ML040090230
ML040090230 | |
Person / Time | |
---|---|
Site: | Sequoyah ![]() |
Issue date: | 04/30/2002 |
From: | Ogle C NRC/RGN-II/DRS/EB |
To: | Scalice J Tennessee Valley Authority |
References | |
FOIA/PA-2003-0358 IR-02-003 | |
Download: ML040090230 (24) | |
See also: IR 05000327/2002003
Text
April XX, 2002
Tennessee Valley Authority
ATTN: Mr. J. A. Scalice
Chief Nuclear Officer and
Executive Vice President
6A Lookout Place
1101 Market Street
Chattanooga, TN 37402-2801
SUBJECT: SEQUOYAH NUCLEAR PLANT - NRC INSPECTION REPORT 50-327/02-03,
50-328/02-03
Dear Mr. Scalice:
On March 29, 2002, the Nuclear Regulatory Commission (NRC) completed a triennial fire
protection inspection at the Sequoyah Nuclear Plant. The enclosed report documents the
results of this inspection which were discussed on March 28-29, with Mr. Dennis Cole and other
members of your staff.
The inspection examined activities conducted under your license as they relate to safety and
compliance with the Commission's rules and regulations and with the conditions of your license.
The inspectors reviewed selected procedures and records, observed activities, and interviewed
personnel.
Based on the results of this inspection, the inspectors identified two issues of very low safety
significance (Green). These issues were determined to involve violations of NRC
requirements. [However, because of their very low safety significance and because they have
been entered into your corrective action program, the NRC is treating these issues as Non-cited
Aid violations, in accordance with Section VI.A.1 of the NRC's Enforcement Policy. The first
9ation involved a failure to ensure that one of the redundant trains for isolation of normal
, letdownrjsnaintained free of fire damage. The second violation involved the failure to properly
establish the plant fire procedure such that actions necessary to mitigate the consequences of a
severe fire could be effectively performed.
If you deny these Non-cited violations, you should provide a response with the basis for your
denial, within 30 days of the date of this inspection report, to the Nuclear Regulatory
Commission, ATTN: Document Control Desk, Washington DC 20555-0001; with copies to the
Regional Administrator, Region II; the Director, Office of Enforcement, United States Nuclear
Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident Inspector at the
Sequoyah Nuclear Plant.
In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy of this letter and its
enclosure will be available electronically for public inspection in the NRC Public Document
Room or from the Publicly Available Records (PARS) component of NRC's Document 0
system (ADAMS). ADAMS is accessible from the NRC web site at http://www.nrc.qov/reading-
rmladams.html (the Public Electronic Reading Room).
Sincerely,
. . .
Charles R. Ogle, Chief
Engineering Branch I
Division of Reactor Safety
Enclosure: NRC Inspection Report 50-327/02-03,
50-328/02-03
SUMMARY OF FINDINGS
Sequoyah Nuclear Plant, Units land 2
IR 05000327-02-03 and IR05000328-02-03 on 03125-29/2002,Tennesee Valley Authority,
Sequoyah Nuclear Plant Units I and 2, triennial baseline inspection of the fire protection
program.
The inspection was conducted by a Brunswick resident inspector, and three regional reactor
inspectors. The inspection identified two Non-cited violations which were determined to be of
very low safety significance (Green). The significance of most findings is indicated by their
color (Green, White, Yellow, Red) using IMC 0609 'Significance Determination Process."
Findings for which the SDP does not apply are indicated by "No Color" or by the severity level
of the applicable violation. Tl
n
Ntv:La~rnrc.
Inspector Identified Findings
Cornerstone: Mitigating Systems Wa
- Green. A Non-cited violation of 10 CFR Part 50RAppendi Il.G.2, was identified for
failure to ensure that one of the redundant trains of a sys em necessary to achieve and
maintain hot shutdown conditions in the event of a fire ree of fire damage.
Specifically, electrical cables for redundant charging flow isolation valves 1-FCV-62-90
ano1 were located in Fire Area FAA-029, the Auxiliary Building Corridor, without
oqt',,-adequate spatial separation or fire barriers. o
[4C1'J The finding had a credible impact on safet n tire damage to the unprotecte
cables could prevent closure of the valves fro mafn control room (MCR) and
challenge the operators' ability to establish adeq t injection flow to the reactor coolant
pump (RCP) seals. This finding was determined be of very low safety significance
because the ignition frequency was relatively low, fire detection and suppression
systems were not degraded, and there were no c mponents in this area whose failure
would rqsult in an accident initiator (i.e., loss of of site power, loss of main feedwater,
etc.) ,se e finding only affected the mitigating sy tems cornerstone. (Section 1R05.02)
- Green. A Non-cited violation of Technical Specifi tion 6.8.1.a. was identified for
inadequate procedure guidance related to the tran ition from abnormal operating
procedure (AOP)-N.01, Plant Fires, to AOP-C.04, hutdown From Auxiliary Control
Room, in the event of a severe fire in the control ilding. AOP-N.01 did not clearly
delineate what conditions would require entry into OP-C.04 and evacuation of the
My. Also, AOP-N.01 did not direct operators t enter AOP-C.04 in the event of a -
sevefe fire in the control building.
This finding had a credible impact on safe in that, t e inadequate guidance in
procedure AOP-N.01 could delay entry into . 4 and could challenge the operators'
ability to perform certain critical safe shutdown functions (e.g., isolate normal charging,
establish adequate seal injection flow to the RCPs) within the times specified in the
licensee's safe shutdown calculation for Appendix R. This finding was determined to be
of very low safety significance because it did not affect fire detection, fire suppression, or
fire barriers. (Section 1R05.05)
Licensee identified Findings
Two violations of very low safety significance which were identified by the licensee were
reviewed by the inspection team. Corrective actions taken or planned by the licensee
appear reasonable. (Section 40A7)
A
Report Details
2. REACTOR SAFETY
Cornerstones: Initiating Events, Mitigating Systems
1R05 FIRE PROTECTION
.01 Systems Required To Achieve and Maintain Post-Fire Safe Shutdown (SSD)
a. Inspection ScoDe
The team evaluated the licensee's fire protection prog aai applicable
requirements, including the Sequoyah Nuclear'(SQN) 1 Units 5and 2 fF- l -
License Conditions 2.C(16) and 2.C(13) respectively-, F ei tle 10 of the Code
14S
of Federal Regulations Part 50 (10 CFR 50) Appendix Rll GIII.J, 111.0, and lII.L;
Appendix A of Branch Technical Position (BTP) Auxiliary and Power Conversion Systems /St,
Branch (APCSB) 9.5-1; 10 CFR 50.48; related NRC Safety Evaluation Reports (SERs); /
NUREGS and the Technical Specifications (TS).
