Catawba -- NRC Staff'S Motion for Interlocutory Review of the Licensing Board'S January 29, 2004 Order Finding a Need-To-Know and Ordering NRC Staff to Provide Petitoner with Acess to Documents Containing Safeguards Information (Superceded)ML040360493 |
Person / Time |
---|
Site: |
Catawba |
---|
Issue date: |
02/02/2004 |
---|
From: |
Fernandez A NRC/OGC |
---|
To: |
NRC/OCM |
---|
Byrdsong A T |
Shared Package |
---|
ML040360488 |
List: |
---|
References |
---|
50-413-OLA, 50-414-OLA, ASLBP 03-815-03-OLA, RAS 7289 |
Download: ML040360493 (5) |
|
|
---|
Category:Legal-Motion
MONTHYEARML12132A4682012-05-11011 May 2012 Motion to Strike ML0513902052005-05-13013 May 2005 Duke Energy Corporation'S Opposition to Blue Ridge Environmental Defense League'S Motion to Exceed Page Limitation ML0505502862005-02-15015 February 2005 Duke Energy Corporation'S Response to the Blue Ridge Environmental Defense League'S Motion to Re-open the Record on Security Contention 5 ML0504901822005-02-15015 February 2005 Catawba - NRC Staff Response in Opposition to Blue Ridge Environmental Defense League'S Motion to Re-Open the Record on Security Contention 5 ML0504700292005-02-15015 February 2005 Catawba - NRC Staff'S Response to Bredl'S February 3rd Letter ML0504503372005-01-31031 January 2005 Duke Energy Corporation'S Motion to Amend Protective Order to Add an Additional Individual to Receive Protected Information ML0502502522005-01-24024 January 2005 Catawba - Corrected Certificate of Service to the NRC Staff'S Motion to Amend December 15, 2003 Protective Order ML0502502492005-01-21021 January 2005 Catawba - NRC Staff'S Motion to Amend December 15, 2003 Protective Order ML0500602012004-12-22022 December 2004 Blue Ridge Environmental Defense League'S Opposition to NRC Staff'S Motion for Interlocutory Review of ASLB Ruling Amending Protective Order ML0436402832004-12-22022 December 2004 Response of Duke Energy Corporation to NRC Staff'S Motion for Expedited Interlocutory Review ML0436400962004-12-21021 December 2004 Catawba MOX - NRC Staff'S Motion for Interlocutory Review of the Licensing Board'S December 17, 2004 Order Amending the Protective Order and Request for Expedited Review ML0500501202004-12-20020 December 2004 Catawba - NRC Staff'S Motion for Stay Pending Interlocutory Review of the Licensing Board'S December 17, 2004 Order Amending Protective Order ML0435503702004-12-20020 December 2004 Letter from Diane Curran to Emile Julian Enclosing Blue Ridge Environmental Defense League'S Motion for Leave to File Prefiled Written Testimony Out of Time CY-03-215, Blue Ridge Environmental Defense League'S Motion for Leave to Reply to NRC Staff'S Response to Need-to-Know Appeal with Accompanying Reply2004-12-15015 December 2004 Blue Ridge Environmental Defense League'S Motion for Leave to Reply to NRC Staff'S Response to Need-to-Know Appeal with Accompanying Reply ML0500404622004-12-15015 December 2004 Catawba MOX - NRC Staff'S Response to Bredl'S Appeal of Staff'S Adverse Need-to-Know Determination Regarding SECY-03-215 ML0435700192004-12-15015 December 2004 Blue Ridge Environmental Defense League'S Motion to Amend Protective Order ML0432803532004-11-22022 November 2004 Catawba - NRC Staff Response to Bredl Motion for Imposition of Interim Discovery Measures to Compensate for Unavailability of ADAMS ML0433501362004-11-15015 November 2004 Duke Energy Corporation'S Response to Bredl Motion for Imposition of Interim Discovery Measures and Delay in the Hearing Schedule ML0431703692004-11-0505 November 2004 Motion for Approval of Consent Order Regarding Document Discovery; Consent Order Regarding Document Discovery; Blue Ridge Environmental Defense League'S Motion for Imposition of Interim Discovery Measures to Compensate. ML0430904602004-10-28028 October 2004 Duke Energy Corporation'S Response to Motion for Reconsideration of CLI-04-29 ML0430104462004-10-18018 