-14 severity 220 steps (control bank B)

Fail the following valves shut:

o 1CS-278 Emergency Boration Valve (OW XA2II50 as is) o FCV-lI3A Boric Acid to Blender (OW XA2IlS1 as is)

Perform a manual reactor trip.

o PATH-1 until transition to EPP-004 directions to borate for rods failing to insert.

FREEZE the simulator in a stable condition. (An KO maybe required to maintain the plant stable and silence annunciators not associated with this JPM)

When candidate is ready, place simulator in RUN.

o AOP-002, Emergency Boration e

o e

READ TO OPERATOR INSTRUCTIONS TO CANDIDATE:

I will explain the initial conditions and state the task to be performed. AI1 control room steps shall be perfomied for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed or asked by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task, return the handout sheet I provide you.

INITIAL CONDITIONS:

The reactor has just tripped from IO0 percent power.

INITIATING CUE(§):

You are the Kcactor Operator. Observation of DKPI following the reactor trip indicates two control rods are stuck out. EPP-EOP-004 is being performed and the SCO directs you to refer to AOP-002 and initiate emergency boration.

Page 3 of 7 Rev Date 10!28/02

JPM-B.1.a HARRIS Retake

  • DENOTES CRITICAL STEP CANDIDATE SHOULD OBTAIN A CQPY OF AOP-002 1

2 3

4 5

6 NA 3.O NA 3.1 3.2 3.2.a RNO Obtain procedure Go to Section 3.0, OPERATOR ACTlQNS.

NOTE: This procedure contains no immediate actions Start a Boric Acid pump ESTABLISH buration flowpath using 1CS-278 as follows:

a. OPEN 1CS-278, Emergency Boric Acid Addition GO TO Step 3 Obtain current copy of AOP-002 Refers to Section 3.0 Reads note and continues with procedure Locates a Boric Acid Pump Control Switch and takes it to START Pump running indication light changes from green to red Locates and 16s-278 Control Switch and takes it to OPEN Valve is failed in the CLOSED position.

1CS-278 position indication light remains green.

I Determines that 1CS-278 will not open and follows the response not obtained instructions-go to step 3 Page 4 of 7 Rev Date 10/28/02

__r_

JPM STEF 4

8 IO

____e PROC STEP 3.3 l.3.a RNO 1.6

.6.a cont)

ELEMENT ESTABLISH boration flowpath using FCV-113-as follows:

a. OPEN the following valves ICs-283 Boric Acid to Boric Acid Blender FCV-I 13A
O TO Step 6 STAIBLISH boration Low from RWST as oliows
a. OPEN the following valves e

1CS-291, Suction From RWST LCV-1 l5B a

1'3-292, Suction From RWST LCV-115D STANDARD Locates FCV-113A Control Switch and takes it to OPEN Determines that IFCV-I l3A will not open and follows the response not obtained instructions-go to step 6 Locates LCV-I 15B and takes the controi switch to OPEN Locates LCV-1 151) and takes the control switch to OPEN PM-B. 1.a HARRIS Retake NOTES Valve is failed in tht CLOSED position.

IFCV-113A indication light remains green.

[Critical that LCS-291 and/or LCS-292 are 3pened -parallel path from RWST)

"osition indication ight for CCV-1158

hanges from green o red

'osition indication ight for LCV-1 15D

hanges from green o red SAT I UMSAl Page 5 of 7 Rev Date 10128XI2

JPM STEP "111 12

  • I3 14 15 PROC STEP 3.6.b 3.6.b
cant)

J.6.C VA I.G.d ELEMENT SHUT the following valves 0

ICs-165, YCT Outlet LCV-I ISC 0

IC§-166, VCT Outlet LCV-I 1%

VERIFY and MANTAIN it least 90 gpm charging inti6 required boration is

ompleted.

OW to RCS (FI-122A. I )

XUTION - Low VCT eve1 is a precursor to gas inding the CSIPs

HECK VCT level greater han or equal to 5% and can

,e maintained on scale STANDARD Locates 1CS-165, VCT Outlet LCV-1 15C and takes the control switch to CLOSE Locates 1CS-166, YCT Outlet LCV-1 15E and takes the control switch to CLOSE Locates Controller FK-122.1 charging flow, and places it in manual.