The team used the licensee's Individual Plant Examination for External Events (IPEEE)
a in-Ian alkdowns to select four risk significant fire areas (FAs) for inspection. The
tfouire area c were:
Fire Area FAA-029, Auxiliary Building, Elevation 690: Auxiliary Building Corridor
This FA includes rooms 690.0-Al, A9, Al 0*\1 3, A14, A17, Al8, A22,tX, A23a, A24,
A27, A30 and A31. This area contains both trains of safe shutdown,,equipment or cables"
and is classified as a 10 CFR Ret 50 Appendix R, III.G.2 area. A significant fire in this
area would require shutdown of either unitbfrom the main control room (MCR).
Fire Area FAA-067, Auxiliary Building, Elevation 734: 6.9 kilovolt (kV) Shutdown Board
Rooms
This des rooms 734.0-A2 and AThis includes both units train A'
auxiliary electric power switchgear. This area S-ct d as a%10 fFRPat-50Appendix
R, llI.G.2. A significant fire in this W ould require shutdown of either unit from the
MCR. Or ,
1107
Fire Area FAC-009, Control Building, Elevation 685: Unit 1 Auxiliary Instrument R
This FA includes control ro safeSS nSS equipment fro e e
-Fomn This area is cla dsas an gerCrt Appendix R, Il .G.3 a. A significant
fire in this area woul involve'evacuation of the MCR and alternative shutdown from the
remote shutdown panuin the Auxiliary Control Room ' 7 R~located inhe-Auxilry
Fire Area FAC-20, Control Building, Elevation 732: Relay Ro JrA/roc a,
This FA includes high voltage electrical relay equipment for offsite power and is located
adjacent to the MCR complex. A significant fire in this area may result in a fire induced
loss of offsite power (LOOP). This are* assified as v1* CFR it -50 Appendix R,
III.G.3 area. A fire in this area woul reqrvacuation of the MCR and alternate
shutdown from the remote shutdown panel using the ACR,*loea in tho-Auxiliary
/0/1/ N 7'
The team reviewed the IPEEE, ppe ix A to calculation SQN-26-D054/EPM-ABB-
lMPFHAMYFire Hazards Analysis (F A), the Sequoyah Fire Protection Report (FPR),
associated procedures, and drawings to identify those systems credited for SSD
of the facility in the event of a fire i the elected fire areas. The inspection included
review of the post-fire SSD capability ande fire protection features o ensure that at
least one post-fire SSD success t was m ained free of fire da ageirnthe event of
ad. L, Bt0,S -r vb
For a selected sample of SSD syste" omponents, and plant monitoring instruments, , nel 7
the team reviewed the SQN Fire PF I Fz rt, the FHA, applicable fire protection
, R
elated-SERs and NUREGS, and system flow diagrams to evaluate the completeness 9
and adequacy of the FPR and the systems relied upon to mitigate fires in the selected
fire areas.
The team inspected the capability to shutdown for the scenario where a fire in FA FAC-
20,BRelay-4emr could initiate a LOOP. The team inspected the control circuits and
associated circuit analysis for the diesel generators to determine whether any devices in
the control circuit were located in FA FAC-20. In a similar manner, the control circuits for
the 6. iV)shutdown board incomig cruit briedkF (i.e. offite poxwor-and diesels
9S_ erwere reviewed to determine whether a fire in FA FAC-20 could
with opening of the offsite breaker or closing the diesel generator breaker.
b. Findings f
No findings of significance were identified.
.02 Fire Protection of Safe Shutdown CaDability
a. InsDection Scope
The team reviewed the licensee's the FPR for FAs FAA-029 and F 7o determine
whether redundant trains of components or circuits required forae s o )re
located in the spm8 FA. From those components, the team selecr i
charging pumpsYA and 1 tri charirgfow isolation valves 1-FCV-
62-90 a n9 spatial separation or
proper fire'a'rrier protection features were l s a fI6ccordance with the design
requirements of 10-F-FR54 Appendix R. For the seleiced cdblaes1he team examined
cable routing, raceway drawings, the actual configuration of the circuits, fire barriers, fire
detection, and fire suppression equipment as applicable for conformance to applicable
NRC requirements and National Fire Protection Association (NFPA) standards. In
addition the team walked down these FAs to verify that the licensee documentation
reflected the as-built configuration.
Team members also walked down thetselected FAsihtcomparethe associated fire
fighting pre-plans and drawings with as-built plant conditions. This was don erif
tha~qwere consistent with the fire protection features and potential fire condions
/ - -descrTed in the FPR all the team reviewed engineering evaluations
associated with th reactor auxilia uilding floor and ufr o ,45O
v ose actions required for post-fire Votive S 5 ould not be inhibited by
(7 A fire suppression activities or leakage from fire su s ystems. IThe team reviewed
fire brigade response, training, Wd drill rogram procedures. Fire brigade drill critiques
for operating shifts from 1999 _Las well as fire brigade training/drill records for , 6o
the rire hat fire brigade drills had been conducted in
high fire risk plant areas and thiltircfliade personnel qualifications, brigade drill
response, and brigade performance met the requirements of the licensee's approved fire
protection program.
The team reviewed selected portions of the SO1THiA and pWa&*e ,gsr Se
prevention/combustible hagards aol procedures to Gt the
conditions established in A fire rotection licensing basis document w
The team performed walkdopwns of fhe four selected St FAs to o be e he
licensee's aetivA4e limit ire hazards A consistent wit~poeures.
The team reviewed the fre brigade response fire emergency/incident repot from 1999
through 2001, as well as the~ft Problem Evaluation Reports (PERs) resulting from fire,
smoke, sparks, arcing, and equipment overheating incidents. This review was conducted
to assess the effectiveness of the fire prevention program and to identify any
maintenance or material condition problems related to fire incidents. Additionally, design
control procedures were reviewed to verify that plant changes were adequately reviewed
for the potential impact on the fire protection program, SSD equipment, and procedures
as required by SQN license conditions 2.Cj16) and 2.C.(13).
A ?
.-The team walked down the primary fire brigade staging and dress-out areas to assess
the condition of fire fighting and smoke control equipment. Fire brigade personal
protective equipment located in the fire brigade house, dress-out area and lockers in the
fire brigade staging area were reviewed to evaluate equipment accessibility and
functionality. The team observed whether emergency exit lighting was provided for
personnel evacuation pathways to the outside exits as identified in the NFPA 101, Life
Safety Code. This review also included examination of whether backup emergency
lighting was provided for access pathways to and within the fire brigade staging and
dress-out areas in support of fire brigade operations should power fail during a fire
emergency. The adequacy of the fire brigade self-contained breathing apparatus
(SCBAs) was reviewed as well as the availability of supplemental breathing air tanks.