October 2004 Blue Ridge Environmental Defense League'S Motion for Reconsideration of CLI-04-29 ML0426703602004-09-22022 September 2004 Catawba - NRC Staff'S Motion to Amend December 15, 2003 Protective Order ML0426800692004-09-17017 September 2004 Duke Energy Corporation'S Opposition to Blue Ridge Environmental Defense League'S Motion to Compel Production of the Proposed Security Plan for Catawba Nuclear Station ML0426401042004-09-0707 September 2004 Blue Ridge Environmental Defense League'S Motion to Compel Production of Revision 17 of Security Plan for Catawba Nuclear Power Plant ML0425702412004-09-0707 September 2004 Catawba - NRC Staff Response to Intervenor'S Motion Requesting Access to Certain Classified Documents ML0425303862004-08-31031 August 2004 Duke Energy Corporation'S Response to Blue Ridge Environmental Defense League'S Request for Need-to-Know Determination on Classified Regulatory Guidance for NRC Category I Facilities ML0424701652004-08-27027 August 2004 Duke Energy Corporation'S Request for Action Under Subpart I of 10 C.F.R. Part 2 ML0424402492004-08-26026 August 2004 Blue Ridge Environmental Defense League'S Request for Need-to-Know Determination ML0421605462004-07-27027 July 2004 Duke Energy Corporation'S Motion to Modify December 15. 2003 Protective Order ML0421003572004-07-20020 July 2004 Blue Ridge Environmental Defense League'S Opposition to NRC Staff'S Motion for Leave to Reply to Bredl'S Opposition ML0420301732004-07-19019 July 2004 Catawba - NRC Staff'S Motion for Leave to Reply to Bredl'S Opposition to NRC Staff'S Petition for Review Regarding Bredl'S Security Expert and NRC Staff'S Reply to Bredl'S Response to Staff'S Petition for Review ML0419803032004-07-0808 July 2004 Duke Energy Corporation Motion to Compel Discovery Responses from Blue Ridge Environmental Defense League Relating to Security Contention 5 ML0419802952004-07-0808 July 2004 Letter from Diane Curran to Administrative Judges Enclosing Blue Ridge Environmental Defense League'S Motion to Compel Security-Related Discovery Responses by NRC Staff ML0419003282004-07-0707 July 2004 Catawba - NRC Staff'S Motion to Compel Bredl to Respond to NRC Staff'S First Set of Discovery Requests on Security Contention 5 ML0418400042004-06-30030 June 2004 Catawba - NRC Staff'S Petition for Review of the Licensing Board'S Ruling Related to Bredl'S Proffered Security Expert ML0418400022004-06-30030 June 2004 Catawba - NRC Staff'S Motions for Temporary Stay to Preserve the Status Quo and for Stay Pending Interlocutory Review of the Licensing Board'S June 25, 2004 Finding Regarding Dr. Edwin Lyman'S Expertise ML0417503272004-05-21021 May 2004 Blue Ridge Environmental Defense League'S Motion for Leave to Withdraw Contention II and Request to Change Hearing Schedule for Contention I ML0414004642004-05-11011 May 2004 Duke Energy Corporation'S Motion to Modify Protective Order ML0411900812004-04-19019 April 2004 Blue Ridge Environmental Defense League'S Proposed Hearing Schedule and Request for Reconsideration of Aslb'S Internal Deadline of August 2004 for Issuing a Decision in This Proceeding ML0411900752004-04-19019 April 2004 Blue Ridge Environmental Defense League'S Motion for Clarification or Reconsideration April 8, 2004, Order ML0411107922004-04-16016 April 2004 NRC Staff'S Motion to Compel Blue Ridge Environmental Defense League to Respond to NRC Staff'S First Set of Interrogatories and Request for Production of Documents ML0410001092004-04-0202 April 2004 Duke Energy Corporation'S Motion for Protective Order ML0409202502004-03-30030 March 2004 Nuclear Regulatory Commission Staff'S Response to Duke Energy Corporation'S Motion to Dismiss Contention III ML0409203312004-03-25025 March 2004 Blue Ridge Environmental Defense League'S Opposition to Duke Energy Corporation'S Motion to Dismiss Contention III ML0408306822004-03-15015 March 2004 