Increases the output to

> 90 gpm and monitors charging flow on FI-122A1.

Reads caution and continues with procedure Locates LI-I 15 and monitors YCT level IPM-B. 1.a HARRIS Retake (Critical that IC§-165 and/or IC§-166 arefis closed-series path from VCT)

Position indication light for LCV-11SC changes from red to green Position indication light for LCV-I 15E changes from red to green SAT I UNSAT -

rA§K COMPLETE WEEK 5 90 GPM FLOWRATE OF BORIC ACID FROM RWST TO RCS S BEING.MAINTAIR'ED AND MONITORED STOP TIME:

Page 6 of?

Rev Date 10i28i02

JPM-B. I.a H A M S Retake CANDIDATE CUE SHEET (TO BE RETURNED TQ EXAMIhTR UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

Ilie reactor has just tripped from 100 percent power.

INITIATING CUE@):

You are the Reactor Operator. Observation of DRPI following the reactor trip indicates two control rods are stuck out. EPP-EOP-004 is being perfomed and the SCO directs you to refer to AOP-002 and initiate emergency boration.

Page 7 of 7 Rev Date 10/28/02

JF'M-B.1.b HARRIS Retake rnCION II INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE JPM -B. 1.b ISOLATE RUBTI.IREB SG;--MSIV WILL NOT CLOSE CANDIDATE:

Page 1 of 9 Rev Date 10/28/02

JPM-B.1.b H A N S Retake REGION I1 INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE TASK:

ALTERNATE PATH:

Implement EOP-PATH 2. Steam Generator 'rube Rupture Ruptured SG MSIV Will NOT isolate. Operator performs a manual isolation of intact SG's from the ruptured SG and minimizes the steani flow from the ruptured SG FACILITY JPM NUMBER:

CR-105 KA:

035A2.01 IMPORTANCE:

SRO 4.6 RO 4.5 MA STATEMENT:

Ability to (a) predict the impacts of the following malfunctions or operations on the SG; and (b) based on those predictions, use procedures to correct, control, or mitigate the consequences of those malfunctions or operations: Faulted or ruptured S/Gs Steam Generator B isolated per PATH-2 and PATH-2 Guide TASK STANDARD:

PREFERRED EVALUATION LOCATION:

SIMULATOK X INPLANT PERFORM X

SIMULATE PREFERRED EVALUATION METHOD:

REFERENCES:

EOP-PATH 2 GUIDE VALIDATION TIME:

15 MINTIJTES TIME CRITICAL:

No

~

CANDIDATE:

STAKT TIME:

FINISH TIME:

PERFOWANCE TIME:

MINUTES PERFORMANCE RATING:

SAT UNSAT COMMENTS:

EXAMINER:

Signature Date Page 2 of 9 Rev Date 10/28!02

IPM-B.1.b HARRIS Retake TOOLS f EQUIPMENT / PROCEDURES NEEDED:

o o

Initialize to a 100% power IC-19. (OR to a saved IC with the following setup)

Fail B Steam Generator MSIV 1MS-82 o ORP XB21037 as is (will not shut from MCB switch) o iMFP MSS05B fail to close (will not shut on Main Steam Isohtion Signal)

Insert an SGTR of sufficient size to require an SI o MFP SGNOSB final severity 160 Select GRID 5 on RM-11 Complete PATH-I until the first PATH-2 transition point. (Step 16--Secondary Radiation Normal.) Transition to PATH-2 tlvough step 5.

J Re-OPEN MS-70 and MS-92 (ifclosed to reduce AFW) and minimize AFW flow Clear all annunciators, RM-I 1 alarms, and stabilize the plant When candidate is ready, place simulator in RUN.

o 0

o o FREEZE the simulator PArH-2 GUIDE READ TO OPERATOR INSTRUCTIONS TO CANDIDATE:

I will explain the initial conditions and state the task to be performed. All control room stips shall be performed for this JPM, including any required communications.