The team reviewed the RCPvoil collection system enclosure drawings to vefy compliance
with 16-6fR-50 Appendix RESection 111.0. Th evaluatig f operator
response procedures to determine if sufficient procedural guidance was provided toft ie f /07
plal~tueperl bee to identify a oil leak fromgtho
one-of-the C Aoo dtk prpi cin. il
b. Findings )P J
A Non-cited violation (Green) of Part 50, Appendix R,Section III.G.2,
I2/CFR
identified for failure to ensure one of the redundant trains of a system cessary to
achieve and maintain hot shutdown conditions in the -eventva fire Free of fire
damage. Electrical cables for redundantcharging flow isolation valves 1-FCV-62-90 and
1'CLJ' 6-'?1 ( -9were located in'FA FAA-029, the'A y i ror,-without spatial separation
or fire barriers. A
,iFm~ FAA-0 29 , the FHA indicated that reactor coolant system (RCS) inventory
control was achieved through isolation of normal charging and letdown while maintaining
RCP seal flow cooling. Through review of associated system prints and safeutdowr<*St
procedures AOP-N.01 and AOP-N.08, the team noted that the stepto acieve charging
flow isolation while continuing RCP eal flow cooling frem- c-' oTwas to
close either valve 1-FCV-62-90 o& These valves were in series and powered from
redundant power sources. The FHA indicated that power and control cables for both
these valves were routed closer than the 20 feet specified in Appendix R, Ill.G.2.b in a
relatively small sub-area of FA FAA-029. Conduitkowings 1,2-45N824-7 and 1,2-
45N824-16 depicted the routing for these cables. FP'a`valkdown of the cable routing, i
the team verified that there was a location where the unprotected cables for valves( 7
andItwere separated by approximately 16 feetsy t they 1uI darnaged-b~.aa t
severelfe-The team noted tPat in liu of protecting the Oandgbcables in accordance 1
wit.b.Appendix R, s afi ~ d from the main cfro , the licensee
I/o6FA5 - c orated steps in the shutdown procedure AOP-N.08 to manipulate valvei)
Tb both thve pcrLng ?ow could be damaged by a
credible fire in FAA-029 Led VIeatr t m r could affect tot-
RCP seal injection flow and RWr seal integrity. The finding was found to have credible
impact on safety in that fire damage to the unprotected cables could prevent closure of
the valves from the MCR and challenge the operators' ability to establish adequate flow
to the RCP seals. The ignition frequency for the sub-area in question was taken from
-theSQNIPEEE-as-1.85E-3 per year. -The team observed that fire detection and
suppression was installed throughout FA FAA-029. Manual suppression capability and
the automatic suppression system were deemed to be in the normal operating state by
the team. The fire mitigation frequency was conservatively calculated to be once per 105
years. The missing barrier condition existed for greater than 30 days. Based on these
factors, the finding was processed using the Phase 2 transient sheet and subsequently
characterized by the Significance Determination Process as having very low risk
significance (Green). This was because the ignition frequency was relatively low, fire
detection and suppression systems were not degraded, and there were no components
in this area whose failure would esult in an accident initiator (i.e., loss of offsite power,
loss of main feedwater, etc.)*" the finding only affects the mitigating systems
cornerstone.
The failure to protect cables with an adequate fire barrier orprovide 20 foot separation
between redundant charging flow isolation valves is a violation of 10 CFR 50, Appendix
....
R, 111.%.fZJKwhich Ierules that unpratected cabdles of ieduiddanttran3bc zcp ar
-O hvoriAntal dictars uf yit~aiei ihaii 20 t. Thi7violation is being treated as a Non-
cited violation and is identified as NCV 50-327/02-003-01. The licensee documented the
violation in PER 02-03645.
.03 Post-Fire SSD Circuit Analysis
a. Inspection Scope G
The tean~~ that selected cables of e4uipment required to achieve and maintain hot , g
shutdown conditions in the event of fire in selected FAs had been properly identified and
either adequately protected from the potentially adverse effects of fire damage or
analyzed to show that fire-induced faults , ir, w ho
,xjound)would not prevent safe shutdown. The team select d powerycontrol and
instrumentation circuits indicated to be credited for safe 454d6wn in the licensee's FHA)
and walked down the routing of the circuits. The circuits selecte were:
Fire Area FAA-067: 1-L068-335, Pressurizer level indication 1r
Fire Area FAC-009: FI-3-1 63C, Auxiliary feedwater flow to steam generator 1.
Fire Area FAC-20: Diesel generator start button
Additionallythe team reviewed selected keelrical coordination studies to verify
that fire induced faults on energized non-shutdown circuits would not prevent the success
of the SSD functions. Specifically, the team reviewed overcurrent protection devices
related to the control circuit for cenrfugeherging -purnCCP1A from,5wr source at
125 volt (V)vital battery board 1 to the circuit breaker close and trip circuits. The
manufacturer's time-current characteristics were checked;and installed devices were
examined and compared to design information. The team reviewed the coordination of
overcurrent devices on the alternat, n rrent (AC) sytem. From the licensee's FHA,
the team reviewed those buse or a fire in A FAA-029. Phase fauls and
ground faults on the 6.9 kV system re consid erdand a review of the 6.9 s stenrtd
coordination was performed for a ase fault on cable emanating from 4 88hutdown
board 1AI-A, reactor MOV board kAl-A and ER MCC 1A-A. T the extent possible
installed devices were examined acompared toein docutr!
b. Findings
No findings of significance were identified.
.04 AkeffnlefiAitd ASQCaDabiltv J-0 Y -~ 5Y8 sA
a. Inspection Scope
The team reviewed the licensee's procedures for fire response anj ASD capability for the gF
,FAs selectedtoq verify conformance with applicable requirem ents(en Section
1R05.01 abov This review included the licensee's ASD methodology to determine the
ht .
adequacy of the identified cor onents anstems to achieve and maain safe
shutdown. The review also *4at the methodology a ressed achieving
and maintaining hot and cold shutdown from outside the MCR, with without off-sit
power available. The team also reviewed the licensee's procedures a t-verifyt
pr
consistency with the calculations and assumptions supporting the operator actions
identified in the ASD methodology.
The team selected several circuits wherRjch, control or instrumentation devices were
determined to be located at the auxiliet panel or other local panels. The team
reviewed relevant drawings to determine wh ther isolation devices were appropriately
designed into the following circuits: 7
- Control circuit for the centrifugal charging pump
- AFW flow to the steam generator FI-3-163C
- Volume control tank outlet isolation valve LCV-62-132 (MOV)
- Source range flux monitor Xl-92-5,
The team erif hot and cold shutdown could be maintained from outside the MCR)
without o sie power through the review of emergency diesel generatEDGYand
breaker circuits. 0-
b. Findings
No findings of significance were identified.