Duke Energy Corporation'S Motion to Dismiss Contention III ML0405004752004-02-11011 February 2004 Certificate of Service for NRC Staff'S Petition for Review of the Licensing Board'S February 4, 2004 Order Relating to Bredl'S Request to Attend a Closed Meeting. ML0405004672004-02-11011 February 2004 Affidavit of John A. Nakoski in Support of NRC Staff Request for Interlocutory Review ML0404202532004-02-0303 February 2004 Blue Ridge Environmental Defense League'S Emergency Motion for Access to NRC Staff Meeting on February 6, 2004 ML0403604932004-02-0202 February 2004 Catawba -- NRC Staff'S Motion for Interlocutory Review of the Licensing Board'S January 29, 2004 Order Finding a Need-To-Know and Ordering NRC Staff to Provide Petitoner with Acess to Documents Containing Safeguards Information (Superceded) ML0403604702004-01-30030 January 2004 Catawba MOX - NRC Staff'S Motions for Temporary Stay to Preserve the Status Quo and for Stay Pending Interlocutory Review of the Licensing Board'S January 29, 2004 Order Regarding Access to NRC Documents Containing Safeguards Information 2012-05-11
[Table view] |
Text
January 30, 2004 February 2, 2004 (superceded)
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE COMMISSION In the Matter of 3 DUKE ENERGY CORPORATION ) Docket Nos. 50-413-OLA, 50-414-OLA (Catawba Nuclear Station, Units 1 and 2) )
NRC STAFF'S MOTION FOR INTERLOCUTORY REVIEW OF THE LICENSING BOARD'S JANUARY 29,2004 ORDER FINDING A NEED-TO-KNOW AND ORDERING NRC STAFF TO PROVIDE PETITIONER WITH ACCESS TO DOCUMENTS CONTAINING SAFEGUARDS INFORMATION INTRODUCTION Pursuant to 10 C.F.R. § 2.786(g)(1), the staff of the Nuclear Regulatory Commission (Staff) hereby requests that the Commission grant interlocutory review of the Order issued by the presiding Atomic Safety and Licensing Board (Board) on January 29, 2004, finding that, in order to frame contentions relating to security at Catawba Nuclear Station during the time fresh mixed oxide fuel (MOX), in the form of four lead test assemblies (LTAs), is present on site, the petitioner, Blue Ridge Environmental Defense League (BREDL) has a need-to-know the contents of certain safeguards documents relating to security. For reasons more fully discussed below, the Order will cause immediate and irreparable harm on the staff and the public that is not amenable to subsequent relief.'
BACKGROUND The instant case arises out of Duke Power Corporation's (Duke) license amendment request (LAR) to irradiate four MOX LTAs at the Catawba nuclear power plant. As further described in the Staff's separate request for a stay filed earlier today, the Board presiding over the case below has I See Private Fuel Storage, L.L.C. (Independent Spent Fuel Storage Installation), CLI 08, 55 NRC 222 (2002).
ordered the Staff to, no later than February 2, 2004, provide access to the following NRC safeguards documents:
- 1. April 29, 2003 Order regarding the Design Basis Threat (DBT) for radiological sabotage;
- 2. April 29, 2003 Order regarding training;
- 3. January 7, 2003 Order regarding access authorization; and,
- 4. Any regulatory guidance associated with these orders.
See Memorandum and Order (Ruling on BREDL Motion for Need to Know Determination and Extension of Deadline for Filing Security-Related Contentions) (Jan. 29, 2004) (Safeguards version). Pursuant to the request filed herein, the Staff requests that the Commission grant interlocutory review of the Board's Order.
DISCUSSION
- 1. Interlocutory Review of the Board's Order is Appropriate Because the Order Threatens Irreparable Harm to the Staff and the Public Inaccordance with 10 C.F.R. §2.786(g) interlocutory review is appropriate "where the disputed ruling threatens the aggrieved party with serious, immediate, and irreparable harm or where it will have a 'pervasive or unusual' effect on the proceedings below." Private Fuel Storage, L.L.C.
