Enclosure 2 - Meeting Handouts from 01/22/2004 Meeting Between NRC-Duke Power and Framatome Anp
ML040370740
Person / Time
Site: Catawba  Duke Energy icon.png
Issue date: 01/22/2004
From: Nesbit S
Duke Power Co
To:
Office of Nuclear Reactor Regulation
References
Download: ML040370740 (5)


Text

MOX Fuel Proj ect Status NRC - Duke Power - Framatome ANP Meeting One White Flint North Steve Nesbit Duke Power January22, 2003 Pa Duke E1Power.

Jl#*-Uq-11,111IDic fUel 0`1101CI Russian Plutonium Disposition

  • Late 2002 - U.S.-Russian agreement on basis for Russian plutonium disposition program

- Russian MOX Fuel Fabrication Facility (R-MiFFF) based on design of United States facility

- Primary use of MOX fuel In WER-1000 pressurized iiater reactors

  • Goal of starting construction on U.S. and Russian fabrication facilities in 2004
  • Issue of liability for western contractors is still unresolved Duke PoPower.

wc pts fiet F201111:1E F1151 Enclosure 2

United States MFFF

  • Construction authorization delayed past 2003 due to change in MFFF Controlled Area Boundary
  • Atomic Safety and Licensing Board hearings in 2004
  • Begin construction in summer 2004, contingent on

- Regulatory approval

- Russian progress

  • Produce MOX fuel for McGuire and Catawba -2009 D Duke O7Power.

3 put UR ilt IVELfROtI~t U.S. Reactor Use of MOX Fuel

  • Lead assembly program

- Feb 27, 2003 - Duke submitted license amendment request (LAR) for approval to use NIOX fuel lead assemblies at McGuire or Catawba

- September 23, 2003- Duke amended LAR to apply to Catawba only

- NRC approval requested by August 2004

- Load lead assemblies In Catawba Unit I spring 2005

  • Batch use of IMIOX fuel

- Submit license amendment request for MlcGuire and Catavba in 2005

- Begin batch use ofrOX fuel around 2009

- Dispose of 34,000 kg of surplus plutonium through use as IOX fuel m Duke 14P~~~~~~ower- ~~~~~~~000 4eposer 0OOMOX

  • ~~~~~~~~~~~~~~~~~~~~~~~~~~~~IE .11U.

GrI *tt eat Wt

  • 3 Lead Assembly Program - Activities and Schedule
  • Spring 2004 - Complete polishing plutonium oxide powder at Los Alamos National Laboratory
  • Summer-fall 2004 - Transport plutonium oxide powder to Europe
  • Winter 2004-2005 -Fabricate MOX fuel pellets and rods at Cadarache and bundle assemblies at Melox
  • Spring 2005 - Transport lead assemblies to Catawba PlkDuke tSPower. 000 FA0.4&_ce 5 Act.01 ~ l10 lttO MOX Fuel Lead Assembly Irradiation Plan
  • Spring 2005 - spring 2008

- Two eighteen month cycles

- Irradiate all four MOX fuel assemblies in relatively high power locations

- Certify MOX fuel for batch use following 2nd cycle, based on poolside post-irradiation examination (PIE) results

  • Spring 2008 - fall 2009

- Conduct hot cell (PIE) of MOX fuel rods removed after two cycles of operation

- Irradiate one or more MOX fuel assemblies for a third cycle In relatively low power locations NMDuke tVPower.

A Vafs E11@16 t

6 °°MOX 000 SII 011O 11 OL FROMI

. ?

Required Regulatory Approvals

  • Duke topical reports (thermal-hydraulic, nuclear analysis)
  • Framatome topical reports (fuel performance, fuel assembly design, MOX fuel design)
  • DOE export license application
  • Packaging Technology transportation package certifications (powder and fuel assemblies)

Duke PSPower. 7 000 MOX FVILIWHOCI

  • [l1 @0111 Lead Assembly License Amendment Request RAI§
  • NRC Request for Additional Information (RAT) -

Boraflex

- Issued Julyl14,2003

- Response October 1, 2003

  • NRC RAI - Reactor Systems, Radiological, Env.

- Issued July 25, 2003

- Partial response October3, 2003

- Complete response November 3, 2003

  • NRC RAI - Quality Assurance

- Issued August 13, 2003

- Response October 1, 2003 Mk Duke UPower. 8 8~ws-r OOMOX 0001Rane Fult ?ECT

Lead Assembly LAR RAIs (cont.)

  • NRC RAI - Environmental, Radiological

- Issued November 21, 2003

- Partial response (radiological) December 10, 2003

- Environmental response scheduled for end oJanuary 2004

  • NRC RAI - Materials, Radiological

- Issued December 16, 2003

- Response scheduled for end of January 2004

  • NRC RAI-QA

- Issued December 24, 2003

- Response scheduled for endof January 2004 Duke PoPower. 9 00MOX 000 WI 0ig9X FoEfPaOJECI Summary

  • The United States MOX fuel lead assembly program is a key element of the international initiative to reduce the stockpiles of weapons grade plutonium in the United States and Russia
  • NRC review and approval schedule is important
  • Duke and Framatome ANP are committed to working with NRC to facilitate regulatory approvals m Duke AvPower. 10 0MOX pill$ 1:111lit FlICIEC