.05 ODerational ImDlementation of Ae iv tn Capability
a. Inspection Scope f
The team reviewd the operational i mlementation of post-fire *afeshutdown capability
for a fire in thekselected FAs to t: (1)the training program for licensed and non-
licensed personnel included alternative or dedicated SSD capability; (2) personnel
required to achieve and maintain the plant in hot standby from outside the MCR could be
provided from normal onsite staff, exclusive of the fire brigade; (3) adequate procedures
existed for use during ASDand A) the licensee periodically performed operability testing ?
eninstn tationaer an contrfunctions. The team reviewed the
A contents of lockers tder`that materials needed to support
implementation of operator actions specified in the ASD procedures for hot standby were
available and properly maintained. Fire brigade staffing was reviewed to& that it met
the requirements of the licensee's fire protection program. Training requirements were
reviewed for the fire brigade members and related support personnel such as incident
commander , reactor operator (O), senior reactor operator (8RM, and auxiliary
operatorst 2vfy compliance with the licensee's fire protection program. Lesson plans
gkx..
and job performance measures (JPMs) were reviewed to determine whether ASD
,¢ f ~activities were included in the training program.
..- +~> Post-fire safe-shutdown procedures forthe selected areas were reviewed to determine if
~4;BA Yt /adequate staffing and approprate guidance was provided for the operators to identify
_ ~ pro6tected equipment and I tfumentation and those recovery actions specified in post-
fireshutdown procedu sidered manpower needs for performing restorations and
P.area accessibility. Spec procedures reviewed included Abnormal Operating
Procedure (AOP)-N.01, Plant Fires, Revision (Rev)14; AOP-N.08, Appendix R Fire Safe
j A
Shutdown, Rev 0; AOP-C.04, Shutdown Eom Auxiliary Control Room, Rev 4. Selected
procedure sections were walked down that the procedures could be performed
within the times specified in the supporting calculations, given the minimum required
staffing level of operators, concurrent with a loss of offsite power. Additionally, the team
walked down the designated pathways and reviewed the licens oke control
procedures, ventilation systems, and the availability of SCBAsdQy-Ls that
environmental conditions, such as smoke and heat, would not prevent operators from
performing the procedures.
b. Findings
One finding of very low safety significance (Green) was identified as a Non-cited violationion11Z
of Technical Specification 6.8.1.a. for inadequate procedure guidance related .,
to the transition from AOP-N.01, IP-ant-fes, to AOP-C.04, ShutdownfomnAailiary
Copyg4Rm, in the event of-a severe fire in the Control Building.
March 2 O2, the team identified that the guidance contained in AOP-N.01 was not
AA601- adequate to transition operators to AOP-C.04, in that, AOP-N.01 did not clearly delineate
what conditions would require entry Into AOP-C.04 and evacu ion of the MCP. Also,
AOP-N.01 failed to direct operators to enter AOP-C.04 in the event of a severe fire in the
-Control Building. The lack of clear guidance in AOP-N.01 was noted during a
walkthrough by the team of the procedures AOP-N.01 and AOP-C.04 with operations
-personnel. The team observed-that the lack of adequate guidance in AOP-N.01
appeared to contribute to the operators' confusion regarding the entry conditions for
-AOP-C.04 and the transition from-AOP-N.01 to AOP-C.04-.-This team determined that
the confusion could cause thvperator to delay entry into AOP-C.04 and the
performance of time critica SD a tions.
This finding had a credible impat on safety, in thatiI'I inadequate guidance in
procedure AOP-N.01 could del& nyiojtoAOP-"4 and could challenge the operators'
ability to perform certain critical sa t n functions (e.g., isolate normal charging,
establish adequate seal injection flow to the RCPs) within the times specified in licensee
calculation SQN-SQS4-0127, Equipment Required for Safe Shutdown Per 10 CFR50
Appendix R, Rev 21. This finding affected the mitigating systems cornerstone and was
determined to be of very low safety significance (Green) using Attachment F to the
Significance Determination Process (SDP), because it did not affect fire detection, fire
suppression, or fire barriers.
Sequoyah Technical Specification 6.8.1.a. and Regulatory Guide 1.33, Rev 2, Appendix
A, Item 6.v, requires, in part, that written procedures be established, implemented, and
maintained for plant operations during emergencies such as plant fires. Embodied in this
requirement is that the procedures have to be adequate. Contrary to the above, the
licensee failed to establish adequate procedural guidance in AOP-N.01, Plant Fires, to
proVide sufficient guidance to operators with regard to what conditions would require
_entry-into AOPj:.04 for-safe-shutdown from outside of the MCR.
Because of the very low safety significance of this issue and because the licensee has
entered this issue in their corrective action program as PER 02-003550, this violation is
being treated as an NCV, consistent with Section VL.A of the NRC Enforcement Policy.
This violation is identified as NCV 50-327, 328/02-03-02, Inadequate Procedure
Guidance for Implementing Abnormal Operating Procedures for Plant Fires.
The team noted other observations during the procedure reviews and walkthroughs
which could challenge operator performance of safezehitown activities. The following
are examples of the types of observations identified: 55-
thoroughness in that, a "tabletop review" was performed instead of a field validation.
- Time requirements specified in calculation SQN-SQS4-0127 for performing certain
critical safe-shutdown functions were not incorporated into AOP-C.04.
- AOP-C.04, Checklist 5 required an excessive amount of time (more than 1.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />) to
complete. The checklist appeared to contain va~eus-unnecessary items and was not
developed to minimize time. The team noted that an additional field validation of AOP-
C.04, Checklists 5 and 6 was performed the week of March 11, 2002. However, this
validation verified accuracy of component identifiers and tags, but did not evaluate
timeliness.
establish seal injection flow to the RCPs (i.e., AOP-C.04 specified as soon as possible
and AOP-N.08 specified 15 minutes);
. Weaknesses were identified in the operators' understanding and familiarity with AOP-
.06 Communications for Performance of Alternative SSD Capability
a. Inspection Scope
The team reviewed the licensee's communications systems separation analysis
the availability of the comy ucation system to support plant personnel in the
performance of al wrrtions and fire brigade duties. Walkdowns
were performed of sections of D procedure AOP-C.04 to evaluate the
adequacy of the plant communication systems to support plant personnel in the
performance of alternative SSD functions. -The team reviewed the adequacy of credited
'I
redundant communications~systems aneg'etd e licensee's portable radio channel
features would operate should the radio repe-ers for the primary communications
system be unavailable. The team also examined Whether sound-powered phone jacks
were present at the locations identified in the aferAWiAmhutdown procedure as
designated by the SQN Updated Final Safety Analysis Report (UFSAR). This review
'--included examination of theisourid powered phone periodic test record and inventory
- -surveillance records of post-fire SSD operator equipment to assess whether the
surveillance test program was.sufficient to verify proper operation of the system.
b. Findings
No findings of significance were identified.