I will provide initiating cues and reports on other actions when directed or asked by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task, return the handout sheet I provide you.

INITIAL CONDITIONS:

The Reactor was at 100% power when a tube rupture exceeds the VCT makeup capability. l h e crew manually Safety Injected and have performed the actions of PATV-1.

A tr,ansilion to PATH-2 was made and the B SG has been identified as ruptured by Main Steam line radiation readings. PATH-2 step 5 has just been completed.

INITIATING CIJE(S):

You are the Balance of Plant Operator. You are to continue with PATH-2 starting at step 6 until otherwise directed. Other operators have the foldout responsibilities.

Page 3 of 9 Rev Date 10!28!02

JPM-B. I.b HARRIS Retake

  • DENOTES CRfTICAL STEP STANDARD CUE CANDIDATE SHOULD OBTAIN A COPY OF PATH-2 STEPS 1-5 of PATH-2 have been completed "3

4 6

6.b Obtain procedure CAUTION At least one Sei must be maintained available for RCS cooldown s Ifthe TDAFW pump is the only available source of feed flow, one steam supply valve from an intact SG must be maintained open Isolate Flow From Ruptured SG

a. Adjust ruptured Sei PORV controller setpoint to 88%

(1 145 PSIG) AND place in ALJTO Check ruptured SG PORV SHUT Obtain current copy of PATH-2 Reviews caution prior tc proceeding with step.

,ocates 1MS-60

ontroller and depresses etpoint raise pushbutton inti1 setpoint is at 88%.

Jerifies controller is in IUTO.

mates Main Steam

'ORV Position idication for PCV 308B nd verifies shut 1 MS-60 COntFOlkI retpoint AUTO pushbutton is lit

'CV 308B ndication light is

reen

§AS I W S A T Page 4 of 9 Rev Date 10!28/02

JPM-B.1.b HARRIS Retake -

SAT f UNSAT -

JPM STEF -

  • 5 ELEMENT STANDARD NOTES PRO6 STEP

_i__l 6.c 6.d 1 MS-70 indication light changes from red to green Locates control switch for 1MS-70 and shuts valve.

Shut ruptured SG steam supply valve to IDAFW pump:

SGB: IMS-70 Verify blowdown isolatior valves from ruptured SG - SHUT On AEP-I, locates indications for 1RD-20, 1BD-26, and 1BD-30 and verifies them SHUT 6

1BD-20,26, and 30 indication lights are green.

  • 7 6.e Locates control switch for 1MS-266 and shuts r.alve IMS-266 indication light changes from red to green Shut ruptured SG main steam drain isolation before MSIV:

SGB: 1MS-266 Shut ruptured SG MISV AND bypass valve.

8 6.f Locates IMS-82 control

witch and takes it to SHUT. (May initiate vlain Ste.am isolation in in attempt to shut the vlSIV.)

hdication light for 1 MS-82 does not

hange. Red indication light is still lit.

6.f RNO 30 TO Step 7 leads RNO and

ontimes with step 7 9
  • la) 7 solate Intact SG(s) From iuptured SG AND vlinimize Steam Flow Zrom Ruptured SG:
a. Shut all remaining MSIV AND bypass valves

,ocates control switches or 1MS-80 and IMS-84 nd takes them to

HUT. (May initiate dain Steam Isolation to hut valves - if MSI nitiated in step 8 valves may already he shut.)

IMS-80 and IMS-

$4 indicator lights will change from red o green.

Page 5 of 9 Rev Date 1028/02

JPM STEP

  • %I 12 CUE 13 14 15 PROC STEP 7.b 4.C ELEMENT STANDARD Place both steam dump interlock bypass switches to OFF//KESET Locates and places both Steam Dump Interlock switches to OFFRESET Use intact SG(s) PORV for all further steam dumping.

Uses A and C Steam Generator PORVs to control RCS temperature if necessary.

I JPM-H.1.h HARRIS Retake Both Steam Dump Interlock switches are in the OFFRESET position.