(Independent Spent Fuel Storage Installation), CLI-01-1, 53 NRC 1, 5 (2001), citing 10 C.F.R. § 2.786(g); PrivateFuel Storage, L.L.C. (Independent Spent Fuel Storage Installation),
CLI-98-7,47 NRC 307, 310 (1998). See also PFS, CLI-02-08, 55 NRC 222 (2002). The instant case warrants Commission interlocutory reviewof the Board's Orderto avoid such irreparable harm to the Staff, to the public and to the Nation's common defense and security. If the Commission denies the instant request, the Staff will be required to allow BREDL's counsel and technical consultant access to the aforementioned documents. Once BREDL has reviewed the documents in question, the harm to the Staff will be irreversible and cannot otherwise be remedied.
The Board's Order threatens the Staff with uimmediate and serious irreparable impact that, as a practical matter, could not be alleviated through a petition for review of the [Board's] final decision," and thus the decision is appropriate for review by the Commission. See e.g. Georgia Power Co. (Vogtle Electric Generating Plant, Units 1 and 2), CLI-94-5, 39 NRC 190, 193 (1994).
See also, Private Fuel Storage (Independent Spent Fuel Storage Installation), CLI-00-13, 52 NRC 23,28-29 (2000). If the Staff were forced to comply with the Board's order BREDL would have access to documents that cover much of the Commission's work in the area of nuclear security since the events of September 11, 2001. In addition, the content of these documents reveal sensitive information pertinent to all operating nuclear power plant licensees. Once the content of these documents is disclosed, the harm to the common defense and security cannot be undone. Indeed, in the event that, acting on the Staff's appeal, the Commission, at a later time, reversed the Board's need-to-know determination it would be too late to undo the disclosure to BREDL.
- 2. The Board's January 29. 2003 Order In its Order, the Board instructs the Staff to provide BREDL with access to NRC safeguards documents based on the Board's conclusion that BREDL has established a need-to-know. See Order at 17. The Board states that its conclusion primarily rests on "statements made in Duke's submittal itself, referring to and/or relying on information contained in various of the non-publicly-available documents sought by BREDL ...." Id. at 10 (emphasis in original). The Board then goes on to cite several portions of Duke's submittal that it believes, although wrongly, support its conclusion. See, e.g., id. at 11-15. None of the language cited by the Board, however, mentions any information that is contained in the documents requested by BREDL. The examples cited by the Board as bases for its conclusion that Duke's application brings the documents
requested by BREDL within the scope of the proceeding are, at best, unenlightening.2 All of the examples cited by the Board in fact refer back to Duke's current physical security plan and do not directly refer to any of the documents requested by BREDL. See, e.g., id. at 11.
In determining that BREDL has a need-to-know this information, the Board agrees with BREDL's representations that certain requirements that are necessary to the filing of BREDL's contentions are not currently available to them. See id. at 11-13. The Board bases its agreement, as described above, on statements made by the licensee in its submittal. Id. While agreeing with BREDL, the Board erroneously seems to believe that some standard other than the existing standards for granting of exemptions requested by Duke in their submittal, set forth in 10 C.F.R. Parts 11 and 73, will be applied in determining the acceptability of Duke's submittal.
Contrary to the Board's decision, Duke's submittal will be reviewed on the basis of the currently applicable standards and not by any further measures that may be compelled by the documents requested by BREDL. See, e.g., 10 C.F.R. §73.5, 10 C.F.R. §11.9. In effect, all of the standards and requirements that Duke must meet in its application are publicly available as regulations codified in the Code of Federal Regulations.
Moreover, the effect of the Board's ruling is tantamount to granting discovery to BREDL prior to it filing any admissible contentions. Northern States Power Co. (Prairie Island Nuclear Generating Plant, Units 1 & 2), ALAB-1 07,6 AEC 188, 192, reconsid. den., ALAB-1 10, 6 AEC 247, aff'd, CLI-73-12, 6 AEC 241 (1973). BREDL is attempting to obtain documents that are not relied upon by Duke in support of its application (nor by the Staff with respect to its review). Duke merely cites to its own practices. To the extent BREDL may wish to obtain additional Duke documents 2Particularly, the Board failed to identify any references by Duke in its submittal that would support any argument that the April 29, 2003 Order regarding training should be made available to BREDL.
referenced in the submittal, it has not made such a request in the proceeding below. Therefore, the matter is not currently before the Commission.
CONCLUSION For the foregoing reasons the Staff submits that the Commission should take review of the Board's Order of January 29, 2004.
Respectfully submitted, Fer Stonioondez Counsel for NRC staff Dated in Rockville, Maryland This 2nd day of February 2004.