.07 Emergencv Lighting for Performance of ASD Calabilitv
a. InsDection ScoDe
The team walked down select e eas where equipment would be controlled or
monitored during post-fir dn to observe whether battery pack emergency lighting QL
units (ELUs) were installed to allow operation of the equipment if normal lighting was lost
-In s6me'cases the installed ELU§-were-tes'ted to demonstrate functionality, and the
llocations and identification numbers on the ELUs were compared to design documents to
assure the as-built configuration was consistent with the design. The team also reviewed
licensee periodic test documentation to verify that the ELUs were being maintained in an
operable manner.
b. Findings
No findings of significance were identified.
.08 -Cold Shutdown ReDairs
a. LnsDection ScoDe - -
.. ..... .... .-
-
-4 O"_ II .
The team randomly selected a component, %rom the section of the FHA that listed (M
repairs that may be needed to achieve cold shutdown, and evaluated th aprb for
success of the repair. The component chosen was the RHR system ion valve1
FCV-074-001 specified for FA FAA-029. The review consideredhte level of difficulty of
the repair as compared to expected skills of the person assigned to perform the task,
adequacy of relevant procedures, and the availability of necessary materials.
b. Findings
No findings of significance were identified.
.09 Fire Barriers and Fire Area/Zone/Room Penetration Seals
a. Inspection Scope
The team walked down the selected FAs to evaluate the adequacy of the fire resistance
of FA barrier enclosure walls, ceilings, floors, structural steel support protection, fire
barrier penetration seals, fire doors, fire dampers, and electrical raceway fire barrier
systems (ERFBS) to ensure that at least one train of SSD equipment would be
maintained free of fire damage. IThe team observed the material condition and
configuration of the installed fire barrier features, as well as, reviewed construction details
._and.supporting fire endurance-tests-for the installed fire barrier features. The team
compared the observed fire barrier penetration seal configurations to the design drawings
and tested configurations. The team also compared the penetration seal ratings with the
ratings of the barriers in which they were installed.
The team reviewed ASD procedures, selected fire fighting pre-plan procedures, and
heating ventilation and air conditioning (HVAC) systems to verify that access to remote
shutdown equipment and operator manual actions would not be inhibited by smoke
migration from one area to adjacent plant areas used to accomplish SSD.
In addition, the team reviewed the licensing documentation, Generic Letter (GL) 86-10
engineering evaluations of fire barrier features, and engineering evaluations for NFPA
code deviations to verify that the fire barrier installations met design requirements and
license commitments.
b. Findings
No findings of significance were identified.
.10 Fire Protection Systems. Features. and Equipment
a. Inspection Scope
The team reviewed flow diagrams, cable routing information, periodic test procedures,
engineering evaluations for NFPA code deviations, and operational valve lineup
procedures associated with the electric driven high pressure service water fire pumps
and fire protection water supply system. The review was to determine whether the
common-fire-protection water delivery and supply components could be damaged or
inhibited by fire-induced failures of electrical power supplies or control circuits.
Additionally, team members walked down portions of the fire protection water supply
system in the selected areas to assess the material condition, operational effectiveness,
and whether the installed configurations were within the parameters of the engineering
evaluations.
The team verified that adequate fire protection features were installed in accordance with
the separation and design requirements in Appendix R to 10 CFR Part 50, Section
Ill.G.2. The team walked down accessible portions of the fire detection and alarm
systems in the selected plant areas to evaluate the engineering design and operation of
the installed configurations. The team also reviewed engineering drawings for fire
detector spacing and locations in the selected plant areas to verify effectiveness of the
systems and compliance with the licensee's FPR and associated NFPA code of record.
Team members walked down the selected areas with sprinklers to assure proper
placement and spacing of the sprinkler heads and the lack of sprinkler head obstructions.
The team reviewed design calculations to verify that the required fire hose water flow and
sprinkler system density for each protected area were available. The team reviewed a
sample of manual fire hose lengths to verify that they could reach the SSD equipment.
Additionally, the team verified whether the placement of the manual fire fighting fire hose
equipment and fire extinguishers were properly reflected in the fire brigade pre-fire plans.
The team reviewed the adequacy of the design and installation of the carbon dioxide
(CO2) fire suppression system for the FA FAC-009. This review included CO2 fire
suppression system controls to assure accessibility and functionality of the system and
associated ventilation system fire dampers. [The team also reviewed licensee design
calculations, vendor certifications, and pre-operational test data to verify that the required
quantity of CO2 for the area was available. Additionally, the team reviewed several
drawings, schematics, flow diagrams, and evaluations associated with the area floor
'drain'system to verify that systems and operator actions required for alternative SSD
would not be inhibited through potential leakage from C02 fire suppression activities.
b. Findings
No findings of significance were identified.
.11 Comnensatorv Measures
a. InsDection Scope
The team reviewed several licensee identified deficiencies, which dealt with maintaining
one redundant train of SSCs free from fire damage in accordance with 10 CFR 50
Appendix R III.G.2. The review was performed to verify that the risk associated with the
adverse conditions were properly assessed and adequate compensatory measures
adequately considered IPEEE risk insights and were implemented in accordance with the
approved fire protection program.
b. Findinas
No findings of significance were identified.
.12 Identification and Resolution of Problems
a. InsDection ScoDe
The team reviewed a sample of PERs related to fire protection and protection of SSCs
for SSD in accordance with 10 CFR 50 Appendix R III.G, III.J. and 111.0 to verify that
items were captured in the licensee's corrective action program in accordance with SPP-
3.1, Corrective Action Program, Rev 4. The items selected were reviewed for
classification and for the appropriateness of the corrective actions taken to resolve the
issues. The team reviewed self-assessments and audits related to the fire protection and
safe shutdown programs to assess whether the licensee was performing comprehensive
audits of these programs in accordance with the requirements set forth in Appendix A of
BTP APCSB 9.5-1.
b. Findings
No findings of significance were identified.
4. OTHER ACTIVITIES
40A6 Meetings
Exit Meeting Summary
The team presented the inspection results to Dennis Cole, and other members of
licensee management and staff at the conclusion of the inspection on March 28-29, 2002
and on April 24, 2002. The licensee acknowledged the findings presented. No
proprietary information is included in this report.
40A7 Licensee Identified Violations
The following findings of very low significance were identified by the licensee and are
violations of NRC requirements which met the criteria of Section VI of the NRC
Enforcement Policy, NUREG-1600 for being dispositioned as NCVs.
NCV Tracking Number Reauirement Licensee Failed to Meet
50-327, 328/02-03-03 10 CFR 50 Appendix III.J states that emergency lighting
units with at least an 8-hour battery power supply shall be
provided in all areas needed for operation of safe
shutdown equipment and in access and egress routes
thereto. The licensee identified during a self-assessment
that the need for emergency lighting for the 1, 2FCV-63-
001 had not been provided. Manual operation of these
valves is required in the event of a severe fire in
accordance with licensee shutdown procedures. The
failure to provide adequate illumination of manual actions
required for safe shutdown is identified as a Non-cited
violation of 10 CFR 50, Appendix R Il.J. The issue is in
the licensee's corrective action program as PER 02-
000550-000 (Green).