[EVALUATOR DISCIbETION: IF PROGRESS IN THE PROCEDURE IS NOT CONTINUING THEN CUE:]

OTHER OPEKATORS WILL MONITOR RCS TEMPERATURE AND MAKE 4DDITIONAL ADJUSTMENTS USING A & C PORVS. CONTINUE WITH PATH-2 1.d NA 1

Isolate steam release path from ruptured SG using Attachment I.

NOTE: Isolation of possible steam release paths downstream of the MSIVs may be completed in parallel with KCS cooidown and subsequent recovery actions.

Verify the following valves SHUT:

Turbine stop valves Reviews Attachment 1 to PATH-2 Guide.

Reviews NOTE and continues with procedure.

Locates valve test panel and chesks TV-I, TV-2, TV-3, and TV-4 SHUT.

All throttle valve I

indications are green.

i j

Page 6 of 9 Rev Date 10/28!02

JPM STEP 16 17 18 19 PROC STEP I (cont) 1 (cont) 1 (cont)

CUE ELEMENT Condenser steam dump valves Atmospheric steam dump valves 0

MSRshutoff AND purge valves:

1MS-15 1

LMS-I 52 IMS-161 1MS-150 IMS-163 IMS-149 Main steam to auxiliary steam isolation valve:

1 AS-244 Kadwaste Control Room) 1 STAR43ARD Locates indications on Status Light Box 1 for CNDSR STEAM DUMP PCV valves and DNDSR COOLDOWN STEAM DUMP Valves and verifies valves are shut.

Locates indications on Status Light Box 1 for ATMOSPIIERIC STEAM DUMP PCV valves and checks valves S W T.

Verifies that 1MS-151 LMS-152 iMS-149 1 MS-161 1 MS-I50 IMS-163 are SI1UT.

Contacts Radwaste Control Room and directs them to SHUT IAS-244 - Main Stearn To Auxiliary Steam Isolation Valve.

JPM-B.1.b H A N S Retake All condenser s t e m indications are green.

I I

All atmospheric I

steam dump valve indications are green.

i I

i Indication lights for IMS-149, 1MS-161, I MS-150, and IMS-163 are green IMS-15 I, 1MS-I 52, I (AS RADWASTE OPERATOR) -Understand SHUT 1AS-244 Main Steam To Auxiliary Stearn Isolaiion Valve. --- Wait a few seconds and report - 1AS-244 Main Steam To Auxiliary Steam Isolation Valve is j SHUT.

Page 7 of 9 Rev Date 10/28!02

JPM STEP 20 CUE PROC STEP 2

ELEMENT STANDARD I

Locally Shut Main Steam Deain LCV Inlet Isolations AND Orifice Inlet Isolation Valves:

Contacts AQ and directs implementation of remaining steps in sheet 2 of 2 0

Main steam drains after MSIVs (platform 10 fl above 26 1 steam tunnel):

1 MS-249 1MS-284 IMS-287 1 MS-252 IMS-319 1 MS-322 Main steam header and steam dump header drains (286 TB near condemer):

1MS-374 (north side) 1MS-377 (north side)

IMS-425 (north side) 1MS-428 (north side) lMS-433(north side) 1MS-409 (north side)

IMS-391 (west side) 1MS-394 (west side)

JPM-B.1.b H A M S Retake NOTES LO ACKNOWLEGES mQUEST TO PERFORM ATTACHMENT 1 STEPS. ALL OTHER LEMAINING STEPS WILL BE PERFORMED BY ANOTHER OPERATOR ASK COMPLETE Page 8 af 9 Rev Date 10!28/02

JPM-R. 1.b HARRIS Retake CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)

INITIAL. CONDITIONS:

The Reactor was at 100% power when a tube rupture exceeds the VCT makeup capability. The crew manually Safety Injected and have performed the actions of PATH-I. A transition to PATH-2 was made and the B SG has been identified as ruptured by Main Stem line radiation readings. PATH-2 step 5 has just been completed.