50-327, 328/02-03-04 10 CFR 50 Appendix R III.G. 2. states that except as
provided for in paragraph G.3 of this section, where cables
or equipment, including associated non-safety circuits that
could prevent operation or cause maloperation due to hot
shorts, open circuits, or shorts to ground, of redundant
trains of systems necessary to achieve and maintain hot
shutdownconditions are located within the same FA
outside of primary containment, one of the following
means of ensuring that one of the redundant trains is free
of fire damage shall be provided: (a.) Separation of cables
and equipment and associated non-safety circuits of
-~- ~ ~~~ redundant trains'by a fire barrier having a 3-hour rating.
Structural steel forming a part of or supporting such fire
barriers shall be protected to provide fire resistance
equivalent to that required of the barrier; (b.) Separation of
cables and equipment and associated non-safety circuits
of redundant trains by a horizontal distance of more than
20 feet with no intervening combustible or fire hazards. In
addition, fire detectors and an automatic fire suppression
system shall be installed in the FA; or (c.) Enclosure of
-: . cable and equipment and associated non-safety circuits of
one redundant train in a fire barrier having a 1-hour rating,
Inaddition, fire detectors and an automatic fire
suppression system shall be installed in the FA. The
licensee identified during a self-assessment that as a
result of inadequate protection to the control/and or control
cables a spurious closure signal to the VCT level control
valves was credible. As the power cables for the RWST
suctions valves are in the same FA and not protected
there was an interaction which existed such that suction to
both the VCT and RWST could be lost. The licensee's
failure to provide adequate protection to prevent the
operation or the maloperation of cables or equipment
necessary to achieve and maintain hot shutdown is
identified as a Non-cited violation of 10 CFR 50 Appendix
R llI;G.2. [The issue is in the licensee's corrective action
program as PER 02-000576-000 (Green).
PARTIAL LIST OF PERSONS CONTACTED
Licensee
J. Bajraszewski, Licensing Engineer
J. Bible, Maintenance and Modifications Manager, SQN
J. Beasley, Site Quality Manager, SQN
P. Boulden, Engineer, SQN
D. Craven, TPS-TOM Service Manager, SQN
T. Davis, Fire Protection Supervisor, WBN
B. Dukes, Engineer, SQN
R. Egli, Fire Protection Systems Engineer, SQN
K. Frazier, Systems Engineer, SQN
E. Freeman, Operations Manager, SQN
R. Gladney, Electrical Design Manager, SQN
J. Gomez, Lead Electrical Engineer, WBN
R. Goodman, Training Manager, SQN
0. Hayes, Operations Support Superintendent, SQN
P. Johnson, Fire Operations, SQN
D. Koehl, Plant Manager, SQN
D. Lundy, Engineering Manager, SQN
J. Patrick,'Senior Specialist, SQN
J. Pierce, Engineer, SQN
D. Porter, Operations, SQN
R. Proffitt, Nuclear Engineer, SQN
J. Reynolds, Nuclear Assurance, SQN
R. Rogers, Engineering Design Manager, SQN
P. Salas, Licensing and Industrial Affairs Manager, SQN
B. Simril, Fire Protection Specialist, SQN
J. Smith, Licensing Manager, SQN
J. Thomas, Mechanical/Nuclear Erigineering Supervisor, SQN
E. Turner, Electrical Engineering Design, SQN
J. Wilkes, Operations Superintendent, SQN
NRC
C. Pay'ne7-Senior Reactor Inspector, Ril
R. Tellson, Resident Inspector
ITEMS OPENED, CLOSED, and DISCUSSED
Oened and Closed
50-327/02-03-01 NCV Failure to Provide Adequate Protection for Cables to
Redundant SSD Components (Section 1R05.03)
50-327, 328/02-03-02 NCV -Inadequate Procedure Guidance for Implementing
-- Abnormal Operating Procedures for Plant Fires (Section
1R05.05)
50-327, 328/02-03-03 NCV Inadequate Emergency Lighting for the RWST Suction
Valve (Section 40A7)
50-327, 328/02-03-04 NCV Failure to Provide Adequate Protection for Cables to the
VCT Suction Valves (Section (40A7)
Closed
None
Discussed
None
LIST OF ACRONYMS
ACR Auxiliary Control Room
AOP Abnormal Operating Procedure
APCSB Auxiliary and Power Conversion Systems Branch
ASD Alternative Shutdown
.BTP.- Branch Technical Position
CFR Code of Federal Regulations
DC Direct Current
EOP Emergency Operating Procedure
ELU Emergency Lighting Unit
FDW/FW Feedwater
FSAR Final Safety Analysis Report
HVAC Heating, Ventilation, and Air Conditioning
IPEEE Individual Plant Examination for External Events
LP/LPI Low Pressure Injection
MCR Main Control Room
NCV Non-cited Violation
NRC Nuclear Regulatory Commission
PER Problem Evaluation Report
PORV Power Operated Relief Valve
PRA Probabilistic Risk Assessment
RCP Reactor Coolant Pump
RCS/RC Reactor Coolant System
SCBA Self-Contained Breathing Apparatus
SER Safety Evaluation Report
SLC Selected Licensee Commitment
SSA Safe Shutdown Analysis
SSD Safe Shutdown--...---
TS Technical Specifications-
UFSAR Updated Final Safety Analysis Report
URI Unresolved Item
LIST OF DOCUMENTS REVIEWED
Procedures:
0-AR-M-29, Annunciator Response Fire Detection System, Rev 8
0-PI-OPS-000-708.0,1 OCFR50 Appendix R Compliance Verification, Rev 3
1-AR-M5-B, Annunciator Response CVCS Seal Water and RCP, Rev 28
1-SO-77-4, System Operating Instruction for Auxiliary Reactor Building Floor and Equipment
1-PI-OPS-000-010.A, Verification of Remote Shutdown Transfer Switches, Rev 0, Completed
11/13/2001
AOP-C.04, Shutdown From Auxiliary Control Room, Rev 4
AOP-N.01, Plant Fires, Rev 14