INITIATING CUE@):

You are the Balance of Plant Operator. You are to continue with PATH-2 starting at step 6 until otherwise directed. Other operators have the foldout responsibilities.

Page 9 of 9 Rev Date 10!28!02

JPM-B.1.c HARRIS Retake RJ3GION II INITIAL LICENSE EXAMINATION JOB BEWORh/lANCE MEASURE JPM-B.1.c Restoring the Control Room Area HVAG System to N ~ m a l After a Control Room Isolation Signal CANDIDATE:

EXAMINER:

Page 1 of 8 Rev Date 10/28/02

IPM-B. I.c HARRIS Retake REGION II INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE TASK:

ALTERNATE PATH:

None FACILITY JPM NUMBER:

NEW KA:

01384.02 IMPORTANCE:

SRO 4.4 RO 4.3 KA STATEMENT:

Ability to manually operate and/or monitor in the control room: Reset of ESFAS channel TASK STANDARD:

Control Room Area HVAC system returned to normal mode (no longer in Recirculation lineup) and periodic monitoring for 0 2 and CO2 is no longer required.

Return the Control Room Area Ventilation Isolation System to Normal SIMULATOR X INPLANT PERFORM X

SIMULATE PREFERRED EVALUATION LOCATION:

PREFERRED EVALUATION METHOD:

REFERENCES:

OP-173, Control Room Area W A C System VALIDATION TIME:

15 MINUTES TIME CRITICAL:

No CANDIDATE:

START TIME:

FINISH ma:

PERFORMANCE TIME:

MINUTES PERFORMANCE RATING:

SAT UNSAT COMMENTS:

EXAMINER:

Signature Date Page 2 of 8 Rev Date 10/28/02

JPM43.l.c H A W S Ketake TOOLS /EQUIPMENT / PROCEDURES NEEDED:

e e

e e

Initialize to a 100% power IC. (OR to a saved IC with the following setup)

Entcr an inadvertent SI signal Respond to SI IAW Path-l to step 28 Transition to EPP-008. Perform step 1 through step 35.b - perform Attachment 1 Plant Systems Realignment (step 8 in Attachment 1 is realign control room area HVAC per OP-173 section 8.4) e e

FREEZE the simulator e

Clear all annunciators and stabilize the plant When candidate is ready, place simulator in RUN.

e UP-173, Control Room Area HVAC System READ TO OPERATOR INSTRUCTIONS TO CANDIDATE:

I will explain the initial conditions and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed or asked by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task, return the handout sheet I provide you.

INITIAL CONDITIONS:

The plant was operating at 100% power when an inadvertent Safety Injection signal was received. The operators have performed the actions of path-1 and transitioned to EPP-008. The crew is now at the point of realigning plant systems for normal operation per Attachment 1. The SCO has directed you to perform Step 8 of Attachment I Realign Control Room Area IIVAC using OF-1 73, CONTROL ROOM A E A HVAC SYSTEM, Section 8.4. The initial conditions are satisfied and the HVAC system is in operation per section 8.1 ofOP-173.

INITIATING CUE@):

You are the Balance of Plant Operator. Restore the Control Room Area HVAC System to normal in accordance with OP-173 CONTROL ROOM AREA KVAC SYSTEM, Section 8.4.

Page 3 of 8 Rev Date 10/28/02

JPM-B. 1.c HARRIS Retake

  • DENOTES CRITICAL STEP JPM STEP CUE -

1 2

CUE 3

"4 5

__i PROC ELEMENT STANDARD I

NOTES SAT f UNSAT STEP E

PROVIDE CAhXUDATE WITH COPY OF OP-173 section 8.4 NA 8.4 Obtain procedure Go to Section 8.4, Restoring the Control Room Area W A C System to Normal after a Control Room Isolation Signal or Manual Recirc.

Obtain current copy of OP-173 section 8.4 Refers to Section 8.4 THE LNITlAL CONDITIONS AME SATISFIED ANXI THE CONTROL MOQM AREA IWAC SYSTEM IS IN OPERATION PER SECTION 8.1 8.4.1 8.4.2.1 8.4.2.2 Initial Conditions

1. Control Room
2. Control Room Isolation Signal clear Isolation Signal clear Place the CONTROL ROOM ISOI, TRAIN A and B RESET switches to RESET Shut any EMER FILT SOUTH (NORTH)

OUTSIDE AIR INLET valves that are open, 1 CZ-9 SA and 1 CZ-10 SB or1CZ-11 SAand 1CZ-12 SB.

Locates and manually operates the Control Room lsol Train A reset switch to reset and the Train B reset switch to reset Locates valves and verifies ALL outside air inlets are closed.

Valves ICZ-9 SA ICZ-IO SB ICZ-I1 SA ICZ-12 SB position indication lights Page 4 of S Rev Date 10:28/02

JPM STEP -

NA p_

  • 6 7

PROC STEP NOTE 3.4.2.3 1.4.2.4

-~

ELEMENT Performing steps 8.4.2.03 through 8.4.2.05 quickly will minimize excessive pressurization of the Main Control Room.

Open NORMAL INTAKES ICZ-l SA and ICZ-2 SB.

[f more than one NORMAL

ESR) is running, stop one Fan and verify associated ialvesfdampers align for the
topped train as follows

SUPPLY FAN AH-15 ASA AH-I5 IN CZ-DI (CZ-D2)

Shut SLB-5 (6)

AH-15 IN CZ-25 (CZ-26)

Shut SLB-5 (6)

CONT ROM NORMAE RECIRC DAMPER CZ-D69 SA (CZD70 SR)

Shut STANDARD Reads note, reviews steps and locates associated control board switches prio to performance of steps to allow minimal time to perform steps.

Locates and Opens NORMAL INTAKES ICZ-1 SA and ICZ-2 SE Locates and STOPS NORMAL SUPPLY FAN (either AH-15 ASA or AH-15 ESB and verifies the associated valves/dampers align for the stopped train AH-I5 IN CZ-DI (CZ-D2)

Shut (indication) OR SL13-5 (6)

AH-15 IN CZ-25 (CZ-26)

Shut (indication) on SLB-5 (6)

CONT ROM NORMAL RECIRC DAMPER Shut CZ-I169 SA (CZ-D70 SB)

JPM-B. 1.E HARRIS Retake NOTES Position indication lights change from green to red Selected Supply fern running indication light changes from red to green SLB indication light changes from red to green SLR indication Light changes from red to green Damper position indication light changes from red to green SAT f U N S A -

Page 5 of 8 Rev Date 10/28i02

P M STEP 8

9 PROC STEP 8.4.2.5 1.4.2.6 ELEMENT Start NORMAL EXHAUST FAN E-9 A (B) and verify:

E-9A(B) IN CZ-D6 (CZ-D7)

Open (loc.ated on SLB-7)

E-9A(B) OUT CZ-D12 (CZ-13)

Modulates (located on SLB-4)

NORMAL EXHAUST 1CZ-3 SA and ICZ-4 SE Open Stop both EMEKGENCY SA and K-2 B-SB and verify:

FILTRATION FANS R-2 A-R2 INLET CZ-23 ((2524)

Shut [located on SLR-5 (611 K2 DISCH CZ-21 (CZ-22)

Shut [Located on SLE-5 (6)]

STANDARD Locates arid starts NORMAL OR (B) and verifies:

EXHAUST FAN E-9 A E-9A(B) IN CZ-D6 (CZ-D7)

Open (located on SLB-7)

E-9A(W) OUT CZ-DI2 (CZ-13)

Modulates (located on SLB-7)

NORMAL EXHAUST IC%-3 SA and 1CZ-4 SB Open Locates and stops both SMERGENCY FILTRATION ANS R-2 A-SA and K-2 B-SB ind verities:

12 ISLE? CZ-23 (CZ-24)

Shut [located on SLB-5 (6)J t2 DISCH CZ-21 (CZ-22)

Shut [located on SLB-5 (6)]