AOP-N.08, Appendix R Fire Safe Shutdown, Rev 0
SPP-9.3, Plant Modifications and Engineering Change Control, Rev 6
SPP-1 0.7, Housekeeping/Temporary Equipment Control, Rev 0S2
SSP-10.10, Control of Transient Combustibles, Rev 1
SSP-10.11, Control of Ignition Sources, Rev 1
SMI-0-317-18, Special Maintenance Instruction - Appendix R - Casualty Procedures, Rev 6
0-SI-FPU-031-001.R, Visual Inspection Fire Dampers, Rev 2
0-PI-FPU-317-299.W, Attachment 4, Operations Fire Protection Weekly Inspection, Rev 10
0-SI-FPU-410-703.0, Inspection of FPR Required Fire Doors, Rev 0
O-SI-234.6, Functional Test of Fire Protection Report Required Detectors, Rev 32
FPI-0102, Appendix C Active Permits (Impairments), dated March 26, 2002
Pre-Fire Plan No. AUX-0-690-00, Auxiliary Building, Elevation 690'- 0, Rev 1
Pre-Fire Plan No. AUX-0-690-01, Auxiliary Building, Elevation 690'- 0, Rev 1
Pre-Fire Plan No. AUX-0-690-02, Auxiliary Building, Elevation 690'- 0, Rev 5
Pre-Fire Plan No. AUX-0-734-00, Auxiliary Building, Elevation 734'- 0, Rev 2
Pre-Fire Plan No. AUX-0-734-01, Auxiliary Building, Elevation 734'- 0, Rev 4
Pre-Fire Plan No. AUX-0-734-02, Auxiliary Building, Elevation 734'- 0, Rev 3
Pre-Fire Plan No. AUX-0-734-03, Auxiliary Building, Elevation 734'- 0, Rev 4
Pre-Fire Plan No. CON-0-685-00, Control Building, Elevation 685'- 0, Rev 3
Pre-Fire Plan No. CON-0-732-00,- Control Building, Elevation 732'- 0, Rev 4
Job Performance Measures (JPMs) and Lesson Plans:
Lesson Plan OPL273C0202, Appendix R Fires (AOP-N.01, AOP-N.08, AOP-C.04), Rev 0
JPM CRO-005, Evacuate the Control Room, Rev 13
JPM CRO-052, Perform Required Actions in Preparation for Manning the SSF, Rev 4
PERS, Audits. and Self-Assessments:
Fire Protection and Loss Prevention Program Audit (Biennial\Triennial) No. SSA0101
Fire Protection and Loss Prevention Program Audit (Annual) No. SSA0001
Fire Protection and Loss Prevention Program Audit (Triennial) No. SSA9802
Self Assessment Report, SQN-OPS-09-001 Rev 1
Self Assessment Report ,SQN-OPS-01-007
Attachment
2
PER 00-011423, Sequoyah Does not Perform Periodic Functional Testing on Alternate
Shutdown Transfer Switches and Controls, dated 12/15/2000
PER 01-009956, Handswitches Had to be Cycled to Pass Continuity Checks During
Performance of Procedure 0-PI-OPS-000-010.A, dated 11/2/2001
PER 01-010214, Discrepancies During Performance of Procedure 1-PI-OPS-000-010.A,
dated 11/8/2001
Calculations
SQN-26-D054/EPM-ABB-IMPFHA, Sequoyah Fire Hazards Analysis Calculation, Rev 31
SQN-SQS4-0127, Equipment Required for Safe Shutdown Per 10 CFR 50 Appendix R,
Rev I
SQN-APPR-1, Analysis of AC/DC Instrument and Control (I&C) Power Systems to Identify
Associated Circuits - 10 CFR 50, Appendix R, Sheets 16A, 16B, 16C, 17, 37, 46, 54, 76 & 79C
of 131, Appendix R Common Power Supply Analysis, Rev 7 [Coordination 125 VDC Vital
Battery Board 1,11, III & IV]
SQN-APS-003, 480 V APS Class 1E Load Coordination Study, Time-Current Curve # 2, Sheet
C-6, Rev 15 [480 V shutdown boards]
SQN-APS-003, 480 V APS Class 1E Load Coordination Study, Time-Current Curve # 3, Sheet
C-7, Rev 12 [480 V reactor mov boards]
SQN-APS-003, 480 V APS Class 1E Load Coordination Study, Time-Current Curve # 8, Sheet
C-13, Rev 28 [480 V ERCW PMP STA MCCs]
Drawing Numbers
1-47W809-1, Unit 1 Chemical and Volume Control System Flow Diagram, Rev 64
1, 2-47W810-1, Units 1 and 2 Residual Heat Removal System Flow Diagram, Rev 39
1-47W811-1, Unit 1 Safety Injection System Flow Diagram, Rev 57
1, 2-47W813-1, Units 1 and 2 Reactor Coolant System Flow Diagram, Rev 49
2-47W809-1, Unit 2 Chemical and Volume Control System Flow Diagram, Rev 64
2-47W811-1, Unit 2 Safety Injection System Flow Diagram, Rev 48
1,2-45N767-1, Wiring Diagrams 6900 V Diesel Generators Schematic Diagrams Sht-1 Rev 26
1,2-45N767-2, Wiring Diagrams 6900 V Diesel Generators Schematic Diagrams Sht-2 Rev 31
1,2-45N767-3, Wiring Diagrams 6900 V Diesel Generators Schematic Diagrams Sht-3 Rev 23
1,2-45N767-4, Wiring Diagrams 6900 V Diesel Generators Schematic Diagrams Sht-4 Rev 20
1,2-45N767-5, Wiring Diagrams 6900 V Diesel Generators Schematic Diagrams Sht-5 Rev 15
1,2-45N765-1, Wiring Diagrams 6900 V Shutdown Aux Power Schematic Diagram Sht-1, Rev
14 [6900 V Shutdown board 1A-A normal feeder breaker 1718]
1,2-45N765-2, Wiring Diagrams 6900 V Shutdown Aux Power Schematic Diagram Sht-2, Rev
16 [6900 V Shutdown board 1A-A emergency feeder breaker 1912]
1-45E890-104-1, 10 CFR 50 Appendix R RCS Pressure Control Operational & Spurious CA
Keys 1,2,4,5,6&9, Rev 4 [conduit and tray plan for charging pump cables in FAA-029]
1,2-45N824-7, Conduit & Grounding Floor Elevation 690.0 Ceiling Plan, Rev 2 [conduit plan for
62-90 & 91 valve cables]
Attachment
3
1,2-45N824-16, Conduit & Grounding Floor Elevation 690.0 Details - Sht-4, Rev 0 [conduit plan
for 62-90 valve cables]
1,2-45N826-8, Conduit & Grounding Floor Elevations 706.0 & 714.0 Ceiling Plan, Rev 2,
[Routing of pressurizer level circuits]
-1 45E890-103-1,ri:10 CFR 50 Appendix R RCS Inventory Control Operational & Spurious CA
Keys 1,2,4,5,6 & 9, Rev 3 [Routing of pressurizer level circuits]
1-45E890-103-2, 10 CFR 50 Appendix R RCS Inventory Control Operational & Spurious CA
Keys 1,2,4,5,6 & 9, Rev 1, [Routing of pressurizer level circuits]
1-45E890-102-2, 10 CFR 50 Appendix k RCS Inventory Control Operational & Spurious CA