IPM-B. I.c HARRIS Retake NOTES Selected fan indication light changes from green to red Indication light changes from green to red both green and red lights are on Indication light changas from green to red Indication light changes from red to green Indication light changes from red to green Indication light shanges From red

o green SAT I WNSA1 -

Page 6 of 8 Rev Date 10/28/02

PROC STEP 8.4.2.7 ELEMENT Shut the EMERGENCY FILTRATION RECIKC dampers C%-D66 SA and CZD61 SB STANDARD Locates the cone01 switches and shuts the EMERGENCY FILTRAFIOX RECIRC dampers CZ-D66 SA and Z D 6 1 SB IPM-5.1.C HARRIS Retake NOTES Indication light changes from red to green Indication light changes from red to green

%hWTPIER OPERATOR WILL CO1MPLETE THE REMAINING VENTILATION ZEESTORATION rASK COMPLETE STOP TIME:

Page 7 of 8 Rev Date 10!28/02

IPM-B.1.c HARRIS Retake CANDIDATE CUE SHEET (TO BE RETLXmD TO EXAMN3.R UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

The plant was operating at 100% power when an inadvertent Safety injection signal was received. The operators have performed the actions of Path-] and transitioned to EPP-008. The crew is now at the point of realigning plant systems for normal operation per Attachment I. The SCO has directed you to perform Step 8 of Realign Control Room Area HVAC using OP-173, CONTROL ROOM AREA HVAC SYSTEM, Section 8.4. The initial conditions are satisfied and the HVAC system is in operation per section 8.1 of OP-173.

INITIATING CUE(S):

You are the Balance of Plant Operator. Restore the Control Room Area HVAC System to normal in accordance with OP-193 CONTROL ROOM AREA HVAC SYSTEM, Section 8.4.

Page 8 of 8 Rev Date 10/28/02

JPM-B.2.a HARRIS Retake REGION II INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEAS ENERGIZE A DEAD BUS WITH A DIESEL LOCALLY CANDIDATE:

EXAMNEW:

Page 1 of 7 Rev Date 10R8/02

JPM-B.2.a HAURlS Retake REGION I1 INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE TASK:

ALTERNATE PATH:

NO FACILITY JPM NUMBER:

IP-135 KA:

062A2.05 IMPORTANCE:

SRO 3.3 RO 2.9 KA STATEMENT:

Load a Diesel Generator Locally per OP-155 Ability io (a) predict the impacts of the following malfunctions or operations on the AC Distribution System; and (b) based on those predictions, use procedures to correct, control, or mitigate the consequences of those malfunctions or operations: Methods for energizing a dead bus Emergency Diesel Generator Output Breaker 126 is CLOSED.

TASK STANDARD:

PRJiTERRED EVALUATION LOCATION:

SIMklLATOR PREFERRED EVALUATION METHOD:

PERFORM INPLANT X

SIMULATE X KEFEIRENCES:

OP-155 10 MINUTES TIME CRITICAL:

No VALIDATION TIME:

CANDIDATE:

START TIME:

FINISH TIME:

PERFORMANCE TIME:

MTI\\UTES PERFORMANCE RATING:

SAT UNSAT COMMENTS:

EXAMINER:

Signature Date fage 2 of 7 Rev Date 10!28i0?

JPM-B.2.a HARRIS Rehke TOOLS / EQIJIPMENT / PROCEDURES NEEDED:

e None OP-155, Section 8.13 READ TO OPERATOR INSTRUCTIONS TO CANDIDATE:

I will explain the initial conditions and state the task to be performed. A11 control room steps shall be performed for this JPM, including any required communications.

I will provide initiating cues and reports on other actions when directed or asked by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task, return the handout sheet I provide you.

INHTHAE CONDITIONS:

Due to a fire, the Main Control Room has been evacuated and AOP-004 is being implemented. During the transfer to the ACP, the normal power feed to 6.9KV bus 1B-SB was lost. EDG lBSR has been locally started per OP-IS5 Section 8.14 but has not been loaded.

INITIATING CUE@):

The SCO instructs you to locally energize 6.9KV bus 1B-SB from the Emergency Diesel Generator per OP-155 Section 8.13.

Page 3 O f 7 Rev Date 10!28!02

JPM-B.2.a HARRIS Retake

  • DENOTES CRITICAL STEP JPM STEP CUE 1

g _ _

2UE 2

W E 3

PROC ELEMENT STANDARD NOTES SAT 1 UNSAl STEP PROVIDE CANDIDATE WITH COPY OF OP-155, Section 8.13 and Attachment 9 01'-155, Section 8.13

>rovide when aF the Generator Control Panel:

kLL Initial Conditions are wet.

nitial conditions:

1. EDG 1B-SB is running
2. At GCP, UNIT-PARALLEL switch in PARALLEL
3. At GCP, VOLTAGE REGULATOR TRANSFER SWITCH in AUTO
4. At GCP, CONTROL TRANSFER SELECTOR SWITCH in LOCAL 8.13.2.1 At GCP, Position synchronizing switch #2 in ON Locates SYNCHRONIZING SWITCH #2 and takes it to ON.

iynchronizing Switch #2 is pointing to ON.

NOTE e

'The Synch Check Relay will be bypassed on an undervoltage on the safety bus e

When EDG output breaker is closed, the sequencer will place loads onto the EDG and the maximum load will be that of the safctv bus.

I Reviews note and continues with the procedure Page 4 of 7 Rev Date 10/28!02

rrpee JPM STEP -

4 3UE 6

XJE JPM-5.2.a HARRIS Retake indicates closed.

Green light is oat, amber light is out, and red light is lit.

CAUTION Do not exceed engine and generator limitations listed in Attachment 9 Reviews Attachment 9.

Checks local indications for Watts and VARS and verifies EDG operation is in the acceptable operation region of.

Examiner note: When EDG Output Breaker 126-SB closes the sequencer will load equipment onto the DUS over the next 45 seconds. The readings below are the bus load AFTER ail loads have sequenced sn.

Located on the upper right portion of the Generator Control Panel are 5 meten.

From left to sight - AC Volts, Megawatts, MegaVars, Freqaency, AC Ammeter. The MegaWatts and MegaVar meters are checked for Attachment 9 eapaeity curve.)

Meter readissgs -

6800 AC Volts 4 MW 2 W A R S 60 Hz 370 Amps These reudings u m within /in& of.4Ftrochment 9)

IF asked about the two Generator meters on the middle ofthe panel)

enerator Field Amps = I80 Amps Field DC Voltage = 60 volts Page 5 of1 Rev Date 10!28/02

JPM-H.2.a H.4RRIS Retake PROC ELEMEN1 STEP 8.13.2.4 I

Position EDG SYNCHRONIZING SWITCH #2 in OFF STANDARD Takes the EDG SYXCIIRONIZING SWITCH #2 to the OFF position.

Synchronizing Switch #2 is pointing to OFF CAUTION 8.13.2.5 To prevent EDG damage, service water should be supplied as soon as possible following emergency bus reenergization.

Monitor EDG temperatures Reviews caution and continues with the procedure Locates Temperature Selector switch on the Engine Control Panel and monitors the temperatures.

Diesel temperatures are normal for the engine load.

8.13.2.6 NOTE: Candidate may contact ACP operator to verify that service water flow has been estabiished.

(If so read CUE after step IO)

Verify service water is to verify service water established.

sirpplicd to EDG 4CP operator reports that Service Water flow has been established. TASK COMPLETE STOP TIME:

Page 6 of 7 Rev Date 10128102

I I

JPM-B.2.a HARRIS Retake CANDIDATE CUE SHEET (TO BE RIETFURNED TO EXAIVINER UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

Due to a fire, the Main Control Room has been evacuated and AOP-004 is bring implemented. During the transfer to the ACP, the normal power feed to 6.9KV bus 1B-SB was lost. EDG lBSB has been locally started per OP-I55 Section 8.14 but has not been loaded.

INITIATPJG CUE@):

The SCO instructs you to locally energize 6.9KV bus 1B-SB from the Emergency Diesel Generator per OP-155 Section 8.13.

Page 9 of 7 Rev Date 10/28/02