Keys 1,2,4,5,6 & 9, Rev 1, [Routing of pressurizer level circuits]
1-47W610-3-3, Mechanical Control Diagram Auxiliary Feedwater System, Rev 17
1,2-45N812-5, Conduit & Grounding Floor 685.0 Details - Sht 3, Rev 1 [Routing of cables for
diesel generator start button] -
1,2-45N765-16, Wiring Diagrams 6900 V Shutdown Aux Power Schematic Diagram Sht-16,
Rev 17 [Centrifugal charging pumps]
1,2-15E500-1, Key Diagram Station Aux Power System, Rev 22
1,2-45N779-1 1, Wiring Diagrams 480 V Shutdown Aux Power Schematic Diagram Sht-1 1, Rev
24, [MOV LCV-62-132]
1,2-45N662-1, Wiring Diagrams Chemical & Volume Cont Sys Schematic Diagram Sht-1, Rev
10, [AOV LCV-62-85]
1-47W610-92-1, Mechanical Control Diagram Neutron Monitoring System, Rev 3
1,2-47A381 -111, Mechanical Heating & Ventilation & Air Conditioning Dampers, Rev 3
1,2-47A381-113, Mechanical Heating & Ventilation & Air Conditioning Dampers, Rev 2
1,2-47W494 series, Fire Protection Fire Cells, Rev 6
1,2-47W600-250, Mechanical Instruments and Controls Fire Detectors, Rev 5
1,2-47W600-254, Mechanical Instruments and Controls Fire Detectors, Rev 2
1,2-47W61 0 series, Control Diagram High Pressure Fire Protection System, Rev 21
1,2-47W611 series, Logic Diagram Fire Detection System, Rev 12
1,2-47W849-1, Flow Diagram Hydrogen System for.Generator Cooling, Rev 31
1,2-47W850-2, Flow Diagram Fire P-rotection,-Rev 25
1,2-47W850-6A, Connectivity Diagram Fire Protection System, Rev 0
-42-47-W866-2, Fow-Diagramr-Heating-&-Ventilation Air Flow, Rev 11.
1,2-47W866-4, Flow Diagram Heating & Ventilation Air Flow, Rev 32
1,2-47W880-26, Conduit and Grounding Cable Tray Fire Stop, Rev 2
1,2-48W990-1, Miscellaneous Steel Fire Protection Reactor Coolant Pump Hood, Rev 3
1,2-48W991-1, Miscellaneous Steel Fire Protection Reactor Coolant Pump, Rev 6
1,2-47W920-8, Mechanical Heating & Ventilation & Air Conditioning, Rev 3
Other Documents Reviewed:
Bussman Mfg. Div. Time-current Characteristic Curve No. 50980, dated 2/4199, for KLC and
KTN-R fuses
Bussman Mfg. Div. Form 236, dated 10/17/70, Total Clearing Time-Current Characteristic
Curves for FRN Fusetron Fuses
Attachment
4
Westinghouse Electric Corporation, Application Data 29-261, Circuit Breaker Types EB, EHB
FB, Mark 75 HFB [Time-Current Characteristic]
Gould Inc. Class L Form 480 Amp-Trap Fuse Total Clearing Time Data 200 - 600 Amp A4BY
ITE Corp Publication 11-18.1.7-2, page 3, Ground Protection Systems [cover GR-5 relay]
Various "Integrated Cable & Raceway Design System" Sheets
Various cable block diagrams prepared as part of the Fire Hazards Analysis
Various drawings associated with DCN M01443A Showing routing of cables for pressurizer
level circuits
Relay Information Setting and Test Record Overcurrent and Ground Relays:
Sheet No. 1817, dated 6/19/92 [for relays in CSS transformer C neutral]
Sheet No. 1986, dated 11/21/82 [for relays at breaker 1418]
Sheet No. 7911, dated 1/8/90 [for relays at breaker 1622]
Sheet No. 760279R1, 8/24/98 [for relays at breaker 1714]
Sheet No. 774579R2, dated 11/30/01 [for reactor coolant pump 2]
Sheet No. 7609, dated 11/27/79 [for relays at breaker 1718]
Sheet No. 178793R1, dated 11/30/01[for essential raw cooling water pump J-A]
Fire Protection Report, Part V, Table V-1, 8 Hour Emergency Lighting Units, Rev 9
Factory Mutual Research, Tests on Sprinklers, dated April, 29,1983
Memorandum, TVA to NRC, Final Closeout Regarding Resolution of Thermo-Lag 330-1 Fire
Barrier Upgrades, dated June 30, 1999
NRC Integrated Inspection Report No. 50-327, 328/97-03, dated May 12, 1997
NRC Integrated Inspection Report No. 50-327, 328/98-07, dated August 4,1998
Correspondence:
Memorandum, To: W.S. Raughley, Chief Electrical Engineering Branch, From R.L. Morley,
Chief, Central Laboratories Branch, on the subject of "Peak Let Through Test" [for limitron KLC-
15 fuse]
AnDlicable Codes and Standards
NFPA 12, Carbon Dioxide Extinguishing Systems, 1973 Edition
NFPA 13, Standard for the Installation of Sprinkler Systems, 1975 Edition
NFPA 14, Standard for the Installation of Standpipe and Hose Systems, 1974 Edition
NFPA 20, Standard for the Installation of Centrifugal Fire Pumps, 1993 Edition
NFPA 30, Flammable and Combustible Liquids Code, 1973 Edition
NFPA 72D, Standard for the Installation, Maintenance, and Use of Proprietary Protection
Signaling Systems, 1975 Edition
NFPA 72E, Standard on Automatic Fire Detectors, 1974 Edition
NFPA 80, Standard on Fire Doors and Windows, 1981 Edition
NFPA 101, Life Safety Code, 1996 Edition
NUREG-1552, Supplement 1, Fire Barrier Penetration Seals in Nuclear Power Plants, dated
January 1999
Attachment
5
PERs Written During This Inspection
PER 02-02866, Incorrect Categorization of Fire Protection PERs
PER 02-03510, Availability of Sound Powered Phones
PER 02-03527, Lack of Adequate Relay Coordination for the Common Service Station
Transformer
PER 02-03530, Lack of Procedural Steps for Cold Shutdown Repair
PER 02-03543, Shift Incident Commander Training on AOP-N.08
PER 02-03550, Deficiencies in AOP-C.04 Procedure Validation
PER 02-03552, OnShift Familiarity with Plant Fire and Appendix R Procedures
PER 02-03564, Fire Equipment Area Emergency Lighting
PER 02-03565, Cardox Floor Drain Loop Seal PM
PER 02-03566, Fire Fighting Effects on the Performance of Electrical Equipment Manipulation
PER 02-03645, Potential NRC Violation for Inadequate Cable Separation
